FORM CM-3 7 March 1, 2011 AGENDA ITEM CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT AGENCY 900 Grand Central Avenue - WOI Machine Shop: Approval of Stage I & II Design 1) Agency Motion to Approve Stage [& II Design AGENCY ACTION Public Hearing [ X J Ordinance [ J Consent Calendar [ J Action Item [ J Report Only [ J Approved !>/I \ II ca lendar ADMINISTRATIVE ACTION Submitted Hassan Haghani, Community Development Director .............. .... . Castillo, Project Manager ..... ............... ........ ........ ........... ..... APprovJea':nes E. Starbi rd , Executive Director ......................................... Reviewed Phi li p Lanzafame, Chief Assistant Director of Community Development .............................................................. Scott Howard, City Attorney ........................................................ . Alan Loomis , Princi pal Urban Designer ........................................ RECOMMENDATION It is recommended that the Agency approve Stage I & II Desi gn for 900 Grand Cent ral Avenue - WDI Mach i ne Shop. 6 C
19

CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

Apr 27, 2018

Download

Documents

nguyennhi
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

FORM CM-37

March 1, 2011

AGENDA ITEM

CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT AGENCY

900 Grand Central Avenue - WOI Machine Shop: Approval of Stage I & II Design

1) Agency Motion to Approve Stage [& II Design

AGENCY ACTION

Public Hearing [ X J Ordinance [ J Consent Calendar [ J Action Item [ J Report Only [ J

Approved !>/I \ II calendar

ADMINISTRATIVE ACTION

Submitted ~Signatre •

~~" Hassan Haghani, Community Development Director .............. .... . ~"L--=-----r--'--6''---

Prepar~~en Castillo , Project Manager ..... ............... ........ ........ ........... ..... ~~

APprovJea':nes E. Starbird , Executive Director ......................................... ~.A~~ Reviewed

Philip Lanzafame, Chief Assistant Director of Community Development .............................................................. ~-:;;j,~::-:ll~~~s;::,.....;

Scott Howard, City Attorney ..... .... ............................................... .

Alan Loomis, Principal Urban Designer ........................................ A~'f:1'1::.::=:;~~=-

RECOMMENDATION

It is recommended that the Agency approve Stage I & II Design for 900 Grand Central Avenue - WDI Machine Shop.

6 C

Page 2: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

SUMMARY & BACKGROUND

900 Grand Central Avenue WDI Machine Shop

Stage 1&11 Design March 1, 2011

Page 2 of 3

In 2000, an Owner Participation Agreement (OPA) and a Development Agreement (DA) was approved between the City of Glendale (City), the Glendale Redevelopment Agency (Agency) and Walt Disney World Company (Disney) to develop a 125-acre high-tech creative campus including a mix of media­related uses, a renovated Grand Central Air Terminal and public infrastructure improvements located within the San Fernando Road Corridor Redevelopment Project Area (the Grand Central Creative Campus or "GC3"). Using a Scope of Development to set standards for development, GC3 will be built according to market demand over 30 years.

PROJECT LOCATION AND DESCRIPTION

The Project is located within the Disney Grand Central Creative Campus (GC3) at 900 and 932 Grand Central Avenue, at the southeast corner of Grand Central Avenue and Flower Street. The Project is adjacent to older, tilt-up concrete warehouse and office buildings on the north and west sides.

The Project will demolish the 932 Grand Central Avenue building, occupy the existing concrete tilt-up building at 900 Grand Central Avenue and add additional square footage to that building to accommodate the proposed WDI Machine Shop. The building will house the machine shop where theme park attractions will be constructed. This includes shops for metal, welding, wood, plastic, paint, hydraulic and electrical. A new parking lot will replace the existing 932 Grand Centra l building. The parking lot will be fenced and new landscaping and irrigation will be provided.

STAGE I & II DESIGN REVIEW

The existing 900 Grand Central building is a standard concrete tilt-up panel bu ilding. The bui lding addition along the Flower Street side (south/east corner) will be constructed with a smooth stucco finish to blend with the existing concrete building . The new building on the west side is a pre-fabricated metal building with the use of textured panels on the lower portion and a standard corrugated metal panel above (Exhibit 1).

The selected colors are Disney's standard "Terra Cotta", "Lite Creme" and "Creme Green". The entire building wi ll be painted Terra Cotta on the lower portion and Lite Creme above. All doors, windows and handrails will be painted Creme Green. The roof screens on the existing 900 Grand Central Building will be painted Lite Creme.

A 7'-0" tall chain link fence with a green screen wi ll be constructed along the perimeter of the parking lot. Near the entry gate, a new CMU wall will be constructed and finished with a smooth stucco finish on both sides. Trees and other landscape items will be planted in the area between the sidewalk and the building. All new exteri or lighting is specified to be LED and in dark bronze finish.

The Project is a simple one-story building , finished in a restrained palate of materials. The scale, setbacks, finishes and colors of the structure are within the parameters established by Disney's Development Agreement and similar structures on the Disney campus. The Project will enhance existing setbacks and landscape, and will provide an obvious front door to what is currently an unadorned industrial warehouse with no street presence. The Project is supported without conditions or comments.

A design analysis reviewed by the Principal Urban Designer is attached as Exhibit 2 to this report.

Page 3: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

ENVIRONMENTAL REVIEW

900 Grand Central Avenue WDI Machine Shop

Stage 1&11 Design March 1, 2011

Page 3 of 3

The Proposed Project is consistent with the original plans and Project Description analyzed in the GC3 Project Environmental Impact Report (GC3 EIR) certified and approved in 2000. The GC3 EIR thoroughly evaluated the potentially significant environmental project impacts consistent with the Californ ia Environmental Quality Act (CEQA).

The GC3 EIR was drafted consistent with the Agency's own environmental analysis for the San Fernando Road Corridor Project Area EIR drafted in 1992. Many of the same impacts related to the GC3 Project such as air quality, water quality, noise, transportation I circulation and public services were analyzed in both the Project Area EIR, but in greater and more project-specific detail in the GC3 EIR. In addition, the benefits of the Project as part of redevelopment project area were identified , including: blight elimination, facilitating the installation of needed public infrastructure, utilities, streets and landscaping (paid by Project tax increment), encouraging new private sector investment and facilitating the retention and expansion of businesses in the area.

The background conditions were thoroughly evaluated in the EIR. These background cond itions included major mobility and safety improvements now nearing completion at SR-134 or 1-5 and other projects like the second phase of DreamWorks. In addition to these projects, general growth of approximately one percent a year to background traffic was assumed in the GC3 Er R. Since the approval of GC3 ErR was approved, there has been little to no other impact generating projects beyond the existing already analyzed as part of the background conditions. In fact, traffic levels now are lower than what was anticipated in the GC3 ErR.

There have been no significant changes to the local background conditions. Accordingly, no additional CEQA review is required for the subject Project.

