Top Banner
CITY OF KIRKLAND Department of Public Works 123 Fifth Avenue, Kirkland, WA 98033 425.587.3800 www.kirklandwa.gov MEMORANDUM To: Kurt Triplett, City Manager From: Dave Snider, P.E., Capital Projects Manager Kathy Brown, Public Works Director Date: July 23, 2015 Subject: ANNUAL STREET PRESERVATION PROGRAM 2014 PHASE II STREET OVERLAY PROJECT – ACCEPT WORK RECOMMENDATION: Staff recommends that the City Council take the following actions: Accept the work on the 2014 Street Preservation Program – 2014 Phase II Street Overlay Project, as completed by Watson Asphalt Paving Co, Inc., of Redmond, WA, and establish the statutory lien period, and Authorize the use of surplus 2014 Street Preservation funds for use on the 2015 Street Preservation Program and/or the NE 85 th Street Overlay Project, as needed. By taking action on this memo during approval of the consent calendar, City Council is accepting the contract work completed for the 2014 Phase II Street Overlay Project and authorizing reallocation of surplus overlay funds. BACKGROUND DISCUSSION: The 2014 Street Overlay Project is Phase II of the Annual Street Preservation Program for the maintenance and rehabilitation of the City’s street network. The Project included subgrade preparation and repair, asphalt grinding, and the application of a new surface layer of asphalt. The 2014 Street Overlay Project included seven schedules of work, resulting in the resurfacing of approximately 11.6 lane miles of roadway (Attachment A). Phase I of the Annual Street Preservation Program was the Curb Ramp & Concrete Repairs Project, which was accepted by the Council at its January 20, 2015 meeting. The Phase III Project of the Annual Program is the Slurry Seal Project, which was also accepted by the Council at the January 20 meeting. The total budget for the 2014 Annual Street Preservation Program is a combination of three revenue sources, including the base CIP funding, Proposition 1 Levy funds, and a City Council approved carry-over from the 2013 program, as follows: Council Meeting: 08/03/2015 Agenda: Other Business Item #: 8. h. (2)
4

CITY OF KIRKLAND Department of Public Works 123 Fifth ...Council/Council+Packets/080315/8… · Watson Asphalt Paving Co., Inc., in the amount of $2,780,964.70. The construction began

Jun 06, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CITY OF KIRKLAND Department of Public Works 123 Fifth ...Council/Council+Packets/080315/8… · Watson Asphalt Paving Co., Inc., in the amount of $2,780,964.70. The construction began

CITY OF KIRKLAND Department of Public Works 123 Fifth Avenue, Kirkland, WA 98033 425.587.3800 www.kirklandwa.gov

MEMORANDUM To: Kurt Triplett, City Manager From: Dave Snider, P.E., Capital Projects Manager Kathy Brown, Public Works Director Date: July 23, 2015 Subject: ANNUAL STREET PRESERVATION PROGRAM 2014 PHASE II STREET OVERLAY PROJECT – ACCEPT WORK RECOMMENDATION: Staff recommends that the City Council take the following actions:

• Accept the work on the 2014 Street Preservation Program – 2014 Phase II Street

Overlay Project, as completed by Watson Asphalt Paving Co, Inc., of Redmond, WA, and establish the statutory lien period, and

• Authorize the use of surplus 2014 Street Preservation funds for use on the 2015 Street Preservation Program and/or the NE 85th Street Overlay Project, as needed.

By taking action on this memo during approval of the consent calendar, City Council is accepting the contract work completed for the 2014 Phase II Street Overlay Project and authorizing reallocation of surplus overlay funds. BACKGROUND DISCUSSION: The 2014 Street Overlay Project is Phase II of the Annual Street Preservation Program for the maintenance and rehabilitation of the City’s street network. The Project included subgrade preparation and repair, asphalt grinding, and the application of a new surface layer of asphalt. The 2014 Street Overlay Project included seven schedules of work, resulting in the resurfacing of approximately 11.6 lane miles of roadway (Attachment A). Phase I of the Annual Street Preservation Program was the Curb Ramp & Concrete Repairs Project, which was accepted by the Council at its January 20, 2015 meeting. The Phase III Project of the Annual Program is the Slurry Seal Project, which was also accepted by the Council at the January 20 meeting. The total budget for the 2014 Annual Street Preservation Program is a combination of three revenue sources, including the base CIP funding, Proposition 1 Levy funds, and a City Council approved carry-over from the 2013 program, as follows:

