Chapter 14 – Resource Planning

Operations Managementby

R. Dan Reid & Nada R. Sanders3rd Edition © Wiley 2007

PowerPoint Presentation by R.B. Clough - UNH

Page 2: Chapter 14

Enterprise Resource Planning (ERP)

What Is ERP? Software designed for organizing and

managing business processes Modules share information across all

business functions Can share customer sales data with the

supply chain to help with global replenishment

All modules are fully integrated and use a common database – some PC based

Page 3: Chapter 14

Integration of ERP

Page 4: Chapter 14

ERP Modules-4 Categories Finance and accounting

Investment, cost, asset, capital, and debt management

Budgets, profitability analysis, and performance reports

Sales and marketing Handles pricing, availability, orders, shipments, &

billing Production and materials management

Process planning, BOM, product costing, ECN’s, MRP, allocates resources, schedules, PO’s, & inventory

Human resources Workforce planning, payroll & benefits, & org.

charts

Page 5: Chapter 14

Evolution of ERP First generation ERP

Managed all internal business activities Second Generation ERP

Late 1990’s software integrated supply chains Systems focused on decision-making SCM (supply chain management) modules

include LP and simulation support SCI (supply chain intelligence) capability allows

collection of intelligence along the entire supply chain

ASP (application service provider) suppliers set-up and run systems for others

Page 6: Chapter 14

Integrating ERP and E-Commerce

Many companies with ERP use e-commerce E-commerce needs to interface with ERP Cybex International is a good example:

Needed to integrate B2C and B2B transactions Cybex installed a Peoplesoft, Inc. ERP system Reduced BOM’s (bill of materials) from 15,200 to

200, suppliers from 1000 to 550, paperwork by 2/3

Reduced supplier material shortages and customer order-to-ship time from 4 to 2 weeks

Page 7: Chapter 14

Benefits of ERP Implementation

ERP presents a holistic view of the business functions from a single information and IT architecture

Increases organizational information flow Increases ability to incorporate better management

control, speedier decision making, and cost reductions

Allows replacement of disparate systems e.g. ExxonMobile used ERP to replace 300 different

systems A study of ERP implementations reports that benefits

typically start 8 months after implementation with median annual savings of $1.6 million

Page 8: Chapter 14

Cost and Implementation Issues

Major suppliers are SAP, Peoplesoft, Oracle, and Baan. Also smaller PC based suppliers.

Costs for larger ERP systems range from hundreds of thousands to several million dollars.

Outside consultants are usually involved in selection, configuration, and implementation.

Consultant costs can run up to 3 times the cost of the system itself according to a Gartner Group study.

Added costs also include additional people, new computer hardware, and the cost to develop a new, integrated database

Successful implementation requires leadership and top management commitment to a vision for the business

Page 9: Chapter 14

Evolution of Material Planning Systems

Back in the sixties, manufacturing planning systems were reorder point systems that simply determined when and how much to order

First MRP systems translated a master schedule of final products into time-phased net requirements for subassemblies, assemblies, and parts

Closed-loop MRP included production planning, master scheduling, and capacity requirements

In mid 1970’s, MRPII systems added functionality to plan and execute all internal functions

Page 10: Chapter 14

Material Requirements Planning (MRP)

Computer-based information system that schedules and orders dependent-demand inventory components;

Uses the master production schedule, bills of materials, and inventory records as inputs;

Outputs recommendations: When to release new orders. When to reschedule open orders.

Page 11: Chapter 14

An Overview of MRP MRP uses the concept of backward scheduling to

determine how much and when to order and replenish

The CPR module checks to make sure the scheduled work load profile is feasible

The MPS module contains the authorized schedule The BOM module contains the product structure for

each unique product The Inventory Record module keeps track of the

inventory status for each item in the database MRP output includes schedules for all internal

activities and parts as well as orders for all supply chain items

Page 12: Chapter 14

MRP System

Page 13: Chapter 14

Input/Output - MRP Process

Page 14: Chapter 14

Types of Demand There are two types of demand. Independent Demand

Is the demand for finished products Does not depend on the demand of other

products Needs to be forecasted

Dependent Demand Is the demand derived from finished products Is the demand for component parts based on

the number of end items being produced and is managed by the MRP system

Page 15: Chapter 14

MRP Responds to the fundamental

manufacturing equation: What are we going to make?

