Top Banner
Hydro Resources, Inc. CHURCH ROCK SECTION 17 RESTORATION ACTION PLAN License No.: SUA-1580 July 23, 2001 (***October 15, 2010 - revisions inserted pursuant to LBP-04-03 and LBP-05-17***)
166

Church Rock Section 17 Restoration Action Plan.

Mar 23, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Church Rock Section 17 Restoration Action Plan.

Hydro Resources, Inc.

CHURCH ROCK SECTION 17RESTORATION ACTION PLAN

License No.: SUA-1580

July 23, 2001

(***October 15, 2010 - revisions inserted pursuant to LBP-04-03 and LBP-05-17***)

Page 2: Church Rock Section 17 Restoration Action Plan.

July 23,:2001

CONT-NTS

A. InTRODUCTION

B., SURITY BONDUFORMAT

C. STANDBY TRUST A.GREEMENT

D. CONSOLIDATIONOF -STATE, EPA AND bNRCSURETY iNSTRUMENTS

E. COSTDETAILS FO6R RES ORATION AND RECLAMATION ACTIVITM8IES

1. Introduction

2. Groundwater Restoration Budget:

3. Analytical Stability

4. Plugging and Abandonment

i. Equpment Removal

6. Wellfield Decommissioning

7. Building Decomissioningi

8;. Surface Reclamation

9. Summmy and Profit

Page 3: Church Rock Section 17 Restoration Action Plan.

Revised October 15, 2010

CHURCH ROCK SECTION 17 - RESTORATION ACTION PLAN

A. INTRODUCTION

The following summarizes the Restoration Action Plan for the Crownpoint UraniumProject Churchrock Section 17 location1 ("RAP-17"). Shown in Attachment A-i, the estimateputs the costs of restoration by an independent contractor at $5,396,075 over a three year periodwhich is based on the conservative assumption that all reclamation activities are postponed untilthe end of the mine life with the resulting liabilities accumulated until the end. The Section 17site is an extension of the Section 8 orebody and will be mined in sequence. There will beoverlap in the mining and reclamation of the Section 17/Section 8 locations and the annual suretyreview completed pursuant to LC 9.5 will necessarily accommodate this overlap. For example,restoration will become completed in one area of Section 8 (and the surety amount reduced)during the same review period that new mining is undertaken in a portion of Section 17 (and thesurety amount increased). The RAP-17 assumptions and resulting cost calculations are based onthe project being a stand alone one. Because the overall surety amount will be a function of theamount of completed restoration vs. new production at both sites, a surety-funding schedule2 isimpossible to project at this time and will not be included in this report.

Consistent with the overlapping nature of the two mine plans, the RAP-17 budgetprojects redundant periods of management personnel costs during stability monitoring anddecontamination and decommissioning ("D&D")3. In the event that mining and groundwaterrestoration were completed in Section 17, then Section 17 is where the final stability monitoringand D&D management costs would be realized4 . At this time HRI will leave the redundant costsestimate in both the RAP for Section 8 and RAP- 17 to serve as further contingency.

The RAP encompasses the full cycle activities necessary to:

* Restore the groundwater at the Churchrock Section 17 site to levels consistentwith those described in License 5 Condition 9.3 and the COP 6.

* Complete a six-month stabilization period during which the chemistry of thegroundwater remains constant.

* Complete the plugging and abandonment ("P&A) of all wells.

See COP Figure 1.1-32 See Churchrock Section 8/Crownpoint Process Plant Restoration Action Plan, Nov. 17, 2000, § F.3 I.e. since Section 8 and Section 17 activities will overlap there will only be one final stability/D & Dperiod at the end of groundwater restoration activities for the two. See Attachment E-2-I.4 I.e. Section 8 stability and D & D will be managed by the same personnel that are providing oversight ofgroundwater restoration in Section 17.5 The "License" that is referenced throughout this RAP- 17 means the U.S. Nuclear RegulatoryCommission Materials License SUA- 1580.6 The "COP" referenced throughout this RAP means the Crownpoint Uranium Project ConsolidatedOperationsPlan, Revision 2.0, August 15, 1997.

Page 4: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

Surface reclamation, decommission and obtain release for unrestricted use, of thesurface and revegetation of restored well fields. When accomplished, the land isreturned tits orginalpre g ue.

There. will be no costs associated with radiological decontaminationr of buildings, processvessels, satellites, andzauxiliariystructuresat the Section I7 location because the site hwillserve aswellfield only and feed the Section, 8 satellite (Le. there will be.:no buildings, process vessels,satellites, and awuliary structures atfthe.Section 17 location),Y

The RAP-17 has been compiled with the absence of actual-development in the field thatwould normally be used, asujusction for the basic assumptions. The greatest p6tential fornaccuracy that may result from the absence of real informationis in lthe mine'area, where' actual

-drillingwill reveal details in the nature of the ore and mine zone. Additionally, there may be.otherdifferences in the- reclamation costs that will result once "as built" conditions areý realized.

The sequence of mining activity and the resulting.shedule for production and:.restorationmay also differ from what-the RAP-17 budget reflects. Based on HRI-s ability to obtain economic

'uranium salescontracts, production rates and the overall groundwater restoration schedule:.maybe more or les.sthan what is expectcd,

The results of the requisite restoration, demonstration for Section'S described inIC 10.28-and COP '10.4.4 may have a significant effect on groundwater restoration, costs. An increase ordecrease ini demonstrated pore, volume, requirements- -will have a, proportional effect ongroundwater restoration costs.

HRI's submittal- presented herein employs assumptions.that are based on best professionaljudgment given the data that is currently available. It is a fact that the detail oftthe RAP-17budget model exceeds the ability.to predict precise field :conditions. Necessarily,, the accuriyofthe budget assumptions willimprove as operations proceed. The annual review required byLC9.5 Would provide the iterative format by which NRC ,cancontinually update the surety amountthat results from the newly available information.

B. SURITYBOND.FORMAT

See the Churchrock Section 8/Crownpoint Process Plant Restoration Action Plan, Nov.1.7,.2000, Section B forthe.SuretyBond format,

C. STANDBY TRUST.AGREEMENT

See the Churchrock Section 8/Crownpoi't Process PIant Restoration Actiont'Plan, Nov.17, 2000, Sbeion-,C for the, Standby Trust format.

Page 5: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

D. CONSOLIDATION OF STATE, EPA AND NRC SURITY INSTRUMENTs

In addition to being crafted tocomplywith theNRGCcriteria, HRI's proposed PerformanceGuaranteeBond is designed to, address.the New Mexico Environmental Department's (NME1Ds).restoration and reclamation requirements, and U.S. Environmental Protection. Agency (USEPA)Underground Injection Control Criteria. These multi-compliant sureties will require multi-agencyconcurrence. The Bond examples shown in Appendix A -are designed to be consistent with 10:CFR Part 40, Appendix A, Criterion 9 (Financial Criteria) which clearly allows for consolidationof State and Federal financial. or surety arrangements; established to meet restoration, reclamation,

and decomissioning costs provided that "the poition Of ,theý surety which covers thedecommissioning and. reclamation of the .mill, ,mill tailings. site and, associated: areas "is clearlyidentified and committed for use in, accomplishing .these activities." Absent a. mill ,or tailings,.essentially all of the process facility, wellfeld, and ancillary.components of the, operations wouldbe. subject to the decommissioning requirements., of both, the State of New Mexico and/or U.S.

'Environmenta ProtectionAgency.:and the .NRC.

Page 6: Church Rock Section 17 Restoration Action Plan.

ATTACHMENT A-1SUMMARY

Page 7: Church Rock Section 17 Restoration Action Plan.

Rev. October 15, 2010

HRI CROWNPOINT URANIUM PROJECTFinancial Assurance Plan for Churchrock Section 17

Summary

Contingency/ Profit Contingency/ ProfitCategory Project Total 15% .25%

Groundwater Restoration $4,089,818 $613,473Groundwater Stability Analysis $56,000 $8,400Well Plugging $474,648 $71,197Welifield D & D $58,879 $14,720Surface Reclamation $7,153 $1,788

ITotals $4,686,497 $693,070 $16,508

lContingency/Profit $709,578

ITotal Surety Proposed $5,396,075

Page 8: Church Rock Section 17 Restoration Action Plan.

July 23,2001

E. COST DETAILS FOR RESTORATION AND RECLAMATION ACTIVITIES

1. Introdiucion

RAP-17 contains details concerning cost basis figures and assumptions, calculations.andor methodologies used inderi:ving cost estimates, referenc, for the Mfll cycle, groundwater

restoration, well plugging and. abandonment,, surface decommissioning And reclamation, closureand ultimate license termination., This information is&designed to be descriptive-enough for theNRC staff to determine the acceptability of HRM!s proposed costC figures; 'and' is! based :on aýnýindependent contractor performing the decommissioning and reclamation work7 .1in1 accordancewith 10 CFR Part 40, .Appendix& ACriterion 9, HMU reviewed Appendix E of the NR0's draft"Standard Review' Plan for In Situ Leach Uranium Extraction License.Applications' (NURG-&I,569, dated 'October 1997), and Section 4 of 'the NRC's "Technical Position on FinancialAssurances for Reclamation, Decommissioning, :and Long-Term Surveillance and Control ofUranium Recovery. Facilities" (dated October 1988) for examples of acceptable "levels of detail"for costestimates pertamiig to this surety plan.

HRI used two different budget formats! to. present.the closure costs ei s in RAP -1'7.Costs for groundwa restoration (2) were estimated -over time as. an. operational budget. Final

decommissioning costs including analytical stability,, plugging, and labandonment, wellfielddecommissioning, and surface reclamation (038) were budgeted on a. lump sum basis. In both.,formats MU deovelopedArthe cost estimate from the bottom -l up. -using the best available costestimate orquotefor the individual component (s) that, were. considered' HIM also called onthe

operation management-resourcesof URI; Inc., the sister companywhoý is* the oldest! uranium insitu leaching company in theUnite•dStates.

• Costs havebeen estimated using standard budgetary techniques as.would be done by a indepedent contractor., Inaddition, HRI has included a subtotal category entitled "contractor profit" that included, 15% of the total cost forgroundwater restoration, groundwater stability analysis, well plugging and equipment-removal and.25%'of the totalcoost for wellfieldD &D, buildingD &D, and surface reclamation.

UR1I, Inc. is a wholly owned'subsi diary of Uranium ResourcesInc. the parent~to HRI, Inc. The firnhas b eenin-the business of ii:situ leach uranium recovery since 1977-.

Page 9: Church Rock Section 17 Restoration Action Plan.

July 23,10.01

2. Groundwater Restoration

21..- Introduction

In. addition to the regulatory guidance provided by NRC, HRI used historic and ongoingcompany experience with similar groundwater restoration operations 'in developing its budgetmodel. Groundwater restoration costs are presented as a monthly restoration budget, withcumulative total .costs., This is an appropriate budget interval because ongoing operational :costsuch. as labor, electricity, reagents, replacement equipment etc. are. paid out ofcash.ona: monthlybasis. The duration of the .restoration cost expenditure was based on the processing andcirculation of 9 pore volumes of. groundwater ,as :required by license condition 9.5 suretyrequirement. Surety will be maintained .at this level until the.number"of pore volumes required torestore the ground water quality of a production scale weilfield'has-been demonstrated as stated inCOP Section 10.4.4.

The, COP that was submitted :in support of the HRI's i-cense contemplated a number ofmethods for liquid. waste treatment and disposal during ground water restoration. The costs thatare. presented .in this budget assume the most conservative liquid waste treatment and disposaloption; reverse osmosis treatment ('RO") and brine concentration-("BC"). It is conservativebecause' it is authorized by the current license (oiher options would. require additional licensingsteps) and it is the most costly option. f HRI is to pursue one of the othertr.eatment/disposaloptions described in the COP Revision 2.0 and it isapproved in a future licensing action,, thenHRI-will adjust the surety budget accordingly during the annual update:review.

RO and BC will be. used to treat water during production operations- and be used for,groundwater restoration conducted in the pilot. demonstation and duringconcurrent restorationthat will -be ongoing with productio-n activities. Becausethe cost of restoration equipment such-aswelifield pumps, ponds, the RO unit, the BC unit,, laboratory equipmen,: trucks, and field.equipment must be incurred for production process operations, they ýare assumed to beoperational capital and are not included .,as capital requirements in. any of the:R'AP budget. lines.NRC will be able to verify the- availability of the restoration equipment during routine:inspections.

The budget model described in this; RAP used 712,913,000 gallons of water to sizeduration of the restorationprogram against the. projected nominal equipment capacity. Rows 21-42 of the restoration budget is a monthly calculation of Water treatment capacity that has beencumulated over the term of restoration and compared with the required nine pore volumes, oftreated water. It., is nominal equipment design capacity that is needed to process: the requisitegalonage that justifies- the length (and cost) of groundwater restoration operations.

2.2. Reverse Osmosis Equipment Description

Reverse osmosis is a water treatment process: Whereby the majority of dissolved "ions" arefiltered from the wastewater, and concentrated into a smaller concentrated brine volume. Theresulting product water typically meets, or exceeds drinking water standards, and duringrestoration activities, is reidjected back into the wellfield further diluting the underground mining

Page 10: Church Rock Section 17 Restoration Action Plan.

'July 2,2j;001

solutionsi-toward' baseline quality. Forthepurposeofthis:budget model, the concentratd brinestre, representing 20%rof the:.feA volume will.be disposed .by bhneconcentration (a form of

,distillation).

Osmosis is;a natural process that: occurs in, all livingclls. Withan appropriae semi-:permeable membraeA asa barrieri to solutions of diffeing, con; n s, larally o g,osmoticvpressure forces pure-water .from the dilute-,solution to pass through. the membrane, anddilute the more concentrated solution. Thi I process will continue untielequilibrium exists betweenthe two solutions..

Reverse osmosis O(R.DO) is a reversal of the natural osmotic; process. By, confining a:concen.tratedsolution against a sm permeable membirane, and applying reverse pressure on theconcentrate greater than-the naturally occurmrig osmotic pressure, water will move across themembrane. ("product water"), and out. of the original concentrate, resulting in an even moreconcentrated. solution ('brine"). The membrane rejects, the p,,sage of the m•jrity of the,dissoiVed •solids while permitting thepassage ofwater.

Post-minrng solutions froma-depleted~mine area• wi be :treated with anariti-scalent Which!:is the, only chemical pretreatment budgeted. The sol0Ution may net be bulkfilltred across sandfilters to remove allt solids greater than', 30 microns., Cartridge filters, will then filter out the

9rem solids great than 1 micron..The solution at this point iS r6ladyfor the reve'rsepsmosisprocess. To acheve reverse osmotic purifiction- te pretreated solution is pr ed and

directed-to the first step of a:two-stage reverse osmosis process. Approximately 60 percent ofthetotal feed volume wil.be converted to produptwatermin the fst stage. The brine:water ofthe firstsae willithen, acts the feedtfor the second stage, w'hicyields an overallproduct-to brine ratio,of4:1. The brine generated will, be flurther treated and reduced by. brine concentration.

The.ROMunitwas sized to operate at anominal9 capacity of0580 gallonsrperminute. Thisdes ra has been utilized by URI at similar ISL facilities with excellentiresuts,. Ad4itionally

theszg is optimal because it will.: alow concurrent restoration to proceed at approximately thesame. .rate production. weilfields are deplted. (I.e. withý m and, retoration going., onconcurrently restoration and mihnigwillproceed, at ýsiniar rates).

RO treatment, operating and maintenance costsu are included wifhin the 0. & MbudgetfinAttachent E42-1.

2.3. Brine Concentrator"Equipment.Description

A. brine concentrator Will-, bei. used for" final reduction ofliquid waste. The, RO rejectstream will be treated with la vertical tube, falling film. vapor compressor evaporator followed- by a

9 RAP-I,7s nominal capacty is an estimat~e. HRJwill delwith capac Iity variances t Ihat result from ~equpmnefficiency,.orýdowntime by incesing ordrsing theequipment size.and posiblyadjusting surge'capacity. Forexample, ifactual operatngresultsindicate thatR O.'equipment downtimeris 5% then increasing the equipmentdesigircapacityfrmn.580 gpm to6610 gpm would allowthe average throughput to remain thfesame. Atbthis stage it.isvimsle for HUI to anticipate and adjust for:evmey operalional.variable that may arise in the fure.

Page 11: Church Rock Section 17 Restoration Action Plan.

J*1y 3,2001

steam driven rotary drum dryer'to, achieve zero liquid discharge (dry'sol•ds), The solids will, be'bulk stored andshipped to;an 1,e2- roduct facilitV for disposal.

Brine concentrationis aprocess 'that -can, process, awastewstream iinto deionied water. and.solid sluny. Electrical utilities inhthe .Four COrers aea and paper, and pulp companies have

employed thistechnology f6r decadestoIandle their waste streams. T7heprinciple behind ,thleprocess is based on, the ideal Carnot cycle where anainitial fixedvolume of concentrated brineis.heited to boiling temperature. The steam vapor created is mechanicaly compressed; resulting ina secondaty steam vapor whose temperature is. elevated (15-20 degrees) byithework energy used

,during'zompression. Distilled water is condensed from the secondary steam.yapor onto internal'heat exchangers. Theheat loss du' condensation istransferred to thecicul• t brine b on ,the'

opposite side of.theheat exchanger. The- brine's temperature is raised, maintainingithe internal,b6iling enonment'. his.,source of heat sustainsthe crea•ion.ofpr y seam used to feedte.compressor. The cycle is continuous to long as energy is addedrat the compressor stage. The,electrical power used incompressing, and elevatingthe temperature of the primary steam vapor,produces_ di product watr Te resultant hper-concenatedbrine allowsslid prcipiate,•inc the forof common salts as determinedtby .te solution~s'limits for solubility. Typically, .forioith,-fomso: slt a, et-each. 1`00,gallons: of waste brine treated, 9 gallons of disiiledewater. and .2'gallon of sluirry solidsare fobred.

ThevBC -was sized to accommodatelthe anti cipated brine that the RO:will produce.

BC costs are included within the O & MMbudget iin Attachment E-2-l-.

2.4A POre Volumestand Flair.Restorationequipmetcapacity ds ' couple with t ftherestora.Ion operations

,budgeted hereIn i•• a -uction:of the quantity ofwaerthat will be processed dn restoration-thatis calculated in this kRAPby using- the pore.volumeunit of measure. The term'b"pore volume"( Iis, &a term of coiivenienceithat hasbeen, conceived by the ISL ýidust-ryto describethe•eqantity

-of freewater in, the, pores of a given volume of rock, The units are provided in gallons&. PV's-provides aunit of reference that a, miner can use to describe the amount f circulation that is

.neee to. lch anore body, :or dscxibe thetibes water mutbe flowedthrougha ofdepleted oretoachieveorestoration. P 's ,provide a way that a mai can takesmll-scale studies,such.as;studies ini the: laboratory, .and scale these studies.up. to field level, ortto compare piloti scalestudies10 to commercial ,scae. "Hence they provide, a miner with an important technique. forcalpcating !SL project economics and restoration:,costs.

PV's are calculated by deermining the three' dimensional volume ofthe rock (that islso"the. ore.ý zone) 'and multiplying .this number by the6.percent' pore space. R used the ,"ore area"method to determine porevolumes' ,, where the extent ofore, of given grade within a mine unit is:

1°'0Le. such as the, Section 9.PfotL SeFEIS p. 4-3 7.".n Differentoe rhave used•iffernt:mmehods toddIeterine the volume of the ore zone. Forvexamope, someuse-te "Pen dhod" whefe parnemdimensionsAaxe used; to determine the, area of theormez6 athen tie area: ismultiplied by sr"'tckssto determine the vou0~ oh*ckib.the five spo The pore volumeof the fv pti

Page 12: Church Rock Section 17 Restoration Action Plan.

July 23,2001

outlined and digitized to provide the ore area12 . This area is then multiplied by the average orethickness to provide the three dimensional volume of the ore that is to be leached. This volume isconverted to a PV by multiplying the ore volume by the percent porosity and then converting tothe units of measurement (i.e. gallons). Table I below shows the PV calculation for theChurchrock Section 17 location that was used as the assumption in the budget model13 .

Table 1 - Churchrock Section 17 Pore Volume Calculation

ZONE Ama(fa) Tk (ft) Vol (03) Per I gal PV W) H-PIF V-PIF IC7V(dI 9XCPVD 123.023 7.5 922.673 0.25 7.48 1725398 1.5 1.3 3,364,525 309280727

UUPC 22.665 8.5 192.653 015 7.48 360260 1.5 13 702,507 6,34566UPC 113,140 7.3 825.M2 0.25 7.48 1544,474 1.5 1.3 3,011, 7

25 27.105.521LPC 50,751 8 406.008 0.25 7.48 759,235 1.5 13 1,480,508 13,324,574UA 36,220 5.6 202,832 0.25 7.48 379V96 1.5 1.3 739,627 6,656,642LA 161,163 8.2 1.321.537 0.25 7.48 2,471=7 1.5 1.3 481,983 43,370 849UB 160,090 9.1 1,456,819 0.25 7.48 2,724,252 1.5 13 5,312.=90 47,810614LU13 186,430 8.5 ,4,655 0.25 7.48 963,305 1.5 1.3 15,77,444 52,006,000LB 175,981 10.6 1,865,399 0.25 7.48 348 95 1.5 1.3 6,82,176 61,219.584UC 181.120 9.1 1,648,192 0.25 7.48 3082119 1.5 1.3 - 6,010_132 54,091,189

ULC 107,214 6.8 729,155 0.25 7.48 1 63 33 1.5 1.3 2.658,500 23 926498LC 169,010 6.5 1,098.65 0.25 7.48 2054 17 1.5 1.3 4,005,917 36,053,255UD 1427694 8.6 l1227168 0.25 7.48 2.294,805 1.5 1.3 4,474,870 40.273.826MD 75r350 11.2 843,920 0.25 7.48 1,578.130 1.5 1.3 -. 354 27,696,189LD 170.394 11.2 P08,413 0.25 7.48 3,568,732 1.5 1.3 959027 62,631,245UE 265,391 10.2 2.70Q988 0.25 7.48 5,062,068 1.5 1.3 9,871,032 8%839.=LE 361,312 7.7 278102 0.25 7.48 5,2531 1.5 1.3 10,1

9 3 6 91.304.428

TAIS 2,501,9481 21,722,900 40,621,823 79.212.556 712.g13000

Explanation of Headings:

Area - Area of cut off grade mineralization.Tk - Thickness of cut off grade mineMlization.Por - Estimated porosity of the rock.PV - Straight pore volume without any correction.H-PIF -Horizontal pore volume incase factor.V-PIF - Vertical pore volume increase factor.CPV - Corrected pore Volume.

'Tlare" factors or pore volume increase factors are multipliers that are commonly used bythe ISL industry to account for leach solution outside of the specific boundaries of the calculated

calculated by multiplying the volume of rock by the percent porosity and then coverting to the units ofmeasurement (i.e. gallons). The total PV of a mine unit is calculated by adding all the five spot patterns in themine unit. This method works well for existing ISL operations where the ore had been fully delineated andwellfield installed such as the existing projects in Wyoming.12 Future wefield patterns will be constructed within the ore that is economic at the time. Patterns will be a subsetof the overall "ore area".13 Testimony of April Lafferty, May 23, 2001 ¶ 21, Lafferty states that HRI does not use site specific data. Astabulated above HRI data is site specific and is based on a zone by zone analysis of the area and thickness of the orebody based on information derived from exploration geophysical logs. This type of analysis is far more detailedthan the general method suggested by Lafferty where she uses the area within the monitor well ring and concludesthat an additional 13 months or 25% more time would be required to conduct groundwater restoration. Lafferty'sanalysis would have an operator post surety for the reclamation of water that has not even been affected byleaching.

Page 13: Church Rock Section 17 Restoration Action Plan.

July •3, 2001

ore PV and are generally accepted increases14 that should be recognized in costestimates.. HRIuses porevol0ume increaserfactors ofl-ý.5for horizontal and 1.3.for vertidals. Hofizontal.,increaseis cakculated by multiplying the, measured or mapped area of the ore, in plan, and multiplyingitheactual area by 1.5. This yields the affected horizontal 'area.. Likewise, vertical increas e iscalculated by multiplying the measures average thickness of the 'ore. by 1.3. Tlis. yields theaffected vertical area. Multiplying the affected.hofizontal times the affected vertical'by porosity.provides the affected pore volume for the, surety cost estimation. This number is in -turnmultiplied by 9 to determine-water treatment and disposal volumes that are entered into the model-to• calculate cqOst. The '1.5 for ho0iontal and 1`3 for vertal porevolume ince factors have

been. calculated by URI engineers based on operating. experience at other restorationdemonstrations and commercial operations and have been. adequate, for monitoring and, reporgrestoration progress at- other operations. During the ChurChrock restoration demonstration that

tisgdescribed inLC 10.28, HRI will user these factorsto measurethe number of pore volumes thatare processed duing restoration.

The methods utilized in the RAP to calculate pore volume and adjusted pore volumes are.consistent with the,methods used for the Mobil Section 9 "Pilot. in New Mexico, which in turnwere the basis for the NRC evaluafionin the FEIS, and are consistent with the methods: used byHRI throughout the CUP licensing. process, and for HRI's submittals during the Subpart. Lhearing. HIM methods ..to calculate pore volume-,and adjusted pore volumes,, and the factors-thatwere used were, not generic, or arbitrary, but rather were consistently proposed, evaluated,litigated and applied throughout the NRC licensing process and this.Subpairt L proceeding.

HII presented the NRC with the Summary'Report for the -Section. 9 In. Situ Leach Pilot1 6

:as a, part of the:License Application support materials because the Pilot was a. substantial- fielddemon.stratioon, and prodvided empirical results]7,- for the ISL development that is:proposed for theCUIP., This Report was a compilation. of the information friom Mobil Oil Company's files andrecords that were, developed when 'the Pilot was. cnducted. HRI. utilized. actual patterndimensions and the actual number of gallons processed during the restoration to compile thesummary report.

4,7Flare, outside of the orel zone is the norm. In the subsurface water move in a radial patter frorm injector toextractor in its path, across the target, ore; By choosing patterns.carefully flair is minimize& However,, asanexpected component, of ISL mining the flair factors, are -included in the bonding calculation as a delileate cost,contingency. Thereissa limit on acceptable flair, the horizontal monitor wells. If fluid is detectedin the horizontalmonitor wellsit'is -no longer simply flair, but then becomesanr excursio•n An excursion .reqi immediate,coective acidonto drawitbac tothe mine zone or the bonding mu beincreasd!ftocomvente for'the.in'crinr on cost (,__ L.C. '10.13which requiresa bondincrease if conrctiveactionis:not completed in60 days)13 Combined-pore volume increase factor.is 1.95.!6 See;Pelizza Affidavit January 19, 2001, Attachment 1.'7The. Section.9 Pilot dataý provide actual ore zone dimensions, and gallons. processed, so thatactual pore-volumecan be processed. ENDAUM witness Lafftity Testimnony May, 23ý 20 -1'¶14.specifically recognizes the-importanceof knowing the quantity of water removed from the~formation in calculating pore volumes".., if:the flair factorwere.icrased,. the number of LpoM Volumes requid should be decreased. Thisscenario may be:true onlyif thetotal gallons of, impact groundwater whereknown." The value ofthe. Section 9 Pilot, or :any demonstration, isthat it'provides known, variables to the equation that allows'porevoume incrae' factors t6 be. assigned. GiOesimila minin technology and geology, the pore volume actors from a demonstration, such as the section

9 Pilot, canbe.applied to an analogous site such as the ChurchrockSection 1716cafibn.

Page 14: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

The cumulative restoration analyses in Attachment C of the Summary Report show that59,173,469 gallons during restoration of the Section 9 Pilot, which equated to 16.7 adjusted porevolumes. Table 2 shows how the adjusted pore volume was calculated using the pattern area,screen thickness, porosity, a horizontal pore volume increase factor of 1.5, and a vertical porevolume increase factor of 1.3. The methods of pore volume analysis utilized in the SummaryReport form the foundation of the NRC impact evaluation in Section 4.3.1 of the FEIS whichultimately resulted in the staff determination that 9 pore volumes would be required for suretycalculations". It is important that HRM continue to use the previously evaluated pore volumeincrease factors in the RAP, and in future restoration analyses for the NRC, so that can projectedand actual performance and costs can be-measured consistently.

Table 2 - Section 9 Pore Volume Calculation

ZONE [ ftlTk(ft)1 Vol(fP3) Por [a3 PV(gal) jH-PIFjV-PIFj CPV(al)V • I -5sfie 1 40,4881 24 1 971,712 0.25 1 7. 1 1,817,1011 1.5 1-13 3 543,3471 ,59,173,4691 16.69

Explanation of Headiuip:

Area - Area oftut offspade minerdizao.7k - Thicknes of cut offga minera oPor - Estimated porosity ofthe rock.FV ,SwrigMt pm volume without any conetion.H-PIP - Horizontal pore volume imncease factor.V-nF - Vatical pin volmne me fator.CPV - Created pm Voimm

HRI has presented similar pore volume estimates during the license application reviewprocess. Specifically, in response to NRC Request for Further Information, Question 59, August15, 1996, pertaining to Ground water Consumption, HRI supplied NRC with a pore volumecalculation for the Churchrock Section 8 site that was similar to the one presented in the RAPSection 2.aP"2 . Consistent with the methodology used throughout the Crownpoint ProjectLicensing process, HRI utilized the ore body outline, not pattern dimensions, to determine theaffected surface area and used a horizontal increase factor of 1.5. These were the same valuesutilized by NRC to conduct the evaluation of water consumption in the FEIS21. HRI's proposedpore volume increase factors are consistent with those, which had been systematically evaluated inthe FEIS22. The FEIS has been found to be adequate for the purpose of licensing the CrownpointUranium Project.2

In summary, HRM correctly used the same methods to calculate adjusted pore volumes inthe RAP cost estimate because they were like those that NRC reviewed, in HRI submittals, that

' See FEIS p. 4440'9 Based on professional judgment, HRI MU rae the estimated.porosity from .21 in Q/59 to .25 in the RAP. Thisresmlted in a more conservative estimate in the RAP. All other factors are the same.20 See RAI Q1/59.11 See FEIS pp. 4-57 through 4-60.22 FEIS p. 4-122 used a combined horizontal and vertical pore volume increase factor of 1.95. I.e 1.3 (HDF) x 1.5(VDF) = 1.95.23 See COMMISSION CLI-0O-04.

Page 15: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

NRC used in the FEIS impact evaluation, and that was placed into evidence by the HRI in thecourse of the Subpart L hearing process.

As an additional test for reasonableness of HRI's cost estimate, Table 3 below comparesimportant project variables for PRI's Highland Uranium Project in Wyominge against similarproject variables for HRI's Churchrock project". Table 3 brings into context the comparativesize, and corresponding scope of reclamation, of the two projects. In this table the actual suretyamount for PRI are shown against the proposed surety amount from this RAP-17. Reviewing thedata in Table 2 in the context of number of wells, acres of wellfield pattern, years of operation andthroughput 26, and number of satellite locations, the PRI Highland project exceeds the size of theHRI Churchrock project by a significant amount. The PRI Highland adjusted pore volume isabout three to four times greater than that estimated by HIRI for the Churchrock site". In thecomparative measures of S/acre wellfield, or S/pound produced, HRI proposed surety amountexceeds that of PRI. In the comparative measures of water process cost in $/ m gal., HRI'sproposed surety amount is slightly less than PRI2'. It is also worthy to note that HR[ estimatedComparative PV size (mm gal.) /acre wellfield is much greater that PRI, most likely because HRIuse of pore volume increase factors is conservative when used in combination with the ore outlinevolume assumptions.

Table 3 - Comparison of Key Project Variables and Reclamation Costs

Project Variables PRIe HRI Section.17Number of wells (all) -4141 -276Acres of welnfield patterns -189 -2830Years of operation 13 4.5Cumulative production (mm lbs. U30%) -13 -3Nominal throughput (gallon per minute) 9000 4000Number of satellites 331 0Number of pore volume's used in surety estimate 6 9Size of adjusted restoration volume (billion gallons) -2.71 -. 713Comparative PV size ( mm gal.) /acre wellfield 14.3 25.5Restoration estimate (-mm $) $21.12 $5.1Comparative /acre wellfild $111,751 $182,142Comparative S/mnd produced $1.63 $1.70Comparative process cost $/re gal. $7.79 $7.19

2 See Testimony of April Lafferty, May 23, 20011 11.25 Mr. Ingle Testimony of December 19, 2000, p. 3 1 states "there is considerable relevant and analogous uraniumISL restoration experience in Wyoming to draw from to develop credible cost estimates".26 Throughput needs to be viewed together with years of operation. While the Highland per minute throughput is -2 times Chr'chrock, operations have been conducted for many more years. Therefore, more mining has beenconducted by PRI at the Highland site than is reflected in the design process capacity.27 As stated in 5 above, it is anticipated that if HKI was to use wellfield patterns rather that ore boundary areas thenthe pore volume and adjusted pore volumes would be smaller and more proportional to PRI when compared to wellfield pattern acreage.28 Dr. Abitz Testimony dated May 23, 2001 continues to describe reasons to use unit groundwater costs from theFernald site. It is more appropriate to use a similar NRC licensed ISL facility.29 Actual from information provided by PRI staff.30 Estimated from COP 2.0, Figure 1.4-8.31 PRI costs include the D & D of the also include the mother plant.

Page 16: Church Rock Section 17 Restoration Action Plan.

July 23,92001

.2.5. Treatment of -Mine Workings

Mine, workings will. not affect groundwater restoration volumes.12 Aside-f om the;reducedrestoration requirements in the mine workings described in the paragraph below, ýthel quantity ofwater that will be processed during restoration of the. mine workings.Will be less .than the! volumesproduced during restoration of native-undisturbed ground given the following factors:,

a Porosity used in, native (unmined) formation sand- iS,25 percent.0. Restoration pore volumesi .native formationiis:9.0 Porosity-in-mineeworkings is I• Restoration pore volumes in mine workings is 1.

The interaction. of lixivint with rock matrix "in the. mined' sandstone shouldl requires,additional flushing during restoration as compared to the mine workings:, which contain onlywater. Also, ,as described below, the'baseline-water quality of the mine-workings is considerablyworse than that, of the native formation sandstone at some distance from the, mine, tunnels. Thusnine-pore volumes of restoration iS.,shown for native formation sandstone and one pore volumefor the -mine workings.

In the case ofmine workings, the water quality target during restoration. operations will. bechanged because conventional mining processes have both chemically affected the mine-water andmechanically altered the host rock. In fact, historic. conventional mining activities have resulted inconsiderably more extensive' mechanical degradation (through excavation) of the formation sandthan would occur. from the proposed in situ leach.-activities. Geochemically, 6xidation due-todewatering and mine ventilationhas resultedlin pre-in situ mining water quality which is similar tothe projected leach solution (see Table 4-below). Therefore, the restoration target Will be higherfor the mine -workings than for the native formation and less restoration will be required.Additionally, since the rock matrix has, been ;removed in the-existing mine: workings, ,theý expectedwater/rock geochemical interaction .during. restoration will be elited, or at least virtually,eliminated, and, only a singles- pore volume of water will require extraction: and/or processing.Given. the nature of the restoration target goal' and the lack, of-natural rock to equilibrate with,restoration water, the one pore volume assumption is reasonable..

Because one -pore volume is-a reasonable assumption for restoration in the-workings, andthe porosity is 100 percent, the total volume of water that will be extracted .and/or processed fromthe workings is approximately 2.•9millibn cubic feet or.22 million gallons (the. same volume as the.workings). This-same volume of formation sandstone, if it had.not been dewatered and excavatedby conventional mining at 25 percent, porosity and nine pore volumes of restoration would beapproximately-45 million gallons. Using a-horizontal pore volume increasefactor of .5 and avertical pore: volume increase factor ,of S.3 will increase the quantity-. of water used in the,restoration -cost. estimate to 96.52 million gallons or morelthan four times what would be used-ifthe workings were broken out- separately.

32 S~ FEIS'p. 447-.

Page 17: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

HRI's estimate-in, the: Table, 1 Churchrock Section 17 Pore:'Volume Calculation will treat.the mine workings as natural rock. The workings will be subject to the same pore volumeincrease factor and 9 pore volumes of circulation will be used. For the. reason 'stated above; thiswigve a greater quanityof water for restorationý osesN and result in a higher cost estimatethan ifthe Workings were broken out and treated sepakatel'y.