Council Meeting: 08/03/2015 Agenda: Other Business Item #: 8. h. (2)

Page 2: CITY OF KIRKLAND Department of Public Works 123 Fifth ...Council/Council+Packets/080315/8… · Watson Asphalt Paving Co., Inc., in the amount of $2,780,964.70. The construction began

Memorandum to Kurt Triplett July 23, 2015

Page 2

Revenue Source Amount 2013-2018 base CIP $1,750,000 Prop 1 Levy funds $2,574,000 2013 Carry-over $240,807 TOTAL $4,564,807

At its regular meeting of July 1, 2014, Council awarded the 2014 Street Overlay Project to Watson Asphalt Paving Co., Inc., in the amount of $2,780,964.70. The construction began on July 21, 2014 and the work was substantially complete in May 2015 after enduring a winter-weather suspension of the construction activities. The project was fully completed on June 12, 2015 after the contractor finished all outstanding punch list work items. The total of all payments made to the contractor was $2,659,499.63. The reduced contract amount was the result of bid item quantities being less than originally estimated. With all costs known for all three phases of the Annual Street Preservation Program, the currently anticipated expenses for the entire 2014 Street Preservation Program are as follows:

Phase Status ORIGINAL Amount

FINAL Amount

TOTAL BUDGET $4,564,807 $4,564,807 Phase I Curbs and Ramps Accepted 1/20/2015 ($383,567) ($349,588) Phase II Overlay Awarded Accept – This Memo ($2,780,965) ($2,659,500) Phase III Slurry Seal Accepted 1/20/2015 ($ 496,081) ($462,242) Eng., Admin., Inspect., Outreach Complete ($ 680,000) ($530,968) Paving, City Crews (NE 132nd St) Complete ($35,000) ($26,258) Remaining Balance $ 189,194 $536,251

The 2014 Street Overlay Project (Phase II) is the final Phase for the 2014 Street Preservation Program. With City Council’s acceptance of the work on this Project, together with all changes from all Phases presently accounted for, over $500,000 remains in the overall budget and staff recommends all remaining funds be transferred to the 2015 Street Preservation Program (Attachment B). Staff recommends that these funds be made available for any potential 2015 street preservation budget needs, including the potential need for the additional overlay work on NE 85th Street, as identified in a separate memo for the August 3, 2015 City Council meeting.

Attachment A: Vicinity Map Attachment B: Project Budget Report – Phase II

Page 3: CITY OF KIRKLAND Department of Public Works 123 Fifth ...Council/Council+Packets/080315/8… · Watson Asphalt Paving Co., Inc., in the amount of $2,780,964.70. The construction began