Master production schedule. What does it take to make it?

Bill of materials. What have we got?

Inventory records. What do we have to get?

Material Requirements plan: planned orders.

Page 16: Chapter 14

Objectives of MRP Determines the quantity and timing

of material requirements Determines what to order (checks BOM),

how much to order (lot size rules), when to place the order (needed date minus lead time), and when to schedule delivery (on date needed)

Maintain priorities In a changing environment, MRP

reorganizes priorities to keep plans current and viable

Page 17: Chapter 14

Building a CD Cabinet With MRP

Page 18: Chapter 14

Definitions End item:

The product sold as a completed item or repair part (an independently demanded item)

Parent items: Items produced from one or more

“children” Components:

Raw materials & other items (“children”) that are part of a larger assembly

Page 19: Chapter 14

MRP Inputs - Authorized MPS

From the authorized MPS, we calculate when we need to have replenishment orders of CD cabinets; when we need a new MPS order.

Table 14-1 Initial MPS Record for CD CabinetItem: CD CabinetLot size rule: FOQ=100Lead time: 1 week

1 2 3 4 5 6 7 8 9 10 11 12Gross Requirements: 25 25 25 25 30 30 30 30 35 35 35 35Projected Available: 80 55 30 5 -20MPS

Table 14-2 Updated MPS Record for CD CabinetItem: CD CabinetLot size rule: FOQ=100Lead time: 1 week

1 2 3 4 5 6 7 8 9 10 11 12Gross Requirements: 25 25 25 25 30 30 30 30 35 35 35 35Projected Available: 80 55 30 5 80 50 20 90 60 25 90 55 20MPS 100 100 100

Page 20: Chapter 14

MRP Inputs-Inventory Records

System checks the inventory record for each BOM item to see if inventory is available or if a replenishment order is needed to build the cabinets.

Table 14-3 First Inventory Record for CD CabinetItem: CD CabinetLot size rule: L4LLead time: 1 week

1 2 3 4 5 6 7 8 9 10 11 12Gross Requirements: 0 0 0 100 0 0 100 0 0 100 0 0Scheduled Receipts:Projected Available: 0 0 0 0 -100Planned Orders

Table 14-4 Updated Inventory Record for CD CabinetItem: CD CabinetLot size rule: L4LLead time: 1 week

1 2 3 4 5 6 7 8 9 10 11 12Gross Requirements: 0 0 0 100 0 0 100 0 0 100 0 0Scheduled Receipts:Projected Available: 0 0 0 0 0 0 0 0 0 0 0 0 0Planned Orders 100 100 100

Page 21: Chapter 14

Bill of Materials (BOM) Contains product description

(components) and sequence of assembly.

Also called product structure or product tree.

Levels: end item at 0, assemblies for end item at 1, subassemblies for assemblies at 2, etc.

Low-level coding: placing identical items used for multiple purposes at the same level.

Page 22: Chapter 14

MRP Inputs-Bills of Material

A BOM lists all of the items needed to produce one CD cabinet

The BOM is exactly like a recipe for baking a cake

The BOM’s must be complete and accurate and can only be changed by an ECN

MRP BOM’s are indented bills of materials

Page 23: Chapter 14

A Product Structure Tree

Page 24: Chapter 14

Inventory Records Contains

information about each inventory item and its status (e.g., on-hand balance).

