Chapter 17: Learning Objectives You should be able to: 1. Discuss the behavioral aspects of projects in terms of project personnel and the project manager 2. Explain the nature and importance of a work breakdown structure in project management 3. Give a general description of PERT/CPM techniques 4. Construct simple network diagrams 5. List the kinds of information that a PERT or CPM analysis can provide 6. Analyze networks with deterministic times 7. Analyze networks with probabilistic times 8. Describe activity ‘crashing’ and solve typical problems 17-1
Chapter 17: Learning Objectives. You should be able to: Discuss the behavioral aspects of projects in terms of project personnel and the project manager Explain the nature and importance of a work breakdown structure in project management Give a general description of PERT/CPM techniques - PowerPoint PPT Presentation
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Chapter 17: Learning ObjectivesYou should be able to:
1. Discuss the behavioral aspects of projects in terms of project personnel and the project manager
2. Explain the nature and importance of a work breakdown structure in project management
3. Give a general description of PERT/CPM techniques4. Construct simple network diagrams5. List the kinds of information that a PERT or CPM analysis can
provide6. Analyze networks with deterministic times7. Analyze networks with probabilistic times8. Describe activity ‘crashing’ and solve typical problems
17-1
ProjectsProjects
Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame
Examples:The Olympic GamesProducing a movieSoftware developmentProduct developmentERP implementation
17-2
Project Life Cycle
17-3
Work Breakdown Structure (WBS)WBS
A hierarchical listing of what must be done during a projectEstablishes a logical framework for identifying the
required activities for the project1. Identify the major elements of the project2. Identify the major supporting activities for each
of the major elements3. Break down each major supporting activity into a
list of the activities that will be needed to accomplish it
17-4
WBS
17-5
Gantt Chart
17-6
PERT and CPMPERT (program evaluation and review
technique) and CPM (critical path method) are two techniques used to manage large-scale projects
By using PERT or CPM Managers can obtain:1. A graphical display of project activities2. An estimate of how long the project will take3. An indication of which activities are most critical to
timely project completion4. An indication of how long any activity can be delayed
without delaying the project
17-7
Network DiagramNetwork diagram
Diagram of project activities that shows sequential relationships by use of arrows and nodes
Activity on arrow (AOA)Network diagram convention in which arrows designate
activities Activity on node (AON)
Network convention in which nodes designate activities Activities
Project steps that consume resources and/or time Events
The starting and finishing of activities
17-8
AON ConventionActivity on Activity Meaning Node (AON)
A comes before B, which comes before C.(a) A B C
A and B must both be completed before C can start.(b)
AC
B
B and C cannot begin until A is completed.(c)B
AC 17-9
Activity on Activity Meaning Node (AON)
C and D cannot begin until both A and B are completed.(d)
A
B
C
D
C cannot begin until both A and B are completed; D cannot begin until B is completed. A dummy activity is introduced in AOA.
(e)A
B
C
D
AON Convention
17-10
B and C cannot begin until A is completed. D cannot begin until both B and C are completed. A dummy activity is again introduced in AOA.
(f)A
C
DB
Activity on Activity Meaning Node (AON)
AON Convention
17-11
AON Example
Activity DescriptionImmediate
PredecessorsA Build internal components —B Modify roof and floor —C Construct collection stack AD Pour concrete and install frame A, BE Build high-temperature burner CF Install pollution control system CG Install air pollution device D, EH Inspect and test F, G
Project Activities and Predecessors
17-12
A
Start
BStart Activity
Activity A(Build Internal Components)
Activity B(Modify Roof and Floor)
AON Network
17-13
C
D
A
Start
B
Activity A Precedes Activity C
Activities A and B Precede Activity D
AON Network
17-14
G
E
F
H
CA
Start
DB
Arrows Show Precedence Relationships
AON Network
17-15
Deterministic Time EstimatesDeterministic
Time estimates that are fairly certainProbabilistic
Time estimates that allow for variation
17-16
Determining Project Duration
Activity Description Time (weeks)A Build internal components 2B Modify roof and floor 3C Construct collection stack 2D Pour concrete and install frame 4E Build high-temperature burner 4F Install pollution control system 3G Install air pollution device 5H Inspect and test 2
