Chapter 8 Cost Estimation and Budgeting
8.1 True/False
1) Direct costs are those clearly assigned to the aspect of the
project that generated the cost.Answer: TRUEDiff: 1Section: 8.1
Cost ManagementSkill: FactualAACSB Tag: Reflective
2) Material is an example of a cost that is recurring, variable
and direct.Answer: TRUEDiff: 2Section: 8.1 Cost ManagementSkill:
FactualAACSB Tag: Reflective
3) An expedited cost is one that does not vary with respect to
their usage.Answer: FALSEDiff: 2Section: 8.1 Cost ManagementSkill:
FactualAACSB Tag: Reflective
4) An order of magnitude estimate is usually more accurate than
a ballpark estimate.Answer: FALSEDiff: 1Section: 8.2 Cost
EstimationSkill: FactualAACSB Tag: Reflective
5) Comparative estimates are more accurate than definitive
estimates when applied to the same project.Answer: TRUEDiff:
2Section: 8.1 Cost ManagementSkill: FactualAACSB Tag:
Reflective
6) A learning rate of 90% means that for every doubling of
output, the time required by the activity falls by 10%.Answer:
FALSEDiff: 2Section: 8.3 Creating a Project BudgetSkill:
FactualAACSB Tag: Reflective7) There is a tendency for different
departments or functions to compete for scarce resources in a
zero-sum game when bottom-up budgeting is used to develop a project
budget.Answer: FALSEDiff: 2Section: 8.3 Creating a Project
BudgetSkill: FactualAACSB Tag: Reflective
8) Activity-based costing is based on the notion that projects
consume activities and activities consume resources.Answer:
TRUEDiff: 2Section: 8.3 Creating a Project BudgetSkill:
FactualAACSB Tag: Reflective
9) A time-phased budget allocates costs across both project
activities and the anticipated time in which the budget is to be
expended.Answer: TRUEDiff: 2Section: 8.3 Creating a Project
BudgetSkill: FactualAACSB Tag: Reflective
10) A budget contingency of $1 million on a $10 million project
means that the project will be planned for a cost of $10 million,
but the project organization receives an extra $1 million to guard
against unforeseen cost overruns.Answer: FALSEDiff: 1Section: 8.3
Creating a Project BudgetSkill: FactualAACSB Tag: Analytic
Skills
8.2 Fill in the Blank
1) Employing an overhead multiplier is sometimes referred to as
the __________ rate for direct labor costs.Answer:
fully-loadedDiff: 1Section: 8.1 Cost ManagementSkill: FactualAACSB
Tag: Reflective
2) __________ costs might be those associated with charges
applied once at the beginning or end of a project.Answer:
NonrecurringDiff: 1Section: 8.1 Cost ManagementSkill: FactualAACSB
Tag: Reflective3) Unplanned costs incurred when steps are taken to
speed up the project's completion are __________.Answer: expedited
costsDiff: 2Section: 8.1 Cost ManagementSkill: DefinitionAACSB Tag:
Reflective
4) The unofficial rule of thumb for __________ estimates is to
aim for an accuracy of plus or minus 30%.Answer: ballpark or order
of magnitudeDiff: 2Section: 8.2 Cost EstimationSkill:
DefinitionAACSB Tag: Reflective
5) __________ cost estimates can only be given upon the
completion of most of the design work at a point when the scope and
capabilities of the project are well-understood.Answer:
DefinitiveDiff: 2Section: 8.2 Cost EstimationSkill: FactualAACSB
Tag: Reflective
6) Cost estimates can be too low if issues outside a firm's
control affect the project organization's ability to complete the
project. These __________ might include inflation or political
instability.Answer: external factorsDiff: 2Section: 8.2 Cost
EstimationSkill: FactualAACSB Tag: Reflective
7) The __________ is a plan that identifies the allocated
resources, the project's goals, and the schedule that allows an
organization to achieve those goals.Answer: project budgetDiff:
2Section: 8.3 Creating a Project BudgetSkill: DefinitionAACSB Tag:
Reflective
8) __________ begins with the work packages of the work
breakdown structure and specifies funds that are needed to support
the tasks. These costs are aggregated by managers and duplicate
costs are removed as managers' budgets are combined.Answer:
Bottom-up budgetingDiff: 2Section: 8.3 Creating a Project
BudgetSkill: FactualAACSB Tag: Reflective9) Activity-based costing
is a budgeting method that identifies __________ associated with
activities that consume resources.Answer: cost driversDiff:
2Section: 8.3 Creating a Project BudgetSkill: DefinitionAACSB Tag:
Reflective
10) __________ is typically added to the project's budget
following the identification of all project costs; that is, the
project does not include __________ as part of the activity-based
costing process.Answer: Contingency money (funds), contingencyDiff:
3Section: 8.3 Creating a Project BudgetSkill: FactualAACSB Tag:
Reflective
8.3 Multiple Choice
1) Which of the following is a direct cost?A) laborB) rentC)
depreciation on equipmentD) health benefitsAnswer: ADiff: 1Section:
8.1 Cost ManagementSkill: FactualAACSB Tag: Reflective
2) Which worker's wages would constitute a direct cost for a
construction project?A) the project's cost accountantB) the brick
masonC) the architect's assistantD) the foreman'sAnswer: BDiff:
1Section: 8.1 Cost ManagementSkill: ConceptualAACSB Tag:
Reflective
3) Three workers complete a full 8-hour day finishing concrete
for a terrace. All three workers are paid $12 an hour and the job
bills to the customer for $450. What are the total direct labor
costs?A) $450B) $12C) $288D) $96Answer: CDiff: 1Section: 8.1 Cost
ManagementSkill: AnalyticalAACSB Tag: Analytic Skills4) Which of
these indirect costs is typically classified as an overhead cost?A)
advertisingB) shippingC) sales commissionsD) taxesAnswer: DDiff:
2Section: 8.1 Cost ManagementSkill: ConceptualAACSB Tag:
Reflective
5) Which of these indirect costs is typically classified as a
selling or administrative cost?A) secretarial supportB) utilitiesC)
insuranceD) depreciationAnswer: ADiff: 2Section: 8.1 Cost
ManagementSkill: ConceptualAACSB Tag: Reflective
6) A systems analyst is paid at the rate of $50/hour and will be
needed for 40 hours. Her employer uses an overhead multiplier of
60% and does not factor in personal time. Her total direct labor
cost that should be billed at:A) $2,000.B) $3,200.C) $1,250.D)
$4,500.Answer: BDiff: 2Section: 8.1 Cost ManagementSkill:
AnalyticalAACSB Tag: Analytic Skills
7) Workers paid $15.00 per hour with an overhead charge of 1.45
and a personal time allowance of 1.15, have what total direct labor
cost for an 8-hour work day?A) $151.30B) $174.00C) $200.10D)
$236.80Answer: CDiff: 2Section: 8.1 Cost ManagementSkill:
AnalyticalAACSB Tag: Analytic Skills8) Which of these is typically
a recurring cost?A) preliminary market analysisB) personnel
trainingC) outplacement servicesD) logisticsAnswer: DDiff:
2Section: 8.1 Cost ManagementSkill: ConceptualAACSB Tag:
Reflective
9) Which of these is typically a nonrecurring cost?A) site
studyB) laborC) materialD) salesAnswer: ADiff: 2Section: 8.1 Cost
ManagementSkill: ConceptualAACSB Tag: Reflective
10) The charge that is most likely a fixed cost is for:A)
materials.B) equipment rental.C) direct labor.D) utilities.Answer:
BDiff: 2Section: 8.1 Cost ManagementSkill: ConceptualAACSB Tag:
Reflective
11) You are probably looking at a bill for a variable cost when
you are paying for:A) leased capital equipment.B) salaries.C)
materials.D) health insurance.Answer: CDiff: 2Section: 8.1 Cost
ManagementSkill: ConceptualAACSB Tag: Reflective12) A normal cost
is incurred when:A) overtime is used more than originally
planned.B) shipments are expedited.C) additional temporary workers
are brought on site.D) the aggressive baseline plan is adhered
to.Answer: DDiff: 2Section: 8.1 Cost ManagementSkill: FactualAACSB
Tag: Reflective
13) Unplanned costs incurred when steps are taken to speed up
project's completion are called:A) expedited costs.B) accelerated
costs.C) pass-through costs.D) normal costs.Answer: ADiff:
2Section: 8.1 Cost ManagementSkill: DefinitionAACSB Tag:
Reflective
14) A key for developing project cost estimates is to:A) cost
the project while considering the total package.B) cost the project
on a work package and task basis.C) cost the project on a major
module basis.D) cost the project and add 33% for
contingency.Answer: BDiff: 2Section: 8.2 Cost EstimationSkill:
FactualAACSB Tag: Reflective
15) The order of magnitude cost estimate is used when:A)
ballpark estimates are not considered accurate enough.B) historical
data are readily available.C) information or time is scarce.D)
parametric estimation has already been performed.Answer: CDiff:
2Section: 8.2 Cost EstimationSkill: FactualAACSB Tag: Reflective16)
When asked to provide an estimate of an irrigation system, Pete
looked from one end of the field to the other, licked a finger and
held it in the air, squinted into the sun and said $25,000, give or
take 30%. The technique employed for cost estimation is:A)
parametric.B) comparative.C) definitive.D) ballpark.Answer: DDiff:
2Section: 8.2 Cost EstimationSkill: DefinitionAACSB Tag:
Reflective
17) Estimates based on the assumption that historical data can
be used as a frame of reference for current estimates are:A)
comparative estimates.B) ballpark estimates.C) definitive
estimates.D) feasibility estimates.Answer: ADiff: 2Section: 8.2
Cost EstimationSkill: DefinitionAACSB Tag: Reflective
18) When their baby was ready to head off to college, the
beleaguered parents pulled out the college folder from their file
cabinet and added up the cost of putting their first child through
college from 1995-2000. The mother whimpered as she factored in the
rising cost of tuition, fees, books, and inflation by multiplying
the total by 2.5. The father felt a searing pain go through his
chest as he saw the total, knowing full well that their cost
estimation approach, called:A) an order of magnitude estimate, was
highly accurate.B) parametric estimation, was highly accurate.C)
feasibility estimation, was highly accurate.D) definitive
estimation, was highly accurate.Answer: BDiff: 2Section: 8.2 Cost
EstimationSkill: DefinitionAACSB Tag: Reflective
19) Effective comparative estimates rely most heavily on:A) an
accurate inflation factor.B) the correct number of years elapsed