PUBLIC NOTICE

The Code requires publication of public noti ces when the Council/Agency is to consider approval of entitlements such as an MND and design review. Staff has published all required notices in the Glendale News Press and has mailed copies of the notices to all property owners within the 500' of the project. In addition, notice of the hearing was mailed to approximately 250 individuals who have expressed interest in Agency activities. A public notice has also been posted on-site.

FISCAL IMPACT

This Project will generate direct and indirect revenue to the City and the Redevelopment Agency.

EXHIBITS

Exhibit 1: Stage I & II Design Exhibit 2: PrinCipal Urban Designer's Comments

Page 4: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

MOIlON

Moved by Agency Member __________ " seconded by Agency

Member _ ________ , that the Stage I & II Final design for the Walt Disney

Imagineering CWOI") Machine Shop located at 900 Grand Central Avenue be, and the

same is hereby approved as outlined in the staff report from the Director of Community

Development dated March 1, 2011, including comments and recommendations from

the C ity's Urban Designer incorporated therein, and subject any Agency comments

and/or conditions thereon.

Vote as fo llows:

Ayes:

Noes:

Absent:

Abstain :

Gener ~?~f~tP Date: ....:::.Le~!...::.!... ___ _

J : \FIL£ S\OOCf"I L<:S\M'I'N\WUl Machine Sho p St age I , II mt n. wpd

6 c 1

Page 5: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

CORE SERVICES 500 S. BUENA VISTA STREET. BURBANK. CALI FORNIA 9152 1 PHONE: 818-560- 1387 CONTACT: BRETT MATTINSON EMAIL: [email protected]

INTERIORS AND ARCHITECTURE 836 SOUTH ARROYO PARKWAY PASADENA. CA. 91105 PHONE: [626] 449- 6222 FAX: [626] 449-2775 CONTACT: JIMMIE DYER EMAIL: [email protected]

IER'3IFIII,D INC. 1241 NORTH BARSTEN WAY ANAHEIM. CA 92806 PHONE: [714] 632-0929 FAX: [714] 632-0930 CONTACT: KYLE D. JACKSON EMAIL: KJackson@dps- sc.com

650 SIERRA MADRE VILLA. SUITE 300 PASADENA. CA 91107 PHONE: [626] 432- 5850 FAX: [626] 432-5858 CONTACT: JOHN KELLY EMAIL: [email protected]

439 WESTERN AVeNUe GLENDALE. CA 91201 PHONE: [818] 240-9600 FAX: [626] 240-9675 CONTACT: MICHAEL A. CAZENEUVE EMAIL: [email protected]

Disney Core Services WDI Research and Development 900 Grand Central Glenda le, Co. 91201

Issued for Design Review

View From Grand Central Looking West

Feb ru a ry 22, 201 1

View From Flower Street Looking East Along Grand Central

844 East Green Street, Suite 201 Pasadena. CA pHONE: [626] 795.2008 PHONE: [626] 795-2547 CONTACT: SCOTT HORSLEY EMAIL:[email protected]

I 650 SIERRA MADRE VILLA. SUITE 300 PASADENA. CA 91107 PHONE: [626] 432-5850 FAX: [ 626] 432-5858 CONTACT: LES SCHULZ EMAIL: [email protected]

814 ALLEN AVENUE GLENDALE, CA 91201 PHONE: [818] 303-9150 FAX: [818] 303- 9160 CONTACT: SEAN HAVEY

INC.

EMNL: [email protected] CONTACT: A1isher Yunusov (EL) EMAlL: [email protected]

3200 PLAYERS CLU8 CIRCLE MEMPHIS. TN 38187

LOCAL 8UILDER KNIGHT 8UILOING SYSTEMS 3421 GILLESPIE AVE. ACTON. CA. 93510 PHONE: [ 661] 257-9407 FAX: [661] 257- 0068 CONTACT: JOHN KNIGHT FAX:

Page 6: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

LANDSCAPE SUMMARY 900 GRAND CENTRAL SITE: 70,870 GSF

931 GRAND CENTRAL SITE: 43,719 GSF

RAILWAY SPUR SITE: 17,181 GSF

TOTAL SQUARE FOOTAGE OF NEW 900 GRAND CENTRAL LOT: 131,871 GSF

AREA OF NEW PARKING: 41,581 GSF

lANDSCAPE REQUIRED: 5 PERCENT OF 41,581 SF = 1,119 SF

lANDSCAPE PROVIDED: 3,644 SF

TREES REQUIRED:

99 TOTAL PARKING STALLS, (I) TREE FOR EVERY 5 STALLS>

TREES REQUIRED: 99 / 5 = 20 TREES REQUIRED

TREES PROVIDED: 13 TREES IN THE PARKING AREA.

PARKING SUMMARY 1 PER 1000 FOR THE FIRST 15,000 SF: 15,0000/1000 = 15 x 1 = 50 STAllS

1.5 PER 1000 FOR THE SECONO 25,000 SF: 15,0000/1000 = 15 x 1.5 = 38 STALLS

1.15 PER 1000 ABOVE 50,000 SF: 6,400/1000 = 6.4 x 1.15 = 8 STALLS

TOTAL REQUIRED: 96 STALLS

((4) MUST BE HANDICAP STALLS)

PROVIDED ON PlAN: 97 STALLS

RESTROOM SUMMARY GROSS SQUARE FOOTAGE: 56,025

F-I OCCUPANCY: (PER TABLE A GROUP F LOAD FACTOR 2000)

56,038 / 2000 = 28.0 = 18 OCCUPANTS

28 / 2 = 14 MEN ANO 14 WOMEN

PER TABLE 4-1: WATER CLOSETS URINALS LAVATORIES

REQUIRED:

MEN: 2 0 2

WOMEN: 1 0 1

PROVIDED:

MEN: 1 1 2

WOMEN: 4 0 2

BUILDING SUMMARY SITE ADDRESS: 900 GRAND CENTRAL AVENUE

RI ~ CITY OF GLENDALE ENGINEERING DEPT. FIELD BOOK R1 ~ PARCEL MAP -GLN NO.1255 MB.83 PG.50-61 RJ = TRACT MAP NO.2J952 MB.669 PC,/4-15

