Yaseen ali shah
Monolithic:A monolithic structure is something carved or cast
from a single piece of a material. Usually (and literally, from the
translation of monolith being "one stone") the material is stone,
but it could equally be applied to a structure cut from a single
block of metal, or cast in metal in a single pieceDEFFERENCE
BETWEEN SHELL, MEMEBRANE & PLATE (ETABS)Hi.. Someone asked here
for the differences between shell, membrane, and plate on slab
category using in Etabs and when to apply what. OK.. here I am
clearing the fact in details that you can see from the attached
image. In general for Etabs modeling, shell is used but when in
practical designing in high rise structures, we can use membrane as
then the moment generated by Etabs for the slab will be greater, as
a result the reinforcement will be increased,hence factor of safety
will be increased but always keep in mind about the economic
condition. So, frequently use the shell option. Again, use the
options to take the values for specific parameters.(FACEBOOK)
REPAIR OF SMALL AND LARGE CRACKS IN CONCRETE
Repair of small, medium and large cracks inconcreteand repair of
crushedconcreteis required to enhance the strength and durability
of damaged concrete members.Repair of small and medium cracks in
concrete:Small and medium cracks in reinforced concrete and masonry
structures reduce their strength considerably to bear the
designloads. Thus repair of such cracks is necessary to restore the
designed strength of members.The repair of small and medium cracks
is done by first marking out the critical damaged zones in concrete
members. Then these cracks can be repaired by injectingcementgrout
or chemical grouts or by providing jacketing. The smaller cracks
less than 0.75 mm width can be effectively repair by using pressure
injection of epoxy.The surface of the member near cracks is
thoroughly cleaned. Loose materials are removed and plastic
injection ports are placed along the length of crack at an interval
equal to the thickness of the structural member. These ports are
placed on both sides of the member and secured in placed with the
help of epoxy seal.When the epoxy seal has hardened, the low
viscosity resin is injected into one port at a time starting from
the port at lowest level and moving upwards. The injection through
port is continued till the resin flows out from the adjacent port
or from the other side of the member. Then the current injection
port is closed and epoxy injection is continued from the adjacent
port.
This process is carried out in sequence till all the ports and
cracks are filled with the grout. This method can be used for all
types of structural members such are beams, columns,wallsand slabs.
This method can also to repair of small cracks in individual
masonry blocks or for filling large continuous cracks.Repair of
Large Cracks and Crushed Concrete:Repair of large cracks (cracks
wider than 5mm) and crushed concrete and masonry structure cannot
be done using pressure injection or grouting. For repair of large
cracks and crushed concrete, following procedure can be adopted:1.
The surface of cracks or crushed concrete is cleaned and all the
loose materials are removed. These are then filled with quick
setting cement mortar grouts.2. If the cracks are large, then these
cracks are dressed to have a V groove at both sides of the member
for easy placement of grouts.
Fig: Filling of cement mortar and stone chips in large cracks in
masonry walls.3. For cracks which are very large, filler materials
such as stone chips can be used.4. Additional reinforcement and
shear reinforcements can be used for heavily damaged concrete
members or wherever necessary based on requirements.These
additional reinforcement should be protected from corrosion by
using polymer mortar or epoxy coatings.5. For damaged walls and
roofs, additional reinforcement in the form of mesh is used on one
side or both sides of the members. These mesh should sufficiently
tied with existing members.
Fig: Reinforcement meshes in repair of roof slabs and walls. 1.
Wire mesh on front face, 2. Clamps, 3. Wire mesh on back face, 4.
Cement plaster, 5. Crack in member.6. Stitching of cracks are done
to prevent the widening of the existing cracks. In this case, holes
of 6 to 10mm are drilled on both sides of the crack. Then these
drilled holes are cleaned, legs of stitching dogs are anchored with
short legs. The stitching of cracks is not a method of crack repair
or to gain the lost strength, this method is used to prevent the
cracks from propagating and widening.
Percentage of Bricks and Mortar in a Masonry WallCase 1:When
thickness of the wall is 4.5 and that of mortar is 12mm, having the
following plan.