2.6. Ground Water Quality

Once the economic: recovery limit of a miner area-is reached,ý lixiviantinjection is stopped,and the affected ground water is treated (restored) to return the quality of water to regulatorystandards. The Churchrock Section-,17 location is different that the adjacent Churchrock Section8 location in that itfhas already been, subject to conventional underground mining ( _te,2.5 above).This has affected water quality-in the mine zone-as most, notably seen-in Total Dissolved Solids.As shown in Table 4 below, TDSI in the Section, 17 portion of the Westwater Canyon Aquifer(".,OCR" samples below). exceeds those found in the adjacent Section 8 portion of the WestwaterCanyon Aquifer., In fact, TDS inf the mine zone moe, closely represents' that Toundd .i- HRI coreleach:studies and the nearby. Teton Pilot test. The uranium values in, the in the:Section, 17 portionoffhe Wýstwater.Canyon Aquifer ("OCR'"samples'below) excee&4?'the .44 mg/I 1 OCFR.Part 20secondary restoration goal35 in three of'four sample locations as compared to the uranium valuesin'.- the in the Section 8 portion of the Westwater Canyon Aquifer ("CR" samples, below) exceed36

the .44 mg/Il OCFR Part 20 secondary restoration goal in twoof four sanplejlocations. In bothcases these urani rum values would be treated as baseline3 7. In the case-of Section:8 the uranium isnaturally occurring because of the proximity 'of the uranium orebody. In the case of;Section.17the current waterquality (both dissolved solids: and radionuclides) is& the result of conventionaluraniumh= minig Which falls outside the Commissions authority38 and in future ISL would be.,treated as !baseline.

33 The groundýAter :dafta that has been. collect to dat is Mot intended to itplace the more detailedcharat tion that isrrequiredbyL.CQ 10I2I' & L.C. 10.22'before injection begins. The existing information doesprovide a pictre of the qualityof grodwater'in the mineralized portion of the, Westwater, Canyon Aquifer, at theChchrock Section 17, & Section 8 sites.3 See Dr. AbitzTestimony dated May 23, 2001,'¶10..35ýFEISp. 4-27.36 Table I of.Dr. Abitz :Testimony dated- May 23, 2001 'mitsthe baseline data for baseline well CR4, and.mistakenly descrbes .CR3 as ore zone well when itis-actilly completed in the'tRbapirFornaftio Using'thisincorrect'data ,he concludes "Perhaps Mr. Pelizza thinks that the high uranium levelsmeasured in the post-undergrud miningwaters assoca•with the Old' Church 'Rock Mine in Section 17 are.partof the.pre-minhingconditions at Sectirn8. Clearly; higher uranium concentrations measured at the Old Church Rocký Mine workings:are not indicative; of pre-mining'conditions below Section 8." The sample data' from CR-6 AND CR-8 (both,Secton 8 Westwater Canyon baseline wells) provide strongevidence -thatthroughoutthe Churchrock mineralizedzone, uranium concentrations may exceed the .44 mg/I10 .CFR Part 20 secondary'restorationtgoal. All. fouroftheSection 8 Westwater Canyon baseline wells exceed the EPA primary drinking standard Contrar to Abitzat.110,Churchrock ore zone water. quality is more'limited due to radionuclide values than-the Fernald example.0 The-natural radionuclide mineralization in uranium ore zones.limits the baseline water's use as drinking 'waterand contrary to.Dr. Abitz in'his Testimony dated -May 23, 2001, ¶8 & 9ebasaeine.restoration :standarde•,not EPAdrnkngwater linit wouldprevail•3 ' Letter dated January 17, 2001 from Richard Meserve to, Paul Gorenson states: "Ydu raise •the point that theCommission's decisionvcould impact efforts to dewater a conventional mine (activities 'inwhich water is.treated to

Page 18: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

Table 4 - Comparison of Total Dissolved Solids (TDS)in Waters from Various Locations and Leach Tests

in the Churchrock Area

Location Uranium TDSor Sands * Date of Analysis (mg/l) (mg/i)

Test *

OCR Shaft BB / WC Sept, 1993 3.07 1,300OCR Gravel Shaft Westwater Canyon Sept, 1993 .041 1,070

OCR VH #1 BB / WC Sept, 1993 3.55 1,290OCR VH #2 Westwater Canyon Sept, 1993 3.41 1,320

CR-3 Westwater Canyon 13 Sample Avg. 0.064 359CR-5 Westwater Canyon 12 Sample Avg. 0.017 339CR-6 Westwater Canyon 12 Sample Avg. 0.474 384CR-8 Westwater Canyon 6 Sample Avg. 6.63 397

CR CoreLeach #1 (1) WestwaterCanyon Sept, 1988 19.2 1,695CR Core Leach #2 (1) Westwater Canyon Feb, 1988 40.9 970

Teton Pilot Test (1,2) Westwater Canyon June, 1980 84 976

Footnotes:

• Abbreviations: OCR = Old Churcbrock; CR = Chjrchrock; VH = Vent Hole;BB = Brushy Basin; WC = Westwater Canyon;

(1) Water samples taken near end of leaching and prior to restoration.(2) Water samples taken near end of leaching and prior to restoration at the Teton pilot test onthe Mancos property near HRr's Churchrock project.

LC 9.14 States: 'Prior to injection of lixiviant, the licensee shall obtain all necessarypermits and licenses from the appropriate regulatory authorities". At the Section 17 location thisprovision requires that HRI acquire an Underground Injection Control Permit through either the

remove uranium so that it may be discharged under a Clean Water Act National Pollutant Discharge EliminationStandards [NPDES] permit). The Commission s decision to treat all waste streams associated with ISL activities as11 e.(2) byproduct material does not impact conventional mine dewatering for the, purposes of mining. Althoughthe Commission has comprehensive regulatory authority over waste derived from uranium and thorium extractionactivities, that authority does not extend to uranium mining. See Kerr-c v. NRC 903 F.2d 1, 7 (D.C. Cir.1990). The Commission continues to believe that, although ISL activities are freluently refere to as mining, theyare not mining in the conventional sense, but instead represent extraction of source material from an ore body in afashion that is in many respects akin to processin. This fact is the fundamental basis for NRC regulation of ISLfacilities. Consequently, wastes from dewatering a conventional mine, although perhaps being processed in thesame manner as restoration waters at an ISL facility, are not subject to NRC regulation because they are a functionof mining, notan aspect of the processing of ore for the express purpose of the extraction source material I SeeInternational Uranium Corporation (USA) 51 NRC at 15-16."

Page 19: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

USEPA or Agreement State andý an Aquifer Exemption39 . Aquifer Exemption is aregulatory,devse of the USEPA that is used to designate, aquifers or portions of aquifers that wouldnormally qual'if as an, underground -source of drinking water as "exempt" because, they -are.mineralized and producible of minerals in commercial quantities. HRI has not acquired either ofthese authorizations or the Section 17 locationhat this time but will be:required todoso by NRCand USEPA before operations begin.4

2.6. GroundWater. Restoration Budget LineItem Assumptions

HRI used historic and ongoing. company experience with similar ISL uranium recoveryand groundwater restoration, operations in developing its budget. model. For example;becauseURI, HRI's sister company is currently reclaiming two other commercial ISL mines, IIU drew-onthis experience to aid, in sizing labor requirements, maintenance needs and. other cost categories,that may not be apparent to someone without similar "hands on" experience. Unit labor costs are

-the same aswhat was provided to, NqRC' apart ofthe: license review, of the overall project.4 1 In

addition HI" used actual costs estimates fromthlie reg'infot utilities,. and othermaterinis thatwillbe used in reclamation.

The assumptions that were used iin the groundwater restoration budget (See AttachmentE-2-l)rare as follows:

For the purpose 0f-the Financial Assurance Plan, HRI assumed employment of technical-professionals whose expertise is needed on a limited basis during the restoration mode.

• 40CFR 146.4 states: "An 4quifer or a portion thereof which.meetsthe :criteria for an "uiderground source.ofdrinking water" in .§ 146;3.may be determined under 40,.CFR 144.8 to beanv "exempted aqufe" if it meets thefollowing criteria:(a). It~does not currently serve as, a source of drinking water;,and,(b) It cannot nowandwill not in the future, serve as a source of drinkingwater because:

() Itkisminrhydrocarbon or geothermal energyproducing,,or can be demonstrated bya,permit applicant as part of a permieapplication, for a:Class I.or-M.operation to contaimnmineralsor hydrocabons that considering their quantity and location are. expected to be commerciaRy.producible.(2) Itist stuitdat a depth orlocation which makes rew0oveyof water. for drinkcing waterpurposes economically or technologically impractical;(3) It is socotminat6e:that it would. be ecanomically or technologically impract torenderthat water fit for human consumption;o(4) It is locatdver. a Class MIwell mingarea subject to, subsidnceor ctastroph•iccollapse;..."

4°Dr. Abitz Testimony dated May 23, 2001, Footnote3 states-that MU does nothave avalidaquifer •on forthe ,ChurchrockSection, 8 location-because it was reversed by the le'Circuit.. Court. In fact the Court determinedthatlfor the Churchrock Section 8, location a jurisdictional dispute.existed, and that until the, dispute.was resolvedthat, EPA not. the State of:New Mexico.has jurisdiction over issuance of UJC permits. The Aquifer. &emptibn for:theChurc•hrock Section 8"ocation(qr anylocation) is issued by USEPA and the Section.8 8Aquif Exemption hasnotbeen withdrawn bytUSEPA. It -appears -that Dr.,,Abitz, is confusing he Aquifer Exemption with the. ICPermit Additionally,, nothing.in the Courts-decision cast doubt on factual. determainations with. regard 0, theState's,UIC Permit or the EPAAquifer Exemption.41 Seg-RAI'QI8 -Feb. 19, 1996.

Page 20: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

Anticipated positions. are listed in the Restoration Budget rows '1-15. However,,to justify their full'time status. and utilize their time on the job, ;it' is assumed. that they are required to provide amultitude of services, i.e., every employee wiTlbe wearing multiple hats. As such, individual jobdescriptions are difficult. For example, in the 'restoration mode, a qualified geologist will: berequired to verify the configuration of restoration patterns to assure efficient results. While thistask requires unique geological expertise;. the time commitment by the geologist to, this task mayonly be several.hours per week., Therefore, to maxhize the use of the, geologist time, he or shewill be assigned to many other tasks for which he or she Will be qualified such as lab analyst, wellsampler, and plant operator. HRI also plans to maintain, several other technical disciplines on staffsuch as radiation safety specialist, and engineers. In the restoration mode they will also performtheir primary finiction and a number of-secondary roles.

Reflecting the very broad nature of each full time employee's job at the CUP during the,restoration mode, the following is a summary of each position that is budgeted in the FinancialAssurance Plan. Anticipated salarie3 that were used in the budget are within Attachment E-2-4.

Operations Manager. AInCharge of all'aspects-of day-to-day activities and planning :forCrownpoint Uranium Project D & D. Responsible- for interface with accounting services includingcoding and approval of all invoices, monthly cost analysis, restoration report generation, andemployee relationresponsibilities.

Environmental Manager. Responsible for the radiation health.and safety, :environmentalcompliance and quality assurance program at the Crownpoint. Uranium Project; Supervise theRadiation Safety Officers to. ensure that all radiation safety, environmental compliance andpermitting/licensing programs, will be conducted inma'responsible-manner and in compliance, with.all applicable regulations and permit/license conditions. Serve as Companyliaison with regulatoryagencies over the term of the restoration activity.

Radiation Safety Officer. Responsible f6r compliance with all USNRC, and MSHA rulesand regulations at, the CUP. Also responsible for assistance with laboratory analysis, vehiclesafety, reporting and public information.

Chemist. Responsible for,. maintaining day to day, analytical, services-including operationaland. environmental. In this capacity the chemist will.assure that proper chemical parameters arereported to operations for the. water treatment processes. He will be responsible for performinganalysis of all routine environmental samples such as monitorwells.

Senior Geologist. Responsible 'for evaltion of logs, and other Well data and itsinterpretation as it pertains to restoration activities. Performs all monitor, well, sampling duties, andwhen possible, helps with wellfield construction as well as Smeal pump hoist operation. Dutiesinclude drafting and ACAD'operator for mapping needs. Provides weekend'call-out and. rotating,operator duties as needed.

Wellfie!d Foreman. Responsible for Wellfield operation and construction. as it pertains- torestoration. Helps with monitor well sampling and backup pump hoist operator.

Page 21: Church Rock Section 17 Restoration Action Plan.

JulyI23,2001

Wages-Direct'

Electrician Responsible: for performing day to day -electrical maintenance. and repairsrces. Performs restoration operator duties on a rotating basis.

Plant Operator. Performs restoration operator duties :on a regular basis. This 'wouldinclidethe operations of :all water treatment equipment including-'the' reverse osmosis unit andbrine concentrator.

Truck driver. Provides CDL driver duties. Will serve as backhoe operator and have,operator duties on a rotating basis.

Wellfield Operator. Perform wellfield restoration operator duties on a regular basis and.rotationsiwith the Plant Operator.

Pump Hoist Operator. Responsible-for the running of-pumps in and out ofithehole as,required'by restoration -activities. Other duties include the operation of the backhoecand labornecessary for field construction..

Insurance-WorlbWa's Compensation

Estimate based, on. projected compensation expenses and prevailing rates.

Payroll Taxes

Estimate based on projected compensation, expensesIand prevailing rates.

Medical Insurance

Estimate based on.headcount and historic premium rates.

401K Contributions

The 401(k)'Contribution cost codesý represent.HRI-funded contributions' underthe,401(k)- the retirement savings plan for :H'R employees. The 401 (k) Contribution portion is made:;concurrent with each bi-weekly payroll, period as a component of each eligible employee's totalcompensation.

Telephone/Telegraph

IEstimated average costs. of regular telephone service, cellular telephone service, and faxlineservice and intern.etline service at all CUPlocations.

Page 22: Church Rock Section 17 Restoration Action Plan.

Juldy. 23o201,

Postage/Freight

Estimated averagelcost of all types of mail service.

Copy Equipment

Estimate average cost for operation of all :types of copy and fax equipment atý all ,CUPlocations.

Other Equipment & Rental

This covers the rental of equipment and :miscellaneous equipment average costs. Asapplied in these estimates, it would include office machine rental, water machines, for potablewater; etc.

Office Supplies

Estimated average costs of office suppliessuch as paper, pens, etc.

Office Equipment Maintenance.

Estimate average :cost for -maintenance for all types of office, equipment at all CUPlocations.

Data Procesping

Estimated average cost for outside data-processing.,

Maps

Estimated average cost of plotting, and reproducing maps for routine, operations andreports.

Drafting & Printing

.Estimated average, for outside, computer automated drawing services for reportpreparation.

Transportation -.Air & Car

Estimated average' for airplane tickets and auto rental.

Meals

Estimated average for travel, related meals.

Page 23: Church Rock Section 17 Restoration Action Plan.

July'2,3,2ý;001,

Misc. Traveltxpense

Estimated average'fOr travel related expensessuch as hotels:.

,EnvDeprecible Equipment1

Replacement equipment and calibration-costs., This would :include: survey andi, sample'equipment-and routine calibration and service.

Env-0peration•,'analyses

This cost code'is-reserved-for outside'analysis

Environmnent - Miscellaneous

As .the name suggests,, any environmental related item not specifically addressed in: theother codes 0190 throUgh.098. Miscellaneous. items may include sample0boes, fltrs, reagents,calibration; etc.

Sqfety.

This isfor costs associated, with safety,, supplies forpthe employees. Items charged to thiS.cost code Would include safety boots, safety glasses, potable water, protective gloves, safkygoggles etc,

Backhoe

All backhoe rental and maintenance such as, oiltchanges, and, repairs would be charged tothis account

Misc. Chemicals

Ther miajor chargewtothis costcdduring restoration is anti-saent forthe RO.Utiliftfes.- Electric, -Welfield

Calculated electrical cost, for operating the pumps-and other, equipment min'theweilfield.The~basisifor these costsisshowin Attachment E-2-2.

Utilities-,Electric, Brine Concentrator,

CAlculated ele6trical cost-for-operait•ng 1te rne;econcentrator. Thebasis for:these costsisýshown in Attachment E-2-2.

Page 24: Church Rock Section 17 Restoration Action Plan.

July P9:2001

Utilities - ElectTh, Plant and RO

Calculated' electrical cost for operating the plant, reverse osmosis unit, and- other officelighting and electrical needs. The basis for these•c•sts is shown in Attachment E-2-2.

Submersible Puimps

Estimated average maintenance and. replacement costs for submersible pumps that areused in extraction wells.

Submersible Motors

Estimated average maintenance andý replacement *costs for submersible pump Ielectricmotors that are used in extractionwwells.

Field Pping & Vatoes

Estimated average maintenance and replacement costs for the various fittings, valves,.glues etc. that isused ain wellfield operations.

Estimated averagezmaintenance and replacement costs for wellfield meters.

Misc. Field

The major charge to this cost code during restoration is PPE, rags, solvents and othermiscellaneous field needs.

Handibols

Estimated average handtool replacement-costs

Plant Piping & Valves

Estimated average maintenance and replacementc:osts for ýthe various fittings, vaivest,glues etc. that is used in plant operafiOns

Plat Brine, Concentrator Inst.

A cost code to charge'anticipated brine c.ncentrator instrument replacement.

Pumps

Page 25: Church Rock Section 17 Restoration Action Plan.

Jldyi23,2001

Estimated average maintenance and replacement costs for pumps, that are used in- thewater treatment plant.

Plant Electrical

Estimated average; electrical maintenance .and replacement costs for water treatment plantoperations.

Filters

Estimated average filter and filter media.. replacement costs and maintenance costs forfiltration equipment.for water treatment plant operations.

Evaporation-Ponds

A cost code to charge anticipated maintenance costs for pond finer repairs andmaintenance.

Roads,

A cost code to charge antficipated maintenance costs-for-road maintenance.

Gas, Oil, and Grease

Equipment fuel costs and lubrication.

Disposal - BC Solids

Ongoig operationalzcost of-dispo sing salt residuefrom bfine concentrator. The basis forthese costs is shownin, Attachment E-2-2.

RO. Unit

A'cost code to charge, anticipated reverse osmosis unit repair, maintenance and instrumentreplacement.

Lab Supplies

Est ted average costs of analytical laboratory supplies such as reagents, filters,glassware, etc.

RO Membrane

Average replacement costs of reverse osmosis-unit membranes. The basis for these costs isshown in Attachment E-2-2.

Page 26: Church Rock Section 17 Restoration Action Plan.

Juy 23', 2001

Field Equip.,Repairs & Maint.

A cost code to charge anticipated maintenance costs for large field 6equpment such as the,pump host- equipment, generators, and trucks.

VehicleRepairs & Maint.A cost code to chargeatcipated ie c costs 'for road vehicles such as pick up,

trucks and company autos.

Vehicles -PiCkups.

The estimatedaverageýcost lbrthe maor repair ofwacompany pickupltruck.

Vehicles - Tractors & Trucks

The estiaed average cost forbthe *or rep-air of a l-arge trucks or trailers.

Vehicles-, Automobiles

The estimatedraverage cost. for the major repair ofa company car.

The.total cost for groundwater restoration and post restoration management is projected-tobe $4,089,818.

Page 27: Church Rock Section 17 Restoration Action Plan.

Jul~y23, 2001

ATTACHMENT:E-2-1GROUNDWATERRESTORATION BUDGET

Page 28: Church Rock Section 17 Restoration Action Plan.

CWmARCPNcTJCN 17OAOWWATERMWJTWATM #AND.~UWfi OT-- ~ *am vmn~win*W36 0360366AMR4

ftw.&,igU.lM

I.. M.. If~ff INS I d fft I If I tM I

S4Is fitouft

17 F~wmpf

13 amn dme"0H~~WU

14 mokw"Oo6ubo

3 akI Fm031 1101"

37 mom

27 03Oin4*

a

in ON3ftainM3

41 t~o5260"l1k

12 36363336ft ,6E3

74 O

is FAM.FmO& dm

64 PUMOV0N

61 BTrdI614AOIIWASW6

IN Iftit .is 03.1036,03

II

11tt

I1III

I1I$

tI

Itti

1!!

1

111I

1t1

I

1 11

I11i

It1

I1

IIII

I1!

1t

t1

1ttI

tt

1It1

t!1I

11

I

II

1

1

1 1 ItI 1 1 1 1t 1 It If It

44 44 44 44 4" 40 am 4 4 44 ON 494,14s 116 Is 113 111 1" 111 1s 1In 1" ild 11s

A4M= MUM63 -l~ Allum MM31* 346413 Wi4MW 344*6 -oo U3JM Mum60 3.30W7111 1657MW 3712.41 14Mum 3.71ya3 364.461m 3.7am 3.74W 313.13 3.713* 314MW sky"Af&Mlm* 454* 6764 41"m 4*6i IMill &O11 6,11326* Vm7& win* 56172430 Oti* 14474.2

1n IS In I3 13 to I3 IS in in M3 inI12 1131 1126 IllS ¶116 ¶113A 11 11ns M 1n6 t 1136 111 13

is z6 211 2A is as is as 26 as as 24513* 6*6*6t loo 6.031 MOM* - a*6m 164I LMM14 - 644513 MomI6.034 4M7M.1 so6451 4SOM* Aallm 6.13451 AMIMM4 Uum*4 466456 SAMM6 4*6113 6.136

111*6 WOO46 "Oft6 WS4*6 "I'M6 36113 I11* 11116 Ism*1 1116 O41* I1

712612*6 137.14.41 66*117* W.MM. 01266.41 SOR603 131.M.3 O&O 610316 *6*6M 4427RM1 O4127*0 41A M* $A an M4 71A ?A 73 7S is3 7.12

Anom3 36.1*406 3.73* 26.646 2171"M6 26.6403 AnsW 267451 26446 3 m 26*4W 3k775.3ILI? 6.14 4.17 an .17 6.17 air MV1 W1 ail7 W17 OR1

371456 AlU 76575* 465A56 13*665 164*1* MIAM51 2151451 247*6.46 2D*6W 26*6* 36.1303MY1 0.34 am1 0as an1 IM6 M3 w 424 1.32 is 2*S

64313M0 117.13 WXA* 66122MA* 36*6U Am.11* 231,12=. A14*665 40AM* 4132PUM 4MWM7* A4.667*$A6 41A to4 in2 I14 7A 7*O 7A6 716 ?A 7.12 US

ow~m

vs6.4 MW4 *IW *saw4 low1 tow tow.4 1ww 610* 61614 616.44 610Ms) 041M stag 61.3 sl.im @16 61.3 slim3 MAN6 11430 6.3 Olinam am am M WAR WSW win mm SM sm SMm $M6404 64.27 64u27 5427 34*4 64*4 SUPS sun57 64 "An4 64*4 64SIAN slim slim3 Sim1 "An6 SIM6 64M1 06 "An6 SIM6 "An1 WAS61*6 sun6 61*M slim "An6 am* am* 646 am* 06 516 6SUN

am1 am1 -m 641 am 641 o3 ow 03 ow1 to6 owI= M sw1 Ml1 611 no 03 M3 M3 on M3 06*3 0w M3 M3 M3 0 M3 M3 M M =0 MM3 as ow me 03 =0 me M3 03 M3 03 0mf so M6 m Ms M IND M3M Mow 9M I=6 03 ow1 o1w "a6 o3 03 on1 ow1 01Mso M6 3 M6 w6 M6 M6 w6 IN 3 MIN w6 w6 IN 3 M6 M6 in M w IN IMIWO 03 an so o3 03 03 sw1 am s3 w3 0no M3 =0 03 M =0 no ow M up 03 MM3 03 03 M3 ow M3 an 03 03 no onow 03 03 036 o4 M1 o3 03 &3 6*w 6110 03

am mm mmo um mm mm Um $am SMm MM mmn mmM3 03 M3 03 03 0 on M =0 no 03 IMM3 M3 ow M3 03 0 0 ONO M 11= 03 owon1 WIN 03 03 03 03 03 WIN 0 an go ON

OLI Sam O4 sun am Ilm am am mmS mm4 am3 AMso=* to=61 $123M SAM,3 642M4 flue6 tam.3 slum6 61265 9423m 6* 612.1363M =am 36* mum S*6Wnun *62mm6Na 11632M1 3 SAM033644SMm INA mm m Sim $1m mlm 9Mm $M mm MmN sunno 03I IM M3 03 IM SIM 11M IND Ml4303 03 S M3 03 03 I= IM M M MP IM ow

ow o3 03 SIM3 am ow SIM SOW 103 SIM 0 Zow ow am No an $03 am o3 WIN ow o3 0

03 MD IM me 03 03 03 "a no ow an603 03 SIM No 03 ow o3 ow1 ow ow1 03 ow

IK.13 1164.0 Kim3 01.146 01,113 61.3 61Wn sk.i* KIM4 64.36 6.36 "A.nM6 M6 w6 3 UP M6 M6 w6 3 M 3 INow ow to o3 o3 o3 am 03 IM 03 03 SIM

61.14 6111 61.11 61130 WA.36 64.6 61.113 64LIN 64.IN Kin KIN SIM1316 1316 6464l 1316 so"4 13w6 W4 64t" am6 am am am6ow =0 M3 03 ow M3 M3 M3 M3 M =0ow6 M3 M3 ow0 ow 03 03N 03 to s1 to1 o

sun mmN "m mm IM sun mm am IMm mm mm ammo1w Ol6 610 6413 061 o3 o3 am e3 o3 ow o303 131 woo an 03 03 M3 we6 -m M o owM3 M3 ow 0 an I3 M3 M3 w on ONO am

S.IM SIAN 61*6 SI*6 su*6 el*6 "m* 61*6 61*6 *6 RA*6 ism

91- M 10" Mum ISMA OWN# 613*640 0ISw 44T 113M73 SI44W MIAMI31 a 26 20 31 3D 31 31 30 31 M as

Page 29: Church Rock Section 17 Restoration Action Plan.

CARCIIOK ECTION 17 ORWOLU~TIMMETOM11OAND007COSTRASSaKN iWFUaANDDW 0ONCON41IOOOUINAND HAWYMECE

ftv.*s,2uySM

I W I m I Wi I m I to I to I 4w I tm I IN 1 1117 1 w I aff i

ý Mmft 1 3m 1 41 1 = m m i m a I MR I "a I IM I. 6 14m6 Co

12 o0od"

1"4 36&4gbmdu

30 dMew

*MK MWowb60MM6 1 lS1 .8"W U~.

so I.mooftemuo6027 "W" NW

0 m-mom

46 ownmm

44 aw 4 4now

41 74ft1mamowa

42 3U6somBo4m

*W Mbd

51 U=-jdKM

73 TWNIb'l pwdn

70 NMWA1*

a poroa m~to 36lof6443mm*2 PAW59U

* ~aw6mwU *0U-I M

Pon&G MQW.ýR0ut

VW1 -TM.MTF

72 M311A0.36071 oodow ~ g3

I 1 1 1 1 1 1 1 1 1 t 11 1 1 1 1 I 1 I !11

t

1

1I

l

11Is

11

1!

11!t

11

l1

1t1!

11

l

1111

Il1

t11

1t!1

11

11

111I

It

t

1 s111

11

m m m m6 m so o so so ms s m444 444 4444 444 446 44 4" 46 4.4 446 46 4 461%6 Its it$ its InI "a0 I1" tie 110 1 119 In

AWAN* 2%36.01 MAN0 316011 2WAD* 311111 ASK"3 akul*6 310Awas X111*6 3111* 3161*0*711* IRPOW51 *712*0 *36411 2712160 AMA*64 UM62* mkm2xm MAW"11 *712111 3*4416 *712

is 21 as is 2A as uS am u5 31 as 2

511156 4.7*76 Moo" 4166,3 $AMA* 4.31* 1.Ww6 cook".044 x 4116 14" 4.36*00 goat"111.11 106110 MAW* 166801 111*4 106m tit=1 IIIAN6 "B6AN tit"1 4601 1114M6

446*67* 38M77.W SKMAO MW*11 AN *WARM 2314411 210.7181M 21111MW 117*16 1301011 13UN140 120.6611to6 MY1 so1 64 am1 to 11 ALTO sN 41A &M1 so

*771*1 24.11411 *6WIN S 2651W 771*1 ak6mW *7MWM *7MAW now=6* *71M 3AW 26*011 7MW0.1? 0.1 al17 a17 0.1 0M? MY1 4017 01?7 6.7 .1 0v .17

3391 6** 2613kWKAC =A 41600W.2 10*0 GS 3716*10G 4WA*0* m63011 63226*1 861416* so-MAN* SWISS.=*in1 1A6 2IV 174 m5 so to3 M.4 an0 2170 M1 41

$A7 .1 S4 ex $A M* 1074 to8 M.1 &M2 to 4M

311.3*1*012*0**03601*3*1*0**0*36 61136*10*1*

14.21 *6.24 16*4 sun21 1614 361274 14*4 14*4 14*4 1*4m 664 sun27"An4 61*0 610 "1AW SIAN "An0 1111M "An1 slim 6111 slim1 SIAN$120 $1*0 "An0 K=* M1W SIAN sun 1* 1 01=21 36* 31=3M

VIN a4W 611 1*1 am6 1*1 sm1 614 &M6 sm MW=0 I= me 611 31 no mW m am1 *0 s1mW

W mW MW - mW - mo MW mW =0 =00Mam MW an wo m1 =0 MW no MW MW MW mW

No 36 m 1 *1 so on *1 m6 No m"a1 610 ow6 6111 661 311 110 611 f61 fm0 614 ow3No w6 36 us0 m1 1 w1 wo 6 w 1 w wNo No w1 m1 am0 we ft6 m1 *1 No If

*0 361 sm -m am1 m ow1 MW ow MW sWmWMW MW MW MW mW MW MW MW= W 1 Mme sm MW MW MW MW MW M W W M W311 No1 611 016 sm 141 61 M s11 3*1 m11 611 11

PaW am0 am41 60 m am* um6 am* am* am3 1111 AOMW M MW me W M M W MW MW MW mWMW0 MW mW MW MW MW MW MW MW MW M Wsm sm No ON go1 $M sm MW we sm MW MW

I,44O SL4W Um41 Woo1 Um 8%w6 3*0 82m1 3.4W SIAN1 I&M1 311213 613*0 512 1,6 61* I 12* "U 12M0 012*0 $am* 61wo1 013* MW1ULM 1***031*3 uWW sum sm mum $am "AN su sum UAW 0*181&*110 am su AM -w am6 amW 1W sum 0 A= 1 ow *0mW MW MW MW mW amW MWD MW mW M MW mWMW MW MW MW MW MW MW MW MaWnW M

166 141 so* 14M -m 9001 11 161 sm 161 661 oww Mo m6 3 m ft ms w1 us I m us

SON1 166 am 611 MW No0 noW We1 311 01s06 61am4 o11 141 616 166 $900 514 611 "s11 am1 011 MW

MW MW MW MW m MW MW MW MW MW MW Mm1 m1 in IN 36 w6 w1 so No *1 3

an mW MW MW MW on MW MW mW MW MW UMW3*1 310 1am 661 sm~ 01" 610 "a6 ow0 511 60 61s0

61.11 111.140 11.160 $1.1410 61.11 311 .160 M141.@ 611,100 36.36 "A"3 VOWon so 6 w6 w 1 m1 m6 3 w NO w

611 o14 111 sm1 611 MW MW 11W s11 161 MW 311*4.111 61.11 01.11 sk.11 61.11 KIM3 Kin 61.36 3136 51.36 61.3 11.N1"461 60111 n"1 ou*1 *361 AM6 $km1 *361 sw6 As61 so"sm mW MW I= m MW MW MW MW MW MW mWM1W 011 0*1 No No1 611 ow1 ow ow6 111 NOW 16

sum aum MM3 W= M PAM aum M= UAW am Am i616 1111 em6 ow6 6*1 M16 61on 111 616 610 sm0MW MW MW MW MW 361 MW MW MW MW MW MWMW MW sm1 sm1 Mw MW MW MW MW MW MW n6

SIAN 11*0 &I*0 SIAN V1*0 VIM0 Pm* "An1 61M sum0 a1*0 61MW MW MW MW MW MW amW MW MW mW MW MW

111306M ''2.36 613U3 1123 612036 M1UM 66036n 511&=3 61at.3 1936 00.3 1vi.301*1511 36*136 61*0*0 usm* SUM=.61 O0261.11 60.344 WA*6* IZ734.60 3133 3O613 1L1.3364

21 21 21 60 21 30 M1 01 so 3f 30 II

Page 30: Church Rock Section 17 Restoration Action Plan.

aPAXInCMPKC1SE07M 0 RUDIAMU I DcoCOMSOmMuO~MRONDAciinmminAPM4MAV9WU

I -w w I qw I tte 1 w II:ftw.jipU.s1

Od-vo

$ sew

17 TMW~ppa

'4 motorwK-t

21 Wafto."N

32 woulkali w

11 *sof

31 "Nolmmso2o1e

Po"

* ftaMf12 -AWsmd

* ~PV61M41 ~ 85tuu

1273PIN mlinMpabvm76U ~ poul

a pmTw* tmo

"Mm~K* rmb

5' LQa NOU

* ma-Inmarm

tI

tt1I

1i1

i

l!

iIt1

1i

1I11

¶1

I

1 1 1 I 1 1 II I ¶ I I I I

1 1 I 1 1 1 1¶ I I I 1 1 I

ts a 1 in In

MAN "On If "m Iti

IU151 PASASJ NAM.6 356666 U*am41A6 4XI.6 617m6 4W1.5 4126

MOM 28A 2.8 25o 20"

4061 4A7.1 4058 41156 USDMA1366 144,46 SA1WA &Aft=6 ItI3Ag

4L" 4M6 4w1 M 4A

ULM6 aim6 swift sa now 66, WAVl 66,41 661"1 MWAI 127,41 U751WA 1Ww SO1W tow MW 12 12 12 1 U Uam6 61.8 slim 81M sun6 66 66 w6 66 6 66am am $am am6 1W a. am 84 aw a. aw amsun4 BI." 814 6134 86.84 4m6 466 4m5 am6 666 am2 am51.12 Si~m BIAS BI An 516 65 m 4w6 61w -m an51.2n V".3 8166 51.6 an m so-a. a

566 em1 ow1 566 on1 s11 sm7 "M1 511 um1 512 5an m s. a. an6 m. M . a. an a.no m. no no m. =0 Wo = an m. m mea. m am a. M. sm on em ow No1 811 5ow

mB 66 66 66 66 B KB wB 6 6 66ow1 811 o11 "a1 811

66~~WA 66 6"6 6 6 BAS BIASWM 66O owl sm sm 1W 26

no ow a. a. a. a a. a. a. a. a. a.. a. a. a. a. a. a. a. a. a. a. a.

an a. a. a. a. a. a. a. a. a. a. a511 866 56 a. a.

am 1WA 1WA 1Wm @amm a. a. a. a.

a. a. a. a. a. DlV~ D ShAMII6ATMKEMSsm pus on sm va

MW6 SUN 1WAN512o= BIm 51285 812*1 Nun.*am 6 SUM 1 NUN W =am su*An sum KM SAN suman a. a. a. a.an a. a. a. a.ow a. sm a. on

m6 6 KB 66 6am a. a. o. a.sm a. "a. o a.

no a. a.ea6so KB KB KB

-m - s, a. I=a. sm a. a. M

IL* "1.in 51.66 51.6 "A.mKB KB w6 w6"a. a. a.t a. a

SLIM1 I".=6 Kin8 51.66 85.6I""8 "A" ILI"5 o1W sma. I= a. a. aow a. em a. a.

sum =Am UAW am suma. a. sm aim a.a. a. a. a. am m an a.

BIAS BIAS BIA MAD MANa. a. a. a. a

to& out= 63166 soft= a.66 Soso $I&= Sean so= 5676 07 "SAO1211611 12.81W 1218.1 MAW= 12,7112 NANA" ammm6 MumS 1Wo I&WAN 851W 51

21 u2 $1 30 31 31 30 31 51 soSI1

Page 31: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

ATTACHMENT E-2-2BUDGET CACULATION AND BACKUP

Labor RatOsElectrical Usage

Solid Production

Page 32: Church Rock Section 17 Restoration Action Plan.

