CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical feasibility study Economic Feasibility study Environmental Impact Reports Selection of LOCATION is very important
56
Embed
CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
CHAPTER 2
DEVELOPMENT AND ORGANIZATION
OF PROJECTS
1) THE LIFE CYCLE OF A CONSTR. PROJECT:
1.1:CONCEPT AND FEASIBILITY STUDIES:
THE START Recognition of a need for a new facility
conceptual analyses
Technical feasibility study
Economic Feasibility study
Environmental Impact Reports
Selection of LOCATION is very important
Traditionally, these early stages are handled
by the Owner alone,
OR
By the Owner working with consultants
Knowledgeable of the most important factors
Affecting the situation
To some extent others are involved:
A/E
Design/constructors
CM
PM
1.2: ENGINEERING AND DESIGN:
A) Preliminary Engineering and Design.
- Arch. Concepts
- Evaluation of technological process
alternatives
- Size and capacity decisions
- Comparative economic studies
Inputs from specialists are needed such as:
geologists
hydrologists
ecologists
Review:
Involve management
External financing
Regulatory bodies
Zoning regulation
Building procedures
Licensing procedures
Safety standards
Environmental Impact
B) Detailed engineering and Design
1.3: PROCUREMENT:
Materials
Equipment
Manpower (contractor, subcontractor)
1.4: CONSTRUCTION:
1.5: START-UP AND IMPLEMENTATION:
Industrial facilities
1.6: OPERATION AND UTILIZATION:
FIGURE 2-1 The life cycle of a construction project
Year 3 Year 2 Year 1 Time
Phase
1. Concept and
Feasibility studies
2. Engineering and
design
3. Procurement
4. Construction
5. Start-up and
implementation
6. Operation or
Utilization
CHAPTER2: DEVELOPMENT AND ORGANIZATION OF PROJECTS
Part 1: CONSTRUCTION INDUSTRY AND PRACTICE
BASIC MANAGEMENT ACTIVITIES
Management theory identifies four essential management
activities that must be accomplished in any successful
organization. Organizations can be designed to best
perform these according to the needs of a specific project.
Controlling__Monitor, influence, and direct achievement
of project objectives throughout the
performance phase.
Organizational concepts
• 1. Functional org.
• 2. Task force (project) org.
• 3. Line and staff org.
• 4. Matrix org.
Functional Organization
• Strengths:
• High stability
• High professional standards
• Use latest technology
• Excellent corporate memory
• Weakness
• Low adaptability
• Minimum appreciation of overall project objectives
• Overly grid operating rules
• Resistance to change
• Difficulty to developing well rounded project manager
Functional org
Project (task force) org
Project Task Force
Strengths:
High adaptability
High understanding to overall tasks
Excellent team spirt
Close personal relationships
Responsive to new ideas
Weakness of task force Poor stability
No corporate memory
Own task is not clear
No functional check for quality and standards
This consists of a line, which is managers who make business decisions for their respective departments, and a staff, whose members perform tasks in support of the directives issued by the line. Though the duties of these two components seem clear, there is often overlap in tasks that they perform.
Line And Staff organization
The Line
The line comprises professionals whose day-to-day tasks directly work toward accomplishing the organization’s mission and goals.
Alternative names for the line are the business groups or, in the financial services industry, the front office.
These employees produce and sell the goods and services of the firm.
For example, the research and development team creates the products, while the supply chain manufactures them. The marketing department works to raise consumer awareness of the products and services.
The Staff
The staff is composed of every non-revenue generating department.
Though these groups do not directly contribute to the firm’s bottom line, their actions make those of the line possible.
The human resources department, for instance, ensures that the line is staffed with top-tier talent, content in their jobs.
Legal makes sure that the actions of the line and its employees are within the scope of the law.
Likewise, the finance group secures capital resources for the organization, while the accounting department balances the books
• Line and staff strength: Combination of functional strength and expertise with the project oriented team weakness: Conflict between operating org and functional staff overall cost may exceed more simplified operating concepts
Matrix org.
Matrix org
• It is a combination between task and functional org.
• Disadvantages:
• Difficulties in defining accountability to both functional and project managers
Contractual relationships
• Traditional approach
• The owner-builder
• Turnkey (design construct or design manage)
• Professional construction management
• Program management
• Public private partnership (PPP)
Traditional Designer-Contractor relationship
Used for projects of moderate size and complexity
The owner often employs a designer; The designer also acts on behalf of the owner
to oversee the project implementation during construction;
The general contractor is responsible for the construction itself even though the work may actually be undertaken by a number of specialty sub-contractors.
AEPM 4 22
Traditional Relationship
AEPM 4 23
Owner
Contractor’s
labor Subcontractors
Contractor
Designer
Advantages of using the traditional relationship
A. The most popular and easiest way to perform because of long experience in practice method.
B. Competitive bidding makes the owner benefit from reducing the cost of the project;
C. Owner can monitor and control all the phases of the project;
AEPM 4 24
Type of contract under traditional approach
• Lump-sum contract
• A unit price contract
• A negotiated cost-plus fixed fees
• Guaranteed maximum price
Single fixed price(lump sum)
• The contractor agrees to peform the work for predetermined price includes profit.