R4 = R/S MB./67 PC.56- 6J

EXISTING 900 FLOWER CROSS SQUARE FOOTAGL 35,260

EXPANSION SPACE, GROSS SQUARE FOOTAGE: 14,784 MAIN EXPANSION SPACE

1,732 PAINT AREA ON WEST

2,982 EAST SlOE EXPANSION

I ,280 COVERED EXTERIOR ROOFING

TOTAL NEW BUILDING: 20,778

NEW BUILDING GROSS SQUARE FOOTAGE: 56,038

OCCUPANCY TYPE: F- I, TYPE III-B

PROJECT DESCRIPTION: THE PROPOSED PROJECT IS TO USE THE EXISTING CONCRETE TILT UP BUILDING AT 900 GRAND CENTRAL, DEMOLISH THE EXISTING EXISTING BUILDING AT 932 GRAND CENTRAL AVENUE AND ADD ADDITIONAL SQUARE FOOTAGE THE 900 GRAND CENTRAL BUILDING TO ACCOMMODATE THE PROPOSED WDI MACHINE SHOP THAT IS TO BE RE- LOCATED FROM NORTH HOLLYWOOD. THE SCOPE OF WORK IS TO CONSTRUCTION 20,765 OF NEW BUILDING BUILDING ADJACENT TO THE EXISTING BUILDING. THE NEW BUILDING IS BEING PROPOSED TO BE PRE -FABRICATED METAL BUILDING WITH A SMOOTH STUCCO FINISH ON THE LOWER SECTION AND A CORRUGATED METAL ABOVE 9'-2.5" THE ROOF WILL BE A NEW SEAMED METAL ROOF. THE FUNCTION OF THE SPACE IS MACHINE SHOP THAT CONSTRUCTS PROPHETICAL THEME PARK ATIRACTIONS THAT WILL BE PLACED IN THE THEME PARKS. THIS INCLUDES METAL SHOPS, WELDING, WOOD SHOP, PLASTICS AND PAINTS AND HYDRAULICS AND ELECTRICAL SHOPS .. NEW PARKING WILL BE PROVIDE ADJACENT IN THE AREA WHERE THE EXISTING 932 BUILDING IS CURRENTLY STANDING. THE PARKING WILL BE PROVIDED WITH A FENCE TO SECURE THE PROPERTY AND NEW LANDSCAPING AND IRRIGATION.

MAXIMIUM BUILDING ALLOWED F- I BUILDING, TYPE II I THE MAXIMIUM SIZE OF BUILDING ALLOW IS 12,000 SQUARE FEET

WITH FULL AUTOMATIC FIRE SPRINKLER WE CAN HAD AN ADDITIONAL 36,000 SQAURE FEET.

THUS BEFORE THE INCREASE FACTOR WE CAN HAVE A BUILOING OF 48,000 SQUARE FEET.

WE ARE ALLOWED TO INCREASE THE EXISTING BUILDING 67 PERCENT BASED UPON THE FORMULA BELOW(EXPANSION CALCULATION.

48,000 MAXIMIUM ALLOWED + 8,040 SQUARE FEET OF INCREASE ALLOWED = 56,040 SQUARE FEET

EXPANSION CALCULATION I = INCREASE

I = INCREASE I = [F/P - .25]W/30

(12,000 X .07 • 8,040 MAX. AU..OW8) 1'ICflEASE(

PROJECT NAME: DISNEY CORE SERVICES

WIll RESEARCH AND DEVELOPI.ENT 900 GRANO CENTRAL GLENDALE, CA. 91201 ARCHITECT:

SHLEMMER+ALGAZE +ASSOCIATES 836 S. Arroyo Pwy. Pasadena, Ca. 91105 (626) 449-6222

Issued for DESIGN REVIEW

FEBRUARY 22, 2011

SHErr TITLE:

PROJECT SUMMARY

SHEET NO:

A1

Page 7: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

The ~~I' Company

2006 OCCUPANCY PLAN

~J [I H J t ____ U ____ --l1 I

bUN AMERICA PROPERTIES I

SITE MAP

L AREA OF WORK

PROJECT NAME: DISNEY CORE SERVICES

WDI RESEARCH AND DE'lELOPMENT 900 GRAND CENTRAL GLENDALE, CA. 91201 ARCHITECT:

SHLEMMER+ALGAZE +ASSOCIATES 836 S. Arroyo Pwy. Pasadena, Co. 91105 (626) 449 --6222

Issued for DESIGN REVIEW

FEBRUARY 22, 2011

SHEET TITLE:

SITE MAP AND SITE PLAN

SHEET NO:

A2

Page 8: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

--

EXISTING UNPAVED AREA TO REMAIN.

PLANT MATERIAL SEE LANDSCAPE DRAWINGS FOR MATERIAL SPECIFICATION

GRAND CENTRAL AVENUE

I I I I

I I I I

~F'ROPERTY LINE

LEGEND

.", NEW CONCRETE.

NEW ASPHALT

• •

• •

i4ROPE:Rfff LINE

EXTENT OF EXITSING CONCRETE TILT UP BUILDING TO REMAIN.

EXTENT OF NEW BUILDING EXPANSION SPACE

120'

PROJECT NAME: DISNEY CORE SERVICES

WDI RESEARCH AND DEVELOI'MENT 900 GRAND CENTRAL GLENDALE, CA. 91201 ARCHITECT:

SHLEMMER+ALGAZE +ASSOCIATES 836 S. Arroyo Pwy. Pasadena, Ca. 91105 (626) 449-6222

Issued for DESIGN REVIEW

FEBRUARY 22, 2011

SHEET TITLE:

SHEET NO:

SITE PLAN

A3

Page 9: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

,- -

\

.~'-~ "" '-PARKIN~ ,

~,

~ ;".---

L

/ I

\

, '- \ , ,

\ , , ,

S T[ MAr

- ---- - --- ----., .... ~"' .• .. _ ['''''''''1

o 50 ' SCALI

, \ ,

I "

60' I " - 60 '

/ ' 1

110'

LIXU

" ffi

LEGEND

--'- --

D .,

S!l ~C F EJ WA"-L IAOUW::O SCONCl uei I I x J L.,J~'_ S_L ShEll AIO 10, SeECI' ICA 0'1. ~OUNI A- - 8'- 0"

SPEC Tm WA ~OIJ~TO A",A -'CHI IIXIURE, S, E SH, E AIQ l OR SPECIFICATO\. MOL NI A - Ib' TO DOn OW.

SP~C 'F r} LJD! flN l) POI F ARFA M00NTED :... GI"I SE ::. SI'I f- I Al fl I- O ~ Sll CI"ICA (N ,JHOVI I) POLE le i AND SuPPOlL

~. 1 I"

@-

L" , , . , .. - - -" . .

c -._--_ .. '

, , :

" .

/

I

I if / '! r

/ , /

/ , /

/

N. W RASll °LA~ Tr ~, ST ANDSCAeT DRAWI ~(; -OR I' LA~ \AA " AL SPEC I CA ION.

N::.W l ~E ::: 'N ii'ASFD ;:: ANTq. SC::-I At.OSCAPE ),AWI,'G FO, CulM MArE "A. SP'I: f- CATIO\.

0,10"TO 'AV_ DISNEY CORE SERVICES

WDI RESEARCH AND DEVELOPMENT 900 C~!\N) v \ I ~I\L Cl - NJAL ' , CA. 9 1)0 A, C" , t,:

S - ,1\1" - ,, CAZ[ - ASSO( A S .~jb S. ,~ 'royo I wy. r csccerc, Co. 91 ' 0:) (675) L 9- 677 7

FrR'll.ARY n , /0 I'

sr- ::. l:. III L::. .