I A B a ID E F I %--- H- I I

3

5a78910

131

12021J

'22

"25

26

3431

3734

37

40

454747W

5i

Rev. March 16, 2001LABOR SUMMARIES

I NumbI Ilouf ulYije~v Vnual

SalariedSawedSalarmedSaawed

SawwedwSalariedSalarledSalaredSalaried

vvteWage

wageWageWageWageWagewae

SalariedSalarleclSalariedWageWa•eSalaredW~age,wageWageWageWageWageWageWagsWage

SalariedSalariedSa~rWSalariedWageWageWageWvaa

MAngm n andAccouningOperations UMnerEn I onmental ManageAcco mtnManageAccountunt

Plant SuperintendientPlaf EngineerRadloldon OffcerChemistPlant ForemanMaintenance ForemanLab Technicans

ElectricianApprentce ElecticanPlant OratorAssistance Plant OperatorDrw OpeoraMaintenance

WWefiel SuperintendentDrilng EngneeForemanTruck DrIvrElecicianData Entry Clerk

Assistat Wel~ffeld Operato

11

$120,000- $106,000

$106,000M0$05,0

I -

$9.62$9.62

1 $14.43$12.01

1 $11.54$11.54$11.54$11.54

11 $11.54

$14.43

$85,000$45,000$30,000$46,000$28,000$28,000

$41,200$40,500$28,000

$20,000$20,000

$86,000$60,000$58,000$48,800$36,000$20,000

BalsncerEnvironmenfta SamplePumP Hoist OperatorsBaddoe OperatorMalntenanceCaing Crew

EngoIn ng I Goklgc PesmnnChfef EnnhwRESERVOIR ENGINEERSenior GeogstGeolgLogging SupervisSecretarySuwa•Assistant SurveyoLowaer

$12.011 $11.50

$11.50$11.50$11.50

S $11.50$10.49$11.50$11.50

1

$12.02$12.02

- U -.

Page 33: Church Rock Section 17 Restoration Action Plan.

0

COST SUMMARY TABLE

KW H/rsnonth $)KW C/onth CCW"W

WELL FIELDSubmersimble pumps 7.4430 extoctom 223.2 720 0.075 $ 12,053 $ 144,633.60

PLANTSand Filter Pump 17 720 0.075 $ 918RO Feed Pump 51 720 0.075 $ 2,754!njeation Pump 33 720 0.075 $ 1,782RO Heater Pump 3.5' 72 0.075 $ 19RO Wash pump 10 24 0.075 $ 18RO Heater 75 72 0.075 $ 405

i$ 5,896 $ 70.750.80_________ ____________TOTAL,* ___ 7,4 :T >1,344

10/12=0 Churchrock eectricaestrten5 5

Page 34: Church Rock Section 17 Restoration Action Plan.

CHURCIIROCKWFIRO ELECTRICREQUIRMENTrrIco$T.

ý0ASSUMPTIONS

I Pw e2 P-u dspt S3. Stti water level

58 wer of " mraowells

7flow ret por elactl eftml'S Flow rate per njecftiwe.9 TlEbotil~cl o-

10, Tank eleakonWEiLLFIELD

A. Toa hued reurmeonts

FAto losswd

I Pie In frKWio =os

600gpm In 6' 5CR.17p pletilenePipe2 Elevatio chage between plant.adW

5 WeOO btbl losTotal submersibe head requirments.

Gndfos modal 255754905(see attahmntd)Run amps for tNs pump 0, 31.8 gp 58 il fheadIs

Full lead currant

An~ergeusd oralobcal u seaga:

Toatal Wefileld amperage I30 1 a mps.ý

KWKW;;.Cos tpewelperyear

Cos pe eler- yearTotal oos(3 ;a)per year-

"mft

3800 ft.

S.0751KWH20 ft

2030

400

8.7173

228.7

9240

,20

40011.8524

7.5 hp

7,3.!0 IE *.PF. 1000

(1 .73"t11480'.85)I1000

7.44

$4,888.00

8.58-

1130.,

1011RJ0 hurchrk el1ist 11

Page 35: Church Rock Section 17 Restoration Action Plan.

PLANTA,

1 INection ruts,2 Injection pressure

WHP =

WHP =

BHP= -_HF!

B•Pi= 25/.7BiP =

435 gpm100 psi

Q`TDHWSG3960

-39W:

25

35

Arnp

Amnps '3307481.73*450*75*85

.Amp 48

1000KW 228KW 2

B.ý Siandfllhi:FOed PumpBHPIf 25

Amps =

AMW

Amps=,

KW'

KW w

KW'"

1. I-73*E*Eff PF25*748

1 .73"0480*.75*.8538

* 100036*460100017

10/`12100 101200Chutrchrlock eioWCbioa~lst~imate 2

Page 36: Church Rock Section 17 Restoration Action Plan.

C. RO Feed PumpBHP

KW

KW=

75

t'173*E*Eff VP750746

1000

1000

10/1210D 10112/00Churchrodk oebeticeabtmats, 0.

Page 37: Church Rock Section 17 Restoration Action Plan.

0. RO Heate Fod pumpBHP 5

Amre=" , SHP * 74,~.1t73*E*Eff *PF

Amps= 5*746' .73"4610"75".85

Amps= 7.5

... :"" ,1000

KW =rm 7.5"4601000

KW= 3.5

EOWR Wash PumpBHP i5

•8 =: .. ;B'HP~er746 ' ;.

: -.73*E*Eff PFAV~S156748 1,73*480 e.75*,85

Amps= 22

-1000KW = 22'460

1000KW= 10

4012/01D 10/12100Clhurch~rok uebc.tralIednmte 4

Page 38: Church Rock Section 17 Restoration Action Plan.

(ft)

1400

1200

100

low

600

-25S75-39DS F Mt Power at Calc.Duty3x460 60 Eft. at Calc. Duty3450 RPM Fluid Temp.

MaLOp.Press.(at 4S°F)Max.Gen.Press.

.. .Temp.RangeSuction Velocity

-Motor PowerFull Load CurrentStart*Curr.Ratio (DOL)Service factor currentService Factor

Min.Well Dia.Outlet ConnectionLengthNet Weight

5 10 15 20 25 30 IUSgpmRVariant CodeProduct Number

8.58 bp53 %59 OF

psi1180.2 ft32/86 OF

ft/s

7.5 bp10.9 A

6512.3 A1.15

4 I,

1 V"

66.8 "

168 lbNone

05113639F

200

Required DutyCalc.Duty

30.0 USgpm at 500.0 ft31.8 USgpm at 562.1 ft

Pos.1.1 - 2SS75-39DS FMtr $ 3106.00 x I

Total S 3106.00

25S75-39DS F Mtr/7.5hp/3 1.8gpm,562.1 ft. of head/8.58 amps/ 53% eff.25S75-39DS G Mtr/7.5hp/3 1.8 [email protected] ft. of head/8.58 amps/53% eff40S75-21 F Mtr/7.5hp/30.8 [email protected] ft. of head/? amps/? eff

-1-

Page 39: Church Rock Section 17 Restoration Action Plan.

NrcpIa-1

Calculation of BC Solids Produced

Flow (g/min)Flow:(VImin)Flowv(ld)Solids (gi/)Solids, (lm),Solids (g/mo)Solids (kg/mo)Solids (lbIro)Solids (yd3imo)"Solids (ft3lmo)Unit disposal cost($/ft3)Monthly disposal cost ($)

5802!195

31,61,2324,

12,644928384,616,560

384,617174;429

872i355$2.78

$60541

*1 yd3~ I toný

10/.19009•15PM Nrcpta-1 Chemicals $ Calcdlations

Page 40: Church Rock Section 17 Restoration Action Plan.

ATTACHMENT E-2-4QUOTES AND PRICES

BC vendor-specsEleCtrical rates

ft

Page 41: Church Rock Section 17 Restoration Action Plan.

SEP.13.29aB 143?qM ,IONICS RCC oMR.-363, P.2

RCC1AD ft,I

3006 N0ebpW8YSelenv, WA 9W

MarkS. Pelizza,

12750 MeAtSuite 720, LB -12

VIA FAX 9,72-31

Subject Brine

RCC has revew4discussed with Afaining fim viipodryer to ahieve

Pfl=: 425 88-240 x 10Fux '425 828.05264-1407

Sepltewbnile 132000.RCC No, 00-3218

17-7779

Concentrator for. Uranium Rwcvery Pr6jc, M ieyCounty, NM

fd your request for a Brine Concent 'System frthe abovepectnmdasX's Process Director, Bob Solomo. RCC would recommend:a vrtficaltbcompresion (MVR) evaporator (BC),followed'by a steam drivenrotauydrum

rein liqufid discharge (dry solids).

proximately4800 mg/I TDS was provided as feed• to th evaporator/drum dryerassumed* acon on fatotr of 40 can be achieved, inthe evaporatorhe feed stream of 125 gpmto3.2 gpm. The 3.2 :m cancentrated evaporatorsent to a rotary drum dryer for solids generation and zeroliquid dishrge,

A chemistry ofRsystle. RC-". bathereby reducingblowdown wilU b

buic& RCCZcn Lquid DisharvVy

0 Copy*ght 2000, Rnumcm Coanaanoan Co. AlRIghts R.mved

Page 42: Church Rock Section 17 Restoration Action Plan.

SEP, 13 :.260M .12 43PIM OIS C O36 .IONICýý P•CC W•.-363, P,,3

MM*Pih Pei:F2.

The o~ffCr inludmotors. Itis despercent of that Vcontain less thancon". ztrate willIIThe proposed Ie.to about 80 othbinslalltions w"designed. Manyrequirement.

,The compositioncalciumt sulfateSall cases whereslurry process toincorporated into

The feed is "p mThe &-ed tank pthrough the heatrecovering the dicarbon dioxide (evapo sump.

Thebrine from Awhere it, flowstube'and falls asicompression themthe vertical tubetthe vapor to relethetubesAisilto thedistillate ta:the deaerator andoperating pressuirsensible heat to t•

Aporion.ofthe cthe drycr feed tanthe sump brine.

The concnrtedanmsfeed to the

crystallizer the sh

matetials of Wide

a all necessary vessels, pumps, duc% valves, controls, instrumetaionangned torprocess I1 00 gpm ofthe specifed wastewater and recovers about 97lumeias high purity dist'llatc forrecycle/reuse.: Theerecovered diillatewould10 mmg4.of total solids, excluding-volatile-species. Thxemaining,3.2 gpm

~portoris verica tues fllig flixi vaor omprssin uit similar in designIRC ystems peurating in thi cury!1andarobn~diteworld.lb Irh t

put on-line in 1974and ctuetodyto p1rfot as originally req mduid5fthosVeunits ae treatingwastewater, which areesseanialy.idencad dtd o

ofthelwastewate•to be processed'is such. tha:t. sparingly soluble.species:(e~g.,id silica) will precipitate isced. This situaon is tpical inamCC Units are employed and necesitates employing RCC's proprietary•sed'Woid scaling and fouling of heat transfer smufaces. This de feateis

the proposed system

ed to jhe:a•ted feed tn Where thepHisadjusdtoS,6 using sulAfoacid.vides sufficient residece time for complete mixing before the feed. is pumped.xcchanger. The; feeadis heated- in-the- heat exchanger to near boiling, by,tillate's sensible heat. The hotfeedthe passes through'the deaerator whereDO) and other non-condensibles, are stried before the feedentrs the

e sump is continuously recircUlatedO theo top of the vetical heat-transfir-tubesough ,a I.CC pat distributor. iserted iuto the top of eachmheat transfer

thi flminid te ubs.A potin of thethinfilm is vaporzed.& vapor,dodymnamic cycle the vapor is comesed and introduced intolthe shell sid ofundle. The temperature'diffm ebetween the vapor and the brine film causese itsheat5of condensation to the failing brine and to cndense on the outkide-of

,ed water. This distillatel'. collected at the bottom of the condenser and flowsik through a pipe :handlingboth lquidand steam. The steam phase-isiventeditoto the atmosphere to remove non-condensibles and maintain proersystem

The hot distillate is-pumped though-the.heat exchangerwhere it gives opVite feed. From this point, the distillate is available for use..

oncentrated brine is continuously withdrawn, from the sump for dicharge'to!L- The rate of discharge is controlled to maintain propersolids-composition in

waste blowdown is collected in the dryer feed tank (by others) and isrotary drum-dryer. A Bufflovak atmospheric double drum dryer is usedto.

.ry•beigdischarged from the Brine Concentrator. This drum :dryetversaftleand widely applied to, dry many food, chemical and pharmacenuticaly varying d ie aw vissity's: dilute solutions, heavy liquids, or past

a CoprWgt2000r~,==:ozesC=#qvtln =Co. Al Uglt Riop ermve

Page 43: Church Rock Section 17 Restoration Action Plan.

bLvlý.,Vzl. eh2w V-44M ILAliu.) M;4- IW. =' r" W4.

Maik PelizA

hge3materials. TheyThe movable druoperation, the shsteam heated rotbeing scraped bydisposal. Steamyearsm andis featProcess vapor fr(the condensate i

The following is'Feed TDSnMEvaporator FDistillate FloDistillate QwEvaporator BEvaporator EStartup SteamRotary Dryer

Dryer Electri,Dryer Solids&Plot Plan Re

arv also effective for heavy sludge's which become saturated and deposit salts.m penrits complete control of film thickness prodcingthe crystals. Inriry is fed to the crystallizer through-the pendulum feedzsystem and over/acrosstng drums. The feed is evenly distributedvupon thednnns and driesbeforea double doctor blade. Solids fall from the blades directly into a dumpste forprsure and temperature control capacity. Theldevicehas been in use for nAnyred'inPaery's Chmic4Engineers Handbook.

m the dryer is vented to atmosphere; supply. steam is condensed and returned tostem. The "dry" solids are dischrged 'from the system and hauled away.

prehiminaryperformance data for the evaporator/crystallizer system.4,769

,ed Flow, gpm 125,Ar, mm 121dity, mg/l (excluding volatiles) <10Lowdown, gpm 3.2[ectrical Energy, kw 600t (for 24 hours), IPyr 1200Feed Flow, gpm 3.2hteam rcq'd.,bM 1900.

.aEnergy, kw 20Produced, lb/hr.(dry basis) 300uired,& 60x 60 x 70 h

A suggested seoe•,ofwork by'R•C and by:others for the proposed system is as follows:

a Perform proO6* Perform sysu

drawings,* Specify ands

as design and prepare Process Flow Diagram (PFD),n design and prepare;P&ID, General Arangement, and Electrial On-line

qpplythe Brine Concentrator/Crystalfie equipment including:

Mateidal (or Similar•

Evaporator VRechirclationSteamDuctsVapor ComprPlate & FranDeaeratorlw/3RecirculationFeed Pwp &Feed TankFeed Tank MSbed/Waste T

sIDucts

,MssM &MotorHeat.Exchanger

ackingPump & MotorMotor

11 setI .se

11.11II1

1

TiItaun6L SS316L SS316LSSCI/SSTitahum Plates,317LSSCd4MCu316 SSFRP316L SS316L SS

xer & Motor,mk

iOcc ropuielazy Jnfoufianun0 COPYrEgh 2000, . meson Cimservation Co. Anl RigWtsReserved

Page 44: Church Rock Section 17 Restoration Action Plan.

. SEP. i3.22912 1:44PM OISRCN.3 P5IONICSRIC.' NO. 3631 P. 5

Seed/WasteSeed/Waste'Disfiflate PulDistillate TmAcid Pump 4ANDRot- ,DrwrFeed Pump ACondensate ,Condensate IControl'Syst4Field InstrnmControl YaWv

ank fixerrank Pump & Motorrp &Motor

; Motor

I1112

Dryer, Motor,'Ank

11111

flot1 lot

6% MoSSCd4MCu316SS316LSSAlloy20

Cr.Plated CCd4MCu316SS316:SSABVariousVarious

PtovideOpehio.s & Maintenance Mman .

Scone of Work b rOthers:

* Desgn anpdelectrical ei

" Erectthe syst* Perform chec

A price for equipDelivery can be

a125 m Brine Cdischarge: $1

ItAation is estcomponents insta

The operation ofGeneral, duties vdchemical (eg., p1

RCC estimates astirup a$ 0pbasis for $ $5.001

ovide foundations, process and utility interfaces, waste disposal systenmpment (including MCC and medium voltage switchgear), and insulaion,am and provide interconnecting piping. manual valves and pipe supporttout , startup and operation.

nent design and supply of the proposed system is as follows, FOB site.iad in 48 weeks following notificaton to proced.,

mentrator System with a 3.2 gpm rotary drum dryer to achieve zero liqUid,700,000

mated to be $800,000 including foundations and building- Installation based on:led onsite although some componentscan beskid mounted atadditional costs.

he proposed system will require approximately four (4) hours per shift!1 involve~routine monitoring with plant walk-through andsimple bench) tests.

proximately one man-month of supervision, construction support, taiigmc, is requiedto support this project RCC offers tis o•natime md material.

er hour plus tmvel-and per diem expenses.

0 Copyrigh 2000, Remoume Coascavaon Co. All Right Rescived

Page 45: Church Rock Section 17 Restoration Action Plan.

SE.13.2000 1:.45.PM, oisRcN.6 P6IONICS RCC. NO. 363 P'.6

Mask Peliiz

Page 5RCC apprmciateganswe any quesby 6x at (425)•

your inquiry and would-be pleasedto provide additional information andions you may have,. Please feel.ee to .ontact me at(425),828-2400,x1306 or18-O526orbyemail at oeb(•ionicsrcc~om.

Very.tutwy yo uS,RBSOURC:ESCONSERVATION'COMPANY

Joe BoctJ anecic

SaleslMag

RCC fP oretaY Infm&in,.6 Copyr1&h 2000, Rmsomrce Cowaemdon Co. Ali Eights Reseived

Page 46: Church Rock Section 17 Restoration Action Plan.

JUL-31-2 0- .. 0....... 585 833 977? P.82-9E5

PUB91C SERVICMCOMPANY OF NEW MEMOCOELECUC SERVICIS EFFECTIVE ON ALL BI.S

RDMERB) ON OR AFTER.DMaPfiB: USTRAL POWER SIMVICC.-TFAE.OF-USUE DECEMMBR • 929LARGE SERVICE 1OR .ININGCUSTOMRk 10,000 KW MINIMUM AT 16KV AND 69KV

The rates on t"is schedule-ar, available to a retail minng customer whocontracts for a definite capadty commensurate wth the: customee's normal requirements but:Inno case less, than 10,0O I0W of capacity :and who talkee service directly from PNM'stransmission system at 115 W and lbe Company's primary d6tributlon voltage of 6so.

Service shall be furnished at the Company's vMiable•tmnsmlsdonvobtgeof 115 WV and at fto 8pan S dl•-tbtio vollage of 9kM Service will be fumished subject to the Companys

Rules and Reg•,atons and any subsequentreWsons. These Rules and Regulations are.'mvg .able at the CompMaYs. office and are, n e with ft New Medco Publf RegulionCommission. These Rules and Regubatons awe part offt lSduadule asif fuiy written heroin.

IMITBBIIQ : 'AlteUritory served:by the Compaf y inwNew MWic• .

_TYPe OF SEMVICE The service avallable under th*sscmdule shall be three-phas•, •serve:derrvemd at the Company's ava•lbe transmislonvoltge of 115 wand disrMn on voltage of69W.

SERICEWIH A CONTRACT EADOI.0?CORM8

1. The Company wil provide service under fts rate schedule to retaw cusomers whocontract, for a demand of 100O.MKW or more and who take service lrom PNM'$transmission system at 115 W and diibu•tion system at SOW only if the custom'agrees to a specified period of service under Mhis rate schedule of not less, than one ye.but in no event to extend pastMthe Ikndiatm of customer choice for generstion servion asprovided for in the ElectM'cUt¢ilty Indusliy Re*aur Act of 1099. The customer mustsign a fdIliefs cota or' appropriate be afteion agreement'fr.any binsmlssion ordistrxbution cos iaumed by the Company for•e aom not covered through rates onthis tariff. IJqupdated damages.provisiotM Wl be IndUded In the contract or fine extension.agreement unless oýterwieagreed to bythe company.

2. All conbad modificafons must be in wrting ad executed as a ,suppleen to the,Contrac

SUBSTATION EQUIMN,: All sUbstation and dist']bution tansfonmmers onthe

strctres vltae eguatng. devices., ighftng arrestors and accessoryequipmentl rewuired by:the cusWomer in order to ubT=fe te Company's servim..at116,AV aMd *V stie be installed,'paid for, *ned, operated. and maintaned by the ustmer.

1

Page 47: Church Rock Section 17 Restoration Action Plan.

JIJ~31-2 ~g17:05505 833 0,. n P. 03/05

PUBLIC SERVICE COMPANY OF NEW UMM~CELECTPIC SERVICE

sCnHEDULU M5 INDUSTMIALPOWER SERVICE--ME-OF-USE.LARGE SERVICE FORMNING CUSTOMERMZ 10,0060KWMINIMUM AT115 KWA69KV

EFFECrIVE ON ALL BILLSRM JMR) ONORAF-ER

DECEAMBR31.00

The cutomer shall also provide t. customers e2Iense suitble; protectIve equipmrent anddevices so as to protect Company' system and serim , and oter electr usem, fromdisturbances or fauts hat may occur on the customes-system or equipment.

Theý customer shall at; all times keep each of the tb phae balanced ase fares pratieblsoas notto afect servioe and v e h s served by the Company. Thevcustomer

el rot uperate any equipment, in armanner which wil Cause voltage distufbnoeselswhereon the Company "stm.

f-B" RA'TI.PERMONTH OR P IRT THEMEOF FOR EMCH SRViCE LOCATIhON: bratsfor electric servicsprovided shall be the sum of A. . C, D. and E below. OnPeak period IBfom 8:00am to 8:00pm Monday throughFriday (60 houw per week). Off Peak period Is alltimes otherthan On4-ak periodl (108 hours per weelk)

(A) CUSTOMER CHARGE:(Per Metered Account(Includes 1st 10,00 kJ fB1led Demar* --

(B) ON-PFEAKDEM•

(For 1i DemIAbove 10.00WD I MDuringOn-Peak.Pedrod)-

(C) EN OY CHARG.

For Eergy Consumed

ouringew k PeCod:

For Enegy ConsumedDurin Off-Peak "Peromod:

$75, 100.OOIBhU

57.6likW

4.4SO/W~

3.•ooWM

2

Page 48: Church Rock Section 17 Restoration Action Plan.

.*.'.JLL"31-20 17-06 W?• I ALAEM S1M58M 0777 P.04,/05

PUBLUC SEMVICECOMPANY OF NWN 1110MZ.ECIMicSERV CUM mA.e~

:! RENDERE:ON;0IAFTER- IDUSj~tRIPOWER SERvICE-TIM.PUE AN=f~ ' RFE

3M ..- mOF-use ECEN AB R 130,196LARGE SERVICE FORMINING CUSTOM11

S10,000KWeMIMUM ATIIS KVAND SV

(0) PW FACTOR AENT: The'above rMteso based on a power factor of

g0 percent or h wer and the Company will suppy, wthout addimol charge aýunof 0.48 ar (Reactive Kilovolt Amperes) per kW of billable, demand Tb.

monoly billwill be nesed $.25 for each kvarin loexc" lthe alowed 0.48 kWAR perkW Mo billable demand.

(E) SPCA A N SES~fA1~~F~ finaUnder this Sche~due Maybe increased by an amount equal to the am of the. taxs payable under the GrossRecelpts and Compesating Tax Act and of 91 other txes, fees. or dcres (SMxLdsDVof ad valorem, stateand federal income tames) Payab.1 by the Company and tevied orassessed by any governmental authority on the public aIfity service rendered, or on thefight or prvgege of renderinf the service, or on any object or event incidental to therenditin of the servce.

MONThLY.MLIMUM CHARGE• The monthly minmum chrg under this.8chedule Is fte On-Peak period demand dchage pplied to the 10,000 W' mnimbum demand. A

iEm -nATomO gEON-PAK- PEROD D MADCARee 'The Om~Paakc perfod demiandcharge for any month shall be as determined by appropdate l'eusureme as :defined by the

Companybut in no event shall It be less fthn-t tehghetMlcf th oloing&aM heatmetered kW demand minus minimum demand; or (b) 50 per~ar. of. the highest fW dmand,dufrtn tIe Precedin, 11, months minus minmum fdemand, OrI0 zeo.

'Mstqrlg shal normally e at'cu$0mer's inbsftaon %ecoLaxy Vola.I The Compny resenMterht to meter at the substation pilmary voltage level, In wich event he metered kWh,,kWdemand, and WAR shal be multiplied by .98 to alow for lMosV.IWhere hhy fluctuating or nteittent. loads which are impra l to determine property (suchas weldngý machline, eledc fumace, hoists, etavalum, X;as. and te 10 I) are in operatonby the customer, the Company reserves the rgt to deteminelft Ming demand by Incthe 1,-minute measured maximum demand and k-varby an amount equal to 85 pern offthenamueplate rated kVA capacity of the fluduasting equipment in opertion by toe custoer.

IT .UPTOON OF SERVICM The Company "Dl use reasonable diligence 1o trish aregular nd unvnterute supply of energy. 'Ho^wee. lntrru~tions or partial Interruptions mayoacu or service may be axWifedbecome irregular, or fail as ja result of cicudaie beyonddie conhMI of Mie Company. or ame te results of acts of-publicoeramm.,se ccdents, strikes, legalpocesse, oa e on esho es, be or damages to gene

" t •

S!

Page 49: Church Rock Section 17 Restoration Action Plan.

__WI -__-- -- 5W5 833- Urn Pi.5,95

PUDUCISERICE COMPANY OF NEWA6MOOELEO.hIC;SORiCS

EPPECflVE ON ALMLL91±RENDERED ON OR AFTIU

.SMULUf. INDUSJTRIAL POWERSERVwCE-TI.E-OP4ISE . DECEMBER30, l86LARGE SERICIF FOR MINING CUSTOMERSa : 19,0KW MINIMUM AT 115KV AND SWKV

tr- on, or di-trb'uaion facmlies of the Coman. repdk or chgs in the CompW's

generaton, transmison, or dist• ution fts, and n any sL* case fte Company W not belIable for damages. Cutoemers whose reliabilidy requirements 6xceed these normally pwvidedshould advise the Company and contraot for additonal facifijand Increased relgability as maybe requfredt The Compaw wi not, under any cirm tancecordaact to povide 100 pwenreflabfly.

"Equip.mnt used to provide eWf, evIce ust be pyscloly accessibe..meteing must be Instaled on eac .service location at I poWnt accessible to Company

peromnnel at. any me.

TERMS ~ ~ A OF PAMET A ills awe net and. payablee wiýain twenty (20) dayu and aredelnun thirt (30) days, from the date theil bis rendered. If payment for any or aill eleobicsen ce rendered is not made withtn thirty (30) days from. th date 1w bilis remdered, tMeCompany-eshel appl an addotional cae .f 16percent pqe month Utot thotalbalanse inareapm., excludan gross recelp ta. Partial paymeM of amquntde,. by Customer W ape.fst to oldest bill, Including any other fees or charges assess6d[ if any. before any- amount isappried to carren kil

LIMITAO, O RAT: EleCtric service under this Scheddle Is ýnot available for standbyservice, is nt. aiable to customers served in: the- doawtn area of Abuquerque, whensensed by the undergroundnetwork system, and-shall rotibe •reold or shared with otherL.

Ij

'I

Ia I

Page 50: Church Rock Section 17 Restoration Action Plan.

Churchrock 17

Calculation of'BC Solids. Produced

Flow (gmin)Flow (I/rain).Flow (lid)r

Solids (g/i)Solids (g/d)Solids (gimo)Solids (kg/mo).Solids (lb/mo)Solids- (yd3/mo)*Solids (ft3/mo)Unit disposal cost ($ift3)Monthly disposal cost ($)

•5802,195

3,1611,2324

12,644,928384,616,560

384,617

174,42987

2,355$2.78

$6,541

*1 yd3v 41 ton

7/22/20011 8:10 PM

Page 51: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

Analytical Stability

3.1. Introduction and Description

Restoration rates will be monitored through analysis of waters produced from theformation. A sample will. be: taken weekly from the composite production line and analyzed forconductivity, and uranium. These ongoing sample and analysis costs are covered within thegroundwater restoration budget.

When sample data indicates that restoration is ai, or near completion, each originalbaseline well will be sampled'for the parameters listed in Table 10.4-1 ofthe: COP and analyzed byHRI on location. If the wellfield average value for each chemical parameter is consistent withbaseline quality, restoration is considered to be complete and stability sampling will begin.

Stability will be determined by three sample..sets taken at two-month intervals from, theoriginal baseline wells, and analyzed for the parameters. in COP Table 8.6-1. Stability analysis willbe performed off location by an independent commercial laboratory.

3.2. Budget Assumptions

The stability analysis budget was developed, with; the assumption that sample labor isprovided from the on site staff and that staff'will be available six months after restoration iscomplete as shown in the Groundwater Restoration Budget. As stated in LC 10.21 there will beýonhebaseline well per acre of wellfield. It is estimated that the Churchrock Section ,17 wellfieldwill be 28 acres when fully developed.

It is estimated that a sample analysis by a commercial laboratory for the parameters shownin Table 10.4-1 of the COP'will cost $120 and a sample analysis by a commercial laboratory forthe parameters shown in Table 8.6-1 of the COPwill:cost $380.

One sample will be taken from each baselinev well and analyzed for all the constituents inTable 8.61 of the COP before restoration begins at a cost of$10,640.

Baseline wells will be sampled once per year and analyzed for all the constituents in'Table10.4-1 of the COP duringrestoration at a cost of$13,440.

Following restoration, stability samples will be taken every 2 months for six months andanalyzed for all the constituents in Table 8.6-1 of the COP ata.cost of $31,920.

As shown in Attachment E-34l, the total cost for restoration analytical sampling isprojected to be, $56,000.

Page 52: Church Rock Section 17 Restoration Action Plan.

July,23, 2001

ATTACHMENT E-3-1ANALYTCAL STABILITY BUDGET

Page 53: Church Rock Section 17 Restoration Action Plan.

,GROUND.WATER RESTORATION SamplingUfits Sub Total Total

Assumptions:Labor from.staff'Routine monitoring is.covered in the restoration budgetOne baseline well sampled per acre of wellfield (28)One sample taken before restoration, startsBaseline .wells samipled once per yearduring restorationStability samples taken every.2 months for-six months

Monitoring and'sampilng.costsA. Restoration well samplingEstimated restoration- period (years) 4.4

1 'Well'Sampling prior to restomtibn: start#,of wells 28SIsample '$30 '$10,640:

*2 Restoration progress sampling# of wells 288/sample $120Samples/year '1 $13,440

B. StabirityEstimated stabilization period (months) 6#.ofwells 28Sample freq. mos. 2.S/sample $380Total $31,920

Total monitorng and :sampling costs "1O10o

Page 54: Church Rock Section 17 Restoration Action Plan.

July -23 2001

ATTACHMENT E-3-2COMMERCIAL LABORATORY RATES

Page 55: Church Rock Section 17 Restoration Action Plan.

TEL 361484-0371 P.O.BOX 2552 78403

JORDAN LABORATORIES, INCORPORATEDANALYTICAL AND ENVIRONMENTAL CHEMISTS

CORPUS CHRISTI, TEXAS

2000'SCHEDULE OF SERVICES

CONTENTS

ITEM PAGE

PRICING, TERMS, ETC. iGENERAL ANALYSES, WATER IGENERAL ANALYSES, SOIL 2METALS 3URANIUM AND RADIOMETRICS 4SPECIAL GROUPINGS 5GLYCOL ANALYSES 5AMINE ANALYSES 5OIL AND GAS ANALYSES 6HAZARDOUS WASTE CHARACTERIZATION 7TOXICITY CHARACTERISTIC LEACHING PROCEDURE (TCLP) 7GAS CHROMATOGRAPHY 8GCIMS, SPECIALTY ANALYSES 8PRIORITY POLLUTANTS 9

Page 56: Church Rock Section 17 Restoration Action Plan.

-4-

URANIUM AND RADIOMETRICS

ParameterlMethod Water Soil/Filters

Vegetation Raw Wastes,Sludges, Etc.

Uranium - Fluorometric(ASTM D2907-83) $12.00

Radium - Total Alpha Emitting Isotopes(Std. Met No. 7500-Ra B.) 70.00

$27.00 $32.00

85.00

68.00

90.00

73.00Radium ,226

(Std. Met No. 7500-Ra C.)

Radium 228(SW846 9320)

Gross Alpha and Beta - Combined(SW846 9310)

Lead.210(HSL Si 76a)

Thorium 230(Anal. Chem. 46, 12 (1974))

53.00

80.00 95.00 100.00

$57.00

115.00

98.00

125.00

75P00

118.00

108.00

30.00 45.00

73.00 88.00

50.00

93.00

83.0063.00 78;00

OtherUranium in Urine - Fluorometric (ASTM D2907-83)Uranium in Slurries and Concentrates for SettlementRadon in Water, Gas or Air (100 cc Sample Size)Cesium 134, 137 & Iodine 131 in Grain or Nuts (by Gamma Spec)Naturally Occuring Radioactive Material (NORM)

Includes Ra 226 & Ra 228In Water (StM 7500 RaC, SW846 9320)In Soil or Solids (by Gamma Spectroscopy)

Alpha Spectroscopy Ask IGamma Spectroscopy $60 plus $10, pe

$14.0080.0025.0032.00

133.0070.00

for Quote,.r Isotope

Page 57: Church Rock Section 17 Restoration Action Plan.

-5-

SPECIAL GROUPINGS

Mineral Analysis of Fresh Water - Includes Sodium, Potassium, Calcium, Magnesium,Chloride, Carbonate, Bicarbonate, Sulfate, Silica, Iron, Alkalinity, Hardness,Dissolved Solids, and pH 190.00

Oil Field Brine - Same as above but including Barium, Resistivity, CaCO3 StabilityCalculations and 'Stiff Diagrams $100,00

TDWR Report - Texas Dept. of WaterResources Uranium In-Situ Mining Report withAccuracy Checks and Ion Diagram - TDWR 0177 (Includes Radium 226)

1 $380.00

TDWR Report 0678 - Same as above with abbreviated Metals list .$306.00

TDWR Common Ion Report -Same as above excluding Metals, Radium 226 andAmmonium $120.00

Naturally OccUring Radioactive Material (NORM)Includes Radium 226 and Radium 228

In Water(StM 7500 RaC, SW846 9320) $i33.00In Soilor Solids (by Gamma Spectroscopy) $

Used Fuel Oil Specification - Includes Arsenic, Cadmium, Chromium, Lead, TOX,and Flash Point $164.00

GLYCOL ANALYSES

Benzene, Toluene, Ethyl Benzene & Xylenes (EPA 5030 & 8021) $45.00Chloride (StM 4500 - CI-B) 10.00pH (EPA 150.1) 5.00Water by Karl Fischer (ASTM D1744) 18.00

AMINE ANALYSES

Amine Concentration, WL % (by titration) $15.00Total Acid Gas Loading 15.00

Page 58: Church Rock Section 17 Restoration Action Plan.

Revised October 15, 2010

4. Plugging and Abandonment

a. Introduction and Description

All production, and injection wells will be permanently plugged, and abandoned uponcompletion of ground water restoration and, stabilized in a manner that prevents interformationaltransfer of fluids. The casing will be cut off three feet from the surface and, the site disked andseeded as outlined below.

b. Budget Assumptions

The plugging budget was developed with the assumption that all labor is contracted. HRIwill use a tremie tube method of well plugging as described in the procedure shown inAttachment E-4-2.

Cement shrinkage is estimated at 120% of the initial volume. Shown in E-4-1cementcost per sack is $6.83. For the purposes of determining labor and equipment requirements, it isestimated that 6 holes will be filled per day. Engineer/geologist supervision will be budgeted at$50,000 per year and the cement and pump hoist contractors will receive $450 and $375 perwell. Finally a backhoe and operator rate of $37.75 per hour as described in Attachment E-6-2was assumed.

As shown within Attachment E-4-1, the total cost for plugging is projected to be$474,648.12.

Page 59: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

ATTACHMENT E-4.4PLUGGING AND ABANDONMENT BUDGET

Page 60: Church Rock Section 17 Restoration Action Plan.