Page 25: Chapter 14

Inventory Record Gross requirements:

The total period demand for the item Scheduled receipts:

An open order with an assigned due date Projected available:

The projected inventory balance for the period Planned orders:

Quantities & released dates suggested by the MRP system

Page 26: Chapter 14

Lot Sizing Rules Rules are used to change the

frequency of replenishment orders & set the quantity of each order (balance holding & ordering costs to reduce total costs)

Common rules: Fixed Order Quantity (FOQ) Lot-for-Lot (L4L) Periodic Order Quantity (POQ)

Page 27: Chapter 14

MRP Record Processing Period 1 2 3 4 5 6

Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Lead time = [# periods] Lot size = [order quantity] Safety stock = [quantity]

Gross requirements: anticipated future usage of (or demand for) the item during each period. Scheduled receipts: existing replenishment orders due in at the beginning of the period. Projected on hand: projected inventory status for the item at the beginning of each period. Net requirements: Gross Requirements minus Scheduled Receipts minus Projected on hand. Planned order receipt: planned receipt of replenishment orders at the beginning of the period. Planned order release: release of planned replenishment orders for the item using lead-time offset.

Page 28: Chapter 14

MRP Terms Time bucket: period, usually 1 week. Planning horizon: number of periods. Lead time offset: offsets a planned

order release from a required replenishment.

Net requirement: difference between the gross requirements and the available inventory.

Page 29: Chapter 14

Definitions Time buckets:

The column in an inventory record that represents a unit of time

Action bucket: The current time period

Action notices: Output from the MRP system identifying

the need for an action (e.g.: expedite or delay an order or receipt)

Page 30: Chapter 14

Example

Inventory Record for Pie Safe

Item: Pie SafeLot size rule: L4LLead time: 1 week

0 1 2 3 4 5 6 7 8 9 10 11 12

Gross requirements 0 0 0 100 0 0 100 0 0 100 0 0

Scheduled receipts 100 100 100

Projected available 0 0 0 0 0 0 0 0 0 0 0 0 0

Planned orders 100 100 100

A Time Bucket

Page 31: Chapter 14

Operating Logic Explosion:

Calculate the children’s time-phased gross requirements by multiplying the parent item’s planned order amount by the number of children required to produce one parent item

Page 32: Chapter 14

The MRP Explosion Process

Using table 14-6 and the product structure tree, we will work through an example of how the MRP explosion process would calculate the requirements for building a CD cabinet. On the next slide we start with the cabinet top to illustrate how MRP calculates the gross requirements for this component.

Table 14-6 Updated Inventory Record for CD CabinetItem: CD Cabinet Parent: noneLot size rule: L4L Children: Top, bottom, door, left side, right side, shelves, shelf supportsLead time: 1 week

1 2 3 4 5 6 7 8 9 10 11 12Gross Requirements: 0 0 0 100 0 0 100 0 0 100 0 0Scheduled Receipts:Projected Available: 0 0 0 0 0 0 0 0 0 0 0 0 0Planned Orders: 100 100 100

Page 33: Chapter 14

Inventory Records - Components

It was noted on the previous slide that the parent item (CD Cabinet) has planned orders in periods 3, 6, and 9.

Its children (top, bottom, door, left & right side, shelves, and supports) have gross requirements in periods 3, 6, and 9.

Page 34: Chapter 14

Inventory Records - Components

Page 35: Chapter 14

Inventory Records– Components (cont.)

Page 36: Chapter 14

Inventory Records– Components (cont.)

Page 37: Chapter 14

Inventory Records – Remaining Components

Page 38: Chapter 14

Inv. Records – Remaining Components (cont.)

Page 39: Chapter 14

Inv. Records – Remaining Components (cont.)

Page 40: Chapter 14

MRP System—Other Issues Safety stock? Lot size?

Lot-for-lot (L4L or LFL): lot size matches net requirements.

Economic order quantity (EOQ): lot size calculated like in Chapter 12.

Least total cost (LTC): calculates a lot size that equalizes holding and ordering costs.

Least unit cost (LUC): averages the LTC across the lot size.

