Chapter 9
FUNDAMENTALS OF SQAPLANNING
8/11/2019 Chapter 9 SQA Planning
2/44
Objectives
Upon completing this chapter, you will be ableto: Define the benefits of SQA for projects specified Modify SQAP checklists for organization-specific projects Incorporate quality assurance with an overall organization Set the standards and procedures for the specific project
implement the SQAP to develop quality end product Develop an SQA plan that complies with the identified
goals.
8/11/2019 Chapter 9 SQA Planning
3/44
BUILDING BLOCKS OF SOFTWAREQUALITY ASSURANCE
IEEE Guideline for Software Quality Assurance Planning[IEEE Std 730.1-1995] defines defines following building
blocks to develop software quality: Purpose Reference Documents Management Documentations Standards, Practices, Conventions, and Metrics
Review, and Audits Test Problem Reporting and Corrective Actions
8/11/2019 Chapter 9 SQA Planning
4/44
BUILDING BLOCKS OF SOFTWAREQUALITY ASSURANCE (cont.)
Tools, techniques, and Methodologies Code Control Media Control
Supplier Control Records Collection, Maintenance, and Retention Training Risk Management
8/11/2019 Chapter 9 SQA Planning
5/44
PURPOSE
This section identifies the specific purposeand scope of SQAP by: developing the names of software items
covered by SQAP and the use of software.
It shall answer for the questions like how issoftware to be used? How critical is this
software? Who does it apply to? Which portion of the software life cycle applies toeach of software items? Etc.
8/11/2019 Chapter 9 SQA Planning
6/44
REFERENCE DOCUMENTS
This section will provide the complete listof document referenced to develop SQAP,e.g. Military, industry specific or corporatequality assurance standards and guidelines.
8/11/2019 Chapter 9 SQA Planning
7/44
MANAGEMENT
This section with the major elements of theorganization that influences the quality ofsoftware, list of tasks covered by this planand specification of organizationresponsible for each task.
Therefore, IEEE has described this conceptto be incorporated in SQA planning-Organization, Tasks and Responsibilities
8/11/2019 Chapter 9 SQA Planning
8/44
Organization This section of SQA plan will depict the
organizational structure by describing eachmajor elements of organization togetherwith the delegated responsibilities.
Project Manager
ManagementTeam
ArchitectureTeam
DevelopmentTeam
AssessmentTeam
Common Organisational Structure
8/11/2019 Chapter 9 SQA Planning
9/44
Role and Responsibilities i) Project Manager:
Project manager is responsible for providingrequirements and directions, reporting bugs and issuesfound by himself and the supervisory committee.Project manager hosts status meeting time to time tocheck the status of project. Project manager is alsoresponsible for grading presentation.
ii) Management Team: Management team is responsible for planning the
effort, conducting the plan and adapting the plan tochanges in understanding of the requirements or thedesign.
8/11/2019 Chapter 9 SQA Planning
10/44
iii) Architecture Team: Architecture team is responsible for the use case
modelers, and for achieving the system-wide qualities.
iv) Development Team: Development team is the most popular team, which is
responsible for quality of individual components,component development, testing and maintenance.
v) Assessment Team: Assessment team is responsible for quality of end
product with respect to the requirement and customerexpectation.
Role and Responsibilities
8/11/2019 Chapter 9 SQA Planning
11/44
Tasks
This section of the plan should identify the planned major checkpoint to assure the
quality, the tasks to be performed withspecial emphasis on software qualityassurance activities and the relationship
between the tasks and the plannedcheckpoints.
8/11/2019 Chapter 9 SQA Planning
12/44
8/11/2019 Chapter 9 SQA Planning
13/44
iii) Architecture Team: It is responsible to resolve the design issues. Architecture team focuses on architecture properties,
architecture maintenance, multiple component issueresolution, performance tuning and qualityimprovements.
iv) Development Team: This team decides how a design or implementation
issues local to a single component is resolved. Itfocuses on critical design, implementation, test andmaintenance.
Associated Tasks
8/11/2019 Chapter 9 SQA Planning
14/44
8/11/2019 Chapter 9 SQA Planning
15/44
DOCUMENTATIONS
This is an important section of quality assurance plan as it identifies the the team, documentationsgoverning the development, verification andvalidation, use and maintenance of software.
The main emphasis of this section is on how thedocuments are to be checked for adequacy byidentifying the appropriate review or audits.