• Unit price
• Are similar to lump sum except that the total cost to the owner will vary with the actual quantities of units put in place
The disadvantages of the Traditional method
A. No benefit from contractor experience while designing the project
B. The design, tendering and implementation takes longer period of time
C. The non-friendly relationship between the owner and the contractor makes a lot of claims
D. The non-friendly relationship between the consultant and the contractor enforce them to return back to the owner to solve the claims
E. A lot of changes in the projects makes claims that increasing the final cost of the project and increase the time of execution
AEPM 4 27
FIXED PRICE
Advantages from the owner’s position include the following:
1. These systems are accepted and historically supported
with well-established legal and contractual precedent.
2. The lump-sum type permits overall cost to be determined
before the construction contract is awarded (except for
scope changes or changed conditions).
3. The unit price type permits variable amounts of work to
be paid for in a fair and equitable manner.
4. Minimal involvement of the owner is required in the
construction process.
5. The owner may benefit from price competition in a
competitive situation.
6. The contractor takes all of the construction risk in the
absence of changed or impacts unforeseen by either
party.
7. Contractor incentives and disincentives may improve
performance (bonus and liquidated damages).
FIXED PRICE
Disadvantages from the owner’s viewpoint are as follows:
1. Design usually does not benefit from construction
expertise through value engineering or constructibility
analysis prior to contract award.
2. Overall design- construct time is usually the longest.
3. The owner is often in an adversary position with the
general contractor.
4. The designer is often in an adversary position with the general contractor, and the owner may be required to be the referee.
5. Changes to the work or unforeseen difficulties will often
end in disputes and litigation that can drive up costs in
spite of the fixed-price concept.
6. The owner has minimal control over performance of the
work.
7. The unit price type requires a substantial expense to
measure pay quantities.
8. Contractor pressures to submit the lowest bid may result
in use of marginal subcontractors.
FIXED PRICE
Advantages from the contractor’s standpoint include:
1. The contractor can name his own price for the work as
well as his profit objective in his bid.
2. There is minimum involvement of the owner or
architect/engineer in the details of the building process
other than for quality, schedule and change control.
3. The innovative contractor may obtain an opportunity to
maximize profits through innovation.
4. Administrative requirements are based upon applicable
law, the contract and the contractor’s own determination.
5. The contractor may pass on much of the risk to lower-tier
specialty contractors when feasible.
FIXED PRICE:
Disadvantages from the contractor’s standpoint include:
1. To be competitive the builder must often use marginal
subcontractors who may have problems performing the
work.
2. On many contracts too many bidders may make it difficult
to obtain the work for a fair price and in weak markets the
cumulative cost of preparing the proposal by all contractors
may exceed the profit potential of the successful bidder.
3. The owner controls the funding on disputed extra work or
changed conditions, and the contractor must often resort to
expensive arbitration or litigation with no assurance that it
will recover for the additional costs.
4. The contractor usually bears the economic risk of unusual
weather, conditions, strikes, or other external factors that
influence a contractor’s cost but which may not be directly
under its control.
5. Last minute telephone quotations may contribute to
misunderstandings with material suppliers and
subcontractors.
COST+:
Advantages from the Owner’s point of view include the
following:
1. These contract systems are also accepted and historically
supported.
2. They permit reduction of design-construct time by utilizing
phased construction.
3. This approach enables the contractor to react quickly to
major design changes and unforeseen conditions, and, in
part, minimizes the adversary position.
4. There is an opportunity to utilize contractor expertise during
the design phase to help minimize overall costs.
5. The owner pays for the actual cost of the work plus a
negotiated fee which may result in savings in periods of
high demand for construction work.
6. The owner and the general contractor can still subcontract
a substantial portion of the work to prequalified
subcontractors, thus achieving the advantage of
eliminating marginal subcontractors as well as achieving
fixed prices for specialty work.
7. The owner may participate fully in the management and control of the project to the extent that he has qualified personnel and may exercise control of expenditures in advance, may participate in major decisions, or actually supply certain services or materials to the contractor.
8. Under the guaranteed maximum price option, the owner may pass on some portion of the construction risk to the contractor.
Cost+:
Disadvantages from the owner’s position are the following:
1. Cost plus a fixed fee may not be the most economical
alternative in a competitive market.
2. Disreputable, unskilled, or unknowledgeable contractors
can abuse this arrangement if the owner is not careful in
selection.
3. The guaranteed maximum, while theoretically setting a ceiling, may not stand up in the event of poor initial scope, changed conditions, price increases, design delays, or major design changes which may result in numerous change orders.
4. Owner involvement (or that of the designer) is increased over the lump-sum method in view of the necessity for controls on expenditures, audits, approvals, and other administrative requirements that are considered good practice when this form of contract is employed.
5. Definition of reimbursable items of cost, particularly those for contractor tools and equipment, contractor home office expense and other items that directly affect contractor profit, may be the subject of overruns, disputes and foster adversarial relationships.
6. Under the guaranteed-maximum-cost option, design and
scope changes may negate the advantages of the
guarantee.