Page 41: Chapter 14

Example Comparing Lot Size Rules: Three common lot sizing rules used within MRP Systems are fixed order quantity (FOQ), lot for lot (L4L), and period order quantity (POQ). Cost comparison is based on Inventory holding costs ($0.10 per period) and ordering cost ($25 per order). In this example POQ is best at $133.50.

Page 42: Chapter 14

Capacity RequirementsPlanning (CRP)

Similar to rough cut capacity planning

CRP is a feasibility check on labor & machine utilization: Compare the open orders & planned

orders (from the MRP) to the actual shop floor capacity

Page 43: Chapter 14

Rough Cut Capacity Example: The CRP module uses data from MRP. We calculate workloads for critical work centers based on open shop orders and planned shop orders. These shop orders are translated into hours of work by work center and by time period.Table 14-11 show items scheduled for work Center 101.

Available = 4 machines x 2 shifts x 10 hours x 5 days x 0.85 utiliza- x 0.95 effi- Capacity per shift per wk. tion ciency Available = 323.0 standard hours Capacity

123456789

1011121314151617

A B C D E F GTable 14-11 Workload for Work Center 101

Run Time Total Setup per Unit in Item Weekly

Item Time Standard Time WorkloadPeriod Number Quantity (hours) Hours (hours) (hours)

4 DN100 250 3.0 0.20 53.0DP100 250 5.0 0.18 50.0DS119 150 2.5 0.30 47.5DT136 400 3.5 0.27 111.5 262.0

5 EQ555 1000 8.0 0.08 88.0ER616 500 4.0 0.22 114.0ES871 100 2.0 0.35 37.0 239.0

6 FA314 250 3.0 0.30 78.0FF369 100 1.5 0.12 13.5FR766 50 0.5 0.15 8.0FS119 200 3.0 0.35 73.0FY486 500 6.0 0.27 141.0 313.5

Page 44: Chapter 14

Workload Graph for Work Center 101: CRP enables a company to evaluate both the feasibility of the MRP system and how well the company is using its critical work centers.

Page 45: Chapter 14

Chapter 14 Highlights ERP is software designed for organizing and

managing all business processes by sharing information across functional areas using a common database and a single computer system.

First generation ERP systems (MPR) managed manufacturing activities only. Second generation systems or SCM –software incorporated the supply chain. The current trend is integrating e-commerce and ERP.

Tangible benefits from ERP include control of operations and a host of information to manage all financial aspects of a business. Systems can be very expensive.

Page 46: Chapter 14

Chapter 14 Highlights (cont.)

MRP systems are designed to calculate material requirements from dependent demand items. MRP uses backward scheduling to determine activity start dates.

The objective of MRP are to determine quantity and timing of material requirements to keep schedule priorities updated and valid.

MRP needs three inputs: the authorized MPS, the BOM file, and the inventory records file.

Once the MPS has been input, MRP checks inventory availability. If a need is determined, MRP checks the BOM file for material needed, then generates planned orders.

Page 47: Chapter 14

Chapter 14 Highlights (cont.)

MRP output includes actions notices to release planned orders, reschedule orders, or adjust due dates.

Different lot sizing rules (FOQ, Period Q, L4L) generate different order quantities and order frequencies.

The CPR module uses planned orders and open shop orders to see if available capacity is sufficient to meet schedules.

CPR calculates the workloads at critical work centers by using planned orders generated by MRP. These planned orders are multiplied by the standard times to calculate individual work center loads.

Page 48: Chapter 14

Homework Hints Problems 14.1-3, 3sp. Use the data given to:

1. prepare a product structure tree.2. determine the product lead time.3. calculate gross requirements, starting with 100 units of

the end item (Q).3sp. do an MRP chart—using either the excel or word chart

given on the website. Assume gross requirements for Q is in period 9; assume L4L is to be used for all components.

Problems 14.23-24. Do a CRP:23. Calculate the required capacity (based on each job’s set

up and run times).24. Calculate the available capacity (based on available time

for three machines adjusted for utilization and efficiency). Determine the match between required capacity (14.23) and available capacity (14.24).