Revised October 15, 2010

CHURCHROCK SECTION 17 WELL PLUGGING AND ABANDONMENT

Assumptions

1. Ceen shrinkage 120%2 Ce.ent post per Sao $66633 Cost for Gel per SX $5.604 Hole Progged Wer dey I5. Engioeer/geloigest - per year (assume 20% Um for this project) $50,000.006. Backhoe & operator - per hour $37.75a Certerf Coohtrtor per ell for -rrnr 8W 6006 hole $450009 Plrp Hoewl Conrector per well for carrrntminrgf006 hole $375.0010. Wellfeld acege fully developed 40 ac11 Aeutrre Cerment Mousre win be 12.5 ppg with 2% gel12 SX req•ed ftr 800 I J6" csg) of 125 pog elment wih 2% Gel (wrihoul shrrrrage fator) 75.313. SX get hbosiftd tsr 75 3 SX Crfr (without shrrnkage factor) 2814. 5X reqmrd for 800 It (5r gI ol 12.5 pip; erent with 2% Gel (w/thour rhnnkrge factor) 52.315 SXXOgl rosNomd t• 5235X Crl lewthod etnkgef sa) t9

UnrtofMeasure I IN 1tofWefts FT CUYO CUFT BBLS I XS SXS w/.shrinkag wlthhshrin BACKHOE DOLLARSITEM WELL $O AVERAGE HOLE HOLE CEMENT CEMENT GEL CEMENT & GELw CEMENT 6GEL I/well ENG/GEOL Contract Ceenter ftr Conbtac Purrp Hoist p TOTAL TOTAL

IDIAMETER DEPTH VOLUME IVOLUME REO REDO REDD S/wel S/well Assurnel0hrdays $1well M mPrnCerren toCrerwel $/we/lI PER HOLE SECTIONS8j

Injectors 6 113 900 6.542 1766 377 84.7 32 $59623 $715.47 562.62 32S06 $506 $42160 t,73656 $96645760Extractors 6 131 900 6.542 176.6 37.7 64.7 3.2 $50623 $71547 $62.92 $3205 $506 $42188 $1,736.56 6227.751 96

Deep Monitor 5 17 1000 5.048 136.3 291 65.4 3.5 $466,11 $55933 $6292 $32.05 $563 146075 61,68555 $28,654.37Brushy Monitor 5 7 60o 4.038 160.0 23.3 52.3 2.8 $372 6 $447.47 $6292 $32.05 $450 $37500 $1,367.43 $9.57204Dakota Monitor 5 4 760 3.W33 95.4 204 45.6 2.5 632626 S9153 $62.92 U32.05 $394 6326 13 $1,206.38 $4,833.51

Recapture Monitor 5 4 1100 5.552 149.9 320 71.9 39 $51272 $61527 62392 $32.05 S619 $51563 $1,84461 $7.37844

I eto A Trtul 11474.s",t21

Page 61: Church Rock Section 17 Restoration Action Plan.

July 23,, 2001

ATTACHMENT E-4-2BACKUPINFORMATION

PLUGGING PROCEEDURECEMIENT PRICE QUOT-E

CEMENT VOLUMIECALCULATIONN.M. STATE ENGINEER RULES-AND REGULATIONS;

Page 62: Church Rock Section 17 Restoration Action Plan.

URI, INC. SOP36NM - P & A OF CASED WELLS

Radioactive Materials License No. L03653 RSO Review/Date:October 12, 2010 MGT Review/Date:

Purpose

The following is the procedure to be used for plugging and abandoning cased wells. There aretwo methods detailed in this SOP for plugging cased wells. Method "A" utilizes a tremmie pipeto circulate in cement from bottom to top. Method "B" is for deeper wells where it is deemedmore convenient to run larger pipe utilizing a pump hoist or a drilling/workover rig to circulatein the cement.

The wells are to be plugged with approximately 12.5 lb/gallon cement slurry with 2% gel mixedwith enough retarder (if necessary) to insure that the cement slurry's pumpability is sufficient toproperly circulate cement into the casing from the bottom to surface.

Resources (Method A and Method B)

The labor and material resources necessary to complete the work include the following:

1. Engineer. The term "Engineer" is used herein to describe any qualified URI employeeor contractor whose task it is to plan, oversee and execute the plugging and abandonmentof cased wells.

2. Backhoe Operator. To operate the back hoe and provide general labor support.

3. Backhoe. Necessary to break off the casing of the well 4 feet below surface and the backfiling of the resulting trench.

4. Down-hole surveying equipment. Such equipment as necessary to allow theverification of the location and competency of the plug down hole. In its simplest form,this could be a weight attached to a surveyors tape that would allow direct reading of thedistance from top of casing to top of the cement plug

5. 12.5 lb/gal Cement Slurry with 2% gel and appropriate retarder as determined byEngineer. This cement is to be mixed either on site, or at a remote location, asdetermined by the designated Engineer. It may be mixed by either a company ownedcement unit utilizing company personnel, or by a contractor owned unit with contractorpersonnel.

6. For Method "A", tremmie pipe consisting of one or more joints of PVC pipe followedby an appropriate amount of poly pipe (with depth markings clearly indicated). The PVCpipe is included on the end to keep the poly pipe from hanging up on the walls or packerassembly while going into the wellbore. For Method "B", a pump hoist unit ordrilling/workover rig will be required in addition to proper piping and associated

SOP36 Page 1

Page 63: Church Rock Section 17 Restoration Action Plan.

handling tools as needed. Piping for each shall be sized to fit casing and screen inwellbore in order to circulate cement from the bottom of the screen to the surface.

Office Preparation:

1. Identify the holes that are scheduled to be plugged.

2. Gather information from completion information, logs or other available data necessaryto determine volumes for the wellbore.

3. Determine the number of barrels of cement required to fill the casing and screen andapply an "excess" factor of 120%.

Method for Plugging Cased Well

1. Run piping into hole to bottom of screen. Mix cement and circulate in cement slurrythrough piping using an excess factor of 120%. Check cement density which is returningto surface to verify that it is representative of the cement being pumped. Take a one cupsample of both the cement being pumped and the returns to verify that the cement issetting up properly. Use a larger excess factor if necessary to get good clean returns.

2. Allow cement to set for two days. Check both cement samples to verify that the cementproperly set up. Tag cement in wellbore to see where it has fallen back to. Calculatehow much additional cement is required fill cement to surface and repeat step one tocompletely fill wellbore.

3. Use backhoe to cut off casing at least four feet below ground level. The engineer recordsthat the hole has been successfully surface plugged and marks it for back filling.

4. The backhoe returns to the hole and back fills the area returning the ground to its originalcontours.

SOP36 Page 2

Page 64: Church Rock Section 17 Restoration Action Plan.

OCT'G--•O20 12:49 HR I PLBLULERGPJE 585 833 077? P. 01/01

-AMERICANCEMENT CRPORATION,

1~~~ism tSPAOLA NWmexico 8751(SOS) 76"260G FAXM 7625 754402

iz - )

Oetobor 6,2000

K;O. Box 77Crowopoint, New Mexico 87313

Wear Qdofloto for yptt, o-11 Portland Cement

We n:dclighlcd to cpiotc your cotnot n seds l'lo•

1yWf/ll Cvnnt fo.b. Albuquerque $83.00 Icis $1.00 Pd by 10E.Trck rWgigt to Churchr.ck, M i.70o

Tolal delired prMO $99.70 lcss4$3 .00 Id by Ij"Per short ton (2000,Ibs)

Pce, should bc good for all of 2001, -however American ('ernnt, rsorwstLh righ to mrr.ndA.prik. onJltdy 1, 2001 should'it becontxnsecomlay duo to priocincrtwscs. (ei geiwnilly do nt occ.d $2 or $3 per .m'

T)"n you ftbr the opportunity tb quotoelso oasc let incknow lfl can beof anyfurther assislaico

*Aincwicn Cement CPTj.

tolmnlooi" *' ; ftfqutee %1LO VOC ~LONI

TOTAL P.,01

Page 65: Church Rock Section 17 Restoration Action Plan.

Cement Cost Worksheet

Cement Volumes (per bag)

Specific Gravity 3.15Absolute Volume Factor (Ib/ft3) 62.4Ab solute volume (Ib/ft3) 196.56Lbs per bag 94Lbs per ton 2000Cement volume per bag (0t3) 0.478

Water Volumes (per bag)

Specific Gravity 1.,00Pounds per gallon (lbs/gal) 8.33Water per bag cement (gal) 6Water weight w/I1 bag cement (Ib) 49.98Absolute Volume Factor (Ib/ft3) 62.4Water volume (ft3) 0.80

Total Volume per bag (ft3) 1.279

Cement costs

Cement cost per ton (delivered) ($) $98.70Cement cost per 94 lbs $4.64Cement/water yield per bag (ft3) 1.279Mixed cement cost per ft3 ($) $3.63Mixed cement cost per yd3 ($) $97.91

Page 66: Church Rock Section 17 Restoration Action Plan.

Mht.

tit . 1

-W-Av

'1 ~ ej.~~~Xj.0.4..

Page 67: Church Rock Section 17 Restoration Action Plan.

ARTICLE 4

WELL DRILLERS' LICENSING-CONSTRUTION,SREPAI, AND PLUGING OF WELLS

44I. LICENSE REQUIREMENTS. Only those persons with a valid water welldri!lle's license issued by the State Engineer may drill for underground Waterwithin a declaredunderground water basin. Such licenses shall not be required for the construction of a drivenwell; provildedthat the casing for such well shall not exceed two and' thr ights (2A) inchesoutside diameter. Adriller'silice memay be acquired by Aplication to the State Engineer. TheState Engineer will issuea Water Well Driller's License to any applicant who, in the opinion of,the State, Engineer, having due regard for the interest :of the: state, of New, Mexico in theproteicton of itsgpublic, waters, is qualified to conduct such drilling.

4-2' APPLICATIONS-FORMS AND FEESPERFORMANCEBOND. Applicationfor-water well drillers: license must be submitted to the State Engineer in quadruplicate on formsfurnished by the State Engineer. An application must be acompanied by a filing fee of fdiydollars ($50) and a performance bond in the penal sum of five thousand dollars (S5,000)ý.mn aform and with surety approved by the State Engineer. The bond will be conditioned that theapplicant will comply-withdthe laws of the state of New Mexico and the.rules and regulations ofýtheiStaiteEngineer in the drilling of water wells. The license shall be valid only so long a4sthe,bond remains in effect

43. DRILLING DEFINED. Drilling deepening, repairig. cleanmain or pluggng,:ofa well rer g the use of a well rig is "drilling" within the meaning of these rules andregulations and. can only be performed by a licensed driller.

4.4. L sE -Ths Water Well4-4. LICESE-ACTIVýITIES PERNHTTED-_AMENDMýENT. TeWtrWl

Drller's License: will show what activities ihe driller named therein. is authorized to performb.Provided, however, any holder of a qurrent license may file an application to-:have his license,,amended to include other activities. Forms for this application are available in the State Engineer,Office. A filing fee offive dollars,($5) must be submitte with this application.

4-5. DRILLERS. IDENTIFICATION CARD-LICENSE NUMBER AND!EXPIRATION DATE ATTACHED TO WELL RIG, Each licensee when drilling in ,a declaedunderground water basin musthave available for inspqcton upon request his, pocket identification,.card which will be issued with the license by the State Engineer. A licensee-must attach,.in plainsight, to any well rig he is operating within a declared underground water, basin a card showinghis license number and the expiration date of the license. Such cards are issued by the StateEngineeruto current license holders. The licensee's name and address , ýin legible letters notless:than one, and one, half (1½) inches in height, shall be conspicuously displayed on any drill rigunder the i~ensees. controlwhich is being operated within a declared underground water 'basin.

-19

Page 68: Church Rock Section 17 Restoration Action Plan.

46. LICENSES-4DURATION-RENEWAL S. Licenses are granted for periods oftwo (2) years. .A licensee may renew his, license by making- application to the -State Engineerbeore the expiration of his current license. Application, forms for renewals are, available at theState Engineer Office and.must be submitted in quadruplicate with a:filing fee of twenty dollars($20). Renewals are also granted for periods of two, (2) yearn.

47. LICENSES-PERFORMANCE BOND-SURETY-CANCELLATION. If thepefonrance b0nd4 supporti he licnse becomes inoperve, the licensee must immediatelycease-operations. Suretiesý must give thirty (30) days written notice to-the State Engineer of anintention to cancel a bond., This, notice mustbe byre:sered mail.

4-. DRILLING-WHERN PERMISSIBLE-EMERGENCY WELL DRILLING. Alicensee may-drill, deepen,- repair, or clean a well within a declarediunderground water basin onlywhen:

a. ownero Ofa-Uch Well ,has avid peýmtfrom ,the State Ennefor thework to be performed; or

b. the requirements of"Article2-1.1 are met. The licenSee must-himself tha the statuoMlrequiments-have been met

4-9. LICENSED DRILLERS-FILING OF OWNERSHIP, OF WELL RIGS-TRANSFER.OF OWNERSHIP-DESCRIPTIONS. Each licensed water well driller shall filewith the State Engineer a current description of each well rig owned or controlled by him.Whenever a liceneese6ven his ýOwnehi!p or control of a well rig, he shal notif the State

Engineer in, writing of such severance within ten (10) days. Whenevera licensee acquiresownership or control of a rig, he shall submit:to the.State Engineer in quadruplica adescription of said equipment. The licensee shall submit a photograph (side view) of the rig.

410. !SUSPENSION OR REVOCATION OF DRILER'S LICENSE-GROUNDS.The State Engineer may, after notice and hearing, suspend or revoke a driller's license if he findsthat said driller:

4a. has made a material mistatemet of facts in his,application for a license;b. has madea material misstatement of factst.in a well record report;C. has violated the conditions of his license;d. has violated any ofthe rules *and regulations of the State Engeer;e. has failed towsubmitawel record report(Article 4-Il).

4-11. DRILLINGRECORD-FORMS-TIME FOR FILING. The well driller -shallkeep a log of each well drilled,.repaired, deepened, cleaned, or plugged, making, a currentrecordaslthe work progresses.A complete and proprl' e•e• dwel record, on.theform prvidedbytheStateEngineer, shall be-filed not later than ten (10) days after completion of the well.

4412. SOIL FORMATION SAMPLES. The well driller shall, when so requested by,the State Engineer, funnish (in sample bags supplied'by the State -gineer) samples ofthe

20,

Page 69: Church Rock Section 17 Restoration Action Plan.

formations encintered during drilling operations. The method and interval of sampling and the:quantities required will be specified by theSate Engineer.

-4-13. WELL CONSTRUCTION. Evey / Well sha. l be onstumcted with an opening ofat least three fourths (%) inch in diameter in the casing above ground level to allw a measuringline to be inserted between the. outsidevcasing and the pump! column, in order that themwater levelin theiwell may be measured. A removkble cap shall be provided for such openings.

" 413. CAPACITY MEASUREMENTS - DISCHARGE 'PIPE - TURNOUT -APPROVED CAPACITY. In order that capacity measurements may bemade, all pumps4otherthan those connected directly-into an underground system shall have a discharge pipe unrestrictedfor at leastrfive (5) diametemin length from the flange ofthe-pump, elbow, orother obstruction.Thoe•,connected' to an, underground system ,hall have ,aturnout ,at the well into whch the entireflow can be diverted With an unrestricted pipe as above. Thi s. turnout may bei- l eqied with avalve or removable cap. Flowing wells must be equipped with a discharge pipe-as describedaboVe and a cap or valve approved by the StatleEngineer.

4414. SHALLOW WELLS-CONSTRUCTION.REPAIR.PLUGGING.: he: SiateEngineer has notadopted any generalspecifications for the, cns tion. repair, or plugging-ofnon-artesian or shallow wells. Any specific requirements and prvisions ma by the State

Fnginee shall be set forth in the pennit. Application for Permit to Repair is required for allrepair work, cleaning. scaling, deepening, modification of casing, or other work requiring themuseof-a well rig., -Any specific requirements or conditions governing the repair will befset out in theapproval of thevpermit. If plugging is required (Article 2413), shallow wells shall be plugged byfilling to theod surface or. if the casing is not tobe removed, by welding a steel platedorcap to, the casing.

b 454-. -ARTESIAN WELLS-CONSTRUCTION. The casingfo0 artesian Wells shallbe 7inspected by the, State -Engineer or his, representative and shall meet or exceed thespecificatio6s as set forth in 4415.1.ý All casing and collars must bei in god condition. Astandard casing shoe shall betised in all instanddc. The casngshll not be perforated in amanner that would allow the commingling of water from the artesian formation with water inoverlying formations.

4I5'.' 1. CASING AND COUPLING-API TABLE OF SPECIFICATIONS. Onlythreaded casingshall be used., Casings and coupings shall meet minimum American PetroleumInstitute (API) specifications for the following sizes:,

Outside Weight Wall Coupling Thread GradeDiamete With Thic••es O.D. Length Per OfInches Couplings Inches Inche Inches Inch Caing

,(bs/ft)4 9.50 0205 5.000 5 8 F-2551 13.00 .0.228 6.050 634 S.F-2

.21

Page 70: Church Rock Section 17 Restoration Action Plan.

Outside Weight WWl Coupling Threads dradeDiameter With Thickness O.D., Length Per OfInches Couplings Inches Inches Inches inch Casing

(Ibs/ft)6 15.00 0.•8: 6.625 7 8 F82.6A 17.00 0.245 7.390 71 8 F4257 17.00 0.231 7.656 7% . 8 F-2571 20.00 0.250 8.500 7s 4 F,258% 24.00 0.264 9.625 "M• 8 F-25'9% 29.30 028,1 10.625 r/4 8 F425I 0P/ 32.75 0.279 11.750 8 8 F-2511% 38.00 0A300 12.750 8 8 FY2513%,I 48.00 01330 14.375 8 T F-25

Ifcasing legth exceeds one thousand (1,000) feet, H-gradeý orbetter shall be used forthirteen and three-eighths (13M) inch, casing

4-152. , HOLE DIAMETIE In all cases the diameter of the drilled hole shall be at least,two, (2) inches greater thanwthe outside diameter of the casing.

4-16. CASING-CEMENTING-TESTING. The followingspecifications shall governcasing, cementing, and testing: the casing shoe shall be welded to the casing to assure properposition. The casing shall be landed on a suitable casing seat in the confming formationoverlying the artesian aquifer formation and sufficient oil well cement shall be used to obtaincirculation to the surface. When circulationwto the surface is not obtained,, cementshall be placedto the surfacebhind the casing. Additives ofpozolanic ntemay be ue above the casing,

shoe but shall not exceed fiy per cent (50%) :by volume.n T e addition of calcium chloride•and/or geltis permissible but shall not in any:case exceed'two per cent (2%),each byweight., A.,sufficient amount, of cement without additives shall be used to allow neatvcement to seal the:casing shoe and rise a minimum of fifty (50) feet abovethe shoe betweenwthe casing and the hole.,Cementshall&beallowed to set a milimum offortyeight (48) hours before dilling is resumed.Sealing off of the formations shall be, checkedby a, method approved. by the State Fngineer or

Sauthorized representative.

4-16.1. CENM TING. Cementing shall'be done by the pump and plUg method asfollows: after the casing has been run and landed' the pamp shallbe started and: mud circulationshall be maintained for at least, thirty (30) minutes with the casing raised slightly in order toequalize the mud pressure inside and outside of the casing. A heavy slurry of oil/well cementand water shall be mixed and poured into the top of thel casing. If additives are used in theslurry, sufficient neat cement (density fifteen (15) pounds per gallon) shall then be added to sealthe casing shoe and rise a minimum of fifty (50) feet above, the shoe. A casing plug of standardmake shall be placed in the casing above the cement and a swedge nipple screwed onto the topofthe casing and connected to the mud pump. Then:amud slimy or water shall bepumped intothe-casing, forcing the cement and casing plug down the casing. A measuring line shall be runbeid'the plig so that the drille may know its location atall times. When the plug reaches the

'22

Page 71: Church Rock Section 17 Restoration Action Plan.

point desired above the bottom of the casing, the pump shall be stopped and the casing loweredto the; casing seat.

4417. CASING, CEMENTING-TESTING-APPROVAL. The casing, cementing, andtesting programs :shall be witnessed and approved by an authorized representative of the StateEngineer.

4-18. EXCEPTION TO CASING AND ,CEMENTING REQUIREMENTS. In thoseareas of declared artesian basin.s. where the well is drilled into the artesianý aquifer, but noconfinigM formation overlying the artesian formation is present, the foregoing requirements forcasing and cementing are: ot applicable and'maybe altered by receiving written approvalof theState Engineer or his representative.

4-19. ARTESIAN WELLS-REPAIR. Before repairs are commenced .the well shallfirst be inspected by a representative of the State Engineer to. determine if-the condition of thewell is such that it may be repaired. Whenleaks in.the casing are found and the casing and wellare otherwise in good condition, the well may be repaired by a method approved by the StateEngineer. A packer or bridge plug approved by the State Engineer shall be used in all wellrepairs. An inspection shall be made at the completion of thework to determine ifthe repair was:satisfactory. During.each inspection, the :hole shall be opený to allow the entrance of equipmentfor well 'logging and leakage, measurement.

4419.1. PLUGGING. If an artesian wellis to be replaced by a new-well, it shall beplugged immediately following the•completion of the new well. All the work shallbe done underthe supervision of the State Engineer or his representative, or a-representative of the appropriateArtesian Conservancy District -who shall designate. the amount of cement to be used and thedepths at which cement plugs:shAll be set

4-20. TEST OR EXPLORATORY WELLS. All testor exploratory wells shall be soconstructed, maintained, and operated that each water shall be confined to the aquifer in whichit is encountered. All test or exploratory wells penetrating. artesian.aquifers shall be cased,cemented, and tested as required for the construction of artesian wells (Articlie4-1 through 4-18)and the casing shall be landed .in the formation -underlying the deepest artesian aquifer andcemented through all known artesian aquifers. The casing, as referred to, in the artesian well.specifications, is designated as the water protection string by the oil industry. If conductor pipeis used, it shall not be removed until after cementing of the casing has been completed. Allcasing, cementing, and testing programs shall be witnessed, and approved by a representative ofthe State Engineer.

4-20.1. SHOTHOLES-PENETRATION. Shotholes for geophysical exploration, shallnot penetrate closer than twenty-five (25) feet above any known artesian aquifer underconfinement.

23

Page 72: Church Rock Section 17 Restoration Action Plan.

4-20.2. ABANDONMENT-PLUGGING. Inthe event that thetest or exploratory wellis to be abandoned, the State Engineer shall be notified. Such well shall be plugg d inaccogrance with Article 4-19.1A s that the fluids Will be permanently confind tthe specificstrata in which they were originally encountered.

4-21. MINE LODE DISCOVERY AND DRILL HOLES. Any person drillinga minelode discovery or mine-drill hole to a depth often (10) feet or more, whobshall encounterdorwhose drill shall cut into a water body or waterbearing strata, shall plug or otherwise construct,maintain, and operate such holes so that any water encounteredtis permanently confined to theaquifer in which. it is found.

4-21.1. DISCOVERY REPORT-FORMS-TIME FORYFLING. Such person, withinninety (90) days from the date of the d•iscovery, shall report to the State Engineer, on formsiprovidedby theo State Engineer, the location and depth of the hole, and themethod andmaterialused in plugging the hole. If the hole is not plugged, te report shall descibe the manner in

which it was constructed and is- being maintained and operated. The report shall include a logof-the hole which is adequate to permit a determination of whether the plugging or constructionand operation and maintenance of the drill hole are satisfactory.

4-2:1.2. ARTESIAN WATER. If artesian water is encountered, the construction,ýoperation, maintenance, or plugging shall be done in accordance with Articles 4-15 throughArticles 4419-1.

4-22. DEVIATIONS FROM SPEC1FICATIONS-APPROVAL. Any deviations fromthe aboveý described casing, cementing, and testing programs must be approved by the Statengieer.

24

Page 73: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

5. Equipment Removal

There is.no process equipment planned for the Section 17 site. Section 17 will be in situweilfield only that will:feed the IX satellite on the adjacent Section 8.

Page 74: Church Rock Section 17 Restoration Action Plan.

Revised October 15, 2010

6. Wellfield Decommissioning

a. Introduction and Description

The Wellfield Decommissioning Budget includes the cost estimates for removingwellfield equipment from the Churchrock Section 17 site. All equipment that was used tocirculate leach solution such a pumps and piping is assumed to be contaminated for the purposeof developing the RAP budget and would be disposed in an U.S. NRC licensed waste disposalfacility. All structures are considered non-contaminated and would be disposed of in a landfill.

After ground water restoration is complete, all well houses, header houses, laterals, andpipelines will be removed. The budget contemplates costs for disassembly, or demolition,loading, transportation and disposal at a NRC licensed facility' or to the Red Rock landfill.Any vegetation, which has been disrupted, will be disked and re-seeded.

b. Budget Assumptions

The Wellfield Decommissioning Budget is formatted with the underlying assumptionsintegrated into the tabulation. The budget figures distinguish individually costs associated withbreak down, excavation, removal, loading, transportation and disposal costs.

Lateral and piping lengths were estimated from the COP schematic Figure 1.4-8. Unitcost calculations are shown in Attachment E-6-2. Well tubing decommissioning costs assumednominal tubing lengths of 600 feet and 40 existing wells. This quantity of wells is what isneeded to supply adequate water to the restoration operations. Other wellfield 0 & M costs arecovered in the groundwater restoration budget.

The Wellfield Decommissioning Budget was developed with the assumption that alllabor is contracted at a rate of $120 per day or $15 per hour. These are reasonable contract laborrates. Estimate labor time requirements are based on best professional judgment. Managementwill be provided from the site staff who will be available six months after restoration.

After all of the wellfield equipment is removed the entire wellfield area will be surveyedto assure that no residual contamination remains on the soil. Surveys will be conductedaccording to the according to the Procedure shown in Attachment E-6-2, and the hot spots arepicked up and disposed of at a NRC licensed facility. The on site management described abovewould conduct these surveys.

Piping will be reduced in volume as indicated in the budget. Pipe volume calculationsare shown in attachment E-6-2. The smaller diameter wellfield pipe and well tubing will becrushed. Larger diameter pipe will be cut into quarter strips for volume reduction. No credit is

' For the purpose of this RAP, HRI assumed that the NRC licensed site would be the IUC White Mesa Mill nearBlanding Utah. Projected unit disposal costs at the White Mesa Mill and the Red Rocks landfill are described inAttachment E-5-2.

Page 75: Church Rock Section 17 Restoration Action Plan.

Revised October 15, 2010

given for reduction in the size of pumps, the dryer, the reverse osmosis equipment or the brineconcentrator. No credit is given for salvage value.

For demolished tankage and pipe transportation and disposal costs, a 50% void factorwas included in all volume calculations. All disposal was priced at the bulk rate as shown inAttachment E-5-2.A contingency was included for health and safety supplies such as disposableuniforms and respirators.

The total cost wellfield decommissioning is projected to be $58,879.

Page 76: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

ATTACHMENT E-1•-WELLFPELD DECOMMISSIONING BUDGET

Page 77: Church Rock Section 17 Restoration Action Plan.

Rev. October 15, 2010

Section 17 Wellfield Buildings and Equipment Removal and Disposal

Description Unit TotalWellfield Piping

Assumptions:Total length of piping (ft) 38770Labor included in per foot costs

A. Removal and loadingWellfield piping removal unit cost ($ift of pipe) 0.36

Subtotal wellfield piping removal and loading costs $13,957B. Pipe crushing

Number of operators 2Operator hourly rate $15Feet pipe per hour 300

Subtotal crushing cost $3,877C. Transport and disposal costs (NRC-licensed facility)

Average diameter of piping (inches) 2Crused volume (ff/ft) 0.012Crushed volume total (if) 476Volume for disposal assuming 100% void space (fl) 952

Transportation and disposal unit cost ($/ft) $3.85Subtotal wellfield piping transport and disposal costs $3,664

Wellfield piping costs per wellfieldTotal wellfield piping costs $21,498

I1. Well Pumps and TubingAssumptions:

Ongoing pump and tubing removal costs included underground water restoration labor costs

40 production wells contain pumps and tubingA. Pump and tubing transportation and disposal

Number of production wells 226Number of injection wells 215

1 Pump volumeNumber of production wells with pumps 40Average pump volume (ftP) 1

Pump volume per wellfield (fe) 402 Tubing volume

Assumptions:Average tubing length/wellfield based on average

well depth minus 600 feetNumber of production wells with tubing 40Average tubing length per well (ft) 600Tubing length per wellfield (ft) 24000Diameter of production well fiberglass tubing (inches) 2Crushed volume reduction (ff/ft) 0.012Wellfield pipe volume w 100% void 589

Volume of pump and tubing (ft3) 629

Volume for disposal assuming 50% void space (fI) 944Transportation and disposal unit cost ($/f) $3.85

Subtotal pump and tubing transport and disposal costs $3,632.76Pump and tubing costs per welifield $3,632.76

Page 78: Church Rock Section 17 Restoration Action Plan.

Rev. October 15, 2010

Ill. Buried TrunklineLength of trunkline trench (ft) 2250A. Removal and Loading

Main pipeline removal unit cost ($ift of trench) $0.45Subtotal trunkline removal and loading costs $1,013

B. Pipe cuttingNumber of operators 2Operator hourly rate $15Feet pipe per hour 100

Subtotal cutting cost $675C. Transport and disposal costs (NRC-licensed facility)

1 10" HDPE trunklinePiping length (ft) 1580Inj and ext length 3160Cut volume (ft

3/ft) 0.14

Cut volume (ft) 4422 14" HDPE trunkline

Piping length (ft) 2250Inj and ext length 4500Cut volume (felft) 0.24Cut volume (ft) 1067

Total trunkline chipped volume (fP) 1509Volume for disposal assuming 50% void space (f) 2263Transportation and disposal unit cost ($/0f) $3.85

Subtotal trunkline transport and disposal costs $8,714Trunkline decommissioning costs $10,401

IV. Well HousesTotal quantity 40Average well house volume (f?) 12.5A. Removal

Total volume (fe) 500Demolition unit cost per WDEQ Guideline No. 12 ($/fe) $0.15

Subtotal well house demolition costs $76B. Survey and decontamination

Assumptions:Cost per well house $5

Subtotal Survey and decontamination costs $200C. Disposal

Total volume (yd3) 19Volume for disposal assuming 10% void space (cy) 20Unrestricted disposal cost of 26.7 $/yd3 $27.00

Subtotal unrestricted disposal costs $530Well house removal and disposal per wellfield $806

Page 79: Church Rock Section 17 Restoration Action Plan.

Rev. October 15, 2010

VI. Header HousesTotal quantity 6Average header house volume (ft) 1600

A. RemovalTotal volume (f?) 9600Demolition unit cost per WDEQ Guideline No. 12 ($/fe) $0.15

Subtotal building demolition costs $1,459B. Survey and decontamination

Assumptions:Cost per header house $200

Subtotal survey and decontamination costs $1,200C. Disposal

Total volume (cy) assume 10% building volume 36Volume for disposal assuming 10% void space (cy) 39Unrestricted disposal cost of 26.7 $/yd3 $27.00

Subtotal on-site disposal costs $1,056Header house removal and disposal costs per wellfield $3,715

V. SoilAssumptions:

Acres of wellfield. 28Surveys by staff.Depth of contaminated soil (in) 2Percent of wellfield contaminated 1Soil analysis each $100

A. Survey costs100 soil sample analysis $10,000Flags, and supplies $1,000

Subtotal survey costs $11,000B. Disposal costs

Backhoe one week $1,510Volume to disposal 2033NRC disposal unit cost (ft3) $3.85

Subtotal NRC-licensed facility disposal costs $7,826Wellfield soil D & D costs $18,826

TOTAL WELLFIELD BUILDINGS AND EQUIPMEN1REMOVAL AND DISPOSAL COSTS $58,879

Page 80: Church Rock Section 17 Restoration Action Plan.

July 23,2001

ATTACHMENT E-6-2BUDGET BACKUP

WELLFIELD PIPING REMOVALMAIN PIPELINE REMOVAL

PIPE VOLUMESREGULATORY GUIDANCE

HRI CLOSEOUT PROCEDURE

Page 81: Church Rock Section 17 Restoration Action Plan.

WELLFIELDPIPING REMOVAL

Assumptions:g

1. Trenching with backhoe at 1500 ft/day2.. Pipeline extraction and backfilling with backhoe at 1500 ft/day3. Backhoe rental:, $750/week,4- Fuel cost: $9/operatingLhour5. Backhoe operation requires I worker at, $15/hour6:. Pipelineextraction requir 2worers at($165/hour (in addition to trackhoe operator),7..Operating schedule: 8 hrs/day, 5 days/week

Weilfield Pipeline Removal Costs perkftof PIP

Equipment &lFuelWeekly Daiyl HourV Per Foot

Backhoe $550.00 $110`00 $13.75 $0.07Fuel $72.00 $9.00 $0.05

LaborBackhoe operator $120.00 $15.00 $0.08Pipeline extactors (2) $24000 4$30.00 $0.16

Totals $67.75

Total PerrFoot Cost $0.36-

Page 82: Church Rock Section 17 Restoration Action Plan.

MAIN PIPELINE REMOVAL

Assumptions:

1.. Trenching with ralckhoe at 1,500 ft/day2. Pipeline extraction and backfilling with trackhoe at 1500 ft/day3. Trackhoe rental: $1600/week4. Fuel cost: $9loperating hour5. Trackhoe operation requires one worker at $15/hour6. Pipeline extraction requires, 2 Workers at$15/hour (in addition to trackhoe operator)7. 'Pipelines removed simultaneously8. Includes removal ofmanholes9. Operating schedule: 8 hours/day, 5 days/week

Main Pipeline Removal Costs perftof Pipe

Equipment& FuelWeekly Diy Hourly, 'Per Foot

Trackhoe $1,200.00 $240.00 $30.00 $0.16Fuel $72.00 $9.00 $0V05

Labor

Trackhoe operator $120.00 $15.00 $0.08Pipeline extractors (2) 1$240.00 $30.00 $0.16

Total Per Foot Cost $0, 15

Page 83: Church Rock Section 17 Restoration Action Plan.

HRI ChurchroCk Project,Section 17Wellfleld Equipment Tabulation

# H. Houses #Injectom # Ed•drctom 8#Feet-21 21 18 4240

2 21 i8 12210i3 1 21 9640

4 23 28 67805 16 30 31506 13 18 2750

Totals n13 -131 38770

#FeetM " #Feet14, GravelRoad

360520

1080340,,280,

3160 4600 2250

Page 84: Church Rock Section 17 Restoration Action Plan.

Pipe Wall Volume Data,

Outside Diameter (in) Area lnside OD (ft2) Wall Volume SDRI7 (ft3/Mf)2 0.022 0.012

2.5 0.0343 0Q049 0.018

,35 0.0674 0:087

4.5 0oI1105 0.136

5.5 0.1656 0.196

6.5 0..2307 04267

7.5 0.3078 0.349

8.5 0.3949, 0.442

'9.486 0,4919.5 0.492

10 0.545 0:140105 0o.601.

10.75 0.63011 0.660

11.5 0.721'12 04785

12.353 0.83212.5 0.85213 0.922

13.5. 0.99414 1.069; 0.237

14.5 1.14715 1.227

'15.5 1.310

Wall Tk14 "SDR 17 0.82410."SDR 17 0.632

Page 85: Church Rock Section 17 Restoration Action Plan.

Hydro Resources, Inc.

PLANT SIGHT AND WELLFIELD CLOSEOUT AND REQUEST FORLICENSE TERMINATION

PUrpose

This document is HRI's Standard Procedure for sampling, Surveys, and documentationmethods for the final decontamination of the ChurchrocklCrownpoint sites and isintended to be an integral part of the Churchrock/Crownpoint sites Churchrock Section8/Crownpoint' Plant, Restoration Action Plan.

Standards,

The. standard by which HRI will measure final decommissioning is the NRC adoptedsoil limits for' radium-226 or radium-228 as described below.

The concentration of radium-226 or radium-228 in soil averaged over any 100 squaremeters (M2) shall not exceed the background level by more than:

A. 5 picocuries per gram (pCilg) averaged over the first 15 centimeter (cm) of soil.below the. surface; and

B. 15 pCi/g averaged over 15-cm thick layers of soil more. than 15 cm ,below thesurface.

Instrumentation

When performing, close out surveys, HRI will use a general'purpose survey meter suchas a 1-inch by 1-,inch sodium iodide probes in conjunction with an appropriate ratemeter or other appropriate instrumentation,, such, as microroentgen meters. The chosen.instrument will be appropriately calibrated and a daily efficiency check will 'beperformed to assure the instrument is working properly. Shielding of the instrument,may be used to eliminate background interference of measurements. Allmeasurements will be. taken at ground surface.

Survey and Sampling Procedures

A, Preliminary Survey Design

A grid spacing of 10 meters will be Used, on all affected areas. The survey technicianalong the entire length of the line will survey, each grid line with readings recorded at10-meter intervals'.

Page 86: Church Rock Section 17 Restoration Action Plan.

Background radiation levels will. be established by surveying areas adjacent to thesurvey.area, which are not ýaffected by facility operations. The survey locations,result, date, check so.Uro ID, and name of surveyor will be!.,recorded in the fieldnotes.Anomalously high survey readings will trigger sampling of •the. soil at the uhot sp•o•'location.