In this caseHeight of the wall along with the mortar = (10 x 3)
+ [(9 x 12)/25.4] = 34.252In the above equation10 = No of Brick
Layers9 = No of layers of Mortar of 12mm each3 = Brick Height in
inchesWidth= 4.5Length of the wall along with the mortar= (5.5 x 9)
+ [(512)/25.4]Volume of the wall along with the mortar=LWHVolume of
the wall along with the mortar= 7993.72 cubic inchVolume of the
wall along with the mortar= 4.626 cftNow Number of Bricks= 55Volume
of One Brick= (9/128) cftTotal volume of bricks used= 55 x (9/128)
= 3.867 cft%age of bricks used = (3.867 / 4.626)*100 = 83.6 =
84%%age of mortar used= 16.4%Case 2:When thickness of the wall is 9
and that of mortar is 12mm, having the following plan.
In this caseHeight of the wall along with the mortar = (10 x 3 )
+ [( 9 x 12 )/25.4] =34.252Width of the wall along with the mortar
=(9+12/25.4) = 9.472Length of the wall along with the mortar= (5.5
x 9) + (5 x 12/25.4) = 51.862Volume of the wall along with the
mortar=LWHVolume of the wall along with the mortar=16826.678 cubic
inchVolume of the wall along with the mortar= 9.7376 cftNow Number
of Bricks= 110Volume of One Brick= 9/128 cftTotal volume of bricks
used= 110 x (9/128) = 7.7344 cftSo%age of bricks used = (7.7344 /
9.7376) x 100 = 79.43% = 80%%age of mortar used= 20.57%= 21%Case
3:When thickness of the wall is 4.5 and that of mortar is 10mm,
having the following plan.
In this caseHeight of the wall along with the mortar = (10 x 3)
+ (9x10/25.4) = 33.543width = 4.5Length of the wall along with the
mortar= (5.5 x 9) + (5 x 10/25.4) = 51.468Volume of the wall along
with the mortar=LWHVolume of the wall along with the mortar= 4.4959
cftNow Number of Bricks= 55Volume of One Brick= 9/128 cftTotal
volume of bricks used= 55 x 9/128 = 3.8672 cft%age of bricks used =
(3.8672 / 4.4959) x 100 = 86%%age of mortar used = 14%Case 4:When
thickness of the wall is 9 and that of mortar is 10mm, having the
following plan.
In this caseHeight of the wall along with the mortar = (10 x 3)
+ (9x10/25.4) = 33.543width = (9 + 10/25.4) 9.3937Length of the
wall along with the mortar= (5.5 x 9) + (5 x 10/25.4) =
51.468Volume of the wall along with the mortar=LWHVolume of the
wall along with the mortar= 9.38513cftNow Number of
Bricks=110Volume of One Brick= 9/128 cftTotal volume of bricks
used= 110x 9/128 = 7.7344cft%age of bricks used = (7.7344 /
9.38513) x 100 = 82.4% = 82%%age of mortar used = 17.6% =
18%Conclusion
Where in itW= wall thickness in inchesm= thickness of the mortar
in mmThe answer will be the %age of mortar, and for better results
round it off.ItsVerificationis given below after the example from
observation.EXAMPLE:If thickness of the wall is 4.5 and that of
mortar is 12mm, then what will the percentage of mortar used in the
wall?Solution:
Specification of 'Bricks Walls'
Brick walls are probably the most common building elements in
construction of a house in India. These walls form basic units for
creating rooms that make up a house. The walls besides being space
dividers are also structural elements that transfer the load of the
roof to the ground. Brick walls are constructed on strip spread or
raft foundations that support the walls. The walls are constructed
using bricks and mortar. These can also be constructed with various
structural qualities and thicknesses.BrickworkBrick walls are
constructed by joining bricks with cement mortar in arrangements
called English Bond, Flemish Bond or Rat Trap Bond. These bonds
give different external appearances to the wall. All construction
systems of brick walls are such devised that vertical cross joints
in any layers are staggered. The bricks thus bonded form a solid
mass that does not split when the wall is loaded with live loads
and dead loads.Classification of Brick WorkThe classification of
brick work according to the quality of brick is following. First
class brick work Second class brick work Third class brick
workFirst Class Brick WorkFirst class brick work is made by using
first class bricks and cement mortar. This brick work is used for
load bearing walls. It is made in rich mortar in which the cement
and sand ratio is from 1:3 to 1: 6.First class bricks are
identified by their uniform color and a ringing sound when struck.
The bricks are equal in size and have even edges and surfaces.