Early Start, Early FinishFinding ES and EF involves a forward pass
through the network diagram Early start (ES)
The earliest time an activity can startAssumes all preceding activities start as early as possible
For nodes with one entering arrow ES = EF of the entering arrow
For activities leaving nodes with multiple entering arrows ES = the largest of the largest entering EF
Early finish (EF)The earliest time an activity can finish
EF = ES + t
17-19
Late Start, Late FinishFinding LS and LF involves a backward pass
through the network diagram Late Start (LS)
The latest time the activity can start and not delay the project The latest starting time for each activity is equal to its latest finishing
time minus its expected duration: LS = LF - t
Late Finish (LF)The latest time the activity can finish and not delay the project
For nodes with one leaving arrow, LF for nodes entering that node equals the LS of the leaving arrow
For nodes with multiple leaving arrows, LF for arrows entering node equals the smallest of the leaving arrows
17-20
Slack and the Critical PathSlack can be computed one of two ways:
Slack = LS – ESSlack = LF – EF
Critical pathThe critical path is indicated by the activities
with zero slack
17-21
Determining the Project Schedule
Perform a Critical Path Analysis
A
Activity Name or Symbol
Earliest Start ES
Earliest FinishEF
Latest Start
LS Latest Finish
LF
Activity Duration
2
17-22
Forward PassBegin at starting event and work forward
Earliest Start Time Rule:
If an activity has only a single immediate predecessor, its ES equals the EF of the predecessor
If an activity has multiple immediate predecessors, its ES is the maximum of all the EF values of its predecessors
ES = Max {EF of all immediate predecessors}
17-23
Forward Pass
Begin at starting event and work forwardEarliest Finish Time Rule:
The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) and its activity time
EF = ES + Activity time
17-24
Start
0
0
ES
0
EF = ES + Activity time
Forward Pass
17-25
Start0
0
0
A
2
2
EF of A = ES of A + 2
0
ESof A
Forward Pass
17-26
B
3
Start0
0
0
A
2
20
3
EF of B = ES of B + 3
0
ESof B
Forward Pass
17-27
C
2
2 4
B
3
0 3
Start0
0
0
A
2
20
Forward Pass
17-28
C
2
2 4
B
3
0 3
Start0
0
0
A
2
20
D
4
73= Max (2, 3)
Forward Pass
17-29
D
4
3 7
C
2
2 4
B
3
0 3
Start0
0
0
A
2
20
Forward Pass
17-30
E
4
F
3
G
5
H
2
4 8 13 15
4
8 13
7
D
4
3 7
C
2
2 4
B
3
0 3
Start0
0
0
A
2
20
Forward Pass
17-31
Backward Pass
Begin with the last event and work backwards
Latest Finish Time Rule:
If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it
If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it
LF = Min {LS of all immediate following activities}17-32
Backward Pass
Begin with the last event and work backwards
Latest Start Time Rule:
The latest start time (LS) of an activity is the difference of its latest finish time (LF) and its activity time
LS = LF – Activity time
17-33
E
4
F
3
G
5
H
2
4 8 13 15
4
8 13
7
D
4
3 7
C
2
2 4
B
3
0 3
Start0
0
0
A
2
20
LF = EF of Project
1513
LS = LF – Activity time
Backward Pass
17-34
E
4
F
3
G
5
H
2
4 8 13 15
4
8 13
7
13 15
D
4
3 7
C
2
2 4
B
3
0 3
Start0
0
0
A
2
20
LF = Min(LS of following activity)
10 13
Backward Pass
17-35
E
4
F
3
G
5
H
2
4 8 13 15
4
8 13
7
13 15
10 13
8 13
4 8
D
4
3 7
C
2
2 4
B
3
0 3
Start0
0
0
A
2
20
LF = Min(4, 10)
42
Backward Pass
17-36
E
4
F
3
G
5
H
2
4 8 13 15
4
8 13
7
13 15
10 13
8 13
4 8
D
4
3 7
C
2
2 4
B
3
0 3
Start0
0
0
A
2
20
42
84
20
41
00
Backward Pass
17-37
Computing Slack Time
After computing the ES, EF, LS, and LF times for all activities, compute the slack or free time for each activity
Slack is the length of time an activity can be delayed without delaying the entire project
= 112/36 = 3.1111Standard deviation of critical pathp = Variance of critical path
= 3.1111 = 1.7638 weeks
p
Computing Variance
17-49
Probability of Project Completion
Note:
Total project completion times follow a normal probability distribution
Activity times are statistically independent
17-50
Probability of Project Completion
Standard deviation = 1.7638 weeks
15 Weeks
(Expected Completion Time)
17-51
Probability of Project CompletionWhat is the probability this project can be completed on or before the 16 week deadline?
Z = TM = Path mean completion time
T = Due date
Z = (16 – 15)/1.7638
= 0.57
Where Z is the number of standard
deviations the due date or target date lies from the mean or expected
date
p
MT - T
17-52
Probability of Project Completion
Time
Probability(T ≤ 16 weeks)is 0.7157
0.57 Standard deviations
15 16Weeks Weeks
Probability(T > 16 weeks)is 1 – 0.7157 = 0.2843
17-53
Project Completion for given confidenceDetermine a due date for the project completion time that will have a 99% probability of meeting.