Random samples will be collected: from the survey -area, With a, minimum ýof, threesamples per acre;, Any hot spots found during the first survey iteration will bedecontaminated and then, resurveyed. The final survey iteration will document thedecontamination of those areas found to be contaminated in preceding surveyiterations.. The purpose-Of the survey program is, to verify that soil limitsfor radium-226,or radim-228 is-not exceeded.

B. Sampling Procedures

HRI's survey and sampling program will cover all areas within -the license areaincluding plant sites, previous wellfield locations and those, locations adjacent to.previous welfields. During the first iteration of the close-out survey HRI will .obtain anumber. of meter readings in the field, accompanied by soil samples, at the samelocation to be analyzed in the laboratory for radium 226. Meter readings and soilsamples taken at regular increments over the range found.at the sight Will be obtained.,

Soil sample locations will be staked' and' marked. for subsequent reference asnecessary. The samples will be cored using a 4-inch barrel auger to a depth, asmeasured in place, of.0-15 cm. Where* appropriate, a second lift will be taken, to adepth,. as measured'in place, of 15,30 cm. Any vegetation and stonesi will be removedand the .soil will be placed in a ziploc bag with the project site, project area, date, time,.sampler,.'sample type, and sample ID clearly marked.

Cross contamination of the soil samples will be prevented by cleaning the auger afterbagging each soil core.

Chain of Custody,, recording the information on the label ,and anyfield measurements,-or, other data will be completed' and. then the samples will be delivered to a ,commerciallaboratory,

Following laboratory analysis, the meter readings and the laboratory results will becomparedas shown in the. hypothetical example 'below. With the laboratory and surveysite correlation available, HRI will develop a calibration :curve for the purpose ofdetermining what levels of activity measured by survey meter correspond to actualconcentration in soil. Hypothetical data :and the resulting calibration curve are shown

'A -hot spot is considered to be;an area with, a reading equal to or greaterthan-the background multiplebased on correlation ofthe laboratort instrument' readings or-an area with a. radionuclide concentrationsufficientlyhigh such that the average for the I00-m2 area will exceed the soil contamination limits.

I

Page 87: Church Rock Section 17 Restoration Action Plan.

below. Site data will define the actual remediation targets, however based on pastexperienced it is anticipated that survey meter gamma radiation levels that are 2 - 3times background will indicate Ra-2262 levels above levels 5-pCi/g and trigger furtherremediation effort.

CPM Ra-226 X-Bkg.pCi/g

2000 1 13000 1.9 1.54000 3.1 25000 3.9 2.56000 5 37000 5.9 3.58000 7.1 49000 7.9 4.510000 9 511000 10.1 5.512000 11.1 613000 11.9 6.514000 13.3 715000 13.9 7.516000 15 817000 16.5 8.518000 17.8 919000 18 9.520000 18.5 10

HRI will average the concentrations of radium-266 over the first 15 cm of soil below thesurface in a 100_M 2 area. In soil more than 15 cm below the surface, the concentrationsmay be averaged in 15-cm layers in a 100-M2 area. HRI will, at a minimum, sample theinitial 15-cm layer (0-15 cm) and the second 15-cm layer (15-30 cm) if concentrations inthe initial 15-cm layer indicate deeper sampling is necessary. A minimum of fivesamples from each layer will be collected within the 100- m2 area and composited foranalysis.

.2

Page 88: Church Rock Section 17 Restoration Action Plan.

Survey MetedSample Correlation

2019'18-1716

U 14S13 -

a.312

,1,E 9.

4

2 .

Metered CountsPer Minute,e-B .ackground

2000 CPM & 1IpcIug

When sampling a contaminated area,, which is less than 100 Mi, the hot spot will besampled as part of a single 100I-m2 area. If contamination occurs in long narrow strips,1 meter wide or less, HRI may divide the 'contaminated area into more than onesampling area, of, 1006 m2 each. The dimensions of the sampling area will not, benarrowerthan 5 meters on any boundary.

All areas, which are surveyed and sampled, will be accurately identified on a scaledmap of both the Churchrock and Crownpointsites. The site plan will include, but not be.limited to,. accurate property boundaries, fences, all state, county, and private roads,location of all existing facilities, delineation of all wellfields, a north arrow, the relatedgraphic scale, and all pertinent information found in typical site plans. A qualifiedlaboratory will analyze all samples.,

3'

Page 89: Church Rock Section 17 Restoration Action Plan.

Request. For NRC ConfirmationSurvey and:Samplinq

When the HRI is confident that the Churchrock and Crownpoint sites are acceptableforrelease for unrestricted use, a written request asking for release for unrestricted usewill be submitted tothe NRC. The information discussed above will be submitted in acomprehensive report accompanied by survey and sample results' that show thatcontamination isless than the limits specified above

The report With the request asking for release for unrestricted use will contain thefollowing information.

A. A scaled survey map as described above; which provides coordinates Of the area

surveyed.

B. A narratiVe describing the conditions before, decommissioning,

C. A narrative describing each phase of the cleanup as follows::

1. Churchrock wellfield - surveyed areas, recorded results,decontaminated hot spots, disposed of contaminated soil,final conditions.

2. Churchrock Satellite -equipment decontaminated, removedand disposed, break-up pad discussion, decontamination ofpad discussion, dispose of clean concrete, disposedcontaminated material resulting from pad cleanup (includingequipment), survey of plant area, decontaminated soil inplant -area and soil which was beneath the pad, disposal ofcontaminated soil.

d. Crownpoint Process Plant .-equipment decontaminated,removed and disposed, break-up pad. discussion,decontamination of pad discussion, dispose of cleanconcrete, disposed contaminated material resulting from padcleanup (including equipment), survey of plant area,decontaminated soil in plant area and soil which wasbeneath the pad, disposal of contaminated soil.

e. Zamzow Wellfield - surveyed areas, recorded results,decontaminated hot spots, stockpiled and/or disposed, ofcontaminated soil, final conditions.

4. Any unusual. or other discussion topics.

4

Page 90: Church Rock Section 17 Restoration Action Plan.

DEPARTMENT OF ENVIRONMENTAL QUALITYLAND :QUALITY DIVISION

GUIDELINE NO. 12

STANDARDIZED RECLAMATIONPERFORMANCE BOND FORMAT AND COST

CALCULATION METHODS

Page 91: Church Rock Section 17 Restoration Action Plan.

TABLE OF CONTENTS

INTRO(DUJ'rON . ..

APPUCA'LE WEQA STATUTE AND LQD RULES AND REGUI ONS..O. . iii

. COST EXaqANATION FOR TEM S USED IN STANDARDZED RECLAMATIONBOND COST ................................................. 1Table D-1. Opemting Costs and Adjusted Costs ($/Hourwlo Operator) For Equipment

in This Standardized Bond Format ......................... 2Table D-la. Purchase Price, Icase Cot, and Operatg Costs for 56 CY Electric Shovel

andl793C Trucks .......... 3Table D-2. Abbreviations Used in This Standardized Bond Format

............ 4...................•

II. STANDARDIZED RECLAMATION BONDPFORMAT.... ..... 4A. Area.Bond ............. . 4

1 Introduction.. .. . . .. .. - 42. Backfl l.................... 43.r Rough GradeBackfil ............ .......... 54. 'Final Grade Backfill ............. ...................... 5

B. Incremental Bond ..................... 51. ',Introduction.52. Native Topsoil Removal From Borrow and/or Backslope Areas. .... 53. Native Overburden Removal From Borrow and/or Backslope Areas .. 54. Miscellaneous Overburden'Redistribution ..................... 55.. Demolition ............................. ;............. 66. Removal of Monitoring Structures and. Other Miscellaneous Items ... 67.. Scarification or Ripping, of All Compacted Surfaces ............. 68. Topsoil Redistribution on All Disturbed Areas ............... 79. Revegetation of All Disturbed Areas ........................ 710. Reclamation Status and Bond Liability Status, of All Lands, Within, theý

PermitAv ......... .... ... .... . . ... . ................ 7a. Land Status Categories............................71b. Line'Item Bond Costs ............................. 8

11. CoalDrilling .... .................... l

12. Miscellaneous Items ............... ...... 1113. Unknown Costs ... ................................. 1314. References. .. ............................... ... 1315. Maps..... ; ....................................... 13

M. APPENDICES ................ ...................... 13Appendix A ......... ...................... ......... 14

DE 3/98' i

Page 92: Church Rock Section 17 Restoration Action Plan.

Appendix B,.Appendix. C.Appendix D.Appendix EAppendix FApendix0.GAppendix HAppendix IAppendix I1AppendixL.Appendix KAppendix LAppendix MAppendix N .Appendix O.Appendix P.Appendix Q.

................... ............. i....... 17

......... ................. ..... 20o •o, o o... . . .......... .. ..... ..... .. 23

eeo * o II Io IIIoI1 a I I eoa o ,o o *o w o o & oo e o A o 25

................ ........ ................. 257

... .... ...... . . . 27

'30

..... . . .... ,, o , ,.....o... ................... 31

o.o...o.0....0........38........ o i4&....... . ...o oo. ... . ... . .. ..... 39

DE 3198 Hi

Page 93: Church Rock Section 17 Restoration Action Plan.

EVRODUCTION

This document 'is a ,uid~1ina a*l- Its contents, are, not: to be interpreted by theapplicant/permittee or Wyoming Department of Environmental Quality (WDEQ).staff asmandatory. This Guideline intends to assist applicants/permittees in understanding and attainingthe reluirements of the Wyoming Envirnmental Quality Act(WEQA) and Land Quality Division(LQD) Rules and Regulations addressing bonding topics.

This Guideline was developed as a joint project of the Wyoming Mining Association (WMA)Reclamation Subcommittee and the LQD. The .LQD has and intends to, selectively andperiodically publish updated versions of the Cost Calculation Methods as contained in the variousAppendices.

APPLICABLE WEQA STATUTES AND LQD RULES AND REGULATIONS

This is a general summary of items from the WEQA.

W.S. §3511-417:Outlines some general provisions applying to initial bond and renewal bond valuesiThis statute outlines the concept of Partial Bond Release.

W.S. §35-11-418:Outlines accejtable bond vehicles.

W.S. §35-11-423:Outlines procodures for bond release for coal and ýother miineral permittees.

W.S. §35- 14-411(d):Authorizes the WDEQ Director' to establish thel bond amount based uponinformation submitted in the annual report, an-inspection and other materials.

These items in LQD Rules and Regulations have some applicability to bonding.

Coal Rules and Regulations, Chapter 1, Section 2.(k) and Noncoal Rules and Regulations,Chapter I,, Section 2.(i) defines bond.

Coal Rules and Regulations, Chapter 2, Section 3.(b)(xxi) requires that shared structuresbe cross-referenced in the bonds-of applicable coal permittees.

" Coal Rules and Regulations, Chapter 4, Section 2.(d)(ix),establishes a minimum ten (10)year bond period for coal permittees.

Coal Rules and Regulations, Chapter 11 and Noncoal Rules and Reguiations, Chapterý 6outlines definitions and procedures for the self-bond program.

DE 3/98 ofi.

Page 94: Church Rock Section 17 Restoration Action Plan.

CoalfRules and Regulations, Chapter 12 applies exclusively to coal permittees. Section2.(a) defne the Area and Incremental Bonds. Section 2.(b) elaborates further bond datarequirements. Section 2,(d explains the liability artas and periods for the Area andIncrementalBonds. Section 2.(e) distinguishes among and establishes procedures for bondadjustments'versus bond reductions versus- partialbondreleae. Secons.()through(h) address requirements for scific bond vehicles.

Coal, Rues and Regulations, Chapter 14, Section 4. and Noncoal Rules and Regulatibns,Chapter 8, Section 3. require a bond for exploration by drilling.

Coal Rules and Regulations•,Chaper 15 outlinesprocedus forpartial or complee release

of coal permittee bonds.

Noncoal Rules and Regulations, Chapter'9, Section 2I. iscusses bond requirements forconversion ofa non-coal Small Mine Permit o a Regular Mine PermitL

Coal Rules and Regulations, Chapter 20 and NoncoalRules and Regulations, Chapter 12details -information on Lettersof Credit used as-a bond'vehicle.

q0

DE 3/98& 'iv,

Page 95: Church Rock Section 17 Restoration Action Plan.

L COST EXPLANATION FOR ITEMS. USED.IN STANDARDIZED RECLAMATIONBOND COSTS

Equipment sizes (loaders, trucks, scrapers, motor graders, etc.) were selected and agreedupon by the WMA Committee and WDEQ/LQD based on the usual types of equipmentcontractors normally have available for use. Costs for other equipment may becalculated byusing methodologies as shown in this package.

Owning and operating costs were determined, except wheree noted, by using the atastuestCost Reference Guide (DQCRG). The total owning and operating costs havebeen adjustedin this package to reflect wholesale prices rather than retail. To do this, a ten percentreduction •has been made to DQCRG costs.

Costs for the electric shovel and the trucks associatedw .with the shovel, were determined fromWestern Mine Engineering, Inc. Surface Mine Estimor's Guide (Oct. 1997 Version). There

was noadjustment factor used for "these costs since they :are: basedon actual costs at miningoperations in theUnited States.

A standard efficiency factor of 0.83 is incorporated into all production calculations. Thefactor accounts -for a fifty-ýminute Work hour as recommended by many costreferences.

Labor costs were obtained from the Wyoming. Department of Transportation. WageDetermination Decision (1997). with an additional 25 percent; for benefits, unemploymentinsurance, socialsecurity, etc.

Supervision costs were determined by adding: $5.00 per hour to labor costs and also includethe 25 percent add-on for benefits, etc. In most cases, only a portion of a supervisor's costsis applied to each task. Theoretically, this allows one supervisor the flexibility to overseemany jobs or pieces of equipment at the same time.

The supervisor's transportation isalso divided among tasks. For example, where one-halfof a supervisor's time is allotted, the same amount of time is used in calculating histransportation costs.

Wjere only a portion of support equipment are used in a calculation (i.e., one-half watertruck), it is assumed that the equipment in question services morethan one area.

DE 3"S I.

Page 96: Church Rock Section 17 Restoration Action Plan.

Table D- . Operating Costs and Adjusted Costs (S/Hour w/o Operator) For Equipment in ThisStandardized Bond Format

I J ~,QCRG11Equipment .Equipment Name Book Cost Multi- Adj. Cost Date

Type 1 ($) plier (%) , ($) ,

Dozer Caterpillar D9R (SU) 113.60 90 102.24 3/98

Blade Caterpillar 161H 72.79 90 65.51 3/98

Scrapr Caterpillar 657E P-P 221.51 90 199.36 3/98

Truck (95 ton) Caterpillar 777D 170.45 90 153.41 3/98

Loader (13 /h yd3) Caterpillar 992D 192.26 90 173.03 3/98

Loader (5% yd)) Caterpillar 980F 64.38 90 57.94 3/98

Dozer Caterpillar DIOR (SU) 148.97 90 134.07 3/98

Dozer Caterpillar DII R (U) 223.85 90 201.47 3/98

Dozer Caterpillar D9N (UI) 105.11 90 94.60 3/98

Backhoe Loader Caterpillar 428B (2WD) 16.74 90 15.07 3/98

Water Truck 14,000 Gallon 135.22 90 121.70 3/98

Dump Truck 10-12 yd" 29.47 90 26.52 3/98

Pickup Truck Crew 4x4 3/4T (Gas) 9.74 90 8.77 3/98

Pickup Truck Crew 44 3/4T (Diesel) 7.85 90 7.07 3/98

Tractor MF 50EX 4W)D 74 9.11 90 8.20 3/98H.P.

Towed Mower Flail 7 ft 1.28 90 1.15 3/98

Rubber Tired Dozer Caterpillar 834B 96.00 90 86.40. 3/98

Scraper Caterpillar 637E P-P 169.05 90 152.15 3/98

0

DE 3/98 2

Page 97: Church Rock Section 17 Restoration Action Plan.

Table*1D-la., Purchase Price, Lcase Cost, and Operating Costs for 56 CY Electric Shovel and793C Trucks

Opemors that use the tnuck/shovel. appendix must show a regrading plan that is suitable for a largeshovel/truck operation., Many backfill operationstare not suited for this type operation'becausethe cuts are no thick enough -to allow the shovel, optimum digging depths, highwall reduction withdozers takes: up a, largepercentageof the required backffi, and there is insufficient backfill to,justifytis'large, shovel/truck fleet.

Operators using the shovel/truck appendixshould submit suitable. cutand fill isopachs that supportthe choice of this backfill method.

This method is not to be used for topsoil movement firm native areas or from stockpiles.

The $7,988,916.00 purchase price of the 56 CY shovel must be. added to the bond costs. Thereis noprofit or other contingency items added tothis cost so it can be added to thebond cost afterall the line!items and add-ons havebeen totaled. Nosalvage value is, allowed' atthe endoftheproject.

56 CY Electric ShovelPurchase Price $7,988,916.00 (WME)Productivity - 56 CY x I pass/35 sec. x3,600.sec/Ir. x.0.968 bucket fill factor = 5,576 CY/hr.

5,576'CY/hr. X 0.8696.BCY/LCY (15% swell of BCY) = 4,849 BCY/hr.4,849 BCY-/hr. x 0.83313 (operating, efficiency) = 4,040 BCY/hr.

Hourly Costs, (WME)

Labr E Lub TDoa1

$55.94 $46.23 $123.64 $22.83. $248.64'

Qteaillar 793CT'zcks 240 Ton)Pur•.•sPrice. $2,539,800.00 (WME)Monthly Lease (@600 hr./month) $45,000.00

- Hourly Leaz Cost $75.00

: - Hourly Costs (WME)

EM Main$.3a2 Eu$2 T.,•00 I•$1 5

$23.04 $16.32 $26.05 $161.80 $35.94 $118.15

DE'3198 3

Page 98: Church Rock Section 17 Restoration Action Plan.

Table 1D-2. Abbreviations Used inThis Standardized Bond Format

DQCRG -

WYDOT-WDD -

WME-BCY-MCYH-

BHB-

Caterpillar Performance Handbook (Edition No. specified where:appropriate)Dataquest Cost Reference Guide (date of data indicated)Wyoming Department of Transportation - Wage Determination Decision(1997 Version)Western Mine Engineering; Inc. (Oct. 1997 Estimating Guide)Bank Cubic YardLoose Cubic YardMiles Per HourBlack Hills Bentonite CorrationDEQ Abandoned Mine Land Reclamation Program

H., STANDARDIZEDRECLAMATION BOND FORMAT

Individuallritems may be expanded. as necessary or noted as not applicable based upon thespecific reclamation practices approved in:each permit.

A. Area Bond

The Area Bond covers the costs of backfillingtand rough grading (and special' reconstructiontechniques when' specifically approved) according to prodiedures, and postmining topographyapproved in the current term permit.

1. Introduction

Present ageneral discussion of assumptions, calculations, procedures, methods, etc. forsummarizing or documenting calculations.

2. Backfill

Describe equipment, procedures, volumes, and costs for bringing all pits to aninterim/bond topography with reference, to a quality,.current map of the project site.The interim/bond topography must come as close as :psible to the approvid final,to__graphy. acknowledging that the current mine site -differs from the finalamnfiguration.-

* Appendices A through F detail equipmentfleets and costs for this-.reclamation activity.

Operators, should clearly show cut and fill areas and'the associated haul distances andgrades on a map.

This section should:clearly list overburden Drilling and Blasting' costrat$0. lO/BCYiwhenapplicable.

DE 3/98 4

Page 99: Church Rock Section 17 Restoration Action Plan.

3. Rough Grade Backfill

Descnrbe procedures and costs for shaping interim/bond topography with reference to aquality map.. NOTE: Depending upon permit approved backfill practices, roughgrading may not be a necessary line itembond cost.

Appendices G and M detail equipment and costs for this reclamation activity.

4. Finl Gra Backfill

Describe equipment, procedures, and, costs for specific site tasks (e.g., drainagereconstruction or permit-specific postmining features).

Appendix G details equipment and costs for this reclamation activity.

B. Incremental Bond

I. Introduction

The Incremental Bond covers all other costs beyond those detailed in the. Area Bond.

SPresent a general discussion of assumptions, calculation procedures, methods, forsummarizing or documenting calculations, etc.

2. Native Topsoil Removal From Borrow and/or Backslope Areas

If-appficable, describe equipment, volumes, haul routes, and: costs with reference to aquality, current map of theproject site.

Appendices A, B, C, E, F and G detail potential. equipment and costs for thisreclamation activity.

3. Native Overburden Removal From BorMowand/or Backslope Areas

-If applicable, describe equipment, haul routes, volumes, and costs with reference to a

quality, current map of the project site.

Appendices A through G detail potential equipment and costs for this reclamation

activity.

4. Miscellaneous Overburden Redistribution

Describe equipment, haul routes, volumes, and. costs (with reference toý a quality map)9for backfilling structures, such, as:

DE31985 5

Page 100: Church Rock Section 17 Restoration Action Plan.

* scoria or shale pit(s) * sediment ponds* diversion ditches * sewage lagoons* access/haul road cut or fill o culverts* railroad cuts/embankments Other

Appendices'A through G (excluding D) detail potential equipment and costs for thisreclamation activity.

. Demoliion

Equipment, procedures, and costs for demolition and disposal of each individual,structure should be described in terms of size,. type of construction, etc. so thatappropriate demolition costs can be estimated, such as:

S fences* power lines,, transformerso hard-surfaced roads* bridges* abandoned equipment (i.e., draglines, shovels, drills and pieces of same)o culvests* railroads (rails, ties,, ballast, scales, etc.)* facility buildings (shops, warehouse, offices, etc.)* mineral handling facilities (truck dumps, conveyors, silos, scales, etc.)• support facilities (ready line, fuel tanks, water tanks, equipment yards, explosive

storage sites, electrical substations)

Appendices H through K contain costslfor these reclamation: and, demolition practices.

6. Removal of Monitoring Structures and.Other Miscellaneous Items.

DescFibe the. procedures, equipment, and costs required to properly abandon or remove

.and disposal of items, such as:

* .groundwater monitor wells* all other operator-owned wells within the permit area.o surface water monitoring stations.* all other experimental study sites- within the permit area* meteorological/air quality monitoring sites

Appendices L through Odetail equipment and costs, for these reclamation practices.

7. Scarification or Rippingof All Compacted Surfaces

Describe equipment, procedures, and costs (preferably on a per acre basis) withreference to a quality, current mapof .the project site.

DE,3/98 6

Page 101: Church Rock Section 17 Restoration Action Plan.

Appendices I I and P detail costs for this reclamation practice.

8. Topsoil Redistribution on AllDisturbed Areas,

Describe equipment, procedures, and costs with reference to a quality, current map ofthe project site. The map should show haul distances and grades.

Appendices. B and C detail equipment and costs for this reclamation activity.

9. Revegetation of All Disturbed Areas

Describe equipment, practices, and costs (preferablyon ha per acre basis),.including:

* seedbed preparation• mulch (purchase and application)* 'seed (purchase and application)* fertilizer (if -equired, purchase and application)* post-seeding maintenance over the minimum bonding periodý (e.g.,, weed 'control,

mowing, interseedng). Operators suggest that alten percent,line item should coverthis issue for the entire bonding period.

P Appendix Q outlines a cost calculation process, for-this reclamation activity. The costsmust be, calculated using the specific seed-mixes and practices. from the approved, termpermit.

10. Reclamation Statusý and Bond Liability Status ofAll'La.nds Within the Permit Area

a. Land Status. Categories

The bond calculation should describe the status of all lands within the permit area.Each land status category should be clearly identified on a quality map and cross-referenced to specific reclamation cost for each category. The. LQD also prefersa tabular summary of the, acreage for each category.

LANDS THAT HAVE BEEN TOPSOILED AND SEEDED BUT HAVE NO BONDRELEASE MUST BE BONDIED. FOR RETOPSOILING. SCARIFICATION. ANDREVEGETATION.. (see Section 10.b.(2)(b)i)e) on.page 10]

.. Tile following is a summary of generic eland status categories. Section 10.,(2) below.details the information and calculations ncessary for each of these, categories.

(1) Native lands undisturbed at the time of this specific: bond-calculatiotn andwhich will remain undisturbed under this bond calculation (e.g.,. no, borrowareas necessary).

Di"-. IN,;A 7'

Page 102: Church Rock Section 17 Restoration Action Plan.

(2) Lands regi-ding and revegetation at thetime of this specific bond calculation.

(a) Lands requiring assessment-of Area Bond costs

(b) Lands requiring assessment of fultlor Incremental Bond costs

(c) lands requiring assessment of partial. Incremental Bond costs

i) Lands permanently reclaimed piOor to December.31, 1982

ii) IAnds permanently reclaimed after December 31, 1982

a) Lands with no approved: Partial or FullBond Release

b) Lands with approved 60 percent Partial Release of theIncremental Bond

c) Lands with approved larger percent Partial. Release of theIncremental Bond

d) Lands with approved Full Release of Area and Incremental

*i Bonds

b. Line Item. Bond Costs

(1) The bond covers 'lands currently disturbed by mining and associatedactivities and. those lands to be disturbed in the next 12-month period.

(2) The bond should include costs for the.Area Bond (through backfill, roughand' final grading): for all open pits; impoundments, sediment ponds,diversions, etc.

(a) Section E. 1of this Guideline, and. its associated- appendices, detailprocedures•and costs forthe Area Bond:_- d. ne bondcalculation-shouiddetail costs forthe oper*ionslisted in:Section•-s ;...), C) andD),,.

(b) Section E.2 of this Guideline and its associated appendices detailgeneral categories, and procedures. for the Incremental Bond. Overall,the, bond calculation shoulddetail costs for theoperations isted' inSections E.2.B) through 1).

i) The bond calculation should, asses the full suite of IncrementalBond tasks and costs for all disturbed lands which have noformally approved partial or full release of the Incremental 'Bond.

DE,3/98 8

Page 103: Church Rock Section 17 Restoration Action Plan.

Historic LQD Administrator policy, LQD Coal Rules and Regulations Chapter, 15 andW.S. §35-I1-417(e), establish three. (3) distinct categories: of Pa•itiaBonid Release forpermanently. reclaimed lands.

a) Lands, Peranently Recaed Prior to December'31, 1982

Prior to this date and prior to approval of the Wyoming'State Coa Program, the LQDAdministrator granted de Partial Bond Release for permanently. reclaimed lands.

The LQD did not specifically approve or otherwise,.record this Partialt Bond Releasecategory, so there is generally no written 'approvl letter.

The bond should specifically identify this-Partial Bond Release category 'if it,!exists.

The bond should include a carry-over cost assessment for interseeding. an appropriate,permit-approved seed mixture on these.lands. These carry-over costs should includeseed purchasewand seed implantation.

b) 60 Percent Partial Bond Release

LQD Coal Rules and. Regulations Chapter 15, Section 5.(a)(i) allows for release of 60percent of.the Incremental Bond, when, the, permittee has completed backf'lling,regrading, topsoil replacement, and drainage control according to the approved termpermit procedures.

This category of Partial Bond Release requires formal, written approval by the DEQ:Director. If this release category exists, for your specificpermit, the bond calculationshould include, the, date of the Director's approval letter.

The bond calculation should specifically identify this category and show the. appropriateunits on a quality map.

The bond calculation should specifically tabuliae the residual, 40 percent 'IncrementalBond costs (preferably on a per acre basis) as the appropriate carry-overcost assessment.As-noted above, the Incremental Bond includes all term.permit approved ReclamationPlan practices beyond rough grading ofthe backfill. The tabulation of the 40 percentIncremental Bond carry-over costs shouldtdetail all approved reclamation practices. -

c) Larger Percentage ofPartial Bond Release

LQD Coal Rules and Regulations Chapter 15, Section 5.(a)(ii)(A) allowsmore than 60percentrelease of the Incremental Bond as determined by -the.LQD Administrator-andDEQ Director.

DE 3/98" 9

Page 104: Church Rock Section 17 Restoration Action Plan.

W.S. §35-1.1-423(d) manda+tes development of specific rules and regulations for releaseof coal bonds. These rules are controlling not withstanding other provisions ofW.S.§35-11-417 and -§35-1,1-423 to the contrary.

LQD Coal Rules and Regulations, Chapter 15 :is that formulation.

Coal Chapter 15 governs partial and 100 percent release ofthe Incremental Bond. Forpartial release, the amount remaining cannot be less than the cost of reseeding.,

This: category of Partial Bond&Release requires- formal, written approval by the DEQ,Director., If this release category exists for your sific -permit, the bond calculation

should identify the date of the Director's approval letter.

The bond calculation -should specifically tabulate-.the. residual percentage IncrementalBond costs (prefe.mbly on a per acre basis) as thedappropriate carry-over cost assessmenLAs previously noted, the Incremental Bond includes all term permit approvedReclamation Plan practices beyond rough- grading of the backfill. The tabulation! of thepercentage Incremental Bond carry-over costs should detail all approved reclamation

practices.

NOTE: The percentages of partial release of the-Incremental[Bond vary for NoncoalPermittees. A Noncoal Permittee seeking partial release should consult with the LQD.

d) Full Bond Release of the Area and Incremental Bonds

This category includes all land permanently reclaimed and formally released underprovisions of the 1973 EnViVonentair Quality Act and LQD-Coal Rules :and RegulationsChapter 15.

Full Bond Release requires formal, written approval by the DEQ Director. If thiscategory, exists for your specific permit, the bond calculation-should, list the date of theDEQ Director's Full Bond' Release decision.

e) Lands Permanently Reclaimed After December 31, 1982

This category includes all land permanently reclaimed, that has no bond release.

These reclaimed lands must be bonded to scarify, retopsoil, and reseed. There-are no,provisions made for where ,the topsoil would come from. It. is assumed that topsoilwould be spread at the same average depth on these lands as it is on the rest of the areasrequiring topsoil. Topsoil haul distance and grade used would be the weighted averageused for the rest of the reclamation. Scarification. and reseeding costs would be the ;sameper acre-as those used on other lands requiring reclamation.

DE 3/98 10.

Page 105: Church Rock Section 17 Restoration Action Plan.

NOTE: The DEQ/LQD continues development of a- DRAFT Guideline on Full andPartial Bond Release Procedures. Please consult.with the LQD concerning the status ofthat Guideline, should you consider bond release for permanently reclaimed lands.

11. Coal. Drilling

Describe the, approximate number, depth, diameter, and location (show on inclusivemap, if possible) of all holes drilled into or through coal during the current and nextannual report period. A tabular format, with.reference tO map locations may be anefficient presentation. This.desciption should distinguish! between coal drill holes whichwill be or have been removed by the pit advance within the annual report period versusthose coal drill holes which will not be mined out in a report cycle. Theoperatormaydistinguish between abandonment/plugging procedures for the coal drillholes mined outin the report cycle versus, the, longer term abandoned holes. Eachcategory should havea total line item cost entry in the .bond. 'The LQD prefers that all coal drill holereclamation costs be estimated according to Appendices L and M.

12. Miscellaneous Items

Each 'individual operator should identify these items as a line item or include each insome specific bond category. Otherwise, the LQD will enter the item as an addition tototal dollar value-of the Area and Incremental Bonds.

a. COSTS FOR AN INDEPENDENT FIRM TO DESIGN THE FINALRECLAMATION PROJECT: All design and engineering work (including fieldand office time) through production of construction documents should be includedunder this heading, At the least, some surveying and redesign of the operator'ýsreclamation plan to fit the current situation would be required. Reference sourcesplace this category at 2 to 61A, percent of the total bond cost. LQDtypically uses3 percent.

b. CONTRACTOR PROFIT, OVERHEAD, MOBILIZATION ANDDEMOBILIZATION COSTS: The Dataquest Cost Reference Guides used toconstruct the appendices do not include these costs. If an operator uses these*appendices in bond calculations, there is still a need for this distinct line: item costin 'the bond. Assorted references place these items from 8 to 15 percent of the totalbond cost. Presently LQD is using 10 percent.

c. PRECONSTRUCTION INVESTIGATION AND STABILIZATION: This itemaddresses all field work necessary to document and mitigate dangeroUs and/orquickly deteriorating conditions, such as slumping 'highwalls or drainage problems.Any assessment under this item will be based upon the LQD's knowledge ofspecific site conditions and the length of time between cessation/forfeiture and'initiation of ,the final reclamation project. When necessary, reference sources, place.this cost. at 'Ir to 2. percent. LQD isusintg 1, percent.

. DE 319S I1I

Page 106: Church Rock Section 17 Restoration Action Plan.

d. COSTS FOR -AN: I EPENDENT FIRM TO MANAGE THE FINAL,RECLAMATION PROJECT: This category includes completeoversight of aUldemolition, onstction, and rclamation aiviti. Prbable,.task would includesupervision of earthmoving and reclamation, construction surveying, and soilsampling. References place this costat 3to 4- percent. LQD uses 3 percent.

e. COSTS FOR ON SITE MONITORINGPROGRAMS FOR TEN YEARS AFERCOMPLETION OF THE FINAL RECLAMATION PROJECT (INCLUDESSUC M S AS! UTlITJ[E AND GROUNDWATER SAMPNG);: Costsofthis item w llyvary depending upon specific permit commitments. The LQD usesa range of 1/2't0o2 percent. Usually LQDusexs 0.5,percent.

f. COSTS FOR SITE SECURITY DURING THE FINAL RECLAMATIONPROJECT AND LIABILITY INSURANCE COST DURING THE FINALRECLAMATION PROJECT AND OVER THEý FULL.BONDING PERIOD:References place this.cost, at.about 1 percent of thei total bond amount.

g. LONG-TERM ADMINISTRATION AND: ACCOUNTING COSTS: Aftercompietion,,of a major reclamation project, a minimum of five-years (non-oallpermits) ora minimum of ten years (coal permits) will expire iefore ,the LQD canmovefOrrfinalbond release. TheLQD will incur-additional administrative costs,during this extended period. The scale of some coal reclamation projects maynecesditate employmentof an outside contractor.

The LQD uses a• range of 1 102 percet for thiiS category depending •upon thie scale

and complepity of ithe, reclamation and post-reclamation monitoring projects.Currently LQD uses 2 percent.

h. ANY OTHER SiTE-SPECIFIC PERMIT COMMITMENTS SHOULD, ALSO BEINCLUDED HERE: Costs will vary -according to specific permiit.commitments.

The LQD has. historically us thefollowing: sources to establish the range of percentageslist in the Miscellaneous Items.

" Means Heavy Construction Cost Data (c t edition), published by R. S. Means!Company, Inc., Kingston, MA

* Means Site Work Cost Data (current edition), published by X. S. Means Company,Inc.,* Kingston, MA

* BuildingConstruction Cost Data (currentedition), published by R. S.,Means Company,Inc., Kingston, MA

- Handbook for Calculation of ReclarmationBond Costs, 1987, Department of Interior,Office of Surface Mining Reclamation and.Enforcement, Washington, D.C.

1DE 3/98 12

Page 107: Church Rock Section 17 Restoration Action Plan.

Wominag DEQ. Abtxdondd Mtte Land Program contracting and rclanmation practices.and cumulative experience

13. Unknown Costs

The items under L) represent the usual contingency items applied to bonds. If thsewitems are included as line items in the bond, the only remaining category could beunknown as per W.S. §35-11-4117(c)(ii). References place thiscost:at2 to5 percent ofthe total bond cost. Under normal circumstances LQD is using 4 percent.

14. References

List sources of information, procedures, costs, etc. which were used, in* the bond:calculations.

15. Maps

This Guidelinerequests that the various tasks, operations, disturbed areas, reclamationareas, etc.,, be illustrated on or referenced to aOUALIY, CURRENT A. Severalof the tasks may be illustrated on the same map. All maps presented lin support of thebond calculations must be clear and legible contour maps or recent (with. date) aerialphotographs. The preferred scAle is 1" =5,00, unless it is necessary to directly compare(e.g.. overliy)-a bond map to-an existingpermit map. In this case the;.scales should beidentical. Each map should be of a reasonable size, generally no-largerutan-48" on aside.

Each map nmst have:a complete titeW block, including:

* Map title* Name and address of penniitee* Permit number and term designation* Annual report period* Scale, north arrow, contour interval,, date of photography or date of preparation

All maps must show and clearly label:

* Legal subdivisions with section, township,.and range lines0 Permit area boundary and tjenn boundary,

m: kPPE.DIcEs

The following appendices are intended foruse in this standardized bond calculation package. Any,references to specific equipment should not be interpreted as a recommendation of any kind byany person, cofiipany or agency for the use of specific. brand-name equipment.