These bricks do not chip and dont have any cracks. First class
bricks do not absorb water more than 1/6 of their weight. There is
no salty residue when the bricks are dry. First class bricks have a
minimum crushing strength of 105.kg. Per sq. cm
Bricks of first class qualitySecond Class Brick WorkSecond class
bricks work is made by using second class bricks and cement mortar.
These bricks also have the property of first class bricks but are
not very regular or even in shape. These bricks should not be used
for load bearing walls for more than two storey buildings. Second
class bricks have minimum crushing strength 70.kg per sq.
meter.
Second classquality of bricksThird Class Brick WorkThis type of
brick work is made by using third class bricks and cement mortar or
mud mortar. Third class brick work is not made in any Govt. work.
Generally this type of brick work is made for temporary work in
private sector.MortarMortar is a mix used to bind brick, stone etc
to each other.It can thus be seen as a binding material that bonds
bricks, stones to make a wall or for cladding purpose. Normally
cement mortar is used in brickwork in present day construction
though lime mortar can also be used but it requires superior
craftsmanship and is hence infrequently used.Cement MortarCement
mortar is a mix of cement and sand with water. The cement is
binding material which requires sand as a filler material. This
cement mortar mix in wet state is plastic and binds two materials
when it dries. Mortar is generally defined as 1:2 or 1:3 or 1:7
etc. This means that one part of cement is mixed with 2, 3 or 7
parts of sand.Precaution for mixing cement mortarThe following
steps should be taken carefully while mixing materials for cement
mortar. The mix should be made on a dry, clean, flat surface. The
mix should be as per specifications. The mix should be by volume.
The quantity of water should be such that the mix can be easily
spread over bricks or applied on a vertical surface. Water more
then required quantity may spoil the mix and it can reduce the
strength of masonry. The mix should be used within half an hour of
its preparation.
Brick Wall FoundationsBrick wall foundations are normally made
as strip foundations.These are continuous along the length of wall
and hence called as strip foundations. These form structural
components of construction system by which the load of whole
building is transferred to the ground.Foundations are made in dug
out trenches so that a hard stable surface on which the building is
supported can be obtained because the top surface of the ground
normally does not have load bearing capacity to take the load of
the building. The other reason is that foundations can by this
method be hidden from view. The architect needs to provide a
foundation plan that indicates exactly where the foundation
trenches are to be dug.The foundation trenches are dug after being
marked on center line principle on the site according to architects
drawings. The size of trench varies with the thickness of walls and
the load bearing capacity of the soil. The base of dug trench is
rammed to solidify the surface. On rammed surface a layer of cement
concrete is laid. This is normally 6 to 8 inches thick. This base
concrete layer needs to be cured for it attains its expected
strength. Base concrete layers or courses of bricks are laid to
create a stepped base that would help in distributing the load over
a larger surface of the foundation.Precautions during construction
of brick wall foundations The marking of foundations must be
absolutely accurate as the location of walls depends on these
markings. The trenches should not be dug in rainy season. The
bricks, mortar mix and cement concrete mix should be as per
specifications. The width and depth of the trenches depends on
loading and soil conditions. As the foundation is an expanded base
to distribute the load coming on it over a large area on ground.
The width of the wall foundation depends on whether the wall is a
load bearing wall, a non load bearing wall, a partition wall or a
toe wall.Load Bearing WallsThe walls that support beams and roof
slabs. These walls take the load of super structure and transmit it
to the ground through foundation. These can also serve the purpose
of dividing the space into required rooms etc. These are also
accommodating door and windows where required. These are of 9 or
more thickness. Such walls are made in first class bricks and rich
mortar.
Non Load Bearing Walls These walls serve the purpose of dividing
the space into required rooms etc. These are also accommodating
door and windows where required. These can be made into thin
sections to save the space. Non load bearing walls are only
partition having no load of super structure so these can be easily
changed whenever required to change the space of the room. These
walls are made 3 inches, 4.5 inches and 9 inches thick as per the
requirement of the site.
Super Structure:The word super structure used in construction
work means/denotes following. Brick work from DPC level to the roof
level/slab level. If columns provided in drawings then RCC columns
to be laid. Rain water pipe is to be embedded in walls. Fixing
doors, windows and ventilators frames in walls. RCC (Reinforced
Beam & slab for roof) including M S Steel bars according to the
designs. Tile terracing lay with brick tiles on the top of the roof
slab. Fixing doors and windows shutters. Fixing cupboard in the
rooms and Kitchen etc. Fixing iron grills for safety of the house.