Due date = TE + Z p
17-54
Determining Project Completion Time
Probability of 0.01
ZFrom Appendix I
Probability of 0.99
2.325 Standard deviations
0 2.325
17-55
Determining Project Completion Time
Probability of 0.01
ZFrom Appendix I
Probability of 0.99
2.325 Standard deviations
0 2.325
Due date (T) = TM + z p
17-56
Determining Project Completion Time
Probability of 0.01
ZFrom Appendix I
Probability of 0.99
2.325 Standard deviations
0 2.325
Due date (T) = 15 + 2.325 (1.7638)
17-57
Determining Project Completion Time
Probability of 0.01
ZFrom Appendix I
Probability of 0.99
2.325 Standard deviations
0 2.325
Due date (T) = 19.1 weeks
17-58
Variability of Completion Time for Noncritical Paths
Variability of times for activities on noncritical paths must be considered when finding the probability of finishing in a specified time
Variation in noncritical activity may cause change in critical path
17-59
What Project Management Has Provided So Far1. The project’s expected
completion time is 15 weeks2. There is a 71.57% chance the
equipment will be in place by the 16 week deadline
3. Five activities (A, C, E, G, and H) are on the critical path
4. Three activities (B, D, F) are not on the critical path and have slack time
5. A detailed schedule is available17-60
Budget ControlBudget control is an important aspect of
project managementCosts can exceed budget
Overly optimistic time estimatesUnforeseen events
Unless corrective action is taken, serious cost overruns can occur
17-61
Time-Cost Trade-OffsActivity time estimates are made for some
given level of resourcesIt may be possible to reduce the duration of
a project by injecting additional resources Motivations:
To avoid late penaltiesMonetary incentivesFree resources for use on other projects
17-62
Time-Cost Trade-Offs: CrashingCrashing
Shortening activity durationsTypically, involves the use of additional funds to support
additional personnel or more efficient equipment, and the relaxing of some work specifications
The project duration may be shortened by increasing direct expenses, thereby realizing savings in indirect project costs
17-63
Crashing DecisionsTo make decisions concerning crashing requires
information about:1. Regular time and crash time estimates for each
activity2. Regular cost and crash cost estimates for each activity3. A list of activities that are on the critical path
Critical path activities are potential candidates for crashingCrashing non-critical path activities would not have an impact
on overall project duration
17-64
Crashing: ProcedureGeneral procedure:
1. Crash the project one period at a time2. Crash the least expensive activity that is on the
critical path3. When there are multiple critical paths, find the sum of
crashing the least expensive activity on each critical path
If two or more critical paths share common activities, compare the least expensive cost of crashing a common activity shared by critical paths with the sum for the separate critical paths
17-65
Crashing Activities
17-66
PERT: AdvantagesAmong the most useful features of
PERT:1.It forces the manager to organize and quantify
available information and to identify where additional information is needed
2.It provides the a graphic display of the project and its major activities
3.It identifiesa. Activities that should be closely watchedb. Activities that have slack time
17-67
Sources of ErrorPotential sources of error:
1. The project network may be incomplete2. Precedence relationships may not be correctly
expressed3. Time estimates may be inaccurate4. There may be a tendency to focus on critical path
activities to the exclusion of other important project activities
5. Major risk events may not be on the critical path
17-68
Project Management SoftwareTechnology has benefited project management
CADTo produce updated prototypes on construction and product-
development projects Communication software
Helps to keep project members in close contactFacilitates remote viewing of projects
Project management softwareSpecialized software used to help manage projects
Assign resources Compare project plan versions Evaluate changes Track performance
17-69
Project Management Software Advantages
Advantages include: Imposes a methodology and common project
management terminology Provides a logical planning structure May enhance communication among team members Can flag the occurrence of constraint violations Automatically formats reports Can generate multiple levels of summary and detail
reports Enables “what if” scenarios Can generate a variety of chart types
17-70
Risk ManagementRisks are an inherent part of project management
Risks relate to occurrence of events that have undesirable consequences such asDelays Increased costs Inability to meet technical specifications
Good risk management involves Identifying as many risks as possibleAnalyzing and assessing those risksWorking to minimize the probability of their occurrenceEstablishing contingency plans and budgets for dealing with
any that do occur
17-71
Operations Strategy Projects present both strategic opportunities and risks
It is critical to devote sufficient resources and attention to projects Projects are often employed in situations that are characterized by
significant uncertainties that demandCareful planningWise selection of project manager and teamMonitoring of the project
Project software can facilitate successful project completionBe careful to not focus on critical path activities
to the exclusion of other activities that may become critical
It is not uncommon for projects to fail When that happens, it can be beneficial to examine the probable