I It- 3 .F I.

Page 108: Church Rock Section 17 Restoration Action Plan.

.IAppcndgz A:Calculaim for loiocavlug i Uaiialzb a C gap Hur 9921 Lma aunad COWkM MDr771 TM*c Plus

N47 f71 oS'S ARE FOR CAVAIMON ONLY. 14•,RALlREQUMJ C 3LASTMG HOLDnRAVE ,ANADDmCIAul.ý0JCsY ADDED FOR DRJUID

A1,D BLASTING C0M,.

MMairalMoqkcdu By Laadcu-Tniak 1k

)apma 777 DThcka (IS im)3)mawaa Domity

4) 9walubW El~hlaic Pm 0OidluIfW5) ahsi tReaIming Fsacl6) T7772 _Thik Oeta-M Co7) 9920 LdcrOpauftia6) Low Cor9) 112 d2r..- 14,000 GaL Was Thick, +1--IOplmm~

10) 1.- 16H SBlad fur Rad Wodk: +I OP1taII) 1. D I9RM cMWeik +I Ovaoar12): Supavwim LUbo Cou253) SqaeviswarTmwudattma

14) Toatalm'HoRmis COWt Okccpt Thacb)

12.2 3I

O8.IDCtV284.00 LBCY0.83A

8$153.42 PetItaIf1173.03 Pe• au

Sl'l.75' Pu•t N

534.26 Pf HI•w5120.99:Perlicur-

$12.50 Per howm

$464..5.3

CPH125CP§12S.CP. 2ýCPK25

€54125

90* atDa?*o" Cost Rdamm aid&90% DQMROWYDOT-WDD112490% DQ0CO

9%DQCRO.+ Opiusuta.90% DQCROJý+:OpertM.112adWYDOT-W/DD112*4d 90% D~

TO USE TABLE' Locate yur approuiimak OWnd byrferage to cam umbeor. Detetiia tio We RCY, by using dI'ane. colmna fst appra lmaicy=our d h. No aftlatimeam-osuy.

t•2,u: iln IL•,vd (•hrnimd ,L,•- rVcK •rdA. & 41L ,fnllh =l ar, •,.t ' -~t~m; r•emndlV fll•l• e.•mle' .l.•dCl•*'IdrV•l n,.ti•sneJmlCm #I: Lcvd CkoLmd. Lemftd (Os v-ý- +AS i-&ý = 4% r--,Rm filk'+AWtow-60-A

Truav, TOrW Taod.y Lod Man- T-na D-p Tom Cyeu Trip

S e r ir=-, V6d2& Tint. MptY TiM pa Pad.(mF .o•Mi 0M.) WMh.) () o&ev.) (O&.) Hour. on) (BCYflhi

ýAdtedý'LAd=

(DCW~vet

efNUnka'

S03 3.50 ,0.70

lOw 3.X 0.70

Lk0o 3.50 0.70

20O0 3.50 0.70

5m 3.50 0.70

30]0 3-50 0.7O

.500, 3.30 0.70

400. 350 0.70

S• 3 3.50. 0.70

700 35.0 0.70:4000 3.50 0.70:

7000 3.5W. 0.70

o07 1.10 0.36 6.13 '9.

0.78 1.o0 o.s6 .64 9.0

1.06 " 1.20. 0.74. 7.10 8

1.34 1.10 0.90 7MM4 .8.0

'260 1.10 I1. 7.96 7.5

588

58.8

58.1

58.8

58.8

1.86 1.I0 I.2 8.33 7.2 55.8

2.11 1.10 1.39 1.20 6. " .518

.237 1.10 I-5 9.22 6. 58.3

2.63 1.10 1.71 9.64 6.2 .55.8

2.89 1.0 1.88 -10.0M 6.0. 58.3

3.15 .1.0. 2.04; 2o09 5.71 58.8

:3.41 L.0 2.21 2I.92 S. U58.8.

3.6 2.10 5237 21.33 5.3 58.

3.92 3.20 2.53 2175 5.1 58.8.

479.6

442.1

414.1

339.9

369.3

30.8

,334.1

312.9

30S.0

292.O

210.3

269.2

259.3

*2S0.2

840.00

3,40.0,

540.0

540.0

540.0

840.0

840.0

840.0

840.0

540:0

140.0

840.0;

140.O

840.0

1175

1.90

2.03

2.15

2.27

2.39

2.51

,2.63

2.75

:2.98

3.00

3.24

3.36

ow•Oper

$0.97

50`99

51t.0

$1.07

st.ii?

$1.09

5124

Opmaing Csa- ((Co TnUka CTrck cost + Libor coat)) + TOW:ha c-UAa M&d.I

DE 3(98 14¸

Page 109: Church Rock Section 17 Restoration Action Plan.

Appeadix A' (CanimkU4Cakalatlan far MtwbA Uatawal With a Cappifllu M9D Lm&dcr and Calapflla M7D Tmwk Il

Mumialt m~eovaa By UimýT1m*c COGbA&IOM

ILamcd (.5% cradc4 4% eofti,- -IS sad4 ~ I AM& (ss ,, ,. '5-, n.- .- . .- '+M --M gluma

40mm-wi. LondDbftmc rdwAl) o"h)

"Tmv Tnvdýthm Dump . 18.

umt. Landad T8.c HoM04 Ots. 0" qw

"t'otd- Adj-Wý~by Tra :lan1dwr -mb o

78. per PWyb-a PuAuwd*i P~~m* Emi coif060 H BCY Q 0 CY1M b) i4 Rwpba aw"CI

sow

:2=0

2m0

ýso

40m

6500

7000

3.3

5.3o

3.So

3.3O

3JO

3.30

.3.30

'3.3

,3.50

0.70

0.70

0."70

0.70,

0.700.70

0.70,

0.70

0.70

o:70

0.70

0.70

030 1.10 0.41

0.58 1.10 0.66

W.74 t10 0.94

0.49 1.10 Li1

1.65 1.10 i.43tjo. IAO' Iti1.20 1.10 1.63

1.35 liGo 1.91

1.50 110 .17

i.6 1.10 2.42

1.81 1.0 2.66

1.96 1.20 2.91

lt 110 3.16

242 1410 3.40

2.42 1.10: 3.65

6.Wm

c98

737

7.78

L.57

6L97

9.38

9.77

10tom10.57

10.97

11I.37

79.9

7.0

A6.

61

5.9

5.7

SiJ'

53.8

58.3

58.8

.58.8

sss

58.8

55.8

58.3

58.

58.

48w.8

"448• -

421.2L

/396.9

•371.9

359.4

,3431SSq.S

327.8,313A

268.0•25S6.

840.0¸

840.

840.0840.0

Saoo

"•0340.0

840.0

040.0

840.010o.0

840.0

840.0

1.4'

1.87/

t.29

-2.91

2.34.

2.56.

2.68

80.912

8094

lags

Sim981.01

,SLAM>

'51.10

51.12

11.1751.2t9

St1:21

SL IM 10%AftaiadnaOrad La~ded 410%cva& +4% mdli., = .6% tatalt ~nEfr t10%:arade. +. 4% mil~. 14%.t~ta1l,:Lm;dad'&10%**r&&,-Iý MhAi6rý- -6t'tntkb

Om-WA7

Disto)

towo

3wo

SOW4500

7000

Tino T'm

3.50 0.70

3.O0 0.70

3.30 0.70

3.50 0.70

3M,0 0.70

33' 0.70

3Io- 0.70

31so M"7o3.50 0.70,5.50 '0.70

3.5" 0.70,

3.0 0.70

3.50 0.70!

Ilia Dmpow Ta. :Cycb TripiL.06&d Tune EMPt*,, 18. ptr

,Ad~nn, Tawk

-okw f0--0CPM O3cift) (SICYflI*

OP-1

0.35 1.10 049 6.14 9.8 58.8 478.3

o052 1O o0.90 6.72 8.9 58.3 437.5

0.67 1.20 1.3m 7.28 L2 S.8 40.8

0.82 .1:0 1.72 7.84 7.7 :58.8 375.0

0.97 1.10 2.13 '6.40 7.1 s68 350.0

1.2 .1.0 I &2.54 L97 P 6.7 58.3 327.8

1.28 1.20 2.94 9.52 6.3 58. SOLS

2.43. 2.10 3.3U 1o.08 . .6.0 :18.8 291.7,

1.59 2.20 3,76 10.65 5.6- . 276.1

1.74 1.10 4.17 11'.2 5 58.8 262".3

2.3 11O A4M8.. 1.77 5.1 56L3 249.8

2.04 1:20 4.99. .33 4.9 AS.l 2M8.4.

2.20 2.1O 1.40 22.90 4:7 S8.8 . 2"7

2:35 :110 5.80 13.45 A4S 58.8 '218.6'

840.0

840.0

840.0,

.840.0840.0

3840.0

840.0,

840.0

840.0

840.0

840.0

840.0

840.0

'840.0

2.75

41.92

2.08

2.24

2.72

2.88

3.04

3.36

3.532

3.69

!3.84

80.91

$1.01

$1.04

5 1.08.

$1.14

$1.28

8$1.2"2

,$131

$1.34

DE 3/98 15.

Page 110: Church Rock Section 17 Restoration Action Plan.

Appeafdi A 9ýainsdCjmhtim for Movimg.MsAlctg With a Cau~pftIr 99D Losdot MWd CMat~xiia 7D 2,mk P1k

Ugraul Mavaurat by Laadu.Thwk C~i6~

-. --- -Im--m i- xiuc v qu um 7 JJ m 1-W EU Y, qW LU *-W u

o.)w,•Malice

.54

Ism

154o

2m4•so

3ow

40o

4540smo

55o0

6mo40oo

3.034m

3.30

3.30

3.50

3.50

3.30

3.o

iVrid. Twm

O.• Tm I m c cTom Los".i -ra am Mmo

0.70 0." 1.10 0.3 6.29

0.70 1.2 1.10 0am 7M2

0.70 I1I 1.10 0.65 7.76

0.70 238 1.10 0.51, 549

0.70 a.m5 I.I0 4.96 9.21

0.70 3. 1.10 1.15 9.94

0.70 4.10 1.10 1.26 10A6

0.0 4.68 1.10 142 1140

0.70 5.2 1.10. 1.57 12.12

0.70 .82 1.10 1.72 12.84

0.70 640 1.10 1.87 M"57

0.70 6.97 1.10 2.M 14.30

0.70 +7.54 1I.0 25 IS."02

0.70 .8.12 1.10 2.33' 1.7s

9S5 55. 447.4

7.1

65

6.0

53

SA

4.7

4A,

4.2

4.0

,$IX,

SI.

SILl

SIL8

SIMS85588

SL8

58:8

S8,8

SLSS

53.5

415.

347.9

311.i

295.0

274A

259.7

245.0

.230.3

215.6205.5

196.0

186.2

A40tdU

pcYA5,

!4o.0

540.0

540.0

540.0

140.0

540.A

8s10.0

540.0•540.0

540.0

540.0

540.0

2.01

2.A3

2A41

2A64

3.A6

3.23

:3143

3.90

4301.4:.5i

acwC-B

50.97.

51.01

s~m

51.40

51.14

'61.13

51.26

$1.30

$135

1.,39

11.43s1.458

114mr-

I .A.1A Alflm M A. A - -,4AM *..lf'I%*o*,, lq ItlqL ll•.,e•m4, d'n.m4* I IAM - AmýCýM-Apq- 104L can&

OFL)

Mmaavcrmbu'Uso

So0

I000

040M2540

SSW

35oo

6m13

45w,

v50'50

•3;,50'3.0

3jO

3-1b

340

3.50.

sio

340

3450

2so

0.70

0.70

0.70

0.70

&.70

O.70

6.70

0.70

0.70

0.70

0.70

0.70

0.70

8-76

Tmvd Trave TOW,79M D.v Taow cyat~ UPa

La~dod 7m ILI Ti Puer(mb,.) 06 .) (Mo +) oti) Hou

0.94 1.10 0r.33 6.5X 9.1,

1.83 1.10 O49 . 7.62 7.9,

2.72 1.10 0.64 8.66 6.9

340 1.10 0.79 9.69 6.2

4.49 110 0.94 10.73 S5

$38 1.10 1.10 I1.785 5.

6.26' I.0 1.25 12.81 4.7

7.15 1310 5A.40 53.5 4.3

5.04 1.10 1.55 1489 4.0

..94 1.50 1.71 15.94 3.5

.9.51. 1.10 1.36 16.97 3.5

.10.70 1.10 2.01 15.01. 3A3

l1.29 1.10 2.16 19.05 3.1

:M44 1310 2.32 20.10 3.0

:,Ackd

Po- -.Ohm. -9IH

5.8+

SIL8

SL•I51.5

'51.

Ste.

S5.

S5L5

SlL8

55.8

445.9:

387.15

3381

302.8

34919

230.3.

210.7.

196.0

'186.2

-171.5

161.7

5t1.9

54r70

540.0

540.0

840.0

540.0

540.0

.+40.0940.0

140.0

540.0

,840.0

540.0

540.0,

540.0,

140.0

,Nu~m~berof Tnwks

1.85

2.47

2.77

3.07

3.37

366

3.96

4.25.

.4.55

A."5

+3.44

15.74

$1.00

C-c

50.94

$1.06

.$1.12,;

$1.18

$1.2441.30

$1.36

S1.49

SImS

$1.61

S1.67

S1.73

DE 3/98 '16,

Page 111: Church Rock Section 17 Restoration Action Plan.

,Caleulatimis far Mavfthg aeijala With a Caleiplla 6M7 Pab-Pvf Scrwwer Pd

NOT& DRILLING AND BLASTING COSTS ARE NOT M1CLUDUI IN 70MCALCUIAflONS. 7MUPLI DOES NOT CON.SWID VRILZDG AND BLASTING COsi

Cafr 657 Pt,%D Scape

4) Mazimum v&;-c Spmd I~S) Op.Wg-.•Efieiiwn• Par (0 rms.)Q 65m7 PP opat CmoSi7h Labaros53 sqervsieu Laba, e

I05 14 dIl - 14000 GaLWatcr.Tramc + I OF Pnor

12 . D'A f- Rik" O,"o. Wd Misc. W*k + I Opauxor

V3) TOW Hty coam

2.W&o. LWCY

34.9 WM K0.83 .%S

199.36 Per Hdm$L8.7S Per HOW53.13 Per HourS1.1O Per Hai

517.56* Per HAurS10.5 Pur lmit

$310.93

PH 25

CM 25CH7.25CIPH is

90% DQMOWYDOT-WDDlit of WYDOT-WDDi/8at 90 DQRO

in of'0s QCROU8*f90SWmQCRO

T.O USE TASLL Locateyear apptoximate grde by rfateew ease ueiber. Deteans ct perICY by, uarj dine cada tpproziMatsyan4im Nwaealculations ame

Oae.~wsyý LouDisum Tin

(FL) 0

LmiteA m~ ~,.A. 4 At ~ = At t~.B .Emni MS trr& -+ 4% ntroaff = 4'IOMa1-ded m% i-d,- + 4% -W-. = 4% lidsh

Trave",,-tlkft

oi-.):

* Mllaneuver& SMad

Time,

sm.

1500

2000

2m0

3006

3S00

4000,

4500

6000

6500

.I.10

1.10

110,

1.10

I.10

I.I0

1.10

3.10

.40

2.10I.I0

1.101.10

,,` IO,

0.42

OM.s

0.92

1.15

137

I.sI

2.02

2.22

2.43

2.68

2.85

3.05

0.60

0.60

0.60

0.600&60o.60

0.60

0.60

0.60

W.60

0•60

0.6

Travllima

0;7

0.75

0.92

1.09

1.26

1.44

1.73

1.95

2.13

2.30

2.41'

cycl

(Mic.)

+2.48

2.95

3.37

3.77

4.16

43i

4.95

5.70

6.U•

6.47

6.85

ý7.22

TfapsPeiHoar

24.2

20.3

17.8

15.9

14A

13.2

12.1

11'+3

10.5

9.9

9.3

8.8

8.3

35.0

15.0

35.0

35.0

15Uo

35.0

35.0

35.035.0

35.0

35.0

0.83

0.83

0.83

0.83

0.83

&.83

:0.83

0.i3

A83

0.83

013

0.83

706

.593

519

44

421

U35

354

328

238

.270

255:

242

230

40.44

$0.60

50.67

$0.74

50.81

53.01

S1.15.

S.22

SL28

S1.35

ElmeneyPym Faoimr

(-CYRfl• (VBCY

I .in It 4& ft -P ft - -9 An "Yo. "seaf-to .35 n

DE .3198' 17I

Page 112: Church Rock Section 17 Restoration Action Plan.

Awimdix 3 (Cafi~nadCaicuitions for Imin~g Mulerala Whb a Cmatpilla6578 PushPut2 SCVape Pbzt

lrJ•sqL et~n,• rs•SA. 1[zA.A I.A sq A ,b, . AI .. ilton = .• 14..tmls VP.r.fv £54 m-A. 4 41. m h,- = , n

omiwq

Soo

50•

IM

1000

25M

1450

soo

Gmm

'rtw, Lmos"ow s-

1.10

1.50

1.10

1.10

'1450.

1.10

1.10

1.10

2.10

1.10

1.10

1.101.10

0.36

054

0.11

1.19

1.16

1.52

1.35

2.01

2.17

2.33

.2:30

Tim

W),6

O.6O

U0.0G6O

O.60

0.600.60

0.60

0.60

0.60

TtdTbw

0.42

0.1

4L"

1.25

.1.43

2.32

'259

2336

3.93'

,TOW

2m4

2.2S

3439

3.11•LU44.24

4.6A7

5•.126.11

7.26

7A69

Per

24.2

32

17.7

15.7

I"

.11.7

10.1

10.2

9A'ILS.Z.313

7A.3

3mim

ow- lo"

3.5.0

35.0

35.035.0

S5.O

J35.0

35.0

3S.035.0

35.0

15.0

0.1

0.13

0.11

0.11

0U3

0.13

0.111

0.13

0.110.83

A3CYMed

706

593

,516

458

413'

342

2i6

U1,1

228

215

S0,6

3cob

GMM

$0.44

30.63

10.7510,1

50.91

$11.06

51.21,

11.29

82.45:

0Crm AS: 10% Asthsh GradeI.

~ .4. a. A~ ...n... = Ir-ndrtýO MIL ...- &• A4 gmIf= 141L ftJn,i L ,0 --- +4I-%6f

OaiWq

(K)

56O

10006

2S0

SSWo

sm

G6M

065W

Trm

.1.10

LtlO

1.10

1.10

1.10

1.10

1.101.10

1.10

1.10

2.10

1101Q.a

TivdTime

0314

0.51

0.6+7

O.81

0,99

1.16

1.32

I.3

1.64

1.31

1.97

2.13

2.30

?2.46

&• Spred

0.60

060

CO.6

0.60

O.6O

0.60

0.60

0.60

0.60

0.60

.0.60

0.60

.a-o,

TendeTim

0..51

2.30

2.'14

3.19

3.63

4.08.

4.97SAl

5.36

2-102.7486

3.19q

Mud)7011dc

3.17

3.78

4-n

4.C

6.21

6.12

7A42

9.249.3

1046

TrsPer

23.5

M8.9

11.9

,13.7

24.0

10.7

9.7

L.I

3.1

7?.5

6.9

6.5

"6A

-S.7

, , 00, O,&

0pslnC-w

OMcM

35.0

35.0

35.0

35.0

35.0

35.0

35.0

3S.0

3S.0135.0

35.03S.0,1.5.0

$5,0

0.83

4.01

0.83

0.13

0.11O.13

0.83

0.11

0.10

omsr

686

552

463

4W.

351

313

232.

237

236

213

203

119

177

.167

80.45

50.36

50.67

M0.8910,99

$1.10

$I.I081.22

$1.43,

$1.6S

311.76

$81.36im Mo '2 630 3SIO OAD

DE'3198 :1.8 -

Page 113: Church Rock Section 17 Restoration Action Plan.

Sra Movig M4dat s Wia Camt 65'7 Pk-Pta r Pka

M Ik Movnaint BySs ,a

Lo.dcd ES% atade +4% ioUinz 9% taibfl MmY (.5% ataik + 4% Endhing = -la tnm,Laaded 15% 04& + 4% rýý =*91L I&III

Ooa-WqThvd71M

TWOnowۥcl oiwd

s5o LIo

lw1.10

2000 LW.I

25W00 1.0

3500 :110

4000 1.10S45q00 3.+0.000 1.0ti

5500 1.10

6000 1.10

GM0 1.10

Cuz6 0: IO1.10Oma

0.25.

I.2

L46

1.92

.2.3

2.83

.3.73,

4.21

44A6

5.12

6.49

0.60

0.60

0.10o

0.60•

0.450¸

0.60:

0.60

0.60

060

0.60

0•60

0.60

IL60:

0.33

0o0

0.66

o.83

0.99

1.15

131IIS

IIA

1.30

1.96

2.13

2.29

TowCycle

2.33

S.21

32.8

4.45

10.07

640

6.91,

373;

9.42

WAS0

In-"4

IPkr

18.7

3.5.713.3

IM.

10.6

9.5

0.7

64

7.0

:7A

VW-od p~mron COmru-

A4WMd

cýdcwnvt)

350

35.0

55.0

35.0

35.0

35.0

35.0

35+0

0.83

om0.13

0.83

0.835

0.83.

0.13+O.83

0.63

0.93

673

545

458

293

245

S08

153

232

214

199

136

174

'16

Op4dIat

I0~

W0.9

$1.01

$1.32

$1.34

$1.45

$1.67

$1.79

0-60 2AS: stoo

118%(2*-a.n + 4 nf mi;,.:= .14% tapa2 a..* fIt-0a &d + 4% a1n, h'tt

Diusaw

CFL)

25001000

130002000

m.o

4100.5000

6000

4500s0o0

7000'

Tnadl

Who. O".)

& Spad:'r'm

Tmtvd TOW

TMivc TomMaL) OfSL)

2.20

23.101.10

I.10

1.10

1.10

U101.10~

0.72

1.43

112

2.12

3.49

4.18

4.37

S.56

.6.U4

6.93

7.62

099

9.63

0.6O

0.6,0

0.60

O.6O

.0.60

,0.60

0.60

0.60

•0.

0.60

a-g

0.32 2.77

0.49 3.62

0.65 4A7

0.31 5S2

0.96 6.17

1.14 7.02

140 7.37'

1.46 8.72

IA63 9.57

0.79 '10.42

L.95 11..2

212 12.13

2.21 12.97

2.44 13.82

TnaUPrPer

H-

21.7.

.16.6

13.4

'11.3

9.7

8.53

7.6

6.9

6.3

5.3

4.9

4.6

Al'

ftylmd Fsact(CyT 4 cs,"

Acyn1) OIKcY)*

33.0

35.0

355.

35.0

35.0

:35.0

"35.0

35.0

35.0

35.0

51.0

35.0

as -a

0.83

0.83

0.930.83

0.33

,0.83¸

0.83¸

0.0

0.D+

o

oml

632

483

391

329

294

29.

201

183

168

'44

135

127

S049

S0.164so.',50.60

S&9S

$1.09

51.25

$1.40

5 1.355

1.00$2.36

$2.36

12:45

DE 38 19

Page 114: Church Rock Section 17 Restoration Action Plan.

APPMOdi Cctsubtionm 1wMmski mauisbmrab a cSeapmu am 637 hmb-Ic suw P~m

MOM DRIMPN AND 3LAS-NGC ait ARE0 NOT DCWU DINMcAIAMIA7M1. 7M LQD DOES NOT ONSEDR onzuJnC AAND BLDA-M Coors

NEMSSARY WHIZNUSDG Ar3ENDIZ C.

1) -CeUCar WS7 Num-NU&rp2) Maia Da~rk

5) Opd•w Efti-mey o 00 mlfr.)d) 6371PP opiravti ol

In &ycgwkor Lab:r9o r + Sqcot4,ozmlOerndm ÷ pmwI SO) d 1'10 Ca!+ +Wa u I Op'sas.11) t- IGR fw ri Oob..-d Wcra.Wak +1 OPmr

LI) TOa Hal Clb

75,000.1I.e

'25.0 DCI33.0 WI

0.83 %li

5152.15 For HOWSIL7S Pt How

b1.5 • lrowSt.0 Patr Raw

$17.$6 Per How,$I.M P7 t am

$263.72

CM125CM125

cGit 25:90%,DQCRGWYDOT, WDDisnd Wt DT-wDD118 of 90% DQCRO1/Sld9o% DQgaO

IMS of 90% DQ=O46 of go% DQC1O

'To USETABLE: .Locwmyour approximaue pad by nesm loran ==&W ~I. Delenise ostpar CIby rng 41gm.. ohrn da pprouimaeaayewastdss&e t"O.aleuttvm aft

t 91 -ýLayc Ornmd Lmded ~E ,ude 4. dLgediw 4~ O~R0 nmntv 4MS ra 4AIL 4 ta fUti - AS lftail,fiM vnk& + AS-m9ing = AIL bfth

TnWd

1000

2500

ý250

4000

6000

6500.

700Oamo

..I=

1.0

1.0

1.0

3.0'

I.0

1.0

1.0

1.0

1.0

942

'0.68

0.92

1.37

1•.9

2.022.32

2.6

2.85-

3.-6

A Sp, Imd(Imm)j

0.60

0.60

0.60

0.6O

O.60

0.60O,60

O.6O

0.60

0-60

0.60

O.6O

0.50i

Tr7wd Toad

Ecm TimePAW P&.).

0.36

0.57

0.75

0.92.

1.09'

1*.4

1.61

1.7t

2.95

L 13,

2.30

2.47

1 Ad,

2-M8

2.85

3.27

3.67

4.06

4.S

5.60

5.98ISMg

6.5S

7.12

7-50

21.1

18.4

16.1

14.8

13.5

12.4

Ili

10.7

10.0

9.4

8.9

M4

3_O

HW-7Paylood FTactor(DCV) 00 subm"

25.0

25.0

25.0

25.0

25.0

25.0

25.0

25.0

25.0

25.0

25.0

25.0

25.0

0M83

0.83

0.83

0.83

0.83

0.83

0.83

0.83

C!83

0.83

0.8.3%

CBCYIMz

532

438

382

338

30?

28D

257

239

203

174

166

10.50

50.60

50.69

$0.78

S0.86

50.94

4$1.0&

$1.11.

41.19

$1.27

$1.43

51,,$Ii$1.3

to 250 083

DE- 3/92 20

Page 115: Church Rock Section 17 Restoration Action Plan.

Appacdix C Cafitw~d) ,Cutculmkmroa r ldavig-htcri~ib Wlhh a Cwwat~aIr,6371 Puaab-Pu11 ScrapW FkCd

MaWWMiaI ?oVd By 8MVrs

• ,, + , o . - ,I• • SeK Au.hmmD 45151dm LaIM IAt'.~.A~ 4. At ~ tMd~ ~. 1St ..~& 4 At ~flIli - Ot ,.~a.hCkso 02. 5% A-Am'- Grp& LAWW + 4% V-w ds% -M;i- - 9% ymýft

toao

.4001

2501

35W1

4501

sim

10+i

1.o

1.0

1.0

1.0

1I0

1'.0

1t.0

1i.0

1.0

2i.0

'1.0

0.71+

0.871T.03

1.19

136

1.68

'IAS1.85

2t17

2.33

2.50

0.40

0.600O

+0.40

GAO

MLO

0.6o

.0.40

0.40

0.60

0460

7km

W10.721

0.9

-1.7k

2-"

249J

232m

3.72

4.34

4.57

SM

6.13,

7.,'f

,7..59

lami

Ham"

25.2,

210.

14J14.51

12.0

10.2

7?.9•

7s

25.0

.25A0

25.0

.25.0

25.0

25.0

11.0

'lskdmy Adjasftd-wa Faitw MXA

* CiV o00mhn 0Cw21I

0.83

am0,;831

0.83

6.83•

0.8310.830.+83

0A83

0.93

523

SOL

378

33':

,272

,249

228

212.

'19T7

,174

.1.56

OPcoOZ

S 0~

8."79

$0.97.Sl.'o6

$1.16

81:25

$1.34

S_43ý

$1.61

i £1.--f lOt ,Arn •4,IIm + Lin&(40t gTr 4. 4~ infl3~ = .ht f~.ft ~vflOt mAe 4. At w..U~ t~aB.Ims&i(AOIL or-&- + 4* mni-!-:-6Wtoftft 9-igivAGIA gmAc +,4% fadigý =44WWUR,

(FL)Sn-.,.+!•

1502O00'

2ObOO

25m1

3060,

3M0

4501

6o5

6 ; 5010

Lmd

1.0

1.0

LI0

1.0

-. 0

1.0

1.0"I.01

1.0

1.0

.I.0.

Trayd

L~Ammcd'*Ain.)

0.34

0.67.

0.83

0.99,

I ."

2;43

2.46

a sww&,Spfcad

0.60;0.60

0.400.60

MOO

0.60

0.60

0.60

0.160

0.40

040

0.60

T'mamImli)

0.41

tlti

1.85

3.19•

3.63Im,+

4.09

4112

4.97:S.4t

4'S.O

'Oin.)Trm•

2.45

3.07

3.68

428

4.89

..5.50,

9.14'

10in

Tri"•Pu~

Maou

24.5

193

163

I40

12.3

10.9

(98

8.9•.2

7.6

7.0

6.2

;S22

Wffioimoy A4ol1AdPayloa Facuw PmduclivayolmV (so mklhf) (DCWINr

25.0

.25.0

25.0

25.0

25.0

25.0

.025;0

25.0

25.0

25.0

2;.0

25.0'

0.83

0.83

0.83

0.83

0.83

0.83.+

0.83

0•3

0:83

405'

338

291

255

Asr203

~IS8:170

135

129'

120

$0.52

so.65

-50.78

$0.91

51.30

52.43

$1.67

SI.82,

SI.M52.05

S1.221

.DE-3/98 21

Page 116: Church Rock Section 17 Restoration Action Plan.

App-&z C (Codiiauý.P ~~~~Cahbulad" (in' Idueu Matm~ahWob a Catinpilar 637 Pu&bPA wAl Via%

M~~inBy Uom &Iyoasw

IJn•4J•i•l•d•m•t•GItntsl•-- 94:- 5% R-hli- (;=ft f9% -- A- + 4% -w- _ 9%r -,-- - +AS - -- I%

OewqADim=*

_m 7%MaIoA 'M".mm"ALr-

Tgad TalTwo CYBM 71M.Ow Ow

50

1000

2ooo

25W0

smo

•smo

GOOD

0 .o

t:o.1.0

2.0

1.0'

1.0

LO

2.0

1.0

IA0'

1.0

1.0

.1.0

1.0

2'.0

0235

2.01

2.46

Lt92

233g

t2.3:3.75J

4.66

'5.12S's2

6.04

6.49

0.60

O.600.40

O;6O

4.60

O.6O

0.604.60

0.600.60.

0.60

.33OJD

Om66

O83

Io

'At

1.30

1.96

its2.29

1.45

.2A8

3.11

L.72

4m3

4.97'sm

4.20

7.453.66

9.31

9.9W

10.54

fbt

2t6.1

12.119.3

10.8

4.9

t40

5.7

ac!) 0o0is(CAIZ)W com

Offim

2S.0r

25.025.0

.25.0

25.0

25.0M0

2W.0

1-20"

-25.0

&M.'

0.3.

.3

4.3,

* 4.33

4.,8

0.83

¸0.83

0.L3

501

,460

38m

2,6

252

201

123

f68

i54

143

133

125

113

10.66

10.79$1131$4.92

11.43

*sim

S$152

$1.72

.11.72

'12.22

1•2.23

I-AL-A QnC -A..Lt¶Imu lift v-;"" Gl,.d L ý-- -- . 1,

on-Way

akL)

1000

20•O

2560

swooS0S0

3560

.0

Tmnd MV• ?mtdLA Ti Spd Traw LcadrA Tom ac04'n) &) O9

2.0

1.0

1.0

2.0l.O

1.0

IED1.0

1.0

* .0I•0

1.0i.0

0.75

"1.43 0.60

0.32

0.49

2.21 0.60 0PAS

231l 0.60 0.31

34A9 0.60 &49

4.11! 4.60 1.24

4.37 ... :.&0 1.30"

'.6.24 .0.60 2.6

,6.93 4.60 I.9

7.62 06 19

1.31 0.60 2.12

.996 4.60 2.2.

9.62. &.6 2.46.

Twm

2.67

3.52

147

C.92

7.77

L.62"9.47*

10.32,

11.17

1287'

12'72

PaHMr

121

13.7

9.9

L.7

7.7

7.0

'.3

'•,

,4.9'

4.7

&4

.25.0

250

25O

25.0

25.0

25L0

25.0

25.0

25.0

2S.0

25.0

25.0

25.0m

0.83

0.83

0.83,

0.83

4.83

4.3,

.33

0.m

QMs

460

353

'24,

158

1205181

131.

120

122

102

98

91

EflkimcY Adjuafd

ownY 00 OliahO (RCYJNI

"osats

tome

10.75

$0.93

$1.11

S1.65

a, 02

12.19

$235

3170-

MR9

DE 3/92 22

Page 117: Church Rock Section 17 Restoration Action Plan.

Appoldiix bCutaafor M~vung Macei4,Js With a Cateipillar 56 CY Cable Sbovel mad'Caftipillar 2407 (793C)T ?uuk

MUM~hCOb&11aAURmmOXIcAvAflCNclL; MAMMAL RS" DLAS1VG SHOULD HAVE AN4 ADDITONAL SS.IOIBCY ADDED-FOR DRIUING AMn

MatetmmaMomiaco By mcsbowh.Tnk combination

1) S CY Sbowd2)k Comlpi~brWlO3I 40.7cc ad'Dmnpa2) maiteial Dolla4) Opeamit~ 311icly PrCO5) olnRasuaPae6),56 C? Abo,dOpuutir Cftoal 0.ownuabip 0in7) 79SC LAmmo + OpeaukiVCmwI) LaborCooft9) 6o14 *(-l.OW'000GL WaktTick.+ Ip~

10) 1. 16H R" *.Ipcao11) 13wD9R +tI perator12) 3 8343 RubberTired Dowr + I Opomaim12) Slaporvition Labor Coil14) Slupavimor ?mimpatila

mS) TowI Fleota Srou cars (Naacsi Thxks)

56.0 WCY Hmped1923.0 •LY/I5s68 Cy

.2,150.0 LOJDCY0.83%,

$241k.64$19.15

)18.75 Par HourSmO2l Per HourS84.26 Pe HoR

$120.99 Po Hour1101.35 IPr Hour

$12.50 Pe at

1123 Fr Hour

i664.91 per HOWr

01125011125CPH 2SWNE,vimWYDOT-WDD'A of W0% DQCRG + Opeurator

+0 QR Operator90% DQCRG + Operator90% OQORO +'OpiraaorOA4of WYDOT-WDD14 of90% DQCRO

10 USE T.4~k LocAweyour approximmt pod. by afor-,- to acm wailbu.. Defteoim mac cgpr DCV by using distamc coliumn that pp hilamea your dietance. No calculahiona arc

qý-• Ana v,-* €2+nt I ... A.A , " - AM . AU l,1 -A all.. CEl A . .AU.•. AUl -n

Qu-Way

2m4

"W

33W0

4m4

4m4

SOW

7mW

La"d Mangume11am Tume

1.70 0.60

.70 0.60

1.70 0.60

1.70. 0.60

1700 0.60

1.70 0.60

1.70 0.60

3.70+ 0.401.70 0.60

1.70 M60

.;;70 0.60

t.70 0.60

Tend Trravd TOWT•me oump Tiel Cycle

Loaded Tit= Empty Ties(Mill) '(Mil.) (Mi-) 04im)

0*4 11.20 0.2 4.1

0.7 120 0.4- 4.6

1.0 L20 0.6 5.1

1.3 1.20 0.7 353

1.6 1.20 0.9 4.0.

1.9 1.20 3 .1 63

2.2 1.20 1.3 7.0

2.4 1.20 ..5 7A4

2.7 1.20 1.7 7.9

3.0 11.20 1.9 14

3.2 1.20 2.1 LI

3.5 0 2.3 m93

-3.8 3.20 2.5 9.8

4.1 1.20 2.7 10.3

TripPur

Hour IBM,) (DCYIHs)

'14.6 156.1

13.0 156.1

11.81 56.1

10.9 156.1

:10.0 1m56.

9.2 156.8

I.6 t56.1

I1l3 356.8

7.6 IS6.,

7.1 156.8

6.8 1356.11

6.3- 5.1

6.1 156.8'

S.8 156.8

1912

1704

1425

1307

1206

1120

ý109.