Providing cement plaster on ceiling and walls. Laying floors
including base coat.
CATCHMENT AREA METHOD
By Catchment Area Method you calculate Column load
HOW TO DO IT ?
1) Suppose you want to calculate load on column c1 AS shown in
figure , now as shown in figure , Purple Hatched one are columns
and Blue Hatched one are Beams and i Have Marked Area with Inclined
Pink Lines
Now Catchement means Hatchmed pink line area is Catchment on
Column C1 , means Half of Slab Area and Half of Horizontal Beam and
Half of vertical Beam is the total catchment area on Column C1
How To Calculate Load on column C1 ?
1) Consider Slab area first
in it You have Live load , finishes load or any other uniform
pressure load in psf
now to convert that uniform pressure load (including self weight
)in psf into point load which will be Load on COLUMN C1 , for that
you have to multiply Pressure load (in psf ) by area of slab(in
ft^2) ,
Area will be Pink Hatched area as shown in Figure
2) Consider Beam now
Above Beams you have Wall Load which is in Kip/ft
Now to Convert that Wall load into point load which will be Load
on Column C1 , for that you have to multiply wall load (in Kip/ft)
by half length of beam
As shown in Figure , it is clearly shown that half length of
horizontal beam and half length of vertical beam will be catchment
length on column C1
now first find out Horizontal half length and vertical half
length and then for horizontal half length multiply it by Wall load
which is in kip/ft and for vertical half length multiply it by wall
load which is in kip/ft , now that will be the Point Load in Kips
on Column C1
Also include Self Weight of Beam
3) Column Self Weight also , means if column height is from
floor to floor is 12 feet and beam depth is 24 inch then column
height will be 12 feet - 2feet(24 inch beam depth)
FOR example
LOAD ON SLABS :
1) LIVE LOAD = 60 psf2) Finishes Load = 36 psf3) sunk Load = 90
psf4) Slab self weight ( thickness x 0.15(density) = answer in
psf
Wall Load on Beam :
1) Height of Wall is 10 feet , thickness of wall is 6 inch then
Wall load will be 10 x (6/12) x 0.144 = 0.72 kip/ft
BEAM SELF WEIGHT ALSO
Size of Column is 6" x 24" , Height of Column is 12 feet from
floor to floor and width of beam is 6 inch and depth of beam is 24
inch , and length of Horizontal Beam is 10 feet and Length of
Vertical Beam is 12 feet ,
Now you have to calculate Load on Column C1 from Slab and Beam ,
as i described above ,
CALCULATE QUANTITIES OF MATERIALS FOR CONCRETEQuantities of
materials for the production of required quantity ofconcreteof
given mix proportions can be calculated by absolute volume method.
This method is based on the principle that the volume of fully
compactedconcreteis equal to the absolute volume of all the
materials of concrete, i.e.cement, sand, coarseaggregatesand
water.
The formula for calculation of materials for required volume of
concreteis given by:
Where, Vc= Absolute volume of fully compactedfresh concreteW
=Mass of waterC = Mass of cementFa = Mass of fine aggregatesCa =
Mass of coarse aggregatesSc, Sfaand Scaare the specific gravities
of cement, fine aggregates and coarse aggregates respectively.The
air content has been ignored in this calculation.This method of
calculation for quantities of materials for concrete takes into
account the mix proportions from design mix or nominal mixes for
structural strength and durability requirement.Now we will learn
the material calculation by an example.Consider concrete with mix
proportion of 1:1.5:3 where, 1 is part of cement, 1.5 is part of
fine aggregates and 3 is part of coarse aggregates of maximum size
of 20mm. The water cement ratio required for mixing of concrete is
taken as 0.45.Assuming bulk densities of materials as
follows:Cement = 1500 kg/m3Sand = 1700 kg/m3Coarse aggregates =
1650 kg/m3Specific gravities of concrete materials are as
follows:Cement = 3.15Sand = 2.6Coarse aggregates = 2.6.The
percentage of entrained air assumed is 2%.The mix proportion of
1:1.5:3 by dry volume of materials can be expressed in terms of
masses as:Cement = 1 x 1500 = 1500Sand = 1.5 x 1700 = 2550Coarse
aggregate = 3 x 1650 = 4950.Therefore, the ratio of masses of these
materials w.r.t. cement will as follows =
= 1 : 1.7 : 3.3The water cement ratio = 0.45Now we willcalculate
the volume of concretethat can be produced with one bag of cement
(i.e. 50 kg cement) for the mass proportions of concrete
materials.Thus, theabsolute volume of concretefor 50 kg of cement
=
Thus, for the proportion of mix considered, with on3 bag of
cement of 50 kg, 0.1345 m3of concrete can be produced.We have
considered an entrained air of 2%. Thus the actual volume of
concrete for 1 cubic meter of compacted concrete construction will
be = 1 -0.02 = 0.98 m3.Thus, the quantity of cement required for 1
cubic meter of concrete = 0.98/0.1345 = 7.29 bags of cement.The
quantities of materials for 1 m3 of concreteproduction can be
calculated as follows:The weight of cement required = 7.29 x 50 =
364.5 kg.Weight of fine aggregate (sand) = 1.5 x 364.5 = 546.75
kg.Weight of coarse aggregate = 3 x 364.5 = 1093.5 kg.