between the old project and the current one.C) true comparability
between the current project and previous project work.D) the
correct number of employees on the new project compared with the
previous one.Answer: CDiff: 2Section: 8.2 Cost EstimationSkill:
FactualAACSB Tag: Reflective
20) Cost estimates that are based as a guideline on real
numbers, or figures derived after the completion of preliminary
design work, are:A) definitive estimates.B) order of magnitude
estimates.C) parametric estimates.D) feasibility estimates.Answer:
DDiff: 2Section: 8.2 Cost EstimationSkill: DefinitionAACSB Tag:
Reflective
21) Once most of the design work is complete, at a point when
the scope and capabilities of the project are quite well
understood, a __________ may be developed.A) definitive estimateB)
comparative estimateC) a parametric estimateD) a non-parametric
estimateAnswer: ADiff: 2Section: 8.2 Cost EstimationSkill:
ConceptualAACSB Tag: Reflective
22) Which of these estimates should be the most accurate?A)
parametricB) definitiveC) comparativeD) order of magnitudeAnswer:
BDiff: 2Section: 8.2 Cost EstimationSkill: DefinitionAACSB Tag:
Reflective
23) An activity with a learning rate of 0.9 takes 20 hours for
the first iteration. How long will it take to complete this task
for the 10th time?A) 0.9 hoursB) 10 hoursC) 14 hoursD) 17
hoursAnswer: CDiff: 2Section: 8.2 Cost EstimationSkill:
AnalyticalAACSB Tag: Analytic Skills
24) If it takes 50 hours to complete the first unit and the
company knows from experience that the learning rate should be
0.85, how fast can they be expected to finish all ten units?A) 29
hoursB) 500 hoursC) 234 hoursD) 356 hoursAnswer: ADiff: 3Section:
8.2 Cost EstimationSkill: AnalyticalAACSB Tag: Analytic Skills
25) It took 80 hours of analysis to complete the first phase,
but the second phase was done in 74 hours. If this learning rate
continues, then the 8th analysis should take a mere:A) 63 hours and
20 minutes, give or take.B) 68 hours and 30 minutes, give or
take.C) 57 hours and 15 minutes, give or take.D) 52 hours and 45
minutes, give or take.Answer: ADiff: 3Section: 8.2 Cost
EstimationSkill: AnalyticalAACSB Tag: Analytic Skills
26) What learning rate is being demonstrated if the first unit
takes 15 hours and the third unit takes 14 hours to complete?A)
greater than or equal to 97 percentB) less than 97 percent but
greater than or equal to 95 percentC) less than 95 percent but
greater than or equal to 93 percentD) less than 93 percentAnswer:
BDiff: 3Section: 8.2 Cost EstimationSkill: AnalyticalAACSB Tag:
Analytic Skills
27) Which statement about the use of learning curves is best?A)
Learning curve effects stay constant across projects.B) A job that
is substantially re-engineered will have no disruption of its
learning curve.C) It may be more likely to see learning curve
effects in construction than in research and development.D) Every
worker performing an identical task will exhibit the same learning
effect.Answer: BDiff: 1Section: 8.2 Cost EstimationSkill:
FactualAACSB Tag: Reflective
28) There was no way that the study tour to Italy could cost
only $1500 for 14 days and 13 nights and include all
transportation, meals and hotels, but the smarmy professor knew
that students would balk at a higher advertised price. Once they
were thousands of miles away from home in a country where none of
them spoke the language it would be easier to tell them about
unanticipated charges and approach the more realistic price of
$3500 per person. This type of:A) specification change is a common
reason for a cost overrun.B) lack of definition is a common reason
for a cost overrun.C) low initial estimate is a common reason for a
cost overrun.D) unexpected technical difficulty is a common reason
for a cost overrun.Answer: CDiff: 1Section: 8.2 Cost
EstimationSkill: ConceptualAACSB Tag: Reflective
29) Whether it is the Boeing V-22 Osprey or a simple storm door
installation for a do-it-yourselfer, nothing is ever completed as
quickly or as cheaply as initial estimates due to:A) lack of
definition.B) low initial estimates.C) specification changes.D)
unexpected technical difficulties.Answer: DDiff: 2Section: 8.2 Cost
EstimationSkill: ConceptualAACSB Tag: Reflective
30) Poor initial scope development and work breakdown structure
often creates cost overruns that are attributable to:A) lack of
definition.B) deliberate low initial estimates.C) unexpected
technical difficulties.D) external factors.Answer: ADiff: 2Section:
8.2 Cost EstimationSkill: ConceptualAACSB Tag: Reflective
31) It began as a simple macro that would extract grades and
post them on a web site, but once the web programmer began the
work, he became obsessed with various charting features, grade
summaries, and reports that could be added to make this the
grandest web site in the tri-county area. As 2 hours of programming
work grew to 20 and then 80, he knew that the client wouldn't be
happy with the cost overrun. The only comment he mumbled as he
finished his work was:A) "I had some technical difficulties,
sorry."B) "There were some specification changes, sorry."C) "This
