Capital Standards
Industry Indicators
North Carolina Jail Standards (see website below)
http://reports.oah.state.nc.us/ncac/title%2010a%20-%20health%20and%20human%20services/chapter%2014%20-%20director,%20division%20of%20health%20service%20regulation/subchapter%20j/subchapter%20j%20rules.html
Capital Standards
Industry Indicators
For detention primarily population and functional capacity.
For functional capacity, currently use 85% because population is down. However, the industry standard is 80%.
Master Plan July 2008 (Kimme & Associates, Inc.)
Capital Standards
Capital Standards
Capital Standards
Industry Benchmarks
American Correctional Association Accreditation (ACA)
Accredited since 2003
First detention facility in North and South Carolina
Facilities of Comparable Size
Accredited by National Commission on Correctional Healthcare (NCCHC)
Capital Standards
Existing Standards for Sheriff’s Office
For detention, adopted direct supervision model
Nothing formalized for non-detention operations
For an area such as Registration Bureau, primary need based on functionality of the area as well as security. One example is the request to separate sex offenders from other customers. This request has prompted the relocation to Sheriff’s HQ in 2014.
Reviewing the current needs of our Field Operations Division to determine long-term needs. Currently outgrown leased space at the ABC Facility.
Overview of Current Facilities
Sheriff’s Headquarters
Jail North Complex
Jail Central
Annex
Work Release and Restitution
Courthouse
Registration Bureau
Field Operations
Overview of Current Facilities
Sheriff’s Headquarters Located at 700 East Fourth Street, Suite 100
Houses Sheriff’s Office
Field Operations Major
Communications Division
Administrative Staff
Overview of Current Facilities
Jail North Complex: 5235 Spector Drive
Original facility had 614 beds and was opened in 1994
336,157 Square Feet
Included Training Facility
Opened Firing Range in 1997
Added Youthful Offender in 2010
Increased capacity to 721
Vocational Facility opened in 2010
Offers Horticulture and Carpentry
Overview of Current Facilities
Jail Central: 801 East Fourth Street
Original facility had 1,004 beds and was opened in 1997 and added 900 beds in 2002
702,884 Square Feet
Arrest Processing Center (APC) is operated from Jail Central
APC renovations currently underway
APC is located at the Annex and it
will reopen this summer
Includes Medical Infirmary
Overview of Current Facilities
Jail Annex: 5225 Spector Drive
Facility had 320 beds and was opened in 2009
In addition to the 320 there is another shell building that could provide another 320 beds but would require construction to open.
Closed May 2011
83,274 Square Feet
APC is occupying while Jail
Central renovations are
underway
Overview of Current Facilities
Work Release and Restitution Center: 901 Elizabeth Ave.
Original facility had 150 beds and was opened in 1997
72,682 Square Feet
Houses IST and HR
Downsized July 2010
Operating 90 beds now
Currently houses Culinary
Program
Overview of Current Facilities
Courthouse: 832 East Fourth Street
Opened in January 2007
Screened over 1.2 million entering in FY 2012
Confiscated over 7,300
items, including 3 firearms
in FY 2012
Provides security to 37
Courtrooms
Courts Division has 113
Staff in Courthouse
Overview of Current Facilities
Registration Bureau: 715 East Fourth Street
12 staff
Sex Offender Registration
969 currently registered
Purchase Permits
Concealed Carry Permits
Non-criminal fingerprints
Relocation planned to
700 East Fourth St. in 2014
Overview of Current Facilities
Field Operations: 3333 North Tryon Street
Civil Unit, Transportation, Domestic Violence, Civil Judgment and K9
Currently lease
4,511 Square Feet
Leased since 2000
$60K per year
Capital Projects
Currently no plans to submit a request for a new Capital Project for consideration unless there is an immediate need identified to relocate the Field Operations Unit.