POOR CONSTRUCTION METHODS AND WORKMANSHIP TO
AVOIDPoorconstructionmethods and workmanship is responsible for the
failure ofbuildings and structure. The poor construction methods
and workmanship is caused due to negligence and inadequate quality
control at construction site. The effects of some of the poor
construction methods are discussed below:(a) Incorrect placement of
steelIncorrect placement of steel can result in insufficient cover,
leading to corrosion of the reinforcement. If the bars are placed
grossly out of position or in the wrong position, collapse can
occur when the element is fully loaded.(b) Inadequate cover to
reinforcementInadequate cover to reinforcement permits ingress of
moisture, gases and other substances and leads to corrosion of the
reinforcement and cracking and spalling of theconcrete.(c)
Incorrectly made construction jointsThe main faults in construction
joints are lack of preparation and poor compaction. The
oldconcreteshould be washed and a layer of rich concrete laid
before pouring is continued. Poor joints allow ingress of moisture
and staining of the concrete face.(d) Grout leakageGrout leakage
occurs where formwork joints do not fit together properly. The
result is a porous area of concrete that has little or nocementand
fine aggregate. All formwork joints should be properly sealed.(e)
Poor compactionIf concrete is not properly compacted by ramming or
vibration the result is a portion of porous honeycomb concrete.
This part must be hacked out and recast. Complete compaction is
essential to give a dense, impermeable concrete.(f)
SegregationSegregation occurs when the mix ingredients become
separated. It is the result of1. dropping the mix through too great
a height in placing (chutes or pipes should be used in such
cases)2. using a harsh mix with high coarse aggregate content3.
large aggregate sinking due to over-vibration or use of too much
plasticizer
Fig: Seggregation of concreteSegregation results in uneven
concrete texture, or porous concrete in some cases.(g) Poor curingA
poor curing procedure can result in loss of water through
evaporation. This can cause a reduction in strength if there is not
sufficient water for complete hydration of the cement. Loss of
water can cause shrinkage cracking. During curing the concrete
should be kept damp and covered.(h) Too high a water contentExcess
water increases workability but decreases the strength and
increases the porosity and permeability of the hardened
concrete,which can lead to corrosion of the reinforcement. The
correct water-to-cement ratio for the mix should be strictly
enforced.
Concrete Mix Proportion MaterialsDry Volume and Wet Volume:Dry
Volume : Bulk Volume with air spaces etc.Wet Volume : Real Volume
to be used.In dry mix volume empty spaces between particles in bulk
material are filled with air. When we add water to concrete the
empty spaces are filled with water, So the reduction in volume from
dry to wet is not by shrinkage of material.For example100kg of each
material, their dry volume and wet volumes typically are:Cement:
Dry V - 66L, Wet V - 32 LSand: Dry V - 62L, Wet V - 38 LCoarse
aggregate: Dry V - 59L, Wet V - 38LThe factor of 1.54 to convert
dry volume is just approximate. For each batch of materials we have
to measure dry volume and actual density to accurately
convert.Cement Concrete Rule of 6
A good concrete depends onproper quantities of its gradients
like cement, crush, sand and water.Here is a simple rule for proper
quantities ratio is the rule of 6's!