Minimum documents required to ensure that theimplementation of software satisfy requirements,may be listed as follows:
8/11/2019 Chapter 9 SQA Planning
16/44
Software Requirement Specification (SRS)
ii) Software Design Description (SDD) iii) Software Verification and Validation Plan
(SVVP) iv) Software Verification and Validation Report
(SVVR) v) User Documentation (UD) vi) Software Configuration Management Plan
(SCMP) Other documentation such as Sw Dev Plan,
Standards and procedures, Sw ProjectManagement Plan and Sw Maintenance Manual
8/11/2019 Chapter 9 SQA Planning
17/44
STANDARDS, PRACTICES,CONVENTIONS AND METRICS
This section will describe the standards, practices, conventions and metrics to beemployed by all associated with the projectincluding management and vendors.
8/11/2019 Chapter 9 SQA Planning
18/44
REVIEWS AND AUDITS
To determine the extent of program of thesoftware developed during the software
development life cycle and to evaluate thetechnical adequacy of the work and itsconformance to software requirements, it is
necessary to review and audit the producton a planned basis.
8/11/2019 Chapter 9 SQA Planning
19/44
i) Software Requirement Review: This review wil1 guarantee the technical feasibility,
adequacy, and completeness of the requirements as
outlined in SRS. It wil1 occur after the initialsubmission of the SRS. Software development team isresponsible to perform such type of review.
ii) Preliminary Design Review:
This is also known as top-level design review. Thisreview is to evaluate the technical adequacy of the preliminary design of the software as depicted in thesoftware architectural design description.
iii) Critical Design Review: The critical design review (CDR) is held to determine
the acceptability of the detailed software design asdepicted in the detailed software design description insatisfying the request in SRS.
8/11/2019 Chapter 9 SQA Planning
20/44
8/11/2019 Chapter 9 SQA Planning
21/44
vi) Physical Audits:
This audit is conducted to verify that the software andits documentation are internally consistent and areready for delivery.
vii) In-Process Audits: In-process audit verifies the consistency of the design
from the various aspects including code versus designdocumentation, interface specifications, designimplementation versus functional requirements andfunctional requirements versus test descriptions.
viii) Managerial Review: Managerial reviews assess the execution of all actions
with items identified in software quality assurance plans
8/11/2019 Chapter 9 SQA Planning
22/44
ix) Software Configuration Management PlanReview: The adequacy and completeness of configuration
management methods defined in software configurationmanagement plan will be evaluated through softwareconfiguration management plan review.
x) Post-Mortem Review: On the successful completion of project, the
development team will submit it to supervisingcommittee to be reviewed. Now the committee has todecide the approval of project. The project isconsidered as complete, when supervisory committeeapproves it.
8/11/2019 Chapter 9 SQA Planning
23/44
TEST Software test plan will be developed by qualityassurance team to outline the test activities, schedule
and resources required for testing and how the test will be implemented.
The entire specific software tests and testing, which arenot addressed in SVVP, will be included in this section.
The testing process described in SQAP may be used toaddress the preparation and review of documentation
associated with the testing process, including test plans,test design and test case specification, etc.
8/11/2019 Chapter 9 SQA Planning
24/44
PROBLEM REPORTING AND
CORRECTIVE ACTION This section deals with the responsibility of
SQA team to provide the continuous feedbackconcerning the problem status to managementand technical team, and describe the practicesand procedures to be followed for reporting,
tracking, and resolving problems identified.
8/11/2019 Chapter 9 SQA Planning
25/44
The tasks performed during the problem reportingand corrective action may be listed as follows: .Identification of all development discrepancies and
submission to development team Validation check for the items submitted to team. Data base maintenance for all discrepancies found in
report. Documentation of system and process related problems
identified by SQA on report. Problem resolution by the end of working session.
Conducting meeting to handle any dispute among teamand relevant parties with manager as a mediator. Documentation and maintenance database for any
problem resolved by the team members.
8/11/2019 Chapter 9 SQA Planning
26/44
TOOLS, TECHNIQUES AND
METHODS This section will describe the specific
software tolls, techniques and methodologies
to be used to support software qualityassurance activity.
8/11/2019 Chapter 9 SQA Planning
27/44
Tools Numerous tools have been proposed in literature for
this purpose. Few of them may be listed as follows: Operating System Utilities - Simulators
Performance Monitor - Test Drivers Structure Analyzer - Code Analyzer Execution Analyzer - Test case Generator
Statistical Analysis Package - Rational Rose Enterprise
Static or Dynamic Test Tools
8/11/2019 Chapter 9 SQA Planning
28/44
Techniques One of the technical and managerial procedures
used to evaluate and improve requirements isSQA technique, such as listed below:
Review of the use of standards Software Inspection Requirements Tracing Requirements and Design Verification Reliability Measurement and Assessments
8/11/2019 Chapter 9 SQA Planning
29/44
CODE CONTROL
It is a way to protect or ensure the validityof completed code. Methods and facilities
used to maintain, store, secure anddocument controlled version of theidentified software during all phases of
software life cycle, will be discussed in thissection.