SITE PLAN

SH =- "10:

A4

Page 10: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

D

CJ

t

- r _ /.1 I I I I I I I TT

f- 1~ 1 ~ DU

- -TI -::=ct-- - -- - - --1 P D

Q--t-I - -:=-:;,:::-~~~--- - -- - - --] n o

<I I - --- - 11---- - --- - ---1 C

LEGEND NEW HVAC UNIT AND EQUIPMENT PAD BENEATH. NEW SCUPPER AND

O.F. DRAJN SEE 7/A9.4 Ial1

PROVIDE CRICKET ON HIGH SIDE AT REAR. ARROW INDICATES THE DIRECTION OF THE ROOF SLOPE.

NEW STANDING SEAM METAL ROOF BY VP BUILDINGS.

IIIIITTIll/ ,.+

P c D ~ I

/ 11-&

V:/'/'2:l AREA NOT IN CONTRACT (N.I.C.)

EXISTING CONSTRUCTION TO REMAJN

NEW CONSTRUCTION.

©

PROJECT NAME: DISNEY CORE SERVICES

WDI RESEARCH AND DEV8..OPI.1ENT 900 GRAND CENTRAL GLENDALE, CA. 91201 ARCHITECT:

SHLEMMER+ALGAZE +ASSOCIATES 836 S. Arroyo Pwy. Pasadena, Co . 91 105 (626) 449 - 6222

Issued for DESIGN REVIEW

FEBRUARY 22, 2011

SHEET TITLE:

ROOF PLAN

D NEW SKYLIGHT TO BE INSTALLED.

NEW ROOF SCREEN. REFER TO OET~L 17/A9.4. SHEET NO: ~~------~--~~----------~~--------~ AS

Page 11: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

=

L

GUnER FASCIA COLOR. GunER COLOR: VP PATRICIAN BRONZE.

EXTERIOR DOOR AND DOOR FRAME COLOR. COLOR TO BE DISNEY STANDARD GREEN CREM I.

LEGEND WALL PANEL, TEXTURED STUCCO FINISH. PANEL IS 18" WIDE. COLOR TO BE DISNEY STANDARD TERRA COnA.

CMU BLOCK WALL WITH STUCCO FINISH. USE PERCISION COMMON BOND PAnERN. WALL IS TO BE A PRECISION BLOCK, 8X16. UNDERNEATH NEW STUCCO FINISH. COLOR TO BE DISNEY STANDARD TERRA COnA.

OJ]

PROJECT NAME: DISNEY CORE SEFMCES

WDI AESEARCH AND DEVELOPIJENT 900 GRAND CENTRAL GLENDALE, CA. 91201 ARCHITECT:

SHLEMMER+ALGAZE +ASSOCIATES 836 S. Arroyo Pwy. Pasadena, Ca. 91105 (626) 449-6222

""'" """""- ,',. aE<ATCN c¥'8 1 1 Issued for DESIGN REVIEW

24 GUAGE SSR STANDING SEAM ROOF, ROOF COLOR: VP COOL REGAL WHITE. GUnER COLOR: VP PATRICIAN BRONZE.

WALL PANEL, RIB WALL PANEL PANEL IS 36" WIDE WITH RIBS EVERY 12" COLOR TO BE DISNEY STANDARD LTCREME.

FEBRUARY 22, 2011

SHEET TITLE:

EXTERIOR ELEVATIONS

SHEET NO:

A6

Page 12: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

L

GUTTER FASCIA COLOR. GUTTER COLOR: VP PATRICIAN BRONZE.

EXTERIOR DOOR AND DOOR FRAME COLOR. COLOR TO BE DISNEY STANDARD GREEN CREM .

LEGEND WALL PANEL, TEXTURED STUCCO FINISH. PANEL IS 18" WIDE. COLOR TO BE DISNEY STANDARD TERRA COTTA.

CMU BLOCK WALL WITH STUCCO FINISH. USE PERCISION COMMON BOND PATTERN. WALL IS TO BE A PRECISION BLOCK, 8X16. UNDERNEATH NEW STUCCO FINISH. COLOR TO BE DISNEY STANDARD TERRA COTTA.

DJ] 24 GUAGE SSR STANDING SEAM ROOF, ROOF COLOR: VP COOL REGAL WHITE. GUTTER COLOR: VP PATRICIAN BRONZE.

WALL PANEL, RIB WALL PANEL PANEL IS 36" WIDE WITH RIBS EVERY 12" COLOR TO BE DISNEY STANDARD LTCREME.

PROJECT NAME: DISNEY CORE SEFMCES

WDI RESEARCH AND DEVElOPMENT 900 GRAND CENTRAL GLENDALE, CA 91201 ARCHITECT:

SHLEMMERtALGAZE tASSOCIATES 836 S. Arroyo Pwy. Posodeno, Ca. 91105 (626) 449-6222

Issued for DESIGN REVIEW

FEBRUARY 22, 2011

SHEET TITLE:

EXTERIOR ELEVATIONS

SHEET NO: A7

Page 13: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

I

~

L

GUTTER FASCIA COLOR. GUTTER COLOR: VP PATRICIAN BRONZE.

EXTERIOR DOOR ANO OOOR FRAME COLOR. COLOR TO BE DISNEY STANDARD GREEN CREM '.

, -" ... .' ',.-." ,.' .,.'

... , .. ' . " ~/~-·· .. ··.'~:··· ",

: .. l: ~~i' ~~~ ~\ ;. ,.. :"~' ;". ~.: ~ . I: .

iilili

LEGEND WALL PANEL, TEXTURED STUCCO FINISH. PANEL IS 18" WIDE. COLOR TO BE DISNEY STANDARD TERRA COTTA.

CMU BLOCK WALL WITH STUCCO FINISH. USE PERCISION COMMON BOND PATTERN. WALL IS TO BE A PRECISION BLOCK, 8X16. UNDERNEATH NEW STUCCO FINISH. COLOR TO BE DISNEY STANDARD TERRA COTTA.

[]I]

I ;cot=. , ___ -----'''"'=ro'M;Bf~ATCLE! ~_ , 1

24 GUAGE SSR STANDING SEAM ROOF, ROOF COLOR: VP COOL REGAL WHITE. GUTTER COLOR: VP PATRICIAN BRONZE.

WALL PANEL, RIB WALL PANEL PANEL IS 36" WIDE WITH RIBS EVERY 12" COLOR TO BE DISNEY STANDARD LTCREME.

PROJECT NAME: DISNEY CORE SEfMCES

WlJI RESEARCH AND DE'IElOPl.ENT 900 GRAND CENTRAL GLENDALE, CA. 91201

ARCHITECT:

SHLEMMER+ALGAZE +ASSOCIATES 836 S. Arroyo Pwy. Pasadena, Co. 91105 (626) 449 - 6222

Issued for DESIGN REVIEW

FEBRUARY 22 , 2011

SHEET TITLE:

EXTERIOR ELEVATIONS

SHEET NO: A8

Page 14: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

LEGEND PROJECT NAME: ~ ______________________________ -, ________________________________ -, ________________________________ ~ ~~~~~ES

TYPICAL METAL ROOF PANEL TEXTURED METAL PANEL COLOR LEGEND ~------------------------------~---------------------------------t--------------------------------~WD~~~D

,." .. ...... ,_ . ......, .......... _" .... , .-~ .. '"' .... . ............. , .. _ ... ...... .-... ,._ ....... .,. ........ .. .. , ..... ~ .. , ......... h., .. ,

T __ ._._ ... ___ ...

