CIVIC CENTER MASTER PLAN STUDY David Barry, Capital Projects Manager Facilities and Fleet Department October 29, 2012
CIVIC CENTER MASTER
PLAN STUDY
David Barry, Capital Projects Manager
Facilities and Fleet Department
October 29, 2012
FORMER SAN JOSE CITY HALL
10/29/12 Facilities and Fleet Department 2
EARLY CIVIC CENTER PLAN
10/29/12 Facilities and Fleet Department 3
BOARD OBJECTIVES (Accepted by BOS on June 19, 2012)
1. Efficiency of Government
2. Highest & Best Use (Maximization of Land Value)
3. Revenue Generation
4. Sustainability Goals (Minimize Environmental Impacts)
10/29/12 4 Facilities and Fleet Department
PROJECT TIMELINE
Research & Analysis
Former City Hall Re-Use Study
Existing Conditions Report
County Facilities Survey
Market Analysis P3 Case Studies Developer Panel
10/29/12
Concepts & Strategies
Preliminary Site Concepts
Draft Ordinance
Direction
Board
Considers Ordinance Allowing for Developer Selection Process
RFQ/RFP for Consultant Team
JUN – OCT 2012 OCT – NOV 2012 DEC – JAN 2013
Facilities and Fleet Department 5
DEVELOPER FEEDBACK
• Site Marketability: “B” or “B+”
• Single-Tenant User Demand ≥600K SF
• Establish County’s Long-Term Strategic Plan
• Maintain Flexibility w/ Land Use
10/29/12 Facilities and Fleet Department 6
PRELIMINARY OPTION 1
10/29/12 Facilities and Fleet Department 7
PRELIMINARY OPTION 3
10/29/12 Facilities and Fleet Department 8
REVISED OPTION 1a
10/29/12 Facilities and Fleet Department 9
REVISED OPTION 3a
10/29/12 Facilities and Fleet Department 10
LAND USE OPTION 1a
10/29/12 Facilities and Fleet Department 11
LAND USE OPTION 3a
10/29/12 Facilities and Fleet Department 12
POTENTIAL SITES
10/29/12 Facilities and Fleet Department 13
STAFF RECOMMENDATIONS
• Adopt Ordinance Allowing for Developer Selection Process
• Select Consultant Team
• Issue Developer RFQ/RFP(s)
• Seek Exclusive Negotiation Agreement with Developer(s)
10/29/12 14 Facilities and Fleet Department
COUNTY TASKS
• Identify Range of County Office and Training Space Required at the Civic Center
• Return on Investment Analysis – Consolidating Gov’t Services & Former City Hall Acquisition Cost
• Outreach to Developers Local and Nationwide
• Evaluate West Wing Historic Significance
• Parking Needs for County Services
• Project Phasing
10/29/12 Facilities and Fleet Department 15
COMING IN DECEMBER
• The Board will be asked to adopt an ordinance in December allowing for an RFQ / RFP process to obtain one or more developer’s proposals for one or more Civic Center land parcels.
10/29/12 Facilities and Fleet Department 16
NEXT STEPS
10/29/12 17
Seek proposals from consultant teams to advise the County
Consultant Team
RFQ/RFP
Evaluate consultant proposals and bring to the Board
Consultant Team
Selection
Solicit proposals for one or more parcels
Developer RFQ / RFP
Facilities and Fleet Department
NEXT STEPS
10/29/12 18
Interested Developers will have 60 days to submit proposals
Developer Response
Period
Review developer responses & present to the Board in a public workshop
Developer RFQ/RFP
Evaluation
The Board may authorize negotiating an Exclusive Negotiation Agreement (ENA)
Developer
ENA
Facilities and Fleet Department
NEXT STEPS
10/29/12 19
Land planning, architectural design, CEQA, Entitlements, Etc.
ENA: Developer
Due Diligence
Board may enter into a DDA negotiation with one or more developers
DDA Negotiations
First occupancy no earlier than late 2015 or early 2016
Development and
Construction
Facilities and Fleet Department
NEXT STEPS
10/29/12 20
Future Civic Center
DEVELOPMENT AND CONSTRUCTION
First occupancy should be expected no earlier than 3 to 5 years, subject to market changes or project phasing.
Facilities and Fleet Department
Thank You For Your Attention