8/11/2019 Chapter 9 SQA Planning
30/44
MEDIA CONTROL
In this section, methods and facilities will be usedto identify the media for each product anddocumentation required to store the media and to
protect these media from unauthorized access ordamage during the development life cycle.
This activity will assure the software storage andretrieval process, accessibility of software to thosewith the need of access, and controls environmentso that the physical media on which the softwareis stored do not degrade.
8/11/2019 Chapter 9 SQA Planning
31/44
SUPPLIER CONTROL
This section will assure that the developedsoftware meets the established requirements
by assuring that the developer receives theadequate and complete requirements.
8/11/2019 Chapter 9 SQA Planning
32/44
RECORDS COLLECTION,MAINTENANCE AND
RETENTION
All the projects artifacts will be stored inconfiguration management system.
A copy of each deliverable will be given to the project manager upon completion of the project.
This section deals with retaining, assembling,safeguarding, and maintaining the documentation.
8/11/2019 Chapter 9 SQA Planning
33/44
TRAINING
This section deals with team trainingsession carried out whenever necessary to
familiarize the team members to new toolsor techniques. The technical manager may prepare this
training. Clients may also be trained after delivering
the software upon the client's request.
8/11/2019 Chapter 9 SQA Planning
34/44
RISK MANAGEMENT
This section will deal with ensuring that any potentialrisks are identified and discussed fully in team meeting.
Risk Notification Procedure will record the risk thatarises throughout the duration of the project.
Risk management is responsible for identifying thelevel of risk associated with the possible failure of eachrequired task or the unavailability of each resource andwill quantify the magnitude of each identified risk.
8/11/2019 Chapter 9 SQA Planning
35/44
8/11/2019 Chapter 9 SQA Planning
36/44
Meta-checklist Examples
Purpose Intended use of the software covered by SQAP has been defined:
Scope of SQAP has been identified: Basic Objective of writing SQAP has been specified:
Software items covered by SQAP has been abbreviated:
Software life cycle development model used has been described:
The reasons for choosing supporting documents that form basisof SQAP has been presented:
8/11/2019 Chapter 9 SQA Planning
37/44
Reference Documents All the documents that form the basis of SQAP has been
listed: These documents has been originated outside the project: The use of most current official version of document has
been ensured : All the standards, procedures and guidelines has been listed: Deviations from identified standards, procedures and
guidelines as been listed: Software deliverables requiring additional or rigorous
practices, procedures or guidelines has been identified:
8/11/2019 Chapter 9 SQA Planning
38/44
Management
i) Organization An appropriate organizational structure has been presented: Each major elements of organization together with the
delegated responsibilities has described: The relationship among SQA organizational elements and
software development elements has been delineated andexplained:
A process to resolve all the conflicts has been followed:
8/11/2019 Chapter 9 SQA Planning
39/44
ii) Tasks Major checkpoints to assure the quality has been identified: Tasks to be performed with special emphasis on software
quality assurance activities has been listed: The relationship between the tasks and planned checkpoints
has been established and shown: A workflow diagram has been designed for SQA activities:
8/11/2019 Chapter 9 SQA Planning
40/44
iii) Responsibilities All the specific organizational elements responsible
for each tasks has been listed: Responsibilities of individuals have been identified
if two organizational elements are sharing theresponsibilities for task.
8/11/2019 Chapter 9 SQA Planning
41/44
Documentation All the documents governing the development, verification and
validation, use and maintenance of software has been identified: An appropriate way to check for adequacy of documents has been
emphasized: Minimum documents required to ensure the implementation has
been identified: All required test documentation has been noted:
8/11/2019 Chapter 9 SQA Planning
42/44
8/11/2019 Chapter 9 SQA Planning
43/44
SUMMARY Software quality assurance is more about the
customer. Creating a product that has gone through proper
software testing is crucial to guaranteeingcustomer satisfaction.
Quality planning involves deciding on a suitabledevelopment process and setting target values forinternal attributes.
Quantitative targets are set for the internal qualityattributes identified in the quality model.
8/11/2019 Chapter 9 SQA Planning
44/44
Below is the meta-checklist prepared toverify and ensure the quality of SQAP.