project lacked definition from the outset, sorry."D) "I thought I'd
never get the wizard's hat! Oh, by the way, your grades
work."Answer: BDiff: 2Section: 8.2 Cost EstimationSkill:
ConceptualAACSB Tag: Reflective
32) The 1974 model Eldorado is a three-ton behemoth with a
500-cubic-inch engine that is long on style but short on gas
mileage. During its five-year development process no one could
possibly have anticipated that gas prices would go through the roof
in 1973, making it far more expensive to operate and subsequently
less attractive to a gas-price-conscious public. Design engineers
scrambled to change the car in the last few months leading up to
its debut, adding a slimmed down version with a smaller engine. All
of the design overtime meant that the project budget took a big hit
though, thanks to:A) the initial low estimate.B) the unexpected
technical difficulties.C) this external factor.D) the lack of
definition.Answer: CDiff: 2Section: 8.2 Cost EstimationSkill:
ConceptualAACSB Tag: Reflective
33) A plan that identifies the allocated resources, the
project's goals, and the schedule that allows an organization to
achieve those goals is:A) the work breakdown structure.B) the risk
management plan.C) the statement of work.D) the project
budget.Answer: DDiff: 2Section: 8.3 Creating a Project BudgetSkill:
DefinitionAACSB Tag: Reflective
34) The project plan is supported by the work breakdown
structure,:A) the budget, and the schedule.B) the budget, and the
work packages.C) the work packages, and the schedule.D) the
schedule, and the contingency plan.Answer: ADiff: 2Section: 8.3
Creating a Project BudgetSkill: DefinitionAACSB Tag: Reflective
35) Input is received from an organization's management to
create a project budget in:A) zero-based budgeting.B) top-down
budgeting.C) bottom-up budgeting.D) activity-based
budgeting.Answer: BDiff: 1Section: 8.3 Creating a Project
BudgetSkill: DefinitionAACSB Tag: Reflective
36) An advantage of top-down budgeting is:A) that top management
estimates of project costs are often quite accurate, at least in
aggregate.B) an elimination of the friction between top and lower
levels in the competition for budget money.C) that projects are no
longer a zero-sum game among lower level managers.D) top management
budgets, by definition, cannot experience overruns.Answer: ADiff:
2Section: 8.3 Creating a Project BudgetSkill: DefinitionAACSB Tag:
Reflective
37) A budget that is created by starting with the work breakdown
structure, determining costs for each work package, and then adding
these costs together is:A) zero-based budgeting.B) top-down
budgeting.C) bottom-up budgeting.D) activity-based
budgeting.Answer: CDiff: 1Section: 8.3 Creating a Project
BudgetSkill: DefinitionAACSB Tag: Reflective
38) When properly performed, bottom-up budgeting has the
disadvantage of:A) a lack of detail needed in project plans.B) a
lack of coordination among project managers and functional
department heads.C) being a hindrance to top managers when
prioritizing projects that are competing for the same scarce
resources.D) a reduction of top management's control of the budget
process to one of oversight.Answer: DDiff: 3Section: 8.3 Creating a
Project BudgetSkill: ConceptualAACSB Tag: Reflective
39) A budgeting method that assigns costs first to activities
and then to projects based on each project's use of resources is:A)
activity-based budgeting.B) zero-based budgeting.C) top-down
budgeting.D) bottom-up budgeting.Answer: ADiff: 1Section: 8.3
Creating a Project BudgetSkill: DefinitionAACSB Tag: Reflective
40) Activity-based costing and bottom-up budgeting share the
step of:A) identifying cost drivers associated with each
activity.B) identifying activities that consumer resources and
assigning costs to them.C) assigning costs to projects by
multiplying the cost driver rate times the volume of units.D)
tending to overestimate project costs due to the lack of
involvement by top management.Answer: BDiff: 2Section: 8.3 Creating
a Project BudgetSkill: DefinitionAACSB Tag: Reflective
41) The new dock would require 24 piers to support it and it was
known that each time a pier is sunk into the harbor it would take
300 man hours of labor at $25 per hour. An activity-based costing
of the entire pier system results in a total cost of how much?A)
$600B) $7,500C) $300,000D) $180,000Answer: DDiff: 2Section: 8.3
Creating a Project BudgetSkill: AnalyticalAACSB Tag: Analytic
Skills
42) A budget containing disaggregated figures across the
schedule when work is planned is a:A) time-phased budget.B) chronic
budget.C) temporal budget.D) calendar budget.Answer: ADiff:
2Section: 8.3 Creating a Project BudgetSkill: DefinitionAACSB Tag:
Reflective
43) Which of the following is NOT contained in a typical
time-phased budget?A) total expenses for each activityB) total
expenses for each time unitC) cumulative expenses for each time
unitD) cumulative time for each expenseAnswer: DDiff: 2Section: 8.3
Creating a Project BudgetSkill: AnalyticalAACSB Tag: Analytic
Skills
44) What is the cumulative cost in February in this time-phased
budget?