---,--_.- .......... _.-

RIBBED METAL PANEL

.... , .... _ .. _ ,_ ' ...................... .,.n ... _' ....... " ... . _,-"' .. "." .. ", .... -

24 GUAGE SSR STANDING SEAM ROOF, ROOF COLOR: VP COOL REGAL WHITE.

GUTTER COLOR: VP PATRICIAN BRONZE.

EXTERIOR DOOR, DOOR FRAME AND COLOR. AWNING COLOR . COLOR TO BE DISNEY STANDARD GREEN CREME.

WALL PANEL, RIB WALL PANEL PANEL IS 36" WIDE WITH RIBS EVERY 12" COLOR TO BE DISNEY STANDARD LTCREME.

WALL PANEL, TEXTURED STUCCO FINISH. PANEL IS 18" WIDE. COLOR TO BE DISNEY STANDARD TERRA COTTA.

DEV8..OPMENT 900 GRAND CENTRAL GLENDALE, CA. 91201 ARCHITECT:

SHLEMMER+ALGAZE tASSOCIATES 836 S. Arroyo Pwy. Pasadena, Co. 91105 (626) 449-6222

Issued for DESIGN REVIEW

FEBRUARY 22, 2011

SHEET TITLE:

COLORS AND MATERIALS

SHEET NO: A9

Page 15: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

L

EXTERIOR WALL MTD. FLOOD ® COOPER LIGHTING .... -

·"·''''·'·'''C''C-"",;o:C7.c:.;c:::~:;;;::;-- -::;:c::c:;-----•• D h,"~.".·~,_ ....... _ .~, .. "'., .... , _~ ~ '~'"'''' ",~*",",,,,,,~, ,,, . ..... " .,' .... _" -.. ............. , ... .......... ~_ ..... · ... d ... .... , .. " ..... , .... ~- ......... , ..... - , ~.~ , ...... ,. .-. , .... ~, ..... " •• " ... '" .." •• <, ....... ~. _u ........ , ...... _ ...... ,~ .. ".~ ........ "'.,_~ ., ... ... -,,.,.~~ ... ~.-, - ... " ......... <_ .. ~ .. . ... .. , ... ~ .• ~ ..... Ut .... ",_ . ............. '''''''' ''' .. o • • ~ ..... ,.._ ...... ,~ •• ' .,,~. ~, .. ~ ......... ~ .. , .. , ....... ,.,." -.... ~ ... "' ... "~. " ....... • 0 .....

~.-.-.- ...... , .--.... ~ .. -.-._ ••• , .......... ~d~

,,~ , .... -.. ,-, ~,,'~ .,,-... , .. ,. u. .... _, -.. " ...... ......... . .......... ...... ,.., ""'~- .. , ..... ,.,,. ••• ·ut.

" ....... . r,,, . .. , . .... ... . .......... _." .. ...... • -, .... , ..... ~ • .-'*. ~ ,".". ...... ~<M-... ~ ._~ .. .. .. ... , W· ... .

............ '''''''".·_ ..... 1 .. '*-."', .... ~ .... " .. ''' ... "''' ... ,,~., .. , .. ,_ ....... 7.,,~' ... 'n r··~~ ....... _,' ..... ~

, ~,' '~'-""'.,," ... ~ ,,.-., ...... _ ...... " ... -.. ,~""'-" ' .... ",.,....., .... ,.. ""-,..~~ .. ~ .. , .... ,."'" .. , .. , ... ~~ ~." ~ .e H. ,,'~ . .. ' ,,< """", .. ,,,,"''''~ .. ",~ ... , .. " ... , ......

.. ,u, .......... ."..,.._ , ~,-." ... ' ... ~ ....... "" ... , .. -~ ..... '''-'' "' •• ~ ~O, ... ~~ • • _", ........ < ... rt .......... '. ~~ ,.',," , ... , ,..,,~,, .. "" .,..~.... ,,' .. "'-' . ',. ... __ ~..,,, .... «0

'''' """ .. ~ .. , '''' ........ .., .. ~" ....... , .. .,"" "''' , ... ",,_j .. , " A """ ' ... v,,,-~ ,,.-,_ -........ "" "'.~.' ~ ..... '.-I'.' ' X " ...... , _ ............. _ ... ",< , ', .. " .. , . ....... , .. ,~,~,~. ",~ .. ,~ ~ . ..,.,,- '- .,. "' ...... -..... ""'" ......... ~- .......... ,' .- ... .... " .... ~ "'~ ... ,,- .. ...... , ...... " ..... "'., .... "'-"'~'" _. - .••• ~ ..... ,, >., •• ~, _h ".,".~ •• _"'''' .... " , ... -""-,"",,, .,- , .... " .. -' .. .. ", ,, -",~ , ~,

.. ......... , '''''''~ ..... _,._ho ~', '~.' " .... ~.-...... ~~ .,' ..... _., .... _."" ............. ".,' ......... .• _~·,."."v", 0 .... "_~'" < .. , ..... "-, ...... ~.~ • ......... -'-', .. ,~".,. , ..... , ---."'~ .. -.. .,. "- ....... --.',, '-.... ~ .. , .. -,., .... -... .... ~-, .. ..... ... ,'" ... ~' .. " .. ,-.......... . ~,.,---,,< .... ~ , .. ..." .... -~, ... ~" . "", " ,'~O~ '~"'~._. .. , ... -, ....... " ... ,~" .. ~ ........... _ ... , ." ••.•.•. n~." ~.o~ '"'' ~" ..

lYPICAL EXTERIOR POLE LIGHT

."" .. ,"" , . '-H~ ,~ ...... ~~~, .--_-", .~", •••. "' ..

" ••. ,' . .. "v.~ ..... " ... , •• ',.,,~ ,,_, 'MLta " ...... , ·'..,., ........ f,~" .~ •.. ~ ... ~. , ___ ......... , _~ ...... _ .• _,.~"." .......... n, •• ~ . ...... ~ <o

., .. " ................. , .. " .. -"'~." ,.~ .... -,

... , ..... .... ,,""" .. c ••• , ••• • , •• ~ ............ , ..... .. " __ ~w"

..... ,.,.~ ....... ""', ...... '" ~rt"" ,. ... '",,"'.~;., .. "' __ ·, .• ,''"'' ',,~.,.c, .... .. w--c._ .• , ...... ... ~ .. -.. ,' ....... ,.~ .. ~-.. ,.-~,,-.-.... .. <~ ........... ><o,'~ "", ......... ,~-., .... ~. -.-.. ~~~ ,,-~ .. "W"' _

... .... ""~·""ftn_,~"_ .. • ~< .... .-',,__._uo ..... · • ., .. · .... _ .... N-'_ ~ ............... ~~ ...... -.. ~ __ <, ~M'n·' ... _ ... ... ,""' M~V~4 .... '~ ..

