Top Banner
CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT To: All Prospective Bidders Subject: Addendum #1 Date: April 20, 2017 This addendum modifies the Contract Documents only in the manner and to the extent stated herein and on any accompanying drawings. This addendum will become part of the Contract Documents. Except as specified or otherwise indicated by this addendum, all work shall be in accordance with the basic requirements of the Contract Documents. Bidder shall acknowledge receipt of the Addendum in the space provided on the bid form. Failure to do so may constitute informality in the bid. a. Changes to prior Addenda a. None with this addendum. b. Changes to Bidding Requirements a. None with this addendum. c. Changes to the Specifications a. None with this addendum. d. Changes to the Drawings a. Drawings C3 and C5 have been revised to include bar scale. e. Clarifications a. The following clarifications are provided i. None with this addendum. b. The following questions have been submitted by Bidders i. “Could you please confirm that C3 and C5 are drawn at 1”:30’ scale and that C4 is H – 1”:20’, V – 1”:2’ scale?”
11

CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT

Feb 05, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT

CITY OF CHARLESTON

PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT

To: All Prospective Bidders

Subject: Addendum #1

Date: April 20, 2017

This addendum modifies the Contract Documents only in the manner and to the extent stated herein and on any accompanying drawings. This addendum will become part of the Contract Documents. Except as specified or otherwise indicated by this addendum, all work shall be in accordance with the basic requirements of the Contract Documents.

Bidder shall acknowledge receipt of the Addendum in the space provided on the bid form. Failure to do so may constitute informality in the bid.

a. Changes to prior Addenda

a. None with this addendum.

b. Changes to Bidding Requirements

a. None with this addendum.

c. Changes to the Specifications

a. None with this addendum.

d. Changes to the Drawings

a. Drawings C3 and C5 have been revised to include bar scale.

e. Clarifications

a. The following clarifications are provided

i. None with this addendum.

b. The following questions have been submitted by Bidders

i. “Could you please confirm that C3 and C5 are drawn at 1”:30’ scale and that C4 is H – 1”:20’, V – 1”:2’ scale?”

Page 2: CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT

Addendum 1

Peach Blossom Drainage Improvement Project

April 20, 2017

Page 2

1. Answer: It is correct that C3 and C5 are drawn at 1”:30’ scale and that C4 is H – 1”:20’, V – 1”:2’ scale.

ii. “The pipe outfall structure is submerged under the water. Is there a place that we can pump the pond to? And if so, where? Or do we have to put sheet piling around it”

1. Answer: The means and methods of dewatering and installing the proposed structures are to be determined by the contractor.

END OF ADDENDUM 1

Page 3: CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT

PEACH BLOSSOM

Page 4: CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT
Page 5: CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT

Feet

0 30 60

Page 6: CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT

Feet

0 20 40

Feet

0 2 4

Page 7: CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT

Meters

0 30 60

Page 8: CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT
Page 9: CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT
Page 10: CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT
Page 11: CITY OF CHARLESTON PEACH BLOSSOM DRAINAGE IMPROVEMENT PROJECT