ActivityJanuaryFebruaryMarchAprilSurvey5,000Design3,0003,000Dirt4,000Foundation10,000Framing35,000Plumb6,000Wire5,500A)
$25,000B) $17,000C) $14,000D) $0Answer: ADiff: 2Section: 8.3
Creating a Project BudgetSkill: AnalyticalAACSB Tag: Analytic
Skills
45) What is the total amount budgeted for design costs in this
time-phased budget?
ActivityJanuaryFebruaryMarchAprilSurvey5,000Design3,0003,000Dirt4,000Foundation10,000Framing35,000Plumb6,000Wire5,500A)
$3,000B) $6,000C) $10,000D) $17,000Answer: BDiff: 1Section: 8.3
Creating a Project BudgetSkill: AnalyticalAACSB Tag: Analytic
Skills
46) What is the total amount budgeted for March in this
time-phased budget?
ActivityJanuaryFebruaryMarchAprilSurvey5,000Design3,0003,000Dirt4,000Foundation10,000Framing35,000Plumb6,000Wire5,500A)
$6,000B) $35,000C) $41,000D) $66,000Answer: CDiff: 2Section: 8.3
Creating a Project BudgetSkill: AnalyticalAACSB Tag: Analytic
Skills
47) What is the total project budget in this time-phased
budget?
ActivityJanuaryFebruaryMarchAprilSurvey5,000Design3,0003,000Dirt4,000Foundation10,000Framing35,000Plumb6,000Wire5,500A)
cannot be determined from the information givenB) $61,000C)
$35,000D) $71,500Answer: DDiff: 1Section: 8.3 Creating a Project
BudgetSkill: AnalyticalAACSB Tag: Analytic Skills
48) What is the total project budget in this time-phased budget?
ActivityJulyAugustSeptemberOctoberNovemberRFP31,000Analysis3,00015,000Design23,00034,000Coding46,000Testing10,000Training15,00015,000Roll-Out18,000A)
$210,000B) $193,000C) $184,500D) $178,300Answer: ADiff: 1Section:
8.3 Creating a Project BudgetSkill: AnalyticalAACSB Tag: Analytic
Skills
49) What is the cumulative project budget for September in this
time-phased budget?
ActivityJulyAugustSeptemberOctoberNovemberRFP31,000Analysis3,00015,000Design23,00034,000Coding46,000Testing10,000Training15,00015,000Roll-Out18,000A)
$210,000B) $152,000C) $137,800D) $80,000Answer: BDiff: 2Section:
8.3 Creating a Project BudgetSkill: AnalyticalAACSB Tag: Analytic
Skills
50) What is the total project budget for design in this
time-phased budget?
ActivityJulyAugustSeptemberOctoberNovemberRFP31,000Analysis3,00015,000Design23,00034,000Coding46,000Testing10,000Training15,00015,000Roll-Out18,000A)
$152,000B) $106,000C) $57,000D) $34,000Answer: CDiff: 1Section: 8.3
Creating a Project BudgetSkill: AnalyticalAACSB Tag: Analytic
Skills
51) What is the project budget for November in this time-phased
budget?
ActivityJulyAugustSeptemberOctoberNovemberRFP31,000Analysis3,00015,000Design23,00034,000Coding46,000Testing10,000Training15,00015,000Roll-Out18,000A)
$21,000B) $15,000C) $18,000D) $33,000Answer: DDiff: 2Section: 8.3
Creating a Project BudgetSkill: AnalyticalAACSB Tag: Analytic
Skills
52) An allocation of extra funds to cover uncertainties and
improve chances that the project can be completed within the
timeframe originally specified is a(n):A) setback.B) budget
contingency.C) reallocation budget.D) reserve line budget.Answer:
BDiff: 2Section: 8.4 Developing Budget ContingenciesSkill:
DefinitionAACSB Tag: Reflective
53) Contingency money is:A) the money that must be received
before any project work can begin.B) money that is spent first to
lock-in all contract guarantees.C) not usually a part of the
activity-based costing process.D) valued at a higher rate than
non-contingency money when determining project costs.Answer: CDiff:
2Section: 8.4 Developing Budget ContingenciesSkill: DefinitionAACSB
Tag: Reflective
54) It was fortunate that the project budget included
contingency funding; the top manager had not foreseen that the
project would need the services of their elite slide rule squad in
more than one area at the same time. Design couldn't complete their
work without their services, nor could marketing, or production.
