Top Banner
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out
21

Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Dec 16, 2015

Download

Documents

Barnard Norris
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Chapters 8, 9, and 10

Design

Stage 1 Preconstruction Stage 2: Procurement

Conceptual Planning Stage3: Construction

Stage 4: Project Close-out

Page 2: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Scheduling in Construction Projects

• The time to construct a project is limited and specified in the contract.

• The owner will expect to be reimbursed for delays. Liquidated damages provision may be included in the contract.

• The contractor will save overhead costs and will be able to reassign some of the resources if the project is not delayed.

Page 3: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

• a large number of different parties is involved in most construction projects. Schedules are essential to provide a common means of communication between them.

• Scheduling is important in estimating and leveling resources.

• Scheduling is done at several stages: – Design in final stages to produce a general or master

schedule– Procurement: contractors need to submit a schedule with

their offer and check that they are committed to a possible schedule

– Construction: detailed scheduling, updated as appropriate

Page 4: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Bar Charts( Gantt Charts)

Page 5: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

• Advantages:– easy to interpret.– show clearly the general progress of a project by showing the

scheduled versus the actual progress. – effective means of communicating to upper management about the

overall progress.

• Disadvantages:– Hard to show complicated interdependencies between activities.– Bar Charts oversimplify the activities and represent activities that

are broad in scope. What will take place on any given day?– Without a software, bar charts are not easily updated.

• Time-Scaled bar charts, combined with networks,avoid many of the disadvantages of bar charts, see schedule of oceanography building.

Bar Charts( Gantt Charts)

Page 6: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Network Analysis

• Notations: arrow and precedence, example.• We will cover arrow diagrams manually and precedence

diagrams through SureTrack.• Advantages:

– Networks show the interdependencies of all activities.– They can easily be updated with a computer software.

which can determine the impact of any change on the other activities.

– Permit the determination of critical activities.

Page 7: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Term DefinitionsArrow diagrams

• Activity: Performance of an operation that consumes time. denoted by arrows in arrow diagrams.

• Event: a point in time such as the beginning or the end of an activity. Can be presented by a node.

• “i” and “j” nodes: start and end of an activity.• Duration: the estimated time to perform and activity.• Dummy: an activity that uses no resources and consumes

no time. Used, when necessary, to provide a unique notation for each activity and to show the proper logic in a network.

Page 8: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Activity Relationship in a network• Activities

– Are represented by arrows.– Must have a definite starting or ending point or node.– Referenced by their node designations. The beginning

is described as the “i” node, the end is described as “j” node. For example, activity (3-4).

• Nodes– Points in time– Consume no resources– They are the beginning and ending points of an

arrow(activity).

3 4

Page 9: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

• An activity can be followed by more than one activity (burst).

• More than one activity may be the immediate predecessors of one activity (merge).

• Dummies: superficial activities inserted to accurately portray the proper relationship in a complex network. Also, activities must have unique IDs. Examples: – Activities A and B are followed by C but activity D is

preceded by B only?– Activities A and B start and end at the same node. More

network logic examples.

Page 10: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Arrow Networks Rules

• A network has a single starting node and a single end node.

• Networks are continuos.

• No activity can start until all preceding activities have been completed.

• Arrows are not to scale

• Each arrow indicates a single activity

Page 11: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Calculating Network Information

• Each network, that we will consider, starts and ends with a single node.

• The first node is assigned the start of the first day.• All values computed describe node occurrence times in

terms of the start of a work day.• What is the meaning of each number in the network?

Remember that there are different ways to organize this

– Numbers inside the nodes are node designations (i or j).– Numbers on the nodes are the early point in time which

is represented by the node (EET).– Numbers on or under the middle of the arrows are the

duration of the activities.

Page 12: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

– Numbers at the head of the arrows are the finish time of the activities

– Numbers at the beginning of the arrows are the beginning time of the activities.

– Numbers underneath the arrow heads, tails, or the nodes (LET) are equivalent to the numbers on top of them computed by performing a “backward pass”. They represent “late times”

3 412

27 3927

28 40

39

40

28

28

Page 13: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

• Early Start (ES): the earliest time that an activity can start. Determined by the latest early completion of all its preceding activities.

• Early Finish (EF): the earliest time that an activity can finish. Determined by adding the duration of the activity to the early start of that activity.

More Definitions

13

17?

Page 14: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

• Late Finish (LF): the latest time that an activity can finish without delaying the entire project completion. Determined by the earliest late start of all its succeeding activities.

• Late Start (LS): the latest time that an activity can be started without delaying the project completion. Determined by subtracting the duration of an activity from its late finish.

• Critical: a term that implies that an activity cannot be delayed without extending the project duration

2426?

Page 15: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Forward Path• Forward Path:

– used to determine the early times– starts with a node at day 1, which is the early start of all

succeeding activities. Add the duration of each activity to its early start to get the early finish.

– In case of a merge the early event time of a node is the latest early finish of merging activities.

– The early event time of a node is the early start of all succeeding activities.

12

58

64

7

41 614

14

1216

21 ? ? ?

Page 16: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Backward Path• To compute the late times• Starts at the last node. The late time of the last node is the

early time.• Subtract the duration of each activity from the late date.• In case of a burst the late finish of the node is the smallest

finish time of the succeeding activities

2521

58

64

7

41 614

14

1216

21 21 25

25

1717

14

??

Page 17: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

• We will discuss total float and free float.

• Total float of an activity is the amount of time that the duration of the activity can be extended without increasing the duration of the project. What happens when a total float = zero ?

• An activity of zero total float is a critical activity and lies on the critical path.

• The critical path consists of a series of connected activities between start and end nodes. Activities on the critical path have zero total float.

• There should be at least one critical path in each network.

Page 18: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Total float = TFact = LSact -ESact = LFact-EFact

3440

TF = 6

58

64

7

40 513

13

1115

20 20 24

24

1616

13

50

TF = 0

TF =?

TF = 0

2011

13TF = 0

TF =?

TF = 0

Or simply compare: 34

28

245

Page 19: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Free Float• The number of days that an activity duration can be increased

before the start date of any activity in the network is effected.

Free float = early event time of node j - EF of activity i-j

or, simply subtract:EET - EF

EFEET

Page 20: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

Summary of network computations• Node times:

– Forward (EET): • merge: take the largest EF• burst: same as EF

– Backward (LET):• merge: same as LS:

• burst: take smallest LF

?9

5?

9 9 ??

3434

3429

29

Page 21: Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.

• Float:– total float = c - a– free float = b - a

• All you really need to compute are the EET and LET at the nodes and the EF of the activities.

• Example

a b

c