Chapter 10 Pricing Excavation and Backfill
Dec 17, 2015
Chapter 10
Pricing Excavation and Backfill
Objectives• Upon completion of this chapter, you
will be able to:– Describe the job factors and the labor
and management factors that influence the price of excavation and backfill operations
– Use historic productivity rates to calculate the unit price of labor and equipment for excavation and backfill work
Objectives (cont’d.)– Calculate the price of gravels and other
backfill materials– Calculate trucking requirements for
hauling excavated material and gravels– Complete the recap and pricing of
excavation and backfill work using manual methods
– Use Excel spreadsheets to price excavation and backfill work
Excavation Equipment and Methods
• Specialized excavation contractors– Concentrate on a single construction
type:• Vast array of excavation equipment• Wide scope of work
– Common activities:• Site cut and fill operations• Basement-type excavations• Trench excavations• Pit and sump excavations
Excavation Equipment and Methods (cont’d.)
• Equipment transportation expenses:– Priced on an item-by-item basis
• Site cut and fill operations:– Equipment depends on project scale
• Basement excavations:– Often performed with a track backhoe– Large basements: one or more track
loaders
• Trench excavations:– Smaller trenches: trenching machines– Larger trenches: backhoes
• Pit and sump excavations:– Mostly performed using backhoes
• Hand excavation:– Rarely used
Excavation Equipment and Methods (cont’d.)
Excavation Productivity• Job factors:
– Type of material excavated or backfilled– Moisture condition of materials– Weather conditions expected– Site access and project size/complexity– Distance to haul materials for disposal– Availability of gravels and fill materials– Wage and price levels at the job location
Excavation Productivity (cont’d.)• Labor and management factors
– Quality of job supervision– Quality of job labor– Motivation and morale of workers– Type and quality of tools and
equipment– Experience and records of similar
past projects
Excavation Work Crews• Labor price per unit of excavation
work– Elements to consider:
• Number of workers that comprise the work crew and their trades
• Wage rates of trades involved• Probable productivity rate of crew or
equipment they are operating• Productivity time factor
Productivity Rates• Sources:
– Provided in publications (e.g., Means Building Construction Cost Data)• Use with caution: general reflect ideal
conditions
– Also available from manufacturers– May be compiled from contractor’s
own projects
Figure 10.3 Productivity of Hydraulic Excavators (Delmar/Cengage Learning)
Figure 10.4 Sample Data Record (Delmar/Cengage Learning)
Excavation Materials• Mostly comprise gravels and fill
materials: – Required to meet designer’s
specifications • Backfilling • Base courses under slabs and paving
• Pricing components:– Supplying material to the site– Spreading and compacting
Swell and Compaction Factors
• Excavated soil or gravel:– Less dense
• Swell factor: – Occupies more volume
• Compaction factor: – Allowance for extra material required
to fill volumes with compacted material
Calculating Trucking Requirements
• Determine optimum number of trucks required to transport materials– Formula:
• Number of Trucks Required = Unloading Time/ Loading Time + One
– Example: Gravel Supply Pricing • Refer to Pages 234 and 235
Additional Examples• Excavation and Backfill Recap and
Pricing Notes – Example 1—House
• Refer to Pages 235 through 240
• Excavation and Backfill Pricing Notes– Example 2—Office/Warehouse Building
• Refer to Pages 240 through 244
Summary• Many subcontractors perform
excavation and backfill work– Most specialize in some aspect
• Common methods:– Site cut and fill operations– Basement-type excavations– Trench excavations– Pit and sump excavations