Contingency funds came in handy to meet the unanticipated:A) change
in project scope.B) abnormal project conditions.C) consequences of
Murphy's Law.D) interaction costs.Answer: DDiff: 2Section: 8.4
Developing Budget ContingenciesSkill: ConceptualAACSB Tag:
Reflective
55) After years of tinkering and reverse engineering
initiatives, Kimray had finally unlocked the secrets of the Beta
tape format. A quick trip to the rental store was an epiphany for
company leadership when they realized that only a handful of Beta
tapes were available; the rest of the world had adopted the VHS
format seemingly overnight. Now they would have to buy a few of
those newfangled VHS machines to see how they ticked. The
contingency funds that management had set aside would be put to
good use on this:A) change in project scope.B) abnormal
condition.C) unanticipated interaction cost.D) latest evidence of
Murphy's Law.Answer: ADiff: 2Section: 8.4 Developing Budget
ContingenciesSkill: ConceptualAACSB Tag: Reflective
56) "If anything can go wrong it often will" is an articulation
of:A) Taylor's Theorem.B) Pinto's Postulate.C) Murphy's Law.D) the
Pareto PrincipleAnswer: CDiff: 1Section: 8.4 Developing Budget
ContingenciesSkill: DefinitionAACSB Tag: Reflective
57) Project cost estimates usually anticipate that resources
will be available, that the weather will not be extreme, and that
funding will materialize, creating what are called:A)
hyperactivity.B) standard operating procedures.C) standard
duress.D) normal conditions.Answer: DDiff: 1Section: 8.4 Developing
Budget ContingenciesSkill: ConceptualAACSB Tag: Reflective58) A
disadvantage of contingency funds is:A) a recognition that the
future contains both knowns and unknowns and the problems that
might arise will impact the budget.B) it is difficult to ascertain
across what project activities contingency funds should be
applied.C) that application to the contingency fund gives an early
warning signal of a potential overdrawn budget.D) that provision is
made in the company plans for an increase in project cost.Answer:
BDiff: 2Section: 8.4 Developing Budget ContingenciesSkill:
ConceptualAACSB Tag: Reflective
59) A contingency rate of 10% on a building project budgeted at
$20 million means:A) the project organization is hoping to bring
the project in for around $22 million.B) the project organization
is hoping to bring the project in for around $2 million.C) the
project organization is hoping to bring the project in for around
$18 million.D) the project organization is hoping to bring the
project in for around $200 million.Answer: CDiff: 2Section: 8.4
Developing Budget ContingenciesSkill: AnalyticalAACSB Tag: Analytic
Skills
60) An early warning signal for the potential of an overdrawn
budget is created when:A) activity-based costing cannot identify
drivers.B) a bottom-up budget never makes it up the chain of
command.C) contingency funds are applied for.D) a top-down process
moves too quickly down to the functional managers.Answer: CDiff:
2Section: 8.4 Developing Budget ContingenciesSkill: ConceptualAACSB
Tag: Reflective
8.4 Essay
1) What are four major categories of costs? Provide descriptions
for each category.Answer: Some of the more common project costs
include labor, materials, subcontractors, equipment and facilities,
and travel. Labor costs are those associated with hiring and paying
the various personnel involved in developing the project. Material
costs apply to the specific equipment and supplies the project team
will require in order to complete the project tasks. Subcontractors
may provide resources (and in the case of consultants, expertise)
for the project, their costs must be factored into the preliminary
cost estimate and be reflected in the budget. Firms commonly
include rental of equipment and facilities as a charge against the
cost of the project when the project is developed away from the
firm's home office. If necessary, expenses that are related to
business travel can be applied to the project as an up-front
charge.Diff: 2Section: 8.1 Cost ManagementSkill: ConceptualAACSB
Tag: Reflective2) Provide examples and discuss the differences
between direct and indirect costs.Answer: Direct costs are those
clearly assigned to the aspect of the project that generated the
cost. Examples include labor that is hands-on in the production of
the project and materials that are used and sold or consumed in the
creation of the project. Indirect costs are generally linked to two
features: overhead and selling and general administration. Health
benefits for the labor force, taxes, insurance, depreciation and
repairs are all indirect costs. Direct costs of materials and labor
are generally easier to calculate than indirect costs, which are
often calculated as a multiplier of some of the direct costs.Diff:
2Section: 8.1 Cost ManagementSkill: ConceptualAACSB Tag:
Reflective
3) Explain the difference between normal and expedited costs,
fixed and variable costs, and recurring or nonrecurring costs.
Create a 2x2x2 matrix and provide one example each (8 total
examples) of each combination of these costs.Answer: Examples may
vary.Nonrecurring costs might be those charges applied once at the
beginning or end of the project while recurring costs are those
that typically continue to operate over the project's life cycle.
Fixed costs do not vary with their usage but variable costs
accelerate through usage. Normal costs are those incurred through
the routine process of working to complete the project according to
the original schedule but expedited costs are unplanned costs
incurred when steps are taken to speed up the project's
completion.Diff: 3Section: 8.1 Cost ManagementSkill:
ConceptualAACSB Tag: Reflective
4) Rank the four different types of cost estimates from most to
least accurate and explain what the inputs are to each type.Answer:
The cost estimates as ranked from most accurate to least accurate
are definitive estimates, feasibility estimates, comparative
estimates, and ballpark, or order of magnitude estimates.
