Chapter 4 Statistical Process Control
47
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Chap_4__SPC

Chapter 4

Statistical Process Control

Page 2: Chap_4__SPC

§ 4.1 Introduction

Page 3: Chap_4__SPC

Weights of the cereal packets:

498 gms, 505 gms, 443 gms, 503 gms, 501 gms

Natural CauseAssignable cause

Page 4: Chap_4__SPC

Possible Factors behind Assignable Causes

• Man – Inexperience, fatigue, personal problem• Machine – Faulty machine, tool wear, aging

machine, broken tool• Materials – Defective raw materials supplied by

new supplier• Method – Work instruction• Measurement – Problem in the measuring

instrument itself• Environment - Temperature, humidity, sudden

power surge

Page 5: Chap_4__SPC

Definition of SPC

Statistical process control is a statistical method of separating variation resulting from special causes from variation resulting from natural causes to eliminate the special causes and to establish and maintain consistency in quality of products/services.

Page 6: Chap_4__SPC

Various SPC Tools• Pareto charts• Flow diagram• Cause and effect diagram• Histogram• Check sheet• Scatter diagram• Run chart

• Control chart

Page 7: Chap_4__SPC

Origin of SPC

Walter Shewhart – Father of SPC

-- The Economic Control of Quality of Manufactured Products (published in 1931)

VariableAttribute

Page 8: Chap_4__SPC

Types of Control Charts

x -b a r ch a rt M e d ia n ch a rt R ch a rt s ch a rt

V a ria b le C h a rts

p ch a rt n p ch a rt c ch a rt u ch a rt

A ttrib u te C h a rts

C o n tro l C h a rts

Page 9: Chap_4__SPC

Overall look of a Control Chart

Sample number

Uppercontrollimit

Centreline

Lowercontrollimit

1 2 3 4 5 6 7

Page 10: Chap_4__SPC

Overall Look of a Control Chart

(Cont’d)

Sample number

Uppercontrollimit

Centreline

Lowercontrollimit

1 2 3 4 5 6 7 8 9 10

О

Page 11: Chap_4__SPC

§4.2Variable Control Charts

Page 12: Chap_4__SPC

Examples of Variables

• Length• Weight• Time• Volume• Temperature• Density• Pressure• Energy• Force• velocity• voltage

Page 13: Chap_4__SPC

Specific Examples of Variables

• Time waiting for service

• Time to process insurance claims

• Time from order receipt to shipment

• Diameter of a piston

• Weight of fertilizer packets

• Volume of shampoo bottles

X-bar and R charts should be used together

Page 14: Chap_4__SPC

R chart

RDUCL

RDLCL

R

R

4

3

Page 15: Chap_4__SPC

For x-bar chart For R-chart

n A2 D3 D4

2 1.880 0 3.267

3 1.023 0 2.574

4 0.729 0 2.282

5 0.577 0 2.114

6 0.483 0 2.004

7 0.419 0.076 1.924

8 0.373 0.136 1.864

9 0.337 0.184 1.816

10 0.308 0.223 1.777

11 0.285 0.256 1.744

12 0.266 0.283 1.717

13 0.249 0.307 1.693

14 0.235 0.328 1.672

15 0.223 0.347 1.653

Page 16: Chap_4__SPC

Example Bukit Battery Corp. has recently been receiving

complaints from retailers that its 9-volt batteries are not lasting as long as other name brands. James West, head of the TQM program at West’s Austin plant, believes there is no problem because his batteries have had an average life of 50 hours, about 10% longer than competitor’s models. To raise the life time above this level would require a new level of technology not available to West. Nevertheless, he is concerned enough to set up hourly assembly line checks. He decides to take size-5 samples of 9-volt batteries for each of the next 10 hours to create the standards for control chart limits (see the following table):

Page 17: Chap_4__SPC

Bukit Battery data –Battery Lifetimes (in hours)

Sample

Hour 1 2 3 4 5

1 51 50 49 50 50

2 45 47 70 46 36

3 50 35 48 39 47

4 55 70 50 30 51

5 49 38 64 36 47

6 59 62 40 54 64

7 36 33 49 48 56

8 50 67 53 43 40

9 43 22 36 27 44

10 70 45 50 47 41

Is the manufacturing process under control?