Redmond

BellevueYarrow Point

Seattle

Hunts Point

S I 40

5

N I 4

05

132N

D AV

E NE

NE 124TH ST

NE 132ND ST

3RD

ST

124T

H AV

E NE

CROS

S KIRK

LAND

CORR

IDOR

4TH

STNE 116TH ST

NE 85TH ST

2ND

ST

116T

H AV

E NE

MARK

ET ST

7TH AVE

84TH

AVE N

E

9TH AVE

NE 60TH ST

NE 128TH ST

NE 80TH ST

108T

H AV

E NE

NE JUANITA DR

98TH

AVE N

E

15TH AVE

5TH

ST

6TH

ST S

120T

H AV

E NE

19TH AVE

LAKE ST S

NE 100TH ST

FORBES CREEK DR

NE 70TH ST

NE 75TH ST

130T

H AV

E NE

5TH AVE W

STAT

E ST S

NE 126TH PL

LAKE

VIEW

DR

8TH

ST S

NE 95TH ST

SLAT

ER AV

E NE

TOTEM LAKE BLVD

NE 120TH ST

S I 40

5ONR

AMP

KIRKL

AND W

AY

6TH ST W

13TH AVE

NE 104TH ST

4TH AVE

136T

H AV

E NE

8TH

ST

6TH

ST

93RD

AVE N

E

87TH

AVE N

E

LAKE AVE W

5TH ST W

122N

D AV

E NE

111T

H AV

E NE

86TH

AVE N

E

104T

H AV

E NE

94TH

AVE N

E

90TH AVE NE

N I 4

05ON

RAMP

10TH

ST W

NE 107TH PL

106T

H AV

E NE

NE 112TH ST

NE 90TH ST

9TH AVE S

NE 118TH ST

114T

H AV

E NE

NE 116TH PL

112T

H AV

E NE

WILL

OWS R

D NE

5TH AVE

NE 65TH ST

10TH AVE S

NE 62ND ST

128T

H AV

E NE

89TH

PL N

E88

TH PL

NE

NE 136TH ST

NE 109TH PL

129T

H PL

NE

109T

H AV

E NE

100T

H AV

E NE

113T

H AV

E NE

1ST S

T

NE 73RD ST

NE 88TH ST

NE 129TH ST

126T

H AV

E NE

NE 121ST ST125TH DR NE

NE 123RD ST

NE 112TH PL

NE 109TH LN

NE 59TH ST

NE 91ST ST

NE 61ST ST

7TH ST W

20TH AVE

98TH

AVE N

E

NE 91ST ST

6TH

STNE 112TH ST

120T

H AV

E NE

116T

H AV

E NE

100T

H AV

E NE

120T

H AV

E NE

5TH

ST

132N

D AV

E NE

NE 120TH ST

H:\Pw\CIP group\Project Files\ST\CST0006\CST1406\SCOPE\Overlay Scoping\2014 Overlay Accept.mxd Produced by the City of Kirkland. © 2015, the City of Kirkland, all rights reserved. No warranties of any sort, including but not limited to accuracy, fitness or merchantability, accompany this product.

0 2,480Feet

0 0.4Miles

©

Schedule AIncludesProject-WideBid Items

Author: Name In Map Doc PropertiesName: 2014 Overlay Accept

Date Saved: 7/13/2015 2:06:16 PM

I5 I1

J1I7 I3 I2I4

J5

I6

J2J6J7 J3J8 J4

L1

J0

L6 L2

I8

La

F1

J9

L0

F4

L5 L4

F2

L7 L3L9 L8

F3F5

KaK1

E2E4E5 E1

C4

K6

E3

C2

K2

C3

N1

C5

K7K9 K8 K0K4 K3

B4

K5

B3B5

A4

C1

B2

H5

N5

A5

H1

O2

D2

N2

D1

N4

M1

D0

N7N8

H2

D4D5

G5

H4 H3

D3

G1

N3

G4 G3

N6

G2

H6

O3

M2 MaM4M9 M5 M0M7M8 M3M6

H7

PROP 1 FUNDEDCIP FUNDEDParks / Open Spaces

Schools

Cross Kirkland CorridorRegional Rail CorridorCity Limits

Text

City CrewsNE 132nd St

Schedule BNE 124th St

Schedule CNE 116th St

Schedule ENE 112th St

Schedule E120th Ave NE

Schedule F132nd Ave NE

Schedule GLake Washington Blvd

Vicinity Map2014 Street Overlay Project

Schedule Street From ToB NE 124th St 116th Ave NE 124th Ave NE

C NE 116th St 108th Ave NE 120th Ave NE

D 120th Ave NE End (South) NE 118th St

E NE 112th St 112th Ave NE 120th Ave NE

F 132nd Ave NE NE 100th St NE 113th St

G Lk Wash Blvd Lakeview Dr 10th Ave S*

City Crews NE 132nd StPavement repairs under I-405

overpass

ATTACHMENT A

Page 4: CITY OF KIRKLAND Department of Public Works 123 Fifth ...Council/Council+Packets/080315/8… · Watson Asphalt Paving Co., Inc., in the amount of $2,780,964.70. The construction began

CIP$1,750,000

PROP 1 LEVY$2,574,000

$- $1,000,000 $2,000,000 $3,000,000 $4,000,000 $5,000,000

FUNDING SOURCES

ACCEPT WORK

AWARD CONTRACT

APPROVED BUDGET

ESTIMATED COST

PHAS

EProject Budget Report

ENGINEERING

CONST - CURB RAMP & CONCRETE REPAIRS(PHASE I)CONST - OVERLAY (PHASE II)

CONST - SLURRY SEAL (PHASE III)

2014 Street Overlay Project(ST-1406)

(July 2014)

$4,564,807

(2013-2018 CIP)

ATTACHMENT B

CITY CREWS(NE 132nd St)$35,000

2013 Carry Over$240,807

CITY CREWS(NE 132nd St)$26,258

(This Memo)

2013 Carry Over$240,807

Available for Future Styreet Preservation

Efforts