1- Minimum cement bags are required for cubic yard concrete = 6
bags2- Maximum water required per cement bag = 6 gallon3- Minimum
curing days required to keep moisture = 6 days4- Air contents
required (if concrete will be subject to freezing and thawing) = 6
%
How to calculate materials for different-ratio concrete
Mix design is commonly referred by mix proportion in a selective
zone where same materials are used in concrete. Suppose, in
Bangladesh, most of the structural designers refer concrete mix
design as ratio in drawing. Because materials of same properties
are used in all over the Bangladesh.The question is,
How do we estimate materials for different ratio concrete?
The most common ratio referred here in Bangladesh for column
concrete 1:1.5:3 and for slab 1:2:4. When we mix cement, sand and
stone chips at 1:1.5:3 ratio, the concrete strength of 28 days cube
test's result comes around 3500 psi. If we mix cement, sand and
brick chips at 1:2:4 ratio the 28 days cube test result will come
around 3000 psi, which is referred for slab concrete.
I will estimate materials for 1:1.5:3 ratio concrete. After
learning this process you will be able to estimate materials for
any concrete ratio.
Now lets estimate the required materials for the volume of 100
cft concrete of 1:1.5:3 ratio:
Wet volume of concrete = 100 cft.Dry volume of concrete= 100 x
1.54 = 154 cft.Sum of ratio 1:1.5:3, 1 + 1.5+ 3 = 5.5.So, Cement
content in concrete = (154/5.5) x 1=28 cft.Sand content= (154 /
5.5) x 1.5 = 42 cft.Stone chips = (154/5.5) x 3 = 84 cft.
As we know, Cement is available as 50 kg bag in the market. The
volume of 50 kg cement bag is 1.25 cft. So the required cement is
28 divided by 1.25 equal to 22.4 bag.
Summary:Cement : 22.4 bag,Sand : 42 cft,Stone chips: 84 cft.
In this estimation, we use cubic feet as our concrete unit. If
you want to use cubic meter, same method can be applied. But that
will be time-consuming. The easiest way to estimate concrete
materials for different unit is, apply the above result as
percentage. That means,Cementcontent for 100 unit of 1:1.5:3 ratio
concrete is 28% (unit will be as concrete unit),Sandis 42% andStone
chipsis 84%.
Now lets calculate the water content of concrete. Suppose,
water-cement ratio for concrete is specified 0.45. That means,
water/cement = 0.45, or W/C = 0.45.for 1 bag cement, water is, =
0.45 x 1.25 (as we know, 1 bag cement equal to 1.25 cft),Water =
0.5625 cft.We know 1 cubic feet water is equal to 28.31685 litre,So
we can write, water = 0.5625 x 28.31685 = 15.92 litre, say, 16
litre.So One bag cement needs 16 liter of water for 0.45 W/C
ratio.That's it.
Here, one thing should be cleared that someone assume the dry
volume of concrete is equal to one and half times of wet volume.
But it is better to use 1.54 for calculating dry volume.
Defects in Brick Work and their Remedies
"sulphate attack on mortars, unsound materials, frost action,
corrosion of iron and steel, crystallization of salts, linear
changes resulting from variation in moisture content"While doing
brickwork and after the brick is completed there are certain
defects which has to be faced, these defects they must be avoided
and remedial measure must be taken. These defects not only ruins
the physical quality andaestheticsof the project but also ruins its
structuralstrength. So to avoid any mishap and loss we must know
what are certain defects in brick work and how to avoid them.
Common defects occurring in Brick work are; sulphate attack on
mortars, unsound materials, frost action, corrosion of iron and
steel, crystallization of salts, linear changes resulting from
variation in moisture content.
Sulphate attack on mortarsSulphate attack leads to expansion of
mortar, thereby causing cracking of brickwork, spalling of brick
edges, deterioration of mortar, wide horizontal and vertical cracks
in the plaster and falling of the plastered surface.
The cause of this attack is the chemical action between the
sulphate salts in bricks and constituents of Portland cement.
Sulphate Attack on Bricks
This action is rapid in the presence of water and hence wherever
moisture penetrates, excessive dampness occurs. This type of defect
may be prevented by preventing moisture penetration. It will avoid
the defect to a large extent. Bricks of low sulphate content and
the sulphate resisting cement should be used.
Unsound MaterialsUnsound materials cause the formation of small
pits at the mortar joints. General expansion and cracking of brick
work is visible. Unsoundness in lime is caused by the presence of
un-slaked particles of lime. Similarly un-slaked lime particles may
be present in the bricks also.