Page 18: Chap_4__SPC

Bukit Battery data –Battery Lifetimes (in hours)

Sample

Hour 1 2 3 4 5 R

1 51 50 49 50 50 2

2 45 47 70 46 36 34

3 50 35 48 39 47 15

4 55 70 50 30 51 40

5 49 38 64 36 47 28

6 59 62 40 54 64 24

7 36 33 49 48 56 23

8 50 67 53 43 40 27

9 30 22 36 27 44 22

10 70 45 50 47 41 29

Page 19: Chap_4__SPC

1 1098765432

24.4

10

20

30

40

51.58

●●

Page 20: Chap_4__SPC

X-bar Chart

RAxUCL

RAxLCL

x

x

2

2

Page 21: Chap_4__SPC

Bukit Battery data –Battery Lifetimes (in hours)

Sample

Hour 1 2 3 4 5 R

1 51 50 49 50 50 50.0 2

2 45 47 70 46 36 48.8 34

3 50 35 48 39 47 43.8 15

4 55 70 50 30 51 51.2 40

5 49 38 64 36 47 46.8 28

6 59 62 40 54 64 55.8 24

7 36 33 49 48 56 44.4 23

8 50 67 53 43 40 50.6 27

9 30 22 36 27 44 31.8 22

10 70 45 50 47 41 50.6 29

x

Page 22: Chap_4__SPC

1 1098765432

47.38

33.30

40

50

60

61.46

Page 23: Chap_4__SPC

When can we say that a process is under control?

• There are no sample points that lie outside the control limits.

• Most of the points are clustered around the center line; not too many points close to the control limits.

• Approximately half of the sample points lie above the center line and approximately half of the points lie below the center line.

Page 24: Chap_4__SPC

Properties of Properties of NormalNormalDistributionDistribution

-3 -2 -1 +1 +2 +3Mean

68.26%95.44%99.74%

= Standard deviation

Page 25: Chap_4__SPC

Special cases

Page 26: Chap_4__SPC

Checklist of questions for out-of-control process

(i) Are there any differences in the measurement accuracy of the instruments used?

(ii) Are there differences in the methods used by different operators?

(iii) Does the environment affect the process?(iv) Is the process affected by tool-wear?

Page 27: Chap_4__SPC

Checklist of questions for out-of-control process (Cont’d)

(v) Were any untrained workers involved in the process?

(vi) Has there been any change in the source of the raw materials?

(vii) Is the process affected by operators’ fatigue?

(viii) Did samples come from different shifts, operators, or machines?

Page 28: Chap_4__SPC

• Revised control limit

• Sample size

• Sample number

Few Points for solving real world problems

Page 29: Chap_4__SPC

§4.3 Attribute Control Charts

Page 30: Chap_4__SPC

Defects and Defective

Defects are non-conformities in the products/services

A product or service is said to be defective if it has one or more than one defects.

Page 31: Chap_4__SPC

p chart

n

pppUCL

n

pppLCL

p

p

)1(3

)1(3

Page 32: Chap_4__SPC

Example

A quality engineer takes 20 samples of 100 transistors each from the output of an assembly line. Each transistor is tested and the number of defectives in each sample is recorded which are shown in the next slide.

Draw the p chart and conclude.

Page 33: Chap_4__SPC

Sample No.

Number of defectives

Sample No.

Number of defectives

1 3 11 9

2 2 12 1

3 1 13 3

4 4 14 3

5 0 15 4

6 2 16 5

7 0 17 3

8 5 18 3

9 1 19 1

10 2 20 6

Page 34: Chap_4__SPC

Sample No.