.... ,,~,., ..... "'"~ ... ·010 ".~.--".--.~, ........ -... -~-,'''. _.,,"' ...... ., .. ,,-"_"',l;", ... ~ .. , .. _ "' .. , ~~ ....... ,~" ....... - ... "-~- .. ,,. ............. "' ....... ',. " ," ... ~-~ ....... .. , ............ ~.c"'- ....... ""

,. '"," , ,. " .",1 . .. f ... "".""""_.,.,,.~·~ .... , .. ~~,''''~''''....,.. .... . .... ""." ........ ~,~".,-. ... " '" .. ,.~., ... ,,-~. . .. , ... ""~ ...... .--., .... ,,<o"'.", ~'''''11'I ., .... "rlA,_" '""",", 'M_' .... _n.' ... ',...., ..... ......... " ....... .....,. . ,.~ .... ,._ ..... ~ .~ .. ,," ..... ·~" .• n.' ... ..".,,~ ....... ~.,"" .... ...... """ . """"" .. -...-................. ' ... .. , ..... ~~-,-~ ~ .•. "', ..... ' .... . ,' --.«' ..... ,.. .. A-"._ ... -,.,', ..... ~ ...... ".-......... " .. ~, ..... .-." ... -...... , .. .-.- ..... -~~ .-.....-. ...... .-. "_·~''''.M~'''' , , ... " ....... " ... _,..' " ............... -~

.... ,

McGRAW·EDISON ' . -.

~, .... -, ,".,"" ....... ~.- .. , .. ~,'-... ~ .... -.. ~ ...... .."~ ..... ""'~ .•• ,,<--, - ,.,-, ...... , ........ ~ .. -" ... ,.~ ........... "' .... ..... -,".-~. _ ..... ~_, .... o" _ .. "'H...--' ........... ,,, " ........ . ., .. ~--<, ... ' ....... ,<"" ... " ...... , .... _,,, 00 ... "' ............. . ...... --.-,-" ..... ~ ... , .. _~,""' ... 'o<~"."" ....-........ ,,.~,., ...... _ .... _.- ..... 0-

... "'" ........ « ..... ... ~.". ,~- ~ •. ~ ........ , .. ..., .. ., ... ~ ......... " ... _.' .. " ...... --, .... ..........~ ..... <~ ..... . '''''' .. U-............ . c.,· ••• • .................. ,·

. ...... , ' ....... 0·, ,....'., .. ,, ...... , ., ....

I

LF·20

nM TALON M E01UM

lEO

'"0

... """,, .. ... . -, ..... ,.", . .

LEGEND lYPICAL REVEAL

1

/'l.-\'-' '' .. T,.~(_," .. ~.''r

> • • H.'.i-~"===ik===,,:~I. . I<.",. ,.", •.• "" •. ,p" ""ol'· r "'" "::-- II ,-,.-... " '''''''''' ''' r ... • ...

.---------- ,~"" ~, .... (' ... , ... "' .. ". " ... 1 ".~,.oI I'"",

lYPICAL EXTERIOR SCONCE McGRAW-EDISON' • .. "

, ...... _. " •.• _~ .. ~ ... ~" .~."~. ,~, ",.--<~~.R .......... " "~,,,_ v.,,,.....· ..... _" r.~ , ••• _, ...... ~ •••• ,,, .... ~," ... " ,,'0'" '"" ,,~ c_~,~,~," .... ,...~<~," .~._ ... " .. , ...... '."" y-, • .....,.-.-,.-........ ~ , .•. , , ..• """" • __ ",'~.~,_,'._~,~._ "".",u "''',,~.

c .... .... ,_ ~" .... ,~., ... -.~ ... " .... ~-- ... ~. -"'-'~.--'" . ,~ , , .. .,,, ••• , .. ,,1',.,.., ..... "",,,"',.,'- .", ___ .·1 ........... ... ," ............ _."""." " .... ' ... -....... .. .. ...... ," ' .~'.-.-"'., ..... ....... ,~."' ........ ."h. 0.._ .•. " ... ', •• , ..... ...

.. .. .. 1 . ..

""', "., ....... ,>O~ ." ,",-' .. _'-. ' .... ,' .... ~" .. •• -nt ....... " ... . , .... ~,"' .. ," ,. ",v If' ' ....... _".,,,., .,.,.,: .• /V_ .~,.",-", .. .... ~"' ..... ~ .. ""' .... ,~ ..... ,--. ....... ---.. ~ ""9 __ •· ........... • .. "~,, .. ,_ ...... 'O""._ ' .. ".", ..... ,,~,"., , ......... ' ......... _,," '""_'m .~, .... '" ..... ,,'

~ ..• ,. .. " .. " . ..,.,., ., .. _._.,','"'~ ,r.. ~ ..... ...-.... ,~. , ,,-.'-., ...... w., ... ~., .. ,,,. ..... , .... ~., .. ~", .. ~. M.'w ....... . "" .. " ... . ............. ~~~, .. .. " _ ... __ .1'<. ....... _~~ ... ~"""" ... ' .... ,~, .. -" ~.--.I ... ".".,.,~~ <,~ ...... -.~,. -..... _ • ".,.,

....., .............. ,D ... ' ... ~""""»'< __ H' ....... .. ~,,~,--...... ~-... , ......... """~I><,~-... ~~ ....... -" ..... , .. ....... __ ft, ........ , ....... <>I'A_" ..... _

-~" ...... ,~-" .... .' .. -*" ........... »"., ...... v. "" ... ". ", .. «.,.., .,. •.

.'",., .... --

."._ .. , " ..... , u~, .... ',.,'·'."0 .... .. '," • ..... _,_, ._L ...... ·' .

.. ... " .. . ... " ..... " ...... "',~.~ ... ~ .... " .... ,- ..... , .... ~,." " .... "'N ,."" ........ ... "p ~.-...... -'-'-',~ -~ ,-,,~ """'"'."".­;~.~ ..... -.. ,-,,-~, .... .w" ,* ••• ,."." ., ... w ••• -." ...... ~", ''''''

.. LI;~ 18 i

'" IMPACT ELITE l EO UUflUIER SI'H£HE

coo

, .. ,,, ... ,, ...... " ... . " .",-,

~.,' ~ -.

lYPICAL PAPAPET

PARAPET COlUr..N

SIDEWALL PARAPET KEY

SHlEWALL COLUMN

PURUN

KPFCBA INSET SIDEWALL _" '/1/2000

(P. RIB OR SSR ROOF) '--....l._.J

lYPICAL GUTIER EQUIPMENT PAD

,.." """"" .... '" ('0' ''') " _c ' LU,

~,~

"""'[S"'.)~ "0- '0 • , 1/1' U_ 000f' ,,!'CO< ~. (01<JOl (W ....... "" (')/STlW' " ~, ...... ""

'-"''1: o.mut

!""'" ,,<-,. . , '10' $.$. 00»' $I""" "' .... c., ... ) • I"JI ..... ,"

SSR ROOF W Pit 'IR O~ II~II .... ~ll ........ . _- [AVE GUTTER

-~ • .... " ~. (00 ' 001 "' ... (..,.,) ""'(~'J>ll

t/.·,. . "a' "'" 'mT0l "-" , '--o' o,c.