Unsound Material
Frost actionDefects due to frost action would cause cracking in
brickwork. Prevention of water accumulation would prevent this
defect.Corrosion of MetalsBrickwork may get opened or cracked or
stained due to corrosion of metals lying adjacent to it.
Unprotected iron and steel are liable to get corroded when acted
upon by moisture and they increase in bulk, thereby causing cracks
in masonry.
Corrosion of Bricks due to Metals
Protecting the metal surface with cement mortar up to a layer of
1 to 2 cm thick is essential to prevent corrosion. Partially
embedded steel or iron members should be surrounded with bituminous
compound for portions not embedded in mortar.
Metal Corrosion
Crystallization of Salt and EfflorescenceThis is a prominent
defect in brick masonry. In moist climate, in damp places, like
basements or under leaky gutter, masonry often gets disfigured by
the formation of a white deposit called efflorescence. Deposit
originates from the mortar and frequently spreads over a part or
entire face of the wall.
Efflorescence
Absorbed water dissolves the salts of sodium, potassium and
evaporating, forms a crystalline deposit on the surface. In
addition to unsightly appearance, the crystallization of salts in
the pores of the bricks or mortar may cause disruptive expansion
resulting in disintegration due to cracking.To avoid Efflorescence
do not use porous bricks in contact with limestone. Protect
brickwork against contamination of salt-bearing materials during
building operations. Bricks should be thoroughly soaked during
construction. Correct design of DPC should be used.Shrinkage
EffectsBrick work may crack due to the shrinkage movements arising
from changes in moisture content. This defect is more common with
concrete and lime mortars.
Shrinkage Effects
10+ FIELD TIPS FOR INSPECTION OF REBARS OR REINFORCEMENT
Good quality bricks should be used in dry condition. All of work
should be protected from rain.
In construction of a mega project there is always insightful
sort of technicalities involved which has to be checked /
identified technically. The process demands a sound technical
engineering judgment and careful observation. Reinforced Cement
Concrete, despite of other important checks, needs to be checked
for rebar against the provided construction drawings / shop
drawings or technical specifications.It must be kept in mind that
the difficulty and cost involved in this activity makes it
vulnerable for shortcomings from the contractors end and it needs
to be rectified / adjusted by a sound consulting firm deputing on
the inspection of execution.
Inspection of Steel Rebar
No doubt it needs experience and also needs know-how of the
steel rebar binding process. But here are some of the tips from top
peers who are doing this in the field for years :-a.Start from the
drawings, one must be well aware of how to read a rebar drawing. As
drawings is a language for engineers one must know how to
communicate with it in the field. Make a habit of reading drawings
that will be your first step towards a successful rebar
checker.b.Always keep a measuring tape with yourself that will help
you in checking the spacing as well as the splice length or
development length.c.Always wear plastic gloves while inspection
because holding steel with naked hands will damage the skin of
yours badly.d.You must be well aware of the physical features of
the construction component i.e. if some sort of drainage pipe or
electrical conduit is to be installed or water stopper to be placed
or any other pipes / embedded item to be placed.e.Some important
things one must check are the rebar diameter You can use vernier
caliper for this purpose, rebar spacing, rebar development length,
lap / splice length, alignment or rebar there must be no sag or
buckling in the bars, couplers if any must be properly fixed
tightened, bars must be properly fixed, bars must not be rusted,
clear cover is one very important factor to be checked, no of bars
must be counted and must be equal to given in drawings and must not
be less or more than 2 bars be placed there.f.If you are a new
comer try to establish a conversation between contractors foreman
or site engineer because they will know how these bars are placed
but never every show to them that you dont know much and are here
to learn things.g.You must be well aware of the steel quality tests
like tensile strength check or torsion failure strength or coupler
tension strength check etc. You must ensure that the steel being
used is from the checked lot and must not be of a failed
quality.h.No doubt in field a true implementation of the design is
very difficult due to harsh field conditions and difficultly in
installation / fixing of rebars but never ever compromise with the
design as it is a driving factor that can even results in collapse
of a building if completely ignored / violated.i.One very important
factor is the orientation of bars like main rebars are always below
the distribution or temperature rebars you can check this from the
drawings provided to you.
So we can say that in a nutshell one must be very keen observer
and should be well conversant with the design methodology and sound
technical knowledge.
Checking of rebars is not difficult neither never testing
process so dont get confused or get upset with your duty enjoy the
work and let the structure have its strength as it is designed.
NotesPage 26