Cost+: Advantages to the contractor will include:
1. The contractor has eliminated the risk inherent in fixed price contracting as a trad-off for a lower guaranteed fee.
2. The contractor is generally paid for the preparation if his initial planning including development of cost estimates, schedules and other work plan items which he must absorb in the preparation of a fixed-price bid.
3. The contractor has an opportunity to obtain future work from the owner with minimal or no competition if the program objectives can be achieved in a harmonious relationship.
4. The jobsite can be staffed to provide most of the required services on a reimbursable basis, thus minimizing the contractor’s home office overhead.
5. The contractor can profit from equipment and tool rental in excess of amounts usually included in fixed-price quotations.
Cost+:
Disadvantages from the contractor’s standpoint include:
1. Fees may be minimal in comparison to profit potential in areas of known performance with a favorable risk/reward ratio.
2. Contractor supervision and management may resent major decisions being made or questioned by the client in areas where they would normally have full responsibility.
3. Planning and control functions and assignment of personnel are
made increasingly difficult because of the simultaneous nature of construction and design. Numerous changes may foster a hip-shooting response that may not be the best training ground for young managers.
4. The contractor’s reputation may suffer in the event of significant delays, cost overruns, or compatibility or personal clashes with owner personnel.
5. Under the guaranteed-maximum-price option, the contractor may bear risks for items not under his control. The owner may resent amounts paid to contractor in event of a large under run.
• The owner may subcontract a substantial portion of the project to outside consultants and contractors for both design and construction
AEPM 4 42
Design- build relationship
AEPM 4 43
Owner
Executing
contractors
Subcontractors
Design & Build
contractor
Consultant
Designers
The Advantages of Design and Build Contract
A. Possibility to benefit from the contractor experience during the design;
B. Reducing the total duration of the project due to possibility to start execution before finishing all designs;
C. The relationship between the designer and the implementers is friendlier;
D. Possibility to reduce the total cost by reducing the changes to the minimum
AEPM 4 44
The Disadvantages of Design Build Relationship
A. No allowance for the owner interference while executing the project.
B. Increase of the cost of construction due to high risk given to the contractor side
C. There is no method to ensure real competiveness of contractor prices
AEPM 4 45
Professional Construction Management
• Used When project is very large or complex
• Project management team consisting of :
– A professional construction manager
– Other participants who will carry out the tasks of project planning, design and construction in an integrated manner
– Contractual relationships among members of the team are intended to minimize adversarial relationships
AEPM 4 46
A professional Construction Manager (PCM)
• PCM is a firm specialized in the practice of professional construction management work with owner and the A/E firms from the beginning and make recommendations on:
• design improvements,
• construction technology,
• schedules and
• construction economy.
AEPM 4 47
• Propose design and construction alternatives if appropriate, and analyze the effects of the alternatives on the project cost and schedule.
• Monitor subsequent development of the project in order that these targets are not exceeded without the knowledge of the owner.
•
AEPM 4 48
A Professional Construction Manager
• Coordinate procurement of material and equipment.
• The work of all construction contractors, and monthly payments to contractors,
• changes, claims and inspection for conforming design requirements
AEPM 4 49
CM Relationship
AEPM 4 50
Owner
Subcontractors
Special
Contractors
Construction
Manger
Designer
The Advantages of Using CM Relationship
A. Use of professional persons in all stages of executing the project.
B. There is individual evaluation for the cost, schedules and implementation and amendments.
C. Continues coordination between the design process and implementation process.
D. Reducing the design and construction periods by using construction packages.
E. Possibility to reduce the cost by using competitions between contractors.
F. Possibility of using efficiently the value engineering concepts.
AEPM 4 51
The Disadvantages of Using CM Relationship
A. The start of execution is usually starts before finalizing the cost of the project
B. It is preferable to use the traditional relationship when the budget is limited
C. The owner has high risk
D. The success of the project depends on the experience of the construction manger
E. No guarantee by the construction manager neither for the total cost nor for the quality
AEPM 4 52
2) PROFESSIONAL CM:
• CM treats the project planning
design
construction phases
as integrated tasks
• This approach unites & tree-party team consisting of
Owner, Designer and CM in a non-adversary relationship.
• It provides the owner with an opportunity to participate fully
in the construction process.
• The team works together from the beginning of
Design to project completion, with the common
objective of best serving the Owner’s interests.
PROJECT (PROGRAM) MANAGEMENT:
PM serves as
The single point of contact to the owner
to coordinate and manage
the various other parties involved in
planning, design, procurement and construction.
Difference bet. PM & CM
- PM is THE party that contacts the Owner
- Ther Owner is not really a team member
• Task force is favorable
• Coordination (more than one project)
• Developed to other industries
Program Management
Program management (sometimes called project
management) is an emerging concept being used on some
of the very largest projects.
Program management services may include no design or
direct construction but the program manager could handle
overall management of a number of individual projects
related to an overall program.
Program management has been applied on several major
projects where the owner has participated heavily in
managing the program in an integrated program
management team utilizing owner top management
personnel and management and specialized personnel