No. of Defectives

Percentage of

defectives

Sample No.

No. of Defectives

Percentage of

defectives

1 3 0.03 11 9 0.09

2 2 0.02 12 1 0.01

3 1 0.01 13 3 0.03

4 4 0.04 14 3 0.03

5 0 0.00 15 4 0.04

6 2 0.02 16 5 0.05

7 0 0.00 17 3 0.03

8 5 0.05 18 3 0.03

9 1 0.01 19 1 0.01

10 2 0.02 20 6 0.06

Page 35: Chap_4__SPC

0.0793

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 17 1816 2019

● ●

● ●

0.029

Page 36: Chap_4__SPC

C chart

ccUCL

ccLCL

c

c

3

3

Page 37: Chap_4__SPC

Example

Coils of synthetic rope are monitored for defects. Each coil contains 1,200 feet of rope. Eighteen rolls have been selected and the number of defects per roll is presented in the next slide. Identify an appropriate control chart and determine the chart’s control limits. Draw the control chart and conclude.

Page 38: Chap_4__SPC

Sample No.

Number of defects

Sample No.

Number of defects

1 1 10 2

2 3 11 1

3 4 12 4

4 2 13 3

5 4 14 0

6 2 15 5

7 0 16 4

8 3 17 2

9 2 18 3

Page 39: Chap_4__SPC

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 17 1816

● ●

1

2

3

4

5

6

7.24

2.5

Page 40: Chap_4__SPC

Start

Collect data. Determine sample size. Select 25 to 30 samples

After tabulating data compute the necessary measures

Compute the center line and control limits for the control chart using the appropriate formulas.

Draw the control chart and plot the sample data on it.

Are any data points outside the

Control limits?

The center line and control limits become permanent, and the control chart is used for monitoring the future behavior of the process.

Special causes are sought for out-of-control conditions and the out-of-control points are removed. New centerline and control limits are computed from the remaining points. The remaining points are plotted ob the new chart.

NoYes

End

Page 41: Chap_4__SPC

Control Chart SelectionQuality Characteristic

variable attribute

n>1?

n>=10 or computer?

x and MRno

yes

x and s

x and Rno

yes

defective defect

constant sample size?

p-chart withvariable samplesize

no

p ornp

yes constantsampling unit?

c u

yes no

Page 42: Chap_4__SPC

§4.4 Applications

Page 43: Chap_4__SPC

Quality Characteristics:

Selected Industries• Hospital: Timeliness and quickness of care, staff

responses to request, accuracy of lab test, cleanliness, checkout time.

• Grocery Store: Waiting time to check out, frequency of stockout items, cleanliness, customer complaints

• Airlines: Flight delays, lost luggage, check-in-time, flight attendant’s courtesy, cabin cleanliness.

• Fast Food Restaurant: Waiting time for service, customer complaints, cleanliness, order accuracy, employee courtesy

Page 44: Chap_4__SPC

1. KFC’s South Central division (Texas and Oklahoma) uses SPC to monitor service times in its drive-through windows. It uses x-bar and R charts.

2. Kurt Manufacturing Company (based in Minneapolis) produces precision machines.

SPC is used by machine operators to monitor their processes by measuring variability, reliability of the machines. SPC charts are displayed on the shop floor so that everybody can see it. If there is any problem in the production, then the operators are empowered to stop production and find out out the cause and remove it.

Page 45: Chap_4__SPC

3. P*I*E* Nationwide is America’s fourth largest trucking company.One part of the company’s quality progrom is to extensive use of SPC.

A p-chart was initially used to monitor the production of daily defective freight bills. This resulted in reduction in the error rate from 10% to 0.8% within one year and the subsequent reduction in inspection time increased productivity by 30%. It is also estimated that use of SPC results savings of $38,000 at a single trucking terminal.

Page 46: Chap_4__SPC

Motorola Malaysia Sdn. Bhd.