992

9b3

891

843

700

'761

(DCYfllt

4046

4040

4040

4040

4040

4040

4040.

4040

4040

4040

4040

4040

4040ý

4040

Numbe Opeating.of Thick Coaequired+ (SC)

2.37

2.6S

1.09

'335

3.61

3.81

4.07

4.33

4.53

4.79

$.05

5;31

50.275

$0.289

S0.303

50.313

'$0.327

S0.340

$0.364

50311

50.402

M0.416

50.430

$0.443

Op-mata Coms;n -(ITu~ (WTsuck e~mm coi Labor emut)) 4 TOWa Rcetcoa~s)Ifbovel Pmductivii4)

DE 3/98 23

Page 118: Church Rock Section 17 Restoration Action Plan.

Caicalkma~ fme Mm*n Motaula Wah a Ctailr5V YC~ aw aud CazpwupIr240!? (1930)Tiuc

Materal Moemmiby Rn;I.Tfu*Cbara

t•l•lrJ. 54L :mn•IthW'•rm4ie D..... £L6~ A ~ 1~ w... - . -- -----.- l ý am& m- , -A A- . . IN.,,, - ,- = ,,I

7mal. Tavwd Tdwa

Laiso tww 1 rmc - op Tb. pAdwumd

ai -NYANumet•ciunxb

73c

3m

moo

so

400O

4100

smo

• .55006000

6500in s

1.70. 0.0 0 .2 . 4.7 .12.

1.70 0.6 1IA 1.20 0.7LT 1067,

.70, 0.40 2. 1.20 1.0 6.7 9.0

1.70 0.0 2.9 1.20 12 7.7: 7.4

1.70 a.m0 3.4 120 1,4 8.7 W 6.6

1.70' am4 4 '1.20 IV 0.7 ti2

2L70 o04 50 . 2.2 1&.7 56

1.70 0.0 5.7 1.20 25 11.7 S.1

1.0 O.4o 6.4 1.20 2.4 12.7 4.7

1.70W am 7. .o "0 3•.2 15 44

L.70 0.60 71.8 .20 5.5 14.3 43

01.7 0.40 Ili 1.20 3. 1.3 3.

2.70. 0.6 9.2 1.10 4.1 16. :L6

1.30 '0.40 9.9 .1.20 4A4 17.4 3A

,156.8

;Ike

156.4

Im,156.3

1L56.8

156.8

1Me.

356.8

1Ml.

166

Im

1019

731

4&9

4a5

440

4m4

4W4

40W

404

'4040'

4W4

4M4

4040

4040

4WD0

4%040

ý2"8

,3.96

4.48

4.99

6A06

6m7

7.09

7.41

L6,4

.9.1,,

30.916

40.34t

3SO7,:10..546

$0.614

10.639

S0."'MW

lgi.ý,LIVX -. A. ý AM A dt i.-I Mf L-kat =,.QAe

L ' Ir

Tauve ITvdi T~aw;.Wy Land Maimwv 'Tkh 6-D~ Time ee 'Trip

W-)(M.) *AV.) -M~ A., Q~ 9~ H

Pala Auiwicr PrAui•Cir*f. A-fift -a~,) drTnaek Ceam(m" g cy,

5 31.70 0.60

lo0 1.70 0O.4

3.500 3.70 0.402= 1.70 0.60

20m0 1.70 0.60

40 1.70 0o,

5m 1.70 0.60

500m 1.70 o06

550 13.7 0.40

,sow 1.710 0460

6500 1.70 o04

7000 1.70 0.60

04 1,20 0.3 4.2 143

0.7 1.20 0, 3 7 12.7

3.0 1.2 0.ý1 '. 1 13

33 13.0 1.0 3.3 10.3

3.,9 1.20 .1.4 7.0 .8.6

2.2 3.20 1.4 7.5 8.2I.5 1.20 .1. ,3/ it

2.3 1.20o 23 .6 -7.0

3.2 120 2.6 9.3 6&.

3 3.20 2.8 9.3 63.

3.83 1i0 3ti 10.4 5S.'

4.1 3=. 20 t4 31.0 5.

,4A4 1.20 3.4 334s 'S.2

I146.8 i86"1.56.8 1662

356.3 1479

Me.8 1344

5.3 1227

156.8 1128

1568 345<yJ•:'

M1563 754156.8 7154

ISU. w8

40404040

40W0

4040;

4040,

406o

4040

4"404w~

4&04

,111C

2.43

2.73,

3.00+

3.29338.,

$.17

4.16

4.78

5.0!?

5.36

5.65

5.03

10.292$Do83

.0322

30.317SOM7.3641

10.46I.

50.4610~.47

DE,3/95: 24

Page 119: Church Rock Section 17 Restoration Action Plan.

Appcndi ECaculnim for Movin Mgsuml wii a Ca•pilk D9N Dow

MacrW Movaat 3) DBy

1) Cou.1aqpr D9N Dowm Wilb U BIlG&2) OpcwOing CmM3) LaorCotm4) Swoeisa LAWor Col5) Sup,"VisoT am

39460 Pu HKm$18.75 ILu HOW

53.13 Ptr How1I.10 ftr How•

S1 17.58 Pu Is=

9Sa dDQCUOWYDOT-WDD1IM ofg0 9 o DQCRGImof90% oDQtG

TO USE TABL& Loct yaw qpm g=ma s by rfuthaig *o'& *dun*. Ddrmaa -o4 pr LWy by aims did That bed bapp o, ma~ao yew diomnc.

I Jab Cwmasb-n PFacloa I

Dim""(FL)

I0S

150

200

250

300

350

900

450

Sa0

2190

1200'9w

700

570

430

410

370

350

340

1.0

1.0

1.0

1.0

1.03.01.0

1.0

1.0,1.

m1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.01.0

V~bbf

0.90

0.90

0.90

0.90

0.90

0.90

0.90

0.90

0.900.90

O.830.83

0.83

0.33

0.83

0.83

0.83

M.83

0.83

0-93

Gmda

1.00

1.00

1.00

1.00

1.00

1.00

1.00

I-an

A4ustd

GLC~fl'f.)

1575

900

675

525

428

360

308

273

263

CAWA

$0.075

$0.131

51L174

50.224

$0.275

50.327

S0.382

$0.423

$0.447

SD.461

Job Corocliom Factonw

Dbaumc(FL)

so

100

200

250

300

350

400

450

(L.CYH.)

2100

1200

900

700

570

430

410

,370

35O

10P

1.0

1.0

1.0

1.0

1.0

1.0

1.0

I _A

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

0.90

0.90

0.90

0.90

0.90

0.90

0.90

0.90

0.90

A Ct

0.93

0.83

0.83

0.M3

0.83--0.33

0.83

0.83

^623

Gnde0.0%)

1.20

1.20

1.20D1.30

1.20

1.20

1.20

1.20

i.20

Adju-tdProducfivky(LWCY.I.)

1890

1030

310

630

513

432

369

2333

I m

50.062

SW109

$0.145

03.37

.229

50.272

50.317

$0.353

so.373

IA *7.7 Gil ~*A

ts. 10ii•Jb Cwatvo F~.-opm•

maurwuGood

Fair50 iaiakir

- 1.001.00

-0.90= 0.83

DE 3/98 25

Page 120: Church Rock Section 17 Restoration Action Plan.

Appmadi R (CadiuuACOkcuhloa fra Movin MasrM W'b a Cakupigm D9N Dow

Ude1S3 UouMM By Dain

10oso

looL0I

200

250

sw

40O

450

5oo

21W 1.0

12W 1.0191w 1.0520 3.0

700 1.0

=70 1.0

M30 1.0

410 1.0

370 1.0

350 1.0

340 1.0

1.0

3.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

!.0

Vbbfay0.910

O.90

0.510

a.go

0.90OjgO

0.90

0.900.90

0.90

Er-

41.13

0.230.83

0.83

0.83

0.83

0.83

(-20%l)

1.40

1.40

1.40

1.40

1.40

1.40

1,40

1.40

1.411

OCikr.)

1260

945

735

5,9

504

431

389

368

I57

msu

0.124

$0.160

0.196

30Z3

$0302

10J20

M.3129

(FL)

100ISO

150

200

250

300

350

40w

450

5So

Produc~iliy , ,

0.cyflk.) -PC2100 1.0

1200 1.0

900 1.0

70D 1.0

570 3.0

480 1.0

410 1.0

370 1.0

350 1.0

340 1.0

MAU"

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

Job ۥco am F.wa'

0.90

0.90

0.90

0.90

0.900.90

0.90

0.90

0.90

0.90&.90

0.13

0.83

0.83

0.83

0.83

0.83

0.83

0.83

0.130.13

(10%)

0.75

0.75

0.75

0.75

0.75

0.75

0.75

0.75

0.75

GCYI1u.)

11813

675

506

394

321

270

231

208

197

191

CLWLCYl

$0.100

M0.174

10.2915

SO.366

50.436

I0..50910..56

S1600

1KI.616

'Job Conectio Famm

Vgp"AgExcdm -3 I.00Good -1.00Fair 0.90Som ba , amO13

DE 3198 26

Page 121: Church Rock Section 17 Restoration Action Plan.

Appmdx FCaul.mions For Moving MaIux W b a Cal•a•pi• DIIR Dowar

Ibtmaid Moveat By Dazin W DI IIt1

1) :Cqmatiw D111 Dow With U Dlt (Opending Ca•) SW.8S pa Dmuam2) Opasting Corn3) Labor€a4) &Vavm LAwr Cods5) &aVmioTb-pmudi

4) TOW1 wlm CNN

3201.47 PSA nmwSI3.75 Per How

3.13 Per Hrow11 .10 ft, Hour

$2.24.5 pr mmw

90s of DQ•OWYDOT-WDDIa Sof90% of DQG14cf90 CEDQCIO

TO USETANLA IA=U Y-w sapnma gradfby .•,rmsg *Ord& o"hms. Doctmh• am pcr LCV by 0i9M tk ,Nmdo bea-.pprao~am yaw dkmm.

Jab C Pa Ou'

100

1.50

250

300

.1O

4901

450

590

3290suoo

1400

1150

19000

750

670

600

opum-

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

* 1.0

bbww

1.0

1.0

1.0

I.0

1.0

1.0

1.0

1.0

1.0

1.0

0,,90t0.90

0.90

0.90

0.9o

0.90

0.90

0.90

0.90

0.90O.90

O.83

0.83

0.83

U.3O.830.83

0.83

0.83

0.83

0.83

(OS)

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

1.00

240

1350

1050

863

750

638

563

450

cam.OILCY)

S0.166

=0.214

S0.260

30.39050.352

S0.400

30.446

S0.50

lab Cvnu:i FwatOr

(FL)

so

too

SO0

20D

250

3903S0

490

450

590

3j0b Comcim Fadt.:

Eff-cca

3290

2700

1400

1150

lwo

750

670

600

1.0

1.0

I.0

1.0

.0.

1.0

1.0

1.0

1.0

1.0

Mduii

1.0

1.0

1.0

1.0

1.0

1.0

1.0"

1.0

10

1.0

0.90

0.90

&.90

0.90

0.90

0.90

0.90

0.90.

0.90

.3-0.83

0.83

0.83

U.83

0.13

0.330.83

0.33

(-00%)

1.20

1.20

1.20

1.20

t.20

1.20

1.20

1.20

1.20

1.20

(LCY.r.)

2430

1620

1260

HUIS

900

765

675

630

340

WC-)

30.078

10.092

$0.139

=0179

$0.217

$0.249

30.293

30333

SO-=4$0.416

3z~UemGoadFair50 m=ibr

= 1.00

-0.900.83

DE 3198 27

Page 122: Church Rock Section 17 Restoration Action Plan.

MV Appcodis F (Cootbumd)cakubtiama FSw Movt haiur•o Wish a CAtoUvir DIIlR Door

MiId Mwov*M By Dcbg Vr' DIIM

G.CYIfi.) OPam-Dhtm

SOk

250.500

550

SW0

350

4wO

450

M)0

1700

3"m6

aIsot4ool

Woo

750

670

600

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

0.90

cogo0.90

0.90

0.90

0.90

0.90

0.90

0.90

0.90

0.0

.0.83

L.83

0.83

L.3

0.85

0.83

M.83

Chu&

140

1.40

1.40

1,40

1.40

1.40

1.40

1.40

1.40

!.40

A49AW

3360

1470

1201

1050

893

789

704

630

Caga

$o.0"67M0*79

$0.119

50.186

50.214

50.251

W0.285

S0"19

S0-56

O Dhft= pt•fv I.,

WO) (,CYflr.) osm

so 3200 1.0

100 2700 1.0

I"0 1800 1.0

Job Crccam Puat='

20D

250

4w

450

500-

1400

1iso

1000

850

750

670

600

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.r0d

1.0

1.0

1.0

1.0

1.01.0

1.0

1.0

1.0

1.0

0.90

0.90

0.90

0.90

0.90

0.90

&.90

0.90

0.90

0.83

0.83

0.83

0.83.

0.13

0.13

0.83

0.83

0.13

OJ)

0.75

0.75

0.75

0.75

0.7S

0.75

0.75

0.75

0.75

0.75

Adjpa"a

1100

1519

1013

64"7

563

478

422

338

LcfilWIX.Y)

$0.125

50.148

$0.222

$0.2S.5

$0.347

S0.39

$0.470

50..59

g0.664

Em-Ezucaca - 1.00Good 1.00Fair = 0.9050 mbwhr , OX

DE 3198 28

Page 123: Church Rock Section 17 Restoration Action Plan.

Appendix GCalculations for Final Grading With a Caterpillar 16H Motor Grader

Final Grading

INPUT, UNIT AS COMMENT/INDICATED SOURCE

Caterpillar 16H Motor Grader

Speed in Miles Per Hour (Second Gear) 3.3 Miles/Hour CPH 25

Width of Grading Per Pass 8 Feet CPH 25

Feet Per Mile 5,280 Feet

Square Feet Per Acre 43,560 Sq. Ft.

Operating Efficiency Factor 50 Min./Hr. 0.83 % CPH 25

.. tin Costs $65.51 Per Hour 90% of DQCRG

Labor Costs $18.75 Per Hour WYDOT-WDD

Supervision Labor Costs $3.13 Per Hour 1/8 of 90% of DQCRG

Supervisor Transportation $1.10 Per Hour 1/8 of 90% of DQCRG

Total Hourly Costs $88.49

Grading Rate

(3.3 Miles/Hour)x(5,280 Ft./Mile)x(8 Ft./Pass) 139,392 Fe/Hour

(139,392 Ft/Hour)/(43,560 Ft/Acre) 3.2 Acres/Hour

(3.2 Acres/Hour)x(0.83 Efficiency Factor) 2.66 Acres/Hour

Operating Costs

($88.49/Hour)/(2.66 Acres/Hour) $33.27 Per Acre

Dc. 3108 29

Page 124: Church Rock Section 17 Restoration Action Plan.

Appendix HCost Estimates for Handling Wire Fencing and Electrical Power Lin

FENCING SOURMtS

Construction 4-Strand Barbed Wyoming Highway DepartmentWeighted Average Bid Prices, 1997

Overall Average -$1. 15ILF

Removal Wyoming Highway Department,Average Bid Prices, 1997

Overall Average -

$0.68/LF

Power Line Removal

Distribution Lines: No Charge From: Tri-County ElectricTransmission Lines: No Charge From: Tri-County Electric

Note: Cost estimates for power line removal are based on phone contact with Tri-County Electric. Distributionlines are owned by Tri-County Electric and would be removed upon request at no charge by Tri-CountyElectric. Transmission lines (lines which go from the main metering point to various electrical substationsand asenot owned by Tri-County Electric) would be removed by Tri-County Electric at no cost for theirsalvage value.

DE 3/98 30

Page 125: Church Rock Section 17 Restoration Action Plan.

Appendix ICost Estimate for Ripping Asphalt Using a Caterpillar D9R Dozer

Asphalt Ripping (3"-4" Mat) ,

INPU, UNIT AS COMMENT/INDICATED I SOURCE

Caterpillar D9R Dozer With 3 Shank Ripper

Speed in Miles Per Hour I Mile/Hour CPH 25

Width of Ripping Pass 3 Feet CPH 25

Feet Per Mile 5,280 Feet

Square Feet Per Acre 43,560 Sq. Ft.

Operating Efficiency Factor 50 Min./Hr. 0.83 % CPH 25

ating Costs $102.24 Per Hour 90% of DQCRG

Labor Costs $18.75 Per Hour WYDOT-WDD

Supervision Labor Costs $3.13 Per Hour 1/8 of 90% of DQCRG

Supervisor Transportation $ 1. 10 Per Hour 1/8 of 90_% of DQCRG

Total Hourly Costs $125.22

Ripper Productivity

(1.0 Mile/Hour)x(5,280 Ft./Mile)x(3 Ft./Pass) 15,840 Ft/Hour

(15,840 Fte/Hour)/(43,560 Fe/Acre) 0.36 Acres/Hour

(0.36 Acres/Hour)x(0.83 Efficiency Factor) 0.299 Acres/Hour

Operating Costs

($125.22/Hour)/(0.299 Acres/Hour) I $418.80 Per Acre I

ni: 1!OR i11

Page 126: Church Rock Section 17 Restoration Action Plan.

Appendix 11Cost Estimate for Ripping Overburden Using a Caterpillar DIOR Dozer

Overburden Ripping

INPUT, UNIT AS I COM ENT/INDICATED J SOURCE

Caterpillar DIOR Dozer With Single Shank

Speed in Miles Per Hour 1 Mile/Hour CPH 25

Width of Ripping Pass 3 Feet CPH 25

Feet Per Mile 5 .280 Feet

Square Feet Per Acre 43,560 Sq. Ft.

Operating Efficiency Factor 50 Min./Hr. 0.75 % CPH 25

-,Depth 2 Feet CPH 25

Operating Costs $134.07 Per Hour 90% of DQCRG

Labor Costs $18.75 Per Hour WYDOT-WDD

Supervision Labor Costs $3.13 Per Hour 1/8 of 90% of DQCRG

Supervisor Transportation $1.10 Per Hour 1/8 of 90% of DQCRG

Total Hourly Costs $157.05

Ripper Productivity

(1.0 Mile/Hour)x(5,280 Ft./Mile)x(3 Ft./Pass) 15,840 Fe/Hour

(15,840 Fe/Hour)/(43,560 Ft2/Acre) 0.36 Acre/Hour

(0.36 Acre/Hour)x(0.75 Efficiency Factor) 0.27 Acre/Hour

Operating Costs

($157.05/Hour)/(0.27 Acre/Hour) ! $581.67 Per Acre I

N"'e: A 75 percent Efficiency Factor was used to account for slowing, raising ripper, maneuvering and turn time.

DE 3/98 32

Page 127: Church Rock Section 17 Restoration Action Plan.

Appendix JCost Estimate for Culvert Removal

Culvert Removal

INPUT, UNIT AS COMMENT/INDICATED SOURCE

Average Length of CMP Section 20 Feet

Assumed Culvert Diameter 48 Inches

Time to Cut One Band 10 Minutes

Time to Load One 20' Section (2 People) 20 Minutes

Average Haul, Dump and Return Time 30 Minutes

Number of Sections of CMP Per Load 2

Operating Efficiency Factor 50 Min./Hr. 0.83 %

r $18.75 Per Hour WYDOT-WDD

Dump Truck (10-12 ydP) $26.52 Per Hour 90% of DQCRG

Caterpillar 980F Front-End Loader . $57.94 Per Hour 90 % of DQCRG

Cost to Remove One 20' Section of CMP

Labor Cost x Tune to Cut One Band $3.13

+ ((Labor Cost x 2) + FEL Cost) x Time to Load I Section $31.78

+_(Labor Cost + Truck Cost) x Haul Time $22.64

Cost to Remove One 20' Section of CMP $57.55(not including dirt removal)

Note: Culverts may be smashed and buried in place when feasible.

a.

DE 3/9S 33

Page 128: Church Rock Section 17 Restoration Action Plan.

Appendix KCost Estimates for Demolition and Removal of Railroad Spurs and Facilities Buildings

REGIONAL ADJUSTEDTASK COST PER UNIT COST COST PER

_ ($) ADJUSTMENT' UNIT ($)Track Removal 6.19/Uin. ft. 84.2% 5.21/1in. ft.

Ballast Removal 2.54/cy 84.2% 2.14/cy

Building Demolition and Diposaf- 2, 3

Mixture of Types 0O18s/ft 84.2% 0.152/ft'

Explosive Demolition, Concrete or Steel o. 18/fi 84.2% 0.152/fte

Disposal 6.47/cy 84.2% 5.45/cy

City Landfill Dump Charges $50.00/ton 84.2% $42.10/ton

icrete Footings and Foundations

6" Thick With Rebar 9.65/sq. ft. 84.2% 8.13/sq. ft.

Footings - 2' Thick, 3' Wide . 13.15/lin. ft. 84.2% 11.07/in. ft.

Cnncrmte Disnnsal On-Site, . 5 751v ,, R4 . 48421eV

Note: Operators may also provide a verifiable cost estimate from a qualified contractor for these demolition tasks.This estimate may be used for one to three consecutive years, assuming few substantial changes in minefacilities.

I Costs From: 1998 Means Heavy Construction Cost Data2 Based on Total Volume of Buildhig, does not include disposal cost3 Based on Concrete Structures Volume Only, does not include disposal cost

DE 3/98 34

Page 129: Church Rock Section 17 Restoration Action Plan.

Appendixk.LAbandonment and Sealing~ofCased Drill Holes and Monitor Wells

DRILL HOLE RECLAMATION COSTS

Site Locating $10.00/site _

Scaling Using High-Solids Bentonite Groutt .

! 500' deep $4.00fUn. ft.- 1,000' deep $6.28/lin. ft.

Capping Using a Pre-cast Concrete Cap (if needed) '$7.50/hole

Site Grading $30.00/site .

Seeding - Small Site (15' x 23') $t1.00/site

1 ouingr &.See.ding - Large Sites (100; x 100') $250.00/site

IONITORING WELL IRECLAMATION COSTS

Site Locating. $10.00/site

Removal of Top Few Feet of Casing (Backhoe & Welder) $15.00/well _

Sealing Using High-Solids Bentonite Grout'"`< 500' deep $4.00/1in. ft.'. 1i,000'+ deep $6,28/Uin. ft

Site Smoothing (Hand Work) & Seeding $5.00/site

Costs based on industry sources.

Assumesathole/weil size of'5." diameter,.

2 Gassy orartesian wells would require class G neat cement: plugging @ $6.46/ft. forwells up to 500' deepand $7.64/ft. for holes over 500' deep.

ii31Nn.

Page 130: Church Rock Section 17 Restoration Action Plan.

Appendix MCost Estimate for Rough Grading BackfiU Using

Caterpillar D9R Dozer or Caterpillar 834B

CATERPILLAR 834BITEMS CATERPILLAR D9R RUBBER TlRED COM IENT/SOURCE

DOZER DOZER

Speed in Miles Per Hour (First Gear) 2.0 Milef/Hour 4.0 Milesflour CPH 25

Width of Dozer Pas 14 Feet 14 Feel CPH 25

Feet Per Mile 5,280 Feed 5,280 Fee

Square Feet Per Acre 43,560 Sq. Ft. 43,560 Sq. FL

Operating Efficiency Factor 50 Min./Hr. 0.83% 0.83% CPH 25

Operating Costs $102.24 Per Hour $86.40 Per Hour 90% of DQCRG

Labor Costs $18.75 Per Hour $18.75 Per Hour WYDOT-WDD

Supervision labor Costs $3.13 Per Hour $3.13 Per Hour 1/8 of 90% of DQCRG

irvisor Transpotation $1.10 Per Hour $1.10 Per Hour 1/8 of 90% of DQCRG

Hourly Costs $125.20 $109.38

SCARMFICATION RATE

(2.0 Miles/Hour)x(5,80 Ft./Mile)x(14 FL/Pans)' 147,840 Ft/Hour 295,680 Ft2 /Hour(4.0 Miles/Hour)x(5.280 Ft./Mile)x(14 FL/Pass)2

(147,890 Ft2/Hour)/(43,560 Fte/Acre)' 3.39 Acres/Hour 6.79 Acres/Hour(295,680 f-t2/Hour)/(43,560 FLt/Acre)2

(3.39 Acres/Hour)x(0.83 Efficiency Factor)' 2.82 Acres/Hour 5.66 Acres/Hour(6.79 Acres/Hour)x(0.83 Efficiency Factor)2

OPERATiNG COSTS

($125.20/Hour)/(2.82 Acres/Hour)' $44.40 Per Acre $19.33 Per Acr($109.38/Hour)/(5.66 Acres/Hour? I I_ I_

Caterpillar D9R Dozer

Citerpdlar 834B Rubber Tired Dozera--

DE 3/98 36

Page 131: Church Rock Section 17 Restoration Action Plan.

Appendix NCost Estimates for Demolition and Removal of One "Standard" Surface Water Monitoring Station

INPUT, UNIT AS COMMENT/INDICATED SOURCE

Assumed Time to Remove One Station 8 Hours

Labor $18.75 Per Hour WYDOT-WDD

Dump Truck (10-12' yd3) $26.52 Per Hour 90% of DQCRG

Caterpillar 980F Front-End Loader - $57.94 Per Hour 90% of DQCRG

Cost to Remove One Surface Water Station =

(Labor Cost x Time to Remove Station) $150.00+ (Labor Cost + Truck Cost) x Time to Remove Station $362.16+ (Labor Cost + Loader Cost) x Time to Remove Station $613.52

Cost to Remove One Surface Water Station = $1125.68

Appendix 0Cost Estimates for Demolition and Removal of One

"Standard" Meteorological or Air Quality Monitoring Site

INPUT, UNIT AS COMMENT/INDICATED SOURCE

Assumed Time to Remove One Station 4 Hours

Labor $18.75 Per Hour WYDOT-WDD

Dump Truck (10-12 yd3) $26.52 Per Hour 90% of DQCRG

Caterpillar 428B (2WD) Front-End Loader $15.07 Per Hour 90% of DQCRG

Cost to Remove One Meteorological or Air Quality Station =(Labor Costjx Time to Remove Station) $75.00+ (Labor Cost + Truck Cost) x Time to Remove Station $181.08

L+ (abor Cost + Loader Cost) x Time to Remove Station $135.28

"t to Remove One Meteorological or Air Quality Station $391.36$391.36

DE 3/83 37

Page 132: Church Rock Section 17 Restoration Action Plan.

Appendix PCost Estimate for Scarification of Compacted Surfaces

INPUT, UNIT AS [ COMMENT/NDICATED SOURCE

CATERPILLAR 16H MOTOR GRADER

Speed in MilesPer Hour (First Gear) 2.4 Miles/Hour CPH 25

Width of Scarifying Pass 12 Feet CPH 25

Feet Per Mfle 5,280 Feet

Square Feet Per Acre 43,560 Sq. Ft.

Operating Efficiency Factor 50 Min.JHr. 0.83% CPR 25

Operating Costs $65.51 Per Hour 90% of DQCRG

Labor $18.75 Per Hour WYDOT-WDD

Supervision Labor Costs $3.13 Per Hour 1/8 of 90% of DQCRG

aupervisor Transportation $1.10 Per Hour 1/8 of 90% of DQCRG

Total Hourly Costs $88.49

SCARIFICATION RATE

(2.4 Miles/Hour)x(5,280 Ft./Mile)x(12 Ft./Pass) 152,064 Ft2/Hour

(152,064 Ft/Hour)I(43,560 Fe/Acre) 3.49 Acres/Hour

(3.49 Acres/Hour)x(0.83 Efficiency Factor) 2.90 Acres/Hour

OPERATING COSTS

($88.49/Hour)/(2.90 Acres/Hour) $30.51 Per Acre

DE 3/98 38

Page 133: Church Rock Section 17 Restoration Action Plan.

!iGeneral Ret cgctatiota A•titir To ~P~xiiic

£'crauk (Aazutuitutvnts

i1) Seedbed Preparation

Ri•ping S

Chisel Plowing $

Disking $

Harrowing or Cultipacking I

2) Drill Seed Stubble Mulch Mix

Seed Costs $

Drill Seeding I $

Mlowing Prior to Planting Permanent Seed Mix $

3) Seeding Permanent Mixes: Detail for each seed mix, if different seed mixes will be applied. The costs/acre for eachindividual mix should thou be oroportioned on the basis of acreaae nTr parcels to derive a single weighted average costiacre.

Drill Seedin_ $

Broadcast Seeding1 $

I ;eed Costs $

4) Mulching,

Mulch Purchase $

Hydromuleh Applicauion $

Straw Mulch Placemeuu and Crimping S

5) Fertilizer

Fertilizer Purchase by Defined Composition $

Application $

6) Fencing

Construction $

Removal S

Subtotal S

7) Maintenance Operations at 10% ofrTotal Revegetation Costs: This cost addresses standard Shusbandry 'practices applied over the minimum 10-year bonding period, such as remedialseeding, mov'ing. selective weed treatment, etc. The 10 percent figure is derived fromhistorical operator experience for the Powder River Basin.

Total Reiegtation Cost Per Acre

IlrE "'03

Page 134: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

ATTACHMENT E-6-3QUOTES.AND PRICES

EQUIPMENT RATES

Page 135: Church Rock Section 17 Restoration Action Plan.

OCT-es-2090 i.2:24

*~I

H.R1 RALRG 505 833, &"n P.01,8i

Crown po(*itrt~eP.O. SOa,777

pJ.to.a.AU~ M MAUt,, of C,,,,oX,,"Croiunpor4 Ne•w 14e%(,& 87313

V0ocec 505.-786-84S5 F•a. SOS-78,86-.555

mome''.K

1& cItt.M T OM do.140 owl isso J vivo 11, ~ MoMTQ4

C eAt SI 1pg~e~y

20(7/" dop"~ die. - . U4~t~L'f&~

SI CTe1cw)

go;tzwý#IL

3 eG4o otr~e*~

I~.

31540 61. I's-so &Y-week-

?,S-O/b ro" -ritA1 e o'Jw

I FWI foCWote ski L( C~e~mfT petL to c'to£S. S-4~ ( R'e. Cý-ve

?~?AVcw21 SC'esr q&~4qa I S,3&

Page 136: Church Rock Section 17 Restoration Action Plan.

July M3, V200

ATTACHMENT E-6-4BUDGET CALCULATIONS

DISPOSAL COSTS

PIPE VOLUMETRANSPORTATION AND DISPOSAL

Page 137: Church Rock Section 17 Restoration Action Plan.

Pipe Wall Volume Data

Outside Diameter (in) Area Inside OD (ft2) 'Wall Volume SDR17 (ft3/fW)2, 0.022 0.012

2.5 0.0343 0.049 0.018

3.5 0.0674 0.087

4.5 0.11,05 0.136

5.5 0.1656 0.196

6.5 0.2307 0.267

7.5 0.3078 0,349

.8.5 0.3949 0.442

9.486 0.4919.5 0.49210 0.545 0.140

10.5 0;60110.75 00630

11 0.66011.5 0172112: 0.785

12.353 0.83212.5 0.85213 0.922

13.5 0.99414 1.069 0.237

14.5 1.14715 1.227

15.5 1.310

Wall Tk14" SDR 17 0.824I0" SDR 17 0632

Page 138: Church Rock Section 17 Restoration Action Plan.

Revised October 15, 2010

TRANSPORTATION AND DISPOSAL

11.e.2 By-Product Material Transportation Disposal Costs per Ft3

Assumptions:1. Based on contract costs for transportation to and disposal at the IUC White Mesa Mill near Blanding Utah2.Transportation assumed a 200 mile trip al$4.76 per mile, $952 per trip. Bulk truck capacity 30 yds3. Drum truck capacity 64.3. All 11 .e.2 disposal fees are based upon actual current contract rates at Texas ISR facilities as itemized in 4 & 5 below.4. Drummed waste. $2,866 per shipment of 64 drums, 7.35 cu. ft. per drum, $6.09 per cubic foot.5. Bulk waste. $1975.45 per shipment of 30 cu. yds. , $2.44 per cu. ft.6. Per truck site unloading ($135.00) and decontamination ($150.00) amounts are specified in URI's current disposal site contract

Type of Waste:

Disposal feeShippingSite unloadingSite scanningTotal shipping and disposa

Type of waste:

Disposal feeShippingSite unloadingSite scanningTotal shipping and disposal

Sludge, resin, and other by-product type wastes shipped in drums.Unit Shipment

Cost Units/Drum Drums/Truck Total $/ft3$2,866.00 7.35 64 $6.09

$952.00 $2.02$135.00 $0.28$150.00 $0.31

$8.71

Soil, sand, demolished concreteand other bulk wastesUnit Shipment

Cost Ft3/Truck Total $/ft3$1,975.45 810 $2.44

$952.00 810 $1.18$45.00 810 $0.06

$150.00 810 $0.19$3.85

Unrestricted Material Transportation Disposal Costs per ton

Assumptions:1. Based on public costs disposal at theWaste Management Red Rocks Landfill. 24 $/ton2. 1 ton is equal to 1 yd32. Transportation assumed a 30 mile trip at $2.00 per mile. Bulk truck capacity 20 yds3.

Disposal fee (ton)Shipping (truck trip)Total shipping and disposal (yd3)

Unit Cost$24.00$60.00

Total $/Vds3$24.00

$3.00$27.00

Page 139: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

ATTACHMENT E-6-5QUOTES AND PRICES

LANDFILLFEESLANDFILL DISTANCE.WHITE MESA FEES

Page 140: Church Rock Section 17 Restoration Action Plan.

• 5EP-12-!20 12:56 ,HRI AUBLXLERME 585 W 833 870?7? P. .1'01

MU!, INC,

Crow npo ait offece-P.O0 So, ,777

Phy9cc'VAd4reW 3% m4Ze.W o r~noCrOWnO&OW, NeWL.u MGjC 87313

Vo•.e ,505-786,-5845 Fc. o505-786-,555

MAR-K/,z UJV MA'QE~oPoxee- ).Si&JOPLL

24vo-ro "WbCWomeEC b ,r

4VO/rati~ 4eoc."i 3 wAsAy

CC6N9AIhoIU LA I eO-I'Sq~A

TT P. wR1

Page 141: Church Rock Section 17 Restoration Action Plan.

SEP-13-20M0 15:48 585 833 f7 P.e01/1

RI, NC*

crownpo f(cP. 0. So* 777

P yscaJAd~rew. - wimZ'W; of Crowo onýrCrownpoitA.Me iu Me%(o 87313

Voi*: 505-786-5,845 Fa, 505-786.-5555

Mi"1is ro LA-r-t

'TO scra zsmiTo SEL 6 -,Cb -

-lu s e• AC -35M6c Cui

piuIrc

tdiUft3 "L.~F-( VLSM

Page 142: Church Rock Section 17 Restoration Action Plan.

BYPRODUCT DISPOSAL AGREEMENT

This BYPRODUCT DISPOSAL AGREEMENT ("Agreement") is made on April 1,2007, by and between, URI, Inc. ("Shipper") with its principal offices at 650 S. Edmonds Lane,Suite 108, Lewisville, Texas 75067 and Denison Mines (USA) Corp. ("DMC"), with its principalcorporate offices at 1050 Seventeenth Street, Independence Plaza, Suite 950, Denver, Colorado80265.

RECITALS:

A. Shipper is the operator and owner of an in-situ uranium recovery project located inKleberg County, Texas near Ricardo, Texas, commonly known as the Kingsville Dome ISRProject (the "Project"), and such operations are conducted in accordance with a permit issued bythe Texas Department of State Health Services (the "DSHS") ("Shipper's Radioactive MaterialsLicense").

B. Shipper desires an agreement with the operator and/or owner of a duly licensedfacility authorized to permanently dispose of all of the Byproduct Material as defined underSection 1 l(e)(2) of the Atomic Energy Act of 1954, as amended, 42 U.S.C. § 2014(e)(2) and 10C.F.R.§ 40.4 (the "Byproduct Material"), associated with the Project or arising from activities atthe Project.

C. DMC is the operator of the White Mesa Mill located near Blanding, Utah (the "WhiteMesa Mill"). The White Mesa Mill is owned by Denison White Mesa, LLC., an affiliate ofDMC. The White Mesa Mill has been duly licensed (the "White Mesa License") to permit thedisposal of Byproduct Material generated as a result of uranium mining and processing byplacement of the Byproduct Material in the White Mesa Mill's tailings impoundment (the"Tailings Facility").

