Top Banner
PowerPoint Presentation by Charlie Cook PowerPoint Presentation by Charlie Cook Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition P ro ject M a n a g em en t P ro ject M a n a g em en t Chapter 9 Chapter 9 Reducing Project Duration Reducing Project Duration
20
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Chapter 09

PowerPoint Presentation by Charlie CookPowerPoint Presentation by Charlie CookCopyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved.

THE MANAGERIAL PROCESSTHE MANAGERIAL PROCESS Clifford F. GrayEric W. Larson

Third Edition

Clifford F. GrayEric W. Larson

Third Edition

Pr ojec t ManagementPr ojec t Management

Chapter 9Chapter 9

Reducing Project DurationReducing Project Duration

Page 2: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––22

Page 3: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––33

Rationale for Reducing Project DurationRationale for Reducing Project DurationRationale for Reducing Project DurationRationale for Reducing Project Duration

• Time Is Money: Cost-Time Tradeoffs–Reducing the time of a critical activity usually incurs

additional direct costs.•Cost-time solutions focus on reducing (crashing)

activities on the critical path to shorten overall duration of the project.

–Reasons for imposed project duration dates:•Customer requirements and contract commitments

•Time-to-market pressures

• Incentive contracts (bonuses for early completion)

•Unforeseen delays

•Overhead and goodwill costs

•Pressure to move resources to other projects

Page 4: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––44

Options for Accelerating Project CompletionOptions for Accelerating Project CompletionOptions for Accelerating Project CompletionOptions for Accelerating Project Completion

• Adding Resources

• Outsourcing Project Work

• Scheduling Overtime

• Establishing a Core Project Team

• Do It Twice—Fast and Correctly

• Fast-Tracking

• Critical-Chain

• Reducing Project Scope

• Compromise Quality

Page 5: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––55

Explanation of Project CostsExplanation of Project CostsExplanation of Project CostsExplanation of Project Costs

• Project Indirect Costs–Costs that cannot be associated with any particular

work package or project activity.•Supervision, administration, consultants, and interest

–Costs that vary (increase) with time.•Reducing project time directly reduces indirect costs.

• Direct Costs–Normal costs that can be assigned directly to a

specific work package or project activity.•Labor, materials, equipment, and subcontractors

–Crashing activities increases direct costs.

Page 6: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––66

Reducing Project Duration to Reduce Reducing Project Duration to Reduce Project CostProject Cost

Reducing Project Duration to Reduce Reducing Project Duration to Reduce Project CostProject Cost

Compute total costs for specific durations and Compute total costs for specific durations and compare to benefits of reducing project time.compare to benefits of reducing project time.

Compute total costs for specific durations and Compute total costs for specific durations and compare to benefits of reducing project time.compare to benefits of reducing project time.

Search critical activities for lowest direct-cost Search critical activities for lowest direct-cost activities to shorten project duration.activities to shorten project duration.

Search critical activities for lowest direct-cost Search critical activities for lowest direct-cost activities to shorten project duration.activities to shorten project duration.

Identifying direct costs to reduce project timeIdentifying direct costs to reduce project timeIdentifying direct costs to reduce project timeIdentifying direct costs to reduce project time

Gather information about direct and indirect Gather information about direct and indirect costs of specific project durations. costs of specific project durations.

Gather information about direct and indirect Gather information about direct and indirect costs of specific project durations. costs of specific project durations.

Page 7: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––77

Project CostProject Cost—Duration Graph—Duration GraphProject CostProject Cost—Duration Graph—Duration Graph

FIGURE 9.1

Page 8: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––88

Constructing a Project CostConstructing a Project Cost—Duration Graph—Duration Graph Constructing a Project CostConstructing a Project Cost—Duration Graph—Duration Graph

• Find total direct costs for selected project durations.

• Find total indirect costs for selected project durations.

• Sum direct and indirect costs for these selected project durations.

• Compare additional cost alternatives for benefits.

Page 9: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––99

Constructing a Project Cost—Duration Graph Constructing a Project Cost—Duration Graph Constructing a Project Cost—Duration Graph Constructing a Project Cost—Duration Graph

• Determining Activities to Shorten–Shorten the activities with the smallest increase in cost

per unit of time.–Assumptions:

•The cost relationship is linear.

•Normal time assumes low-cost, efficient methods to complete the activity.

•Crash time represents a limit—the greatest time reduction possible under realistic conditions.

•Slope represents a constant cost per unit of time.

•All accelerations must occur within the normal and crash times.

Page 10: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––1010

Activity GraphActivity GraphActivity GraphActivity Graph

FIGURE 9.2

Page 11: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––1111

CostCost—Duration Trade-off Example—Duration Trade-off ExampleCostCost—Duration Trade-off Example—Duration Trade-off Example

FIGURE 9.3

Page 12: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––1212

CostCost—Duration Trade-off Example (cont’d)—Duration Trade-off Example (cont’d)CostCost—Duration Trade-off Example (cont’d)—Duration Trade-off Example (cont’d)

FIGURE 9.3 (cont’d)

Page 13: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––1313

CostCost—Duration Trade-off Example (cont’d)—Duration Trade-off Example (cont’d)CostCost—Duration Trade-off Example (cont’d)—Duration Trade-off Example (cont’d)

FIGURE 9.4 (cont’d)

Page 14: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––1414

CostCost—Duration Trade-off Example (cont’d)—Duration Trade-off Example (cont’d)CostCost—Duration Trade-off Example (cont’d)—Duration Trade-off Example (cont’d)

FIGURE 9.4 (cont’d)

Page 15: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––1515

CostCost—Duration Trade-off Example (cont’d)—Duration Trade-off Example (cont’d)CostCost—Duration Trade-off Example (cont’d)—Duration Trade-off Example (cont’d)

FIGURE 9.4 (cont’d)

Page 16: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––1616

Summary Costs by DurationSummary Costs by DurationSummary Costs by DurationSummary Costs by Duration

FIGURE 9.5

Page 17: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––1717

Project CostProject Cost—Duration Graph—Duration GraphProject CostProject Cost—Duration Graph—Duration Graph

FIGURE 9.6

Page 18: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––1818

Practical ConsiderationsPractical ConsiderationsPractical ConsiderationsPractical Considerations

• Using the Project Cost—Duration Graph

• Crash Times

• Linearity Assumption

• Choice of Activities to Crash Revisited

• Time Reduction Decisions and Sensitivity

Page 19: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––1919

What if Cost, Not Time is the Issue?What if Cost, Not Time is the Issue?What if Cost, Not Time is the Issue?What if Cost, Not Time is the Issue?

• Commonly Used Options for Cutting Costs

–Reduce project scope

–Have owner take on more responsibility

–Outsourcing project activities or even the entire project

–Brainstorming cost savings options

Page 20: Chapter 09

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 9McGraw-Hill/Irwin 9––2020

Key TermsKey TermsKey TermsKey Terms

Crash point

Crash time

Direct costs

Fast-tracking

Indirect costs

Outsourcing

Phase project delivery

Project cost–duration graph


Related Documents