PROJECT NAME: DISNEY CORE SEFMCES

WIll RESEARCH AND DEV8..OI'MENT 900 GRAND CENTRAL GLENDALE. CA. 91201 ARCHITECT: SHLEMMER+ALGAZE +ASSOCIATES 836 S. Arroyo Pwy . Pasadena. Co. 91105 (626) 449 - 6222

Issued for DESIGN REVIEW

FEBRUARY 22. 2011

SHEET TITLE:

DETAILS AND LIGHT FIXTURES

SHEET NO: A10

Page 16: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

GRAND CENTRAl~~'

III I I . .." ...... SEE A12 FOR PLANT MATERIAL LEGEND

L

PROJECT NAME: DISNEY CORE SERVICES

WIll RESEARCH AND DEVELOPMENT 900 GRAND CENTRAL GLENDALE, CA. 91201 ARCHITECT:

SHLEMMER+ALGAZE +ASSOCIATES 836 S. Arroyo Pwy. Pasadena, Co. 91105 (626) 449-6222

Issued for DESIGN REVIEW

FEBRUARY 22, 20 11

SHEET TITLE:

LANDSCAPE PLAN

SHEET NO:

A11

Page 17: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

PLANTING NOTES

1. IN ALL SHRUB AND GROUNDCOVER AREAS APPLY 28

LAYER OF FOREST flOOR BARK MULCH PER AGUINAGA FERTlUZER CO/APANY, INC. CONTRACTOR SHALL SUBMIT SAMPLE TO LANDSCAPE ARCHITECT FOR APPROVAL. PHONE: (949) 786-9558 FAX: (949) 786-9574

2, ALL CLEARANCE DATA PER LOCAL JURISDICTION'S TREE PLANTING STANDARDS AND GUIDEUNES.

3. INSTALL 'DEEP ROOT' (OR APPROVED EQUAL) TREE ROOT BARRIERS ON ALL TREES WITHIN 5'-O~ OF SIDEWALKS OR HARD SURFACES. CHECK MANUFACruRERS CALCULATOR CHART FOR NUMBER OF PANELS FOR EACH SIZE TREE. AVAILABLE FROM; DEEP ROOT PARTNERS, LP, 345 LORTON AVENUE, SUITE 305 BURUNGAME, CA, 94010 (8DD)LV-ROOTS, (415) 344-1464.

4. PROVlDE PHOTOGRAPHS OF PLANT MATERIAL FOR LANDCSAPE ARCHITECT FOR INITIAL APPROVAL.

5. PRDVlDE SAMPLES OF DECOMPOSED GRANITE AND GRAVEL INSTAlLED PER OETAILS FOR APPROVAL BY LANDSCAPE ARCHITECT.

6. lANDSCAPE ARCHITECT SHALL APPROVE FINAL PLACEMENT OF TREES AND SHRUBS PRIOR TO PLANTING.

7. ALL AREAS SHALL BE GRADED TO SLOPE TO CATCH BASINS OR FLOW UNES AS INDICATED ON THE PLANS OR AS DIRECTED BY THE LANDSCAPE ARCHITECT. SOIL SHALL BE 1 1/2" BELOW ADJACENT HEADERS AND PAVlNG IN GROUNDCOVER AREAS AND 1/2" IN LAWN AND D'tMONDIA AREAS.

8. CONTRACTOR TO AMEND ALL SOIL IN PlANTING AREAS TO A MINIMUM OF 6" DEEP. THE AMENDMENTS SHALL BE PER SOIL AND FERTIUTY REPORT. ALL AMENDMENT PRODUCT SHAll. BE A PART OF THE CONTRACTOR'S SCOPE,

9. SOIL PREP AND BACKFILL PER AGRONOMISrS REPORT, CONTRACTOR RESPONSIBLE TO TAl<E 5 SOIL SAMPLES FROM VARIOUS AREAS OF THE SlTE AND SUBMIT TO WALLACE LABORATORIES. SUBMIT RESULTS TO lANDSCAPE ARCHITECT.

10. GUARANTEE: ALL PLANT MATERIAL SHALL BE GUARANTEED FOR REPLACEMENT AFTER FINAL INSPECTION AS FOLLOWS; 5 GAL AND SMALLER- 90 DAYS IS GAL AND LARGER-ONE YEAR

11. UPON COMPLETION OF AlL PLANTING OPERATIONS,THE PORTION OF THE PROJECT USED FOR THE APPARAruS OF THIS WORK SHALL BE CLEANED OF ALL DEBRIS, SUPERFLUOUS MATERIAL AND EQUIPMENT. ALL SUCH MATERIALS AND EQUIPMENT SHALL BE ENTIRELY REMOVEO FROM THE PROJECT SITE. PAVING SHALL BE WASHED CLEAN AT THE COMPLETiON OF WORK.

12. PLANT QUANTIllES IN LEGEND ARE FOR REFERENCE QNLY, CONTRACTOR TO PROVIDE AND INSTALL ALL PLANT MATERIAL SHOI'IN ON PLANS.

PLANTING LEGEND: Trees

SYMBOL NAME SIZE aTY DETAIL

0 Existing Tree - - -

0 Agonla ftexuO!lo 36" Box • B/LJ.02 P"pp"rmint Ir""

0 Pinus conarllnlil 48" Box 2 C/LJ.02 Canary Island Pine

0 48" Box

Pistocio chinen sis Owner Supplied

" C/L3.02 Chlne~e Plalach" Conlroctor Inslollad

0 Prosopis chilens;s 36" Box 5 B/I-3.02 Chi/ean t.4 ... quil"

PLANnNG LEGEND: Shrubs end Vines

SYMBOL NAME SIZE aTY DETAIL

® 'M~O"P;'~- 15 gal. .., A/L3.02

E ~ R.d ""d 0' '0""" 15 gal. 29 A/L3.02

0 ,,<0' '''m '"Uf, 5 gol. ' ''' AjLJ.02

0 ~

15 yal. 15 A/L3.02

@ 5 gol. 32 A/L3.D2

e ~,. ,

5 gol. "" A/L3.02

0 ),I)qIorum parvlfoUum \ gal. .71 A/L3.02

6) ~: europo"a 'LlttI" Ollie' 5 gol. 15' A/L3.02

e , 5 !lol. '" A/L3.02

@ 'ow Zoo'ood ~o: Wo .. 5 goL " A/13.02

® , , "."' 5 901. ,. A/L3.02

PLANTING LEGEND: Ground Cover and Turf

SYMBOL NAME SIZE aTY DETAIL

~ - E/L3.02

\ !lol. 0 18" O.C - A,F/L3.02

~ , gal. 0 9" O.C - A,F/L3.02

Flats 0 6" O.C F/Ll.02

~ ~u~ea Plant Fiats 0 6" O.C F/L3.02

2" x 4" Recycled Plastic H"ader - D/lM2

PLANTING NOTES

,. In oil shrub ond groundcover ","08 apply 2~ laysr of forest floor borlt mulch per Agu1nO!lO Fertilizer Company. Inc. Conlroctor shall submll sampl" to landscope orchltect far oppro",,1.