Definitive estimates are expected to have an accuracy of plus or
minus 5% and can be competed only after the completion of most
design work, at a point when the scope and capabilities of the
project are quite well understood. Feasibility estimates are within
plus or minus 10% and are made after completion of the preliminary
design work following initial scope development upon receiving
quotes from suppliers and subcontractors. Comparative estimates
approach plus or minus 15% accuracy and are based on the assumption
that historical data can be used as a frame of reference for
current estimates on similar projects. Ballpark estimates are
created when information or time (or both) are scarce and are
targeted at plus or minus 30%.Diff: 3Section: 8.2 Cost
EstimationSkill: ConceptualAACSB Tag: Reflective5) What are
parametric cost estimates and how are they developed?Answer:
Parametric estimates are a form of comparative estimates, which are
based on the assumption that historical data can be used as a frame
of reference for current estimates on similar projects. Parametric
estimation takes older work and uses a multiplier to account for
the impact of inflation, labor and materials increases, and other
reasonable costs.Diff: 2Section: 8.1 Cost ManagementSkill:
ConceptualAACSB Tag: Reflective
6) Define learning curve theory and describe how learning curves
are used in project management.Answer: Learning curve theory says
that a task can be performed more quickly as repetitions increase,
specifically a doubling of output results in a fixed percentage
reduction in time required to complete the last unit produced.
Learning curve rates can be used in a project if there is an
activity that remains fairly constant and is performed repeatedly.
Rather than using a direct multiplier of the number of repetitions
times the time required to complete the first iteration, the
project manager can use the learning curve equation:
Yx = aXb
to calculate the time required for successive units as long as
the learning curve rate can be estimated. The result will be a time
estimate lower than by direct multiplication, which might permit
the project manager to more accurately gauge the amount of labor
and time required and prepare a more competitive bid.Diff:
2Section: 8.2 Cost EstimationSkill: DefinitionAACSB Tag: Analytic
Skills
7) Big Mike has to prepare a bid for the swimming pools to be
placed in every backyard in a new housing addition. Each swimming
pool represents only a slight variation on the other, so there is a
good opportunity to leverage learning effects in the bid process. A
swimming pool installation can be broken down into four major
steps: excavation, concrete, plumbing, and finish work. Mike has
found the best contractors and asks each of them how long it will
take to complete work on the first pool and what their learning
rates are. Amazingly, each contractor is intimately familiar with
learning curve theory and knows what his learning rate is for this
type of work. This information is summarized in the table.
FunctionFirst PoolLearning RateExcavation22 hours.95Concrete32
hours.90Plumbing10 hours.85Finishing30 hours.85How long will it
take to complete the 25th pool for the subdivision?How long will it
take to complete all 25 pools for the subdivision?Answer: The
twenty-fifth unit for each function is calculated as follows:
A full table for units one through twenty-five is below:
Rate0.95Rate0.9Rate0.85Rate0.85ExcavationConcretePlumbingFinishingUnit
#UnitTotalUnitTotalUnitTotalUnitTotal12222323210103030220.942.928.860.88.518.525.555.5320.363.227.187.97.726.223.278.7419.983.025.9113.87.233.521.7100.4519.5102.625.1138.96.940.320.6120.9619.3121.824.4163.26.646.919.7140.6719.0140.923.8187.06.353.219.0159.7818.9159.723.3210.46.159.418.4178.1918.7178.422.9233.36.065.317.9196.01018.6197.022.6255.85.871.217.5213.51118.4215.422.2278.05.776.917.1230.61218.3233.721.9300.05.682.416.8247.31318.2251.921.7321.75.587.916.4263.81418.1270.021.4343.15.493.316.2279.91518.0288.021.2364.35.398.615.9295.81617.9305.921.0385.35.2103.815.7311.51717.8323.820.8406.15.1109.015.4326.91817.8341.520.6426.75.1114.115.2342.21917.7359.220.5447.25.0119.115.0357.22017.6376.920.3467.45.0124.014.9372.12117.6394.420.1487.64.9128.914.7386.82217.5411.920.0507.64.8133.814.5401.32317.4429.419.9527.54.8138.614.4415.72417.4446.819.7547.24.7143.314.2429.92517.3464.119.6566.84.7148.014.1444.0The
total time for all twenty-five pools is:Total Time = 464.1 + 566.8
+ 148 + 444 = 1623 hoursDiff: 2Section: 8.2 Cost EstimationSkill:
AnalyticalAACSB Tag: Analytic Skills
8) What are the major issues with cost estimation of software
projects?Answer: The software project industry has a very poor
record when it comes to project performance. Research has shown
that for large companies, less than 9% of IT projects are completed
on schedule and budget and over half of the software projects will
cost almost 200% of their original budget. A recent book by Steven
McConnell offers some insights why software projects suffer. Among
these findings are the common failure to budget adequate time and
funding for project activities. Small IT projects spend the
majority of their time in detailed design, coding and debugging,
and unit testing. As the complexity of the projects rises, the
focus of activity shifts to three other activitiesarchitecture,
integration, and system testing. The implications suggest that IT
project budgets must consider the size of the project as they
calculate cost components so that the separate functions can be
allocated an appropriate budget.Diff: 2Section: 8.2 Cost
EstimationSkill: ConceptualAACSB Tag: Use of IT
9) Describe any three reasons that cost overruns occur in
project work.Answer: The most common reasons for cost overruns are
low initial estimates, unexpected technical difficulties, lack of
definition, specification changes, and external factors. Low
initial estimates may be created deliberately, perhaps as an effort
to gain approval, or accidentally, through carelessness, but will
almost always result in a cost overrun. Unexpected technical
difficulties often occur in high-tech projects that require
bleeding-edge technology. Lack of definition as a result of poor
initial scope development creates projects with poorly defined
features or goals, which spills over into poor cost estimates.