D. DMC and Denison White Mesa, LLC have the necessary expertise, equipment,facilities, permits and licenses to safely and lawfully dispose of the Byproduct Material and toperform all work required in accordance with the terms and conditions set forth in thisAgreement. Denison White Mesa, LLC is also signing this Agreement as a guarantor of DMC'sobligations hereunder.

E. DMC is willing to accept Byproduct Material from Shipper for permanent disposal inthe Tailings Facility at the White Mesa Mill upon the terms and conditions set forth in thisAgreement.

NOW, THEREFORE, in consideration of the mutual promises, covenants and agreementsset forth in this Agreement, Shipper and DMC agree as follows:

1. AGREEMENT TO ACCEPT BYPRODUCT MATERIAL.

A. The initial term of this Agreement shall be one year commencing April 1, 2007 to and

Page 143: Church Rock Section 17 Restoration Action Plan.

Byproduct Disposal AgreementKingsville Dome ISR ProjectUranium Resources Inc. and Denison Mines (USA) Corp. Page 2

including March 31, 2008, unless terminated earlier as hereinafter provided. Upon expiry of theinitial term, this Agreement shall automatically renew each April 1 for additional one yearperiods, up to a maximum of four such additional one year periods, on the same terms andconditions as then in effect, subject to adjustment pursuant to Paragraph 11 hereof, unless, notless than 60 days prior to any such anniversary date, either DMC or Shipper shall have givenwritten notice to the other that it does not wish to renew this Agreement or this Agreement hasbeen terminated in accordance with the provisions contained herein. The term of this Agreement(the "Term") shall be the initial term plus all such additional one year renewal periods up to amaximum of four additional periods (i.e., up to March 31, 2012 at the latest).

B. During the Term, unless this Agreement is terminated earlier under Paragraph 14hereof, Shipper shall ship all of the Byproduct Material of Shipper associated with or nowlocated at the Project from activities at the Project site, up to a maximum total of 5,000 cubicyards of Byproduct Material from the Project, to DMC for final disposal at the White Mesa Millpursuant to the terms and conditions of this Agreement. A corporate officer of the Shipper willcertify in writing that the Byproduct Material has originated from the Project, and suchcertification shall be included in the Bill of Lading delivered to DMC.

C. DMC agrees to accept for final disposal the Byproduct Material of Shipper, asdescribed herein, which is delivered to the White Mesa Mill pursuant to the terms and conditionsof this Agreement during the Term of this Agreement, up to a maximum total of 5,000 cubicyards from the Project, unless this Agreement is terminated sooner under Paragraph 14 hereof.

2. ANALYSIS, TRANSPORTATION, SCHEDULING, AND DELIVERY OFBYPRODUCT MATERIAL.

A. Shipper shall provide and arrange for the transportation of Shipper's ByproductMaterial through a transportation contractor. Any and all Byproduct Material shipped fordisposal shall be transported in bulk in trucks, end dump containers, or in 55 gallon drums orsuper sacks. All trucks shall be selfdumping/end dump trucks, and all such drums shall be full ofByproduct Material and shall be so labeled. Shipper shall require that the transportationcontractor comply with all applicable federal and state transportation regulations. Shipper shallmake a copy of its contract with the transportation contractor available to DMC upon request;provided, however, that Shipper may first black out pricing and other confidential commercialinformation. By releasing a shipment from the Project, Shipper shall be deemed to haverepresented and warranted that all information set forth in the forms, reports and logs completedby Shipper is in accordance with this Agreement, and all applicable laws, rules and regulations.All deliveries of Byproduct Material to the White Mesa Mill shall be between the hours of 7:30a.m. and 3:30 p.m., Monday through Friday (excluding holidays in the State of Utah). Shippershall schedule loading at the Project accordingly. Shipper shall be responsible for any demurragecharges resulting from failure to load trucks to ensure that this delivery requirement can be met.As used herein, "shipment" is defined as any number of drums loaded on one truck or a partial orone full truckload of Byproduct Material, transported at one time. Scheduling of the shipments

Page 144: Church Rock Section 17 Restoration Action Plan.

Byproduct Disposal AgreementKingsville Dome ISR ProjectUranium Resources Inc. and Denison Mines (USA) Corp. Page 3

shall be coordinated with DMC. Shipper shall segregate types of Byproduct Material based onthe categories set forth in Paragraph 10(A) hereof to facilitate determination of quantities beingshipped for disposal and all shipments shall be in compliance with the requirements of Paragraph5(D) hereof.

B. Shipper shall notify DMC, in writing, thirty days prior to an intended shipment of theByproduct Material. Such notice shall include: (1) a detailed description of the content of theproposed shipment, setting forth with specificity a list of categories or types of ByproductMaterial that it intends to ship to the White Mesa Mill, and; (2) a date when sampling (asdescribed in Paragraph (C)) of the material proposed for shipment will occur.

C. At its sole expense, Shipper shall provide sample analyses (RCRA TCLP analysis,natural uranium, Radium-226 and Thorium-230, and other characterizations requested by DMC)in sufficient detail to enable DMC to confirm the content of the intended delivery of ByproductMaterial. Shipper shall collect and analyze representative samples for each category or type ofByproduct Material that will be delivered to DMC for disposal. Where the Byproduct Material isnot suited to sample collection (i.e. metals, process equipment, filter media and similarmaterials), the Byproduct Material, at a minimum, shall be evaluated in an appropriate manner todetermine the total amount of activity due to Radium-226 in each shipment. DMC reserves theright to have its representative present when Shipper collects the samples. The samples shall besent to a commercial analytical laboratory that is acceptable to both DMC and Shipper. Acorporate officer of the Shipper will certify in writing that the analyses as listed in this Paragraph2 (C) have been completed for each shipment. An original report of the results of thecommercial analytical laboratory analyses and the Shipper's certification will be provided toDMC thirty (30) days prior to scheduling the actual delivery of the Byproduct Material.

D. Shipper shall provide DMC with advance notice of the actual date of delivery of theByproduct Material two (2) business days prior to such delivery.

E. Unloading at the White Mesa Mill shall occur only in areas designated for unloadingby DMC, and in strict accordance with the procedures established by DMC.

3. REJECTION OF MATERIAL. DMC shall be entitled to reject delivery of anyByproduct Material or other material of Shipper which, (1) DMC is not authorized topermanently dispose of at the White Mesa Mill by any term or condition of the White MesaLicense, or by the terms or conditions of any other applicable permit or license, or by anyapplicable laws or regulations, or (2) DMC, in good faith, determines it is not the material fromwhich a sample analysis has been provided to DMC. Upon receipt of notice from DMC of anysuch rejection, Shipper will promptly remove any such nonconforming material from the WhiteMesa Mill. DMC may also direct the transportation contractor to return the entire load to theProject. The removal cost, including any demurrage or delay costs incurred by the trucker, andall of DMC's costs associated with identifying and handling any rejected material shall be paidfor by Shipper. To the extent that DMC has the legal obligation to identify, and to notify

Page 145: Church Rock Section 17 Restoration Action Plan.

Byproduct Disposal AgreementKingsville Dome ISR ProjectUranium Resources Inc. and Denison Mines (USA) Corp. Page 4

governmental agencies of any shipment of material (or portion thereof), which DMC believes notto be in compliance with applicable regulations, DMC shall not be liable to Shipper for any lossor damage incurred by Shipper because of such identification and notification. DMC shall makeevery effort to notify Shipper of such identification and notification in a timely manner. DMC'sright to reject material of Shipper shall continue up to the time that DMC has accepted thematerial for permanent disposal at the Tailings Facility. "Permanent disposal" means the actualplacement of the material in the Tailings Facility at the White Mesa Mill. After permanentdisposal, Shipper's Byproduct Material will not be segregated from any other material receivedfrom any other third party or from any of DMC's material. Title to the Byproduct Material shallpass to DMC upon acceptance of the material by DMC for permanent disposal at the TailingsFacility.

4. REPRESENTATIONS AND WARRANTIES OF DMC. As material inducements toShipper to enter into this Agreement, DMC represents and warrants to Shipper as follows:

A. DMC is a corporation duly organized, validly existing, in good standing under thelaws of the State of Delaware, and is duly qualified and authorized to do business in the State ofUtah.

B. DMC has full corporate power and authority to own its property, carry on its businessas being conducted on the date of this Agreement, and has full authority to enter into and performits obligations under this Agreement.

C. The obligations of DMC, which are set forth in this Agreement, are enforceable inaccordance with their terms except as such terms may be limited by bankruptcy, insolvency, orsimilar laws affecting the enforcement of creditors' rights generally.

D. The White Mesa Mill facility (i) is not or has not been the subject of response costs asdefined by the Comprehensive Environmental Response, Compensatory, and Liability Act, asamended, 42 U.S.C. § 9601-9662 ("CERCLA"), or (ii) is not listed, or is not proposed to belisted, on the National Priority List as defined in CERCLA.

E. The White Mesa License is in full force and effect and permits DMC and DenisonWhite Mesa, LLC to accept and dispose of Byproduct Materials in accordance with the terms andconditions of this Agreement.

5. REPRESENTATIONS AND WARRANTIES OF SHIPPER. As material inducements toDMC to enter into this Agreement, Shipper represents and warrants to DMC as follows:

A. Shipper is a corporation duly organized, validly existing, in good standing under thelaws of the state of its incorporation. Shipper has been duly licensed under the Shipper'sRadioactive Materials License to operate the Project and to generate the Byproduct Material.

Page 146: Church Rock Section 17 Restoration Action Plan.

Byproduct Disposal AgreementKingsville Dome ISR ProjectUranium Resources Inc. and Denison Mines (USA) Corp. Page 5

B. Shipper has full corporate power and authority to own its property; to carry on itsbusiness as being conducted on the date of this Agreement, and has full authority to enter intoand perform its obligations under this Agreement.

C. The obligations of Shipper, which are set forth in this Agreement, are enforceable inaccordance with their terms except as such terms may be limited by bankruptcy, insolvency, orsimilar laws affecting the enforcement of creditors' rights generally.

D. Each shipment of Byproduct Material to be delivered to the White Mesa Mill forfinal disposal in the Tailings Facility will comply with all applicable provisions of Titles 10 and49 of the U.S. Code of Federal Regulations, Shipper's Radioactive Materials License, the WhiteMesa License, and all other applicable regulations, permits and licenses.

E. The Byproduct Material is not and does not contain any hazardous waste as defined inthe Resource Conservation and Recovery Act, as amended, 42 U.S.C. § 6901-6992, orcomparable state laws or regulations. The Byproduct Material has not been transported from anysite or facility which (i) is or has been the subject of response costs or demands for the paymentof response costs as defined in CERCLA, or (ii) is listed, or is proposed to be listed, on theNational Priority List as defined in CERCLA.

6. COVENANTS OF DMC. DMC covenants as follows:

A. DMC shall remain in compliance with its representations and warranties as set forthin this Agreement during the term of this Agreement.

B. DMC shall maintain, at its expense, during the continuance of the effectiveness of thisAgreement, policies of insurance which provide at least the following types of coverage in atleast the following amounts:

COVERAGE LIMITS

Worker's Compensation StatutoryEmployer's Liability $1,000,000 each occurrenceGeneral Liability $2,000,000 combined single limitAutomotive Liability $1,000,000 each accident(bodily injury & property damage)

C. Worker's Compensation insurance shall contain a waiver of subrogation clause, to theextent permitted by law.

D. DMC shall, throughout the continuance of the effectiveness of this Agreement,remain in compliance with the requirements of any federal or state agency for the deposit ofsurety bonds, cash funds, or other surety arrangements as required by any such agency, to assure

Page 147: Church Rock Section 17 Restoration Action Plan.

Byproduct Disposal AgreementKingsville Dome ISR ProjectUranium Resources Inc. and Denison Mines (USA) Corp. Page 6

it of performance and completion of requirements for reclamation of the White Mesa Mill inaccordance with applicable law and regulations.

7. COVENANTS OF SHIPPER. Shipper covenants as follows:

A. Shipper shall remain in compliance with its representations and warranties as set forthin Paragraph 5 of this Agreement during the continuance of the effectiveness of this Agreement.

B. Shipper shall maintain or cause the transportation contractor to maintain, at itsexpense, during the continuance of the effectiveness of this Agreement, policies of insurancewhich name each of DMC and Denison White Mesa LLC as an additional insured, and whichprovide at least the following types of coverage in at least the following amounts. Prior todelivering any Byproduct Material to the White Mesa Mill and, as a condition to doing so, then,and from time to time during the continuance of this Agreement, Shipper shall furnish to DMCduly executed certificates of insurance establishing that the required insurance coverage has beenobtained and is being maintained in full force and effect.

COVERAGE LIMITS

Worker's Compensation StatutoryEmployer's Liability $1,000,000 each occurrenceGeneral Liability $2,000,000 combined single limitAutomotive Liability $1,000,000 each accident(bodily injury & property damage)Automotive Liability $5,000,000(LSA - Highway Route Controlled Quantity Coverage)

C. Worker's Compensation insurance shall contain a waiver of subrogation clause, to theextent permitted by law.

D. The Byproduct Material to be delivered to the White Mesa Mill for disposal in theTailings Facility will consist of contaminated soil, sand, rocks, demolition masonry, concreterubble, filter material, pond liners, processing equipment, piping, pond sludge and othermiscellaneous material and equipment. No separate pieces of any material shall exceed 30 cubicfeet in volume, with no single dimension greater than six feet. Any and all material containingvoid space of one cubic foot or greater, except open-ended steel piping, shall be opened byShipper such that the void space can be filled during disposal, or the material shall be crushed byShipper such that the remaining void space is less than one cubic foot. No partially filled drumsshall be shipped, and Shipper shall crush any empty drums that are shipped for disposal.Materials of a friable nature, such as PVC or fiberglass, shall be crushed or chipped by Shipperto reduce void space. Byproduct Materials saturated with liquid will not be shipped. No rebar orother sharp objects shall be protruding from concrete or cement type of rubble. Any deviationfrom these requirements must be approved in writing by DMC prior to transporting such

Page 148: Church Rock Section 17 Restoration Action Plan.

Byproduct Disposal AgreementKingsville Dome ISR ProjectUranium Resources Inc. and Denison Mines (USA) Corp. Page 7

materials. The Byproduct Material is expected to include the radionuclides Radium-226,Thorium-230, and natural uranium. The Radium-226 levels will not exceed 6,000 pci/gram, andtotal radioactivity will not exceed 6,000 pci gross alpha activity per gram, and sample reportsshowing radioactivity levels shall be included with the Bill of Lading delivered to DMC for eachshipment.

E. With each shipment of the Byproduct Material to the White Mesa Mill, Shipper shallexecute and deliver to DMC (or the transporter, as appropriate) a Bill of Lading and MaterialRelease Authorization, and the information provided on such shall be true and accurate in allrespects.

8. INDEMNIFICATION BY DMC. DMC shall indemnify, defend, and save harmlessShipper and its officers, employees, and agents against all liability whatsoever, including allcosts and expenses Shipper and its officers, agents, and employees may incur, including withoutlimitation by reason of enumeration, claims asserted against Shipper by any employee of DMC,environmental response costs, clean up costs, governmental fines, costs of settlement, andreasonable attorney's fees which in any way relate to or arise out of or are incurred in connectionwith any of the following: a breach by DMC of its representations, warranties or covenants madein this Agreement, the failure of DMC to comply with the terms and provisions of the WhiteMesa License and/or any state issued permits, or other applicable federal and state statutes orregulations, or the disposal of any Byproduct Material at the White Mesa Mill provided that theByproduct Material conforms in all material respects to the terms of this Agreement and the datasupplied on any of the reports, logs or forms provided by Shipper.

9. INDEMNIFICATION BY SHIPPER. Shipper shall indemnify, defend, and saveharmless DMC, Denison White Mesa, LLC. and their respective officers, employees, and agentsagainst all damages and liability whatsoever, including all costs and expenses that DMC,Denison White Mesa, LLC. and their respective officers, agents, and employees may incur,including without limitation, loss of profits or revenues, claims asserted against DMC or DenisonWhite Mesa, LLC. by any employee of Shipper, environmental response costs, clean up costs,governmental fines, costs of settlement, and reasonable attorney's fees which in any way relate toor arise out of or are incurred in connection with the disposal of any Byproduct Materialdelivered to the White Mesa Mill from Shipper, if such damages or liability, in any waywhatsoever, results from the failure of the Byproduct Material to conform to the terms of thisAgreement or the data supplied on any of the reports, logs or forms provided by Shipper, or saidshipment fails to meet applicable standards prescribed by the Department of Transportation, orany other federal or state governmental agency, having jurisdiction over such matters, or whichare related to breaches by Shipper of its representations, warranties or covenants made in thisAgreement, or the failure of Shipper to comply with the terms and provisions of the Shipper'sRadioactive Materials License, and/or any other permits or other applicable federal and statestatutes or regulations, regardless of whether title to the Byproduct Material has passed to DMCunder the terms of this Agreement.

Page 149: Church Rock Section 17 Restoration Action Plan.

Byproduct Disposal AgreementKingsville Dome ISR ProjectUranium Resources Inc. and Denison Mines (USA) Corp. Page 8

10. PAYMENTS AND FEES. For all the Byproduct Material delivered to and disposed ofby DMC, Shipper shall pay DMC as follows:

A. Subject to the provisions of Section 11 hereof, Shipper shall pay DMC within thirty(30) days of receipt of an invoice therefor, the following disposal fees for quantities of ByproductMaterial delivered for disposal, as indicated below:

(i) For Byproduct Material consisting of soils, sand, gravel, rock, concrete rubblewithin size specification, and masonry-type demolition material: $100.00 per ton.

(ii) For Byproduct Material consisting of unpackaged pond sediments, PVC,fiberglass and process equipment and other miscellaneous items: $120.00 per ton.

(iii) For Byproduct Material consisting of packaged or drummed demolition andprocessed waste, including PVC, fiberglass, ion exchange resin, processequipment, and other miscellaneous items not included as bulk material: $140.00per ton.

(iv) An unloading charge of $45.00 per hour, or any part thereof, not to exceed $135,will be made for unloading of each shipment at the White Mesa Mill.

(v) A decontamination charge of $150 per shipment for decontamination of the truckand container to meet the applicable NRC release standards as listed in Table 1 ofthe NRC "Guidelines for Decontamination of Facilities and Equipment Prior toRelease For Unrestricted Use or Termination OfLice-hses F6or-Byi-ir-6ocI- Sc-iuce,or Special Nuclear Material," (May 1987) and the applicable Department ofTransportation regulations contained in 49 CFR Part 173. DMC uses high-pressure water to decontaminate equipment. In the event additionaldecontamination equipment or methods are required, additional charges will beapplied equal to the cost for such additional decontamination reagents, man-hours,and equipment plus a fee of 10% thereon.

(vi) Any truckload consisting of any combination of both A(i) and A(ii) will becharged at the rates provided in A(ii).

(vii) Any truckload consisting of any combination of either A(i), A(ii) and A(iii) willbe charged at the rates provided in A(iii). As used herein, "ton" shall mean 2,000pounds. The determination of "cubic feet" shall be based on the shippingcontainer volume.

DMC will provide Shipper with a copy of DMC's scale ticket to support DMC's weightmeasurement and subsequent invoice.

Page 150: Church Rock Section 17 Restoration Action Plan.

Byproduct Disposal AgreementKingsville Dome ISR ProjectUranium Resources Inc. and Denison Mines (USA) Corp. Page 9

B. The Utah State Radioactive Waste Tax applicable to the Byproduct Material disposedof at the White Mesa Mill shall be paid by Shipper.

C. All sales and use taxes, that are applicable to the services covered herein, shall be paidby Shipper.

11. FEE REVIEW AND INCREASE.

A. Any material increase of DMC's costs of operation, due to regulatory requirements,shall be charged to the Shipper, in a fair and reasonable proportion, from the date a particularrequirement becomes effective; provided, however, that DMC shall give Shipper at least 60 daysadvance notice of any such increase and the increase shall only apply to shipments made after theexpiration of such 60 day notice period.

B. On each anniversary of the date hereof, during the Term, the fees set out in ParagraphI0A, as they may have been previously adjusted pursuant to this Section 11, shall be adjusted bymultiplying each such fee by the sum of 1 plus the percentage increase in the Price Index overthe 1 year period ending on the date of such adjustment.

For the purpose of this Paragraph 111B, the term "Price Index" shall mean the GeneralProducer's Price Index for Finished Goods as published by the United States Department ofLabor, Bureau of Labor Statistics for the closest month ending prior to the adjustment dates.

12. INSPECTIONS. Shipper's representatives, as designated to DMC in writing, shall havethe right to inspect DMC's White Mesa Mill facilities which are related to receipt, handling, anddisposal of the Byproduct Material, at reasonable times and frequency designated by DMC, andupon at least seven days written notice from Shipper. Shipper shall also have the right to inspect,upon reasonable notice, DMC's licenses and permits to receive, handle and dispose of ByproductMaterial at the White Mesa Mill facility. Such inspections shall be at the sole cost and risk ofShipper's participating representatives, and shall not interfere with DMC's operations at theWhite Mesa Mill.

13. SAFETY. Shipper, its employees, all its contractors and subcontractors ("Shipper'sPersonnel"), shall abide by all health, safety, and security rules and regulations in force at theWhite Mesa Mill, or on any property controlled by DMC or Denison White Mesa, LLC. whilethey are present on the premises. Shipper shall indemnify and hold harmless DMC and DenisonWhite Mesa, LLC. for any loss or damages, including reasonable attorney's fees, suffered byDMC or Denison White Mesa, LLC. resulting from the failure of Shipper's employees,contractors or subcontractors to comply with the terms of this Paragraph 13.

14. TERMINATION.

A. This Agreement may be terminated by notice from either party in the event of

Page 151: Church Rock Section 17 Restoration Action Plan.

Byproduct Disposal AgreementKingsville Dome ISR ProjectUranium Resources Inc. and Denison Mines (USA) Corp. Page 10

substantial failure by the other party to fulfill its obligations through no fault of the terminatingparty, provided that no such termination may be effected unless the other party is given not lessthan 15 business days written notice (delivered in person or by certified mail, return receiptrequested) of intent to terminate, during which time the default may be cured and the Agreementreinstated.

B. If termination is caused by default of Shipper, Shipper shall pay DMC all sums duehereunder, through the date of termination.

C. In the event termination is caused by default of DMC, DMC will reimburse Shipperfor all sampling and characterization costs incurred for any pending shipments and anytransportation costs incurred for pending shipments.

D. In the event any one party shall have declared force majeure, as cited in Paragraph 25herein, for any event or events cumulating over 60 days, the other party may terminate thisAgreement by five days written notice.

15. CONFIDENTIALITY. DMC and Shipper shall endeavor to keep this Agreement and theterms and conditions contained herein confidential and shall not disclose same to third partieswithout the other party's prior written consent, which will not be unreasonably withheld, unlesssuch disclosure is required pursuant to applicable law or regulation, including tax and securitieslaws and regulations, or for the purposes of the financing of either party or any of its affiliates.Either party may make such disclosures as it deems appropriate to affiliates, employees, agents,contractors or prospective purchasers, lessees or assigns, provided that any such persons areadvi-sed of this confidentiality-cause and agree to be bound by it.

16. NOTICES. Except as specifically provided to the contrary in this Agreement, any noticesor communications permitted or required hereunder shall be deemed properly transmitted whendelivered in person or sent by mail, telecopy, or any other form of written communication,addressed to the respective party at the addresses listed below or at such other address as eitherparty may notify that other in writing in accordance with the provisions of this Paragraph.Notices shall be deemed to have been given on the date of receipt.

IF TO DMC OR DENISON WHITE MESA LLC:

Denison Mines (USA) Corp.Independence Plaza, Suite 9501050 Seventeenth StreetDenver, Colorado 80265Phone: (303) 628-7798Fax: (303) 389-4125

Page 152: Church Rock Section 17 Restoration Action Plan.

Byproduct Disposal AgreementKingsville Dome ISR ProjectUranium Resources Inc. and Denison Mines (USA) Corp. Page 11

IF TO SHIPPER:

URI, Inc.711 N. Carancahua Street, Suite 600Corpus Christi, TX 78475Phone: (361) 883 - 3990Fax: (361) 884 - 6744

17. SURVIVAL OF OBLIGATIONS. As provided in this Agreement, the obligations,representations and warranties of each party to the other, which are to be performed aftertermination, shall survive the termination of this Agreement regardless of the cause oftermination.

18. GOVERNING LAW AND VENUE. This Agreement shall be governed by andconstrued in accordance with the laws of the State of Colorado.

19. INUREMENT. The terms and provisions of this Agreement shall be binding upon andinure to the benefit of the parties hereto, their successors, and permitted assigns. Provided,however, neither party shall assign or transfer any of its rights or obligations under thisAgreement except with the prior written consent of the other party, and the written assumptionby the transferee of all of the obligations of such assigning party in a form satisfactory to theother party. Either party's consent to one transfer shall not operate as a waiver of such party'srights as to any subsequent transfer or any subsequent transferee.

20. -- COMPLETE AGREEMENT AND A7MENDMENT. Thi§-Agreementoco-MnftiUles thand complete understanding of the parties with respect to the subject matter hereof andsupersedes any prior agreement, oral or written, relating thereto. This Agreement shall not beamended except in writing, signed by both parties, unless otherwise provided for within thisAgreement. The parties hereto agree that any amendments that may be necessary to achieve ormaintain compliance with any regulatory program that may apply to the subject of thisAgreement shall be made as soon as practicable, provided, however, either party may elect toterminate this Agreement rather than agree to any amendment unless such amendment applies toByproduct Material already disposed of at the White Mesa Mill, in which case the necessaryamendment shall be made.

21. HEADINGS. The paragraph headings used in this Agreement are for convenience only,and shall not be deemed part of this Agreement nor used in its interpretation or construction.

22. ARBITRATION. Any controversy or claim arising out of or relating to this Agreementor the breach thereof shall be resolved in accordance with the Commercial Arbitration Rules ofthe American Arbitration Association by one arbitrator. The selection of the Arbitrator shall bein accordance with such rules. The Arbitrator's decision shall be final and binding upon theparties hereto; and judgment upon the award may be entered in any court having jurisdiction.

Page 153: Church Rock Section 17 Restoration Action Plan.

Byproduct Disposal AgreementKingsville Dome ISR ProjectUranium Resources Inc. and Denison Mines (USA) Corp. Page 12

The parties shall each pay one-half of the fees and expenses of the Arbitrator except for all feesand expenses of its own witnesses and counsel. The arbitration shall be held in Corpus Christi,Texas. Disputes shall not interrupt operations or other actions contemplated herein.

23. COSTS AND ATTORNEY FEES. Except to the extent that such will be consideredliquidated damages payable to Shipper under Paragraph 24 and/or to the extent a matter issubmitted to arbitration under Paragraph 22, if it is necessary for either party to obtain legalrepresentation to enforce any provision of this Agreement, the non-prevailing party agrees tobear the court costs and reasonable attorney fees of the prevailing party.

24. LIMITATIONS OF REMEDY. The parties agree that neither party shall be liable forany incidental and/or consequential damages of any nature claimed by the other party. If DMCis unable for any reason, except as a result of a breach of this Agreement by Shipper or an eventof force majeure, to accept delivery and dispose of Byproduct Material of Shipper, Shipper's soleremedy in such an instance shall be a refund of any advance payments and costs incurred byShipper for pending shipments, including transport costs from the Project to the White Mesa Milland from the White Mesa Mill to the Project or another licensed disposal facility. Refund ofsuch amount shall be considered as constituting liquidated damages, including any and allincidental and/or consequential damages that might be claimed by Shipper. The parties agree thatsuch a refund is reasonable compensation, and not a penalty, for the reason that actual damages,if any that might be sustained by Shipper are uncertain and would be difficult to ascertain.

25. FORCE MAJEURE. Except for both parties' indemnification, the obligations ofconfidentiality and Shipper's obligations to make payments, the obligations of either party shallbe suspended to thteextent,-and-for the period that performanc- is-•preve ntýe-d-1by any cautse,whether foreseeable or unforeseeable, beyond its reasonable control, including, withoutlimitation, labor disputes (however arising and whether or not employee demands are reasonableor within the power of the party to grant), acts of God; laws, regulations, orders, proclamations,instructions or requests of any government or governmental entity whether federal, state or local;acts of war or conditions arising out of or attributable to war, whether declared or undeclared,terrorism, riot, civil strife, disobedience, insurrection or rebellion, fire, explosion, earthquake,storm, flood, sink holes, drought or other adverse weather condition, or any other cause whethersimilar or dissimilar to the foregoing, but specifically excluding increases in the costs oftransportation or handling of Byproduct Materials. The affected party shall promptly give noticeto the other party, as appropriate of the suspension of performance, stating therein the nature ofthe suspension, the reasons therefor, and the expected duration thereof. The affected party shallresume performance as soon as reasonably possible.

26. BOOKS AND RECORDS. Each party shall keep complete and accurate books andrecords respecting all matters covered by this Agreement, including without limitation, records ofthe quantities and disposition of all Byproduct Materials, which shall be open for inspection bythe other party during business hours.

Page 154: Church Rock Section 17 Restoration Action Plan.

Byproduct Disposal AgreementKingsville Dome ISR ProjectUranium Resources Inc. and Denison Mines (USA) Corp. Page 13

IN WITNESS WHEREOF, the parties have caused this Agreement to be executed bytheir duly authorized representatives as of the day and year first set forth above.

DENISON MINES (USA) CORP.

By: __

By signing below, Denison White Mesa, LLC fully and co nally guarantees the timely

and complete performance of all of DMC's obligations under this Agreement.

Denison White Mesa, LLC

By: •K--

Title: ?,--a s- ck &e- - -r-

Page 155: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

ATTACHMENT E-6&6BUDGET BACKUP

RELEASE STANDARDS

Page 156: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

Limits for Release to Uncontrolled Areas

Nuclide Averagea Maximumb Removablec

U-nat 5,000 dpm/10 m2: i5,000 dpm/'00 cm= 1,000 dpm/100 cm2226-Ra Io0Q. dpm/1o00 .cm2 30 dpm/100 cm 20 dpm/100 ým

a. Averaged over no more than 1 m2.b. Applies to an area of not more than 100 cm2 .a. Determined by smearing: with dry filter, or soft absorbent paper.,applying moderate pressure and assessing the amount of radioactive material onthe smear.

ýSource: Regulatory Guide 1.86, "Termination of Operating Licenses for NuclearReactors.i" and: "Guidelines for Decontamination of Facilities and Equipment Prior to.Release for Unrestricted tUse, or Termination of License. for Byproducti Source, orSpecial Nuclear Material."

Page 157: Church Rock Section 17 Restoration Action Plan.

July 23, 2001

,7.. BUilding Decommissioning

There is no office or process buildings planned for the Section 17 site. Section 17will bein situ weilfield only that will feed the IX'satellite onthe adjacent Section 8.

Page 158: Church Rock Section 17 Restoration Action Plan.

Juy 23,2001

8. Surface Reclamation

8.1. Introduction and Description

The, purpose of'theý surface, reclamation program will be to reestablish the sites to theirpremining topographic conditions, :stabilize the site with self-sustaining vegetative cover,. and'torestore all land disturbed by mining, and related, activities to a, productive condition for livestockgrazing, and wildlife habitat consistent with the present, 'and historical use of the area. It isanticipatedthat future land use will be similar to current uses.

'There are no ponds planned forthe Section, 17 site. Section 17 will be in situweifieid

only that will feed the IX satellite on the adjacent Section, .

8.2. Budget Assumptions

The Surface Reclamatioh Budget is formatted with.thetunderlyingassmptions integratedinto the tabulation. The budget figures distinguish individually costs associated with wellfield areareclamation, welifield road.

Wellfield sizes and road lengths were estimated using the schematic diagram COP Figure1.4-8. Unit costs for road, wellfield, pond were calculated by HRI (ee Attachment E-8-2).

Aftr all of the equipment is removed the entire wellfield area will.be.,scanned to assurethat no residual contamination remains on the soil. Scans will be conducted according to theaccording to Procedure shown in Attachment E-6-2, and the hot spots characterized, .picked -upand disposed of at a NRC licensed facility. The: on ,site. management would .conduct these surveys.

All disposal was priced at the bulk rate as shown in AttachmentvE-6-4.

As shown in Attachment- E-8-1, the total cost for final surface teclamation is $7,153.

Page 159: Church Rock Section 17 Restoration Action Plan.

July 3, 2001

ATTACHMENTE-&-1SURFACE RECLAMATIONBUDGET

Page 160: Church Rock Section 17 Restoration Action Plan.

Rev. July 23, 2001

Wemfield Surface Reclamation

Deseription UnitToa

I. Welfleld Area Reclamation

Weflfelds area (acr) 28Disking/seeding unitcost ($/acre) $200

SubtotA re-lamatnon coSts for W"olfild $6,800

IL Welfleld Road, ReclamationLength of welfleld roadsi(1000 It) 2.25Wedlfield :ioad eclanmtlon Unittcost' ($/1000 ft) $690

'SubtDtal wellfleld.road;reclamation costs $1,553

TOTAL WELLFIELD AND SATELLITE SURFACE RECLAMATIONCOSTS $79153

Page 161: Church Rock Section 17 Restoration Action Plan.

July 23. 2001

ATTACHMENT F-8-2BUDGET CALCULATIONS

ROAD REMOVAL.

Page 162: Church Rock Section 17 Restoration Action Plan.

WELLFIELD ROAD RECLAMATION

Assumptions:

1. Gravel road base removed at cost of$0.6o0cy/tl 000 ft (WDEQ Guideline No. 12, Appendix C)2. Gravel road base:; average depth = 0. averaaverage width= 15 ft3. Roads sadrfied prior to topsoil application at cost of $30.51/acre (WDEQ Guideline NO. 12, Appendix P)

4. Grading of scarified roads prior to topsoil application at cost of $33.27/acre (WDEQ Guideline No., 12, Appendix G)5. Topsoil applied ,at cost or $0.601cy!1 000 ft (WDEQ Guideline NO. 12, Appendix C, surfac grade: level ground)6. Stripped topsoil: average depth =.0.67 ft, average: width: 25 ft7. Discing/seeding cost of $200/acre

Costs per 1000 ft of roadWidth (ft)

Road base removal 15Topsoil application 25

Thick (ftI.0.5

0.67

Yd3,278620

$00d3$•0.60$0.60

$/Acres$30.51$33.27

$200,00

ScarificationGradingDisking/seeding

Width (if)25

2525

Acres0.60.60.6

Total$166.67$372.22

Total$17.51$19.09

$114.78

$690.28TOTALWELLFIELD ROAD RECLAMATION

Page 163: Church Rock Section 17 Restoration Action Plan.

DISKING/SEEDING

Assumption:

1.,Based on actual. contractor costs

TOTAL DISCING/SEEDING:COSTSPER ACRE = $200.00

Page 164: Church Rock Section 17 Restoration Action Plan.

Revised October 15, 2010

9. Contingency/Profit

Contractor profit has been included at 15% of the total cost for groundwater restoration,groundwater stability analysis, well plugging and equipment removal and 25% of the total costfor wellfield D & D, building D & D, and surface reclamation.

Shown in Attachment A- 1 Contingency/Profit is $709,578.

Page 165: Church Rock Section 17 Restoration Action Plan.

Revised October 15, 2010

10. Summary

HRI CROWNPOINT URANIUM PROJECTFinancial Assurance Plan for Churchrock Section 17

Summary

Contingency/ Contingency/Category Project Total Profit 15% Profit 25%

Groundwater Restoration $4,089,818 $613,473Groundwater Stability Analysis $56,000 $8,400Well Plugging $474,648 $71,197Wellfield D & D $58,879 $14,720Surface Reclamation $7,153 $1,788

Totals $4,686,497 $693,070 $16,508

Contingency/Profit $709,578

STotal Surety Proposed $5,396,075

Page 166: Church Rock Section 17 Restoration Action Plan.

ABBIREVIATIONSIACRONYMS

Dollars

$!Kgal Dollars per 1000. gallons

avg average

ft feet.

U12 square feet

ft3 cUbictfeet

gail g;llons

gpm gallons per minute

H&S Healthtand-Safety

H2S Hydrogen Suffide

H2SO4 Sulfuridc Acid

HCI Hydrochloric Acd

Hpi Horsepower

Kgal 1.l000gallons

KWh Kilowatt-ours

HaOH CausbcSoda

00 Outside Diameter

:PPE personal protective equipment'

PV Pore Volume

reqm't requirement

RO. Reverse osmosis

WDEQ Wyoming Departmentr•joEnvi onmental Quality

WDW Waste Disposal Well,

yd3 cubic yards

.yr year