2.

,. All clearonce data per City of Glendole tree planting slondards ond 'luldellnes.

Plant quantilles ore for REEEBfHCf ONI Y moterial shown on drawIngs.

Conlroctor to provide ond Install on plant

PROJECT NAME: DIStEf CORE SERVICES

WDI AESEARai AND DE'lELOPI.£NT 900 GRAND CENTRAL GLENDALE, CA. 91201 ARCHITECT:

SHLEMMER+ALGAZE +ASSOCIATES 836 S. Arroyo Pwy. Pasadena, Ca. 91105 (626) 449 - 6222

Issued for DESIGN REVIEW

FEBRUARY 22, 201 1

SHEET TITLE:

LANDSCAPE PLAN LEGEND

SHEET NO:

A12

Page 18: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

C I TY OF GLENDALE CAL I FORN I A I NTERDEPARTMENTAL COMM UNI CAT I ON

By: Allen Castillo, Project Manager, Community Development

Reviewed By: Alan loomis, Principal Urban Designer, Community Development

Date: February 15, 2011

Re: Agency Stage 1&11 Design Review for WDI Machine Shop (900 Grand Central Avenue)

Exhibit 2

The following is an evaluation of the above project based on drawings prepared by Shlemmer+Algaze+Associates, February 15, 2011. Summary comments are provided al the end of this memo.

Project Description

The Project is located within the Disney Grand Central Creative Campus (GC3) at 900 and 932 Grand Central Avenue, at the southeast corner of Grand Central Avenue and Flower Street. The Project is adjacent to older, tilt-up concrete warehouse and office buildings on the north and west sides, and GWP's Grayson Power Plant 10 the south.

The Project will demolish the 932 Grand Central Avenue building, occupy the existing concrete tilt-up building at 900 Grand Central Avenue and add additional square footage to that building to accommodate the proposed WDI Machine Shop. The building will house the machine shop where theme park attractions will be prototyped. This includes shops for metal, welding, wood, plastic, paint, hydraulic and electrical. The building will 101a156, 114 square feet.

Project Design I Design Review Analysis

Existing Buildings, Adaptive Reuse, andlor Historic Preservation

• Existing Bui/dings - The proposal is an addition to the existing 900 Grand Central Avenue building, a one-story concrete tilt-up warehouse. The existing building located at 932 Grand Central will be demolished.

Overall Site Plan

• Site Plan - The Project will construct a 20,854 square feel addition existing building. A new parking will be located where the existing 932 Grand Central building is currently standing, west of the proposed addition. The parking 101 will be fenced and new landscaping will be provided.

• Setbacks - Per Disney's Scope of Development, the Project has an average required setback of 10' throughout the site.

• Open Space - The Project will provide a small entry garden at the building's new fronl door. Chilean Mesquite and Pepperminl trees are proposed for the area as well as shrubs and vines. A secondary and private garden for the WDI Shop employees will be located behind a 7' tall smooth stucco finished wall adjacent to the parking lot.

• Landscape - New landscaping will be provided around the perimeter of the parking area and building on both Flower Street and Grand Central Avenue. This area will be planted Canary Island Pine and Chinese Pistachio trees, shrubs, and ground cover. The existing trees along these two streets will be reused. The existing lawn and other plants will be replaced.

Page 19: CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT …€¦ · CITY OF GLENDALE CALIFORNIA REPORT TO THE REDEVELOPMENT ... tilt-up concrete warehouse and office ... All new exterior

Mass and Scale

Agency Stage 1&11 Design Review WDI Machine Shop {gOO Grand Central Avenue}

March 1, 2011 Page2of2

• Height and Massing - The proposal is essentially two adjacent one-story box-shaped warehouses. The existing building is 24'-4" at the highest point. New roof screens will hide the HVAC equipment on the roof, raising the perceived height to approximately 31'. The parapet of the new building will align these roof screens on the existing building. The Project is well below the maximum height of 175' permitted under Disney's Scope of Development for this site.

• Frontage and Facade Design - The existing tilt-up building has few windows and no architectural detail and an ambiguous unclear front entry. The addition will establish a modest facade fronting Grand Central Avenue and a small entrance garden. There are two entrances to the building, one from the existing building which consists of a glass door, and the other from the new addition. However, the entrance from the new addition will be the main entrance for the entire Project and is pronounced with the Creme Green finish. Windows will also be added to the addition facing Grand Central Avenue and the parking lot.

Building Design and Detailing

• Materials and Colors - The existing building is standard concrete tilt-up panel building. A small addition on the Flower side (south/east comer) will "square out" the tilt-up building with a smooth stucco finish to blend with the existing concrete building. The larger addition on the west side is a pre-fabricated metal structure of textured panels on the lower third portion and a standard corrugated metal panel above. Both the existing building and addition will be painted in Disney's standard colors: "Terra Cotta", "Lite Creme" and "Creme Green". The building will be painted Terra Cotta below the lower third portion and Lite Creme above. The roof screens on the existing 900 Grand Central Avenue building will also be painted Lite Creme. All doors, windows and handrails will be highlighted in Creme Green.

The parking area will be screened with a 7' tall chain link fence with green mesh. Near the entry gate, a new CMU wall with a Terra Cotta colored smooth stucco finish will be constructed. Trees, shrubs and ground cover will be planted in the area between the sidewalk and the building.

• Lighting - The site plan provides the locations and details of simple wall mounted sconces, wall mounted area light fixtures, and parking lot lights. All new exterior lighting is specified to be LED and in dark bronze finish.

• Signs - There is no proposed sign for the project other than the address located above the entrance of the new building.

• Public Art - Disney's existing Development Agreement with the Agency exempts the Project from the public art ordinance.

Summary Comments, Recommendations and Draft Record of Decision

The Project is a simple one-story building, finished in a restrained palate of materials. The scale, setbacks, finishes and colors of the structure are within the parameters established by Disney's Development Agreement and similar structures on the Disney campus. The Project will enhance existing setbacks and landscape, and will provide an obvious front door to what is currenlly an unadorned industrial warehouse with no street presence. The Project is supported wittiout conditions or comments.