Specification changes resulting in scope creep from the initial
baseline project inevitably require more time and money to bring
the project into alignment with the new, larger scope. External
factors beyond the control of the project organization require a
response, one that calls unanticipated resource requirements into
the fray, resulting in cost overruns.Diff: 2Section: 8.3 Creating a
Project BudgetSkill: ConceptualAACSB Tag: Reflective
10) What's the relationship between WBS, scheduling, and
budgeting?Answer: The central goal of a budget is the need to
support, rather than conflict with the project's and organization's
goals. The project budget is a plan that identifies the allocated
resources, the project's goals, and the schedule that allows an
organization to achieve those goals. The project budget must be
coordinated with the project activities defined in the work
breakdown structure, as the WBS sets the stage for creating the
project schedule and the budget assigns the necessary resources to
support the schedule.Diff: 1Section: 8.3 Creating a Project
BudgetSkill: ConceptualAACSB Tag: Reflective
11) How are top-down and bottom-up budgets created? What
advantages does each approach hold over the other?Answer: Top-down
budgeting requires direct input from the organization's top
management; in essence, this approach seeks to first ascertain the
opinions and experiences of top management regarding estimated
project costs. Bottom-up budgeting begins inductively from the work
breakdown structure to apply direct costs to project activities
that are then aggregated, first at the work package level, then at
the deliverable level, at which point all task budgets are
combined, and then higher up the chain to create an overall project
budget. Top-down budgeting has the benefit of experienced senior
personnel getting directly involved in project estimation, but can
create friction between departments, functions, and managers at
lower levels in the organization as they scramble for the largest
share of the budget that they can grab. Bottom-up budgeting
emphasizes the need to create detailed plans and facilitates
coordination between project managers and functional department
heads. Unfortunately, bottom-up budgeting reduces top management's
control of the budget process to one of oversight and may result in
a disconnect between their strategic plans and the direction the
project is taking.Diff: 2Section: 8.3 Creating a Project
BudgetSkill: ConceptualAACSB Tag: Reflective
12) What is activity-based costing and how is it
performed?Answer: Activity-based costing (ABC) is a budgeting
method that assigns costs first to activities and then to the
projects based on each project's use of resources. It is based on
the notion that projects consume activities and activities consume
resources. Activity-based costing consists of four steps:- Identify
the activities that consume resource and assign costs to them as is
done in a bottom-up budgeting process.- Identify the cost drivers
associated with the activity.- Compute a cost rate per cost driver
unit or transaction.- Assign costs to projects by multiplying the
cost driver rate times the volume of cost driver units consumed by
the project.Diff: 1Section: 8.3 Creating a Project BudgetSkill:
ConceptualAACSB Tag: Reflective
13) What is a time-phased budget and how does it help a project
manager control costs?Answer: A time-phased budget allocates costs
across both project activities and the anticipated time in which
the budget is to be expended. The budget can be displayed as a
table with one dimension representing time and the other dimension
representing the major cost categories or the budget can be
summarized by a time plot of dollars. A time-phased budget allows
the project manager to match the project schedule with a budget
baseline, identifying milestones for both schedule performance and
project expense.Diff: 1Section: 8.3 Creating a Project BudgetSkill:
ConceptualAACSB Tag: Reflective
14) What is a budget contingency and what are three reasons it
might be useful?Answer: A budget contingency is the allocation of
extra funds to cover uncertainties and improve the chances that the
project can be completed within the timeframe originally specified.
Contingency money is added to the project's budget following the
identification of all project costs. The author identifies four
reasons why it might make sense to include contingency funding in
project cost estimates:Project scope is subject to change as the
project moves through its development cycle external events or
internal forces can require or call for a change in scope beyond
what was initially planned for.Murphy's Law is always present if
something can go wrong, it will, and this unfortunate circumstance
necessitates additional funds to fix the problem.Cost estimation
may not have anticipated interaction costs one event or work
package interacts with another that requires more work from the
first. This iteration can be accommodated with contingency
funds.Normal conditions are rarely encountered projects are planned
for a "normal" set of operating conditions and quite often, the
abnormal occurs.Diff: 2Section: 8.4 Developing Budget
ContingenciesSkill: ConceptualAACSB Tag: Reflective
15) What are three benefits to the use of contingency
funds?Answer: Use of contingency funds is at first glance not a
cause for celebration; however the author identifies three benefits
derived from the use of these funds. The first benefit is that
their use recognizes that the future contains unknowns and the
problems that arise are likely to have a direct effect of the
project budget. The project has a cushion of contingency to combat
the time and money variance. The second benefit is that the company
has already made provision for extra expense and as these funds are
used, it opens management's eyes to the possibility of a
significant budget increase on the horizon. Finally, application to
the contingency funds givens an early warning signal of potential
overdrawn budget so management can take a close look at the project
and begin formulating additional plans in case the negative trend
continues.