Top Banner

of 43

Chap017 Project Management

Apr 03, 2018

Download

Documents

aprian
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/28/2019 Chap017 Project Management

    1/43

    17-1 Project Management

    William J. Stevenson

    Operations Management

    8th edition

  • 7/28/2019 Chap017 Project Management

    2/43

    17-2 Project Management

    CHAPTER

    17

    ProjectManagement

    McGraw-Hill/Irwin

    Operations Management, Eighth Edition, by William J. StevensonCopyright 2005 by The McGraw-Hill Companies, Inc. All rights reserved.

  • 7/28/2019 Chap017 Project Management

    3/43

    17-3 Project Management

    Unique, one-time operations designed to accomplish

    a specific set of objectives in a limited time frame.

    Bui ld A

    A Done

    Bui ld B

    B Done

    Bui ld C

    C Done

    Bui ld D

    Ship

    JAN FEB MAR APR MAY JUN

    On time!

    Projects

  • 7/28/2019 Chap017 Project Management

    4/43

    17-4 Project Management

    Project Management

    How is it different? Limited time frame

    Narrow focus, specific objectives

    Less bureaucratic Why is it used?

    Special needs

    Pressures for new or improves products orservices

  • 7/28/2019 Chap017 Project Management

    5/43

    17-5 Project Management

    Project Management

    What are the Key Metrics Time

    Cost

    Performance objectives What are the Key Success Factors?

    Top-down commitment

    Having a capable project manager

    Having time to plan

    Careful tracking and control

    Good communications

  • 7/28/2019 Chap017 Project Management

    6/43

    17-6 Project Management

    Project Management

    What are the Major Administrative Issues? Executive responsibilities

    Project selection

    Project manager selection Organizational structure

    Organizational alternatives

    Manage within functional unit Assign a coordinator

    Use a matrix organization with a project leader

  • 7/28/2019 Chap017 Project Management

    7/43

    17-7 Project Management

    Project Management

    What are the tools? Work breakdown structure

    Network diagram

    Gantt charts Risk management

  • 7/28/2019 Chap017 Project Management

    8/43

    17-8 Project Management

    Planning and SchedulingMAR APR MAY JUN JUL AUG SEP OCT NOV DEC

    Locate new

    facil i t ies

    Intervi ew staff

    Hire and train staff

    Select and o rder

    furn i ture

    Remodel and in stal lphones

    Move in /star tup

    Gantt Chart

  • 7/28/2019 Chap017 Project Management

    9/43

    17-9 Project Management

    Deciding which projects to implement

    Selecting a project manager

    Selecting a project team

    Planning and designing the project

    Managing and controlling project resources

    Deciding if and when a project should be

    terminated

    Key Decisions

  • 7/28/2019 Chap017 Project Management

    10/43

    17-10 Project Management

    Project ManagerResponsible for:

    Work Quality

    Human Resources TimeCommunications Costs

    17 11 P M

  • 7/28/2019 Chap017 Project Management

    11/43

    17-11 Project Management

    Temptation to understate costs

    Withhold information

    Misleading status reports

    Falsifying records

    Comprising workers safety

    Approving substandard work

    Ethical Issues

    17 12 P j M

  • 7/28/2019 Chap017 Project Management

    12/43

    17-12 Project Management

    Project Life Cycle

    Concept

    Feasibility

    Planning

    Execution

    Termination

    Manag

    ement

    17 13 P j M

  • 7/28/2019 Chap017 Project Management

    13/43

    17-13 Project Management

    Work Breakdown StructureProject X

    Level 1

    Level 2

    Level 3

    Level 4

    Figure 17.2

    17 14 P j t M t

  • 7/28/2019 Chap017 Project Management

    14/43

    17-14 Project Management

    PERT and CPMPERT: Program Evaluation andReview Technique

    CPM: Critical Path Method

    Graphically displays project activities

    Estimates how long the project will take

    Indicates most critical activities

    Show where delays will not affect project

    17 15 P j t M t

  • 7/28/2019 Chap017 Project Management

    15/43

    17-15 Project Management

    The Network Diagram

    Network (precedence) diagram

    Activity-on-arrow (AOA)

    Activity-on-node (AON)

    Activities

    Events

    17 16 P j t M t

  • 7/28/2019 Chap017 Project Management

    16/43

    17-16 Project Management

    The Network Diagram (contd)

    Path Sequence of activities that leads from the starting

    node to the finishing node

    Critical path

    The longest path; determines expected project

    duration

    Critical activities

    Activities on the critical path Slack

    Allowable slippage for path; the difference the

    length of path and the length of critical path

    17 17 Project Management

  • 7/28/2019 Chap017 Project Management

    17/43

    17-17 Project Management

    Project NetworkActivity on Arrow

    1

    2

    3

    4

    5 6

    Locate

    facilities

    Orderfurniture

    Furniture

    setup

    InterviewHire and

    train

    Remodel

    Move

    in

    Figure 17.4

    AOA

    17 18 Project Management

  • 7/28/2019 Chap017 Project Management

    18/43

    17-18 Project Management

    Project NetworkActivity on Node

    1

    2

    3

    5

    6

    Locate

    facilities

    Order

    furniture

    Furniture

    setup

    Interview

    Remodel Movein

    4

    Hire andtrain

    7S

    Figure 17.4

    AON

    17 19 Project Management

  • 7/28/2019 Chap017 Project Management

    19/43

    17-19 Project Management

    Network Conventionsa

    b

    c ab

    c

    a

    b

    c

    d

    a

    b

    c

    Dummy

    activity

    17 20 Project Management

  • 7/28/2019 Chap017 Project Management

    20/43

    17-20 Project Management

    Time Estimates

    Deterministic Time estimates that are fairly certain

    Probabilistic

    Estimates of times that allow for variation

    17-21 Project Management

  • 7/28/2019 Chap017 Project Management

    21/43

    17-21 Project Management

    Example 1

    1

    2

    3

    4

    5 6

    8 weeks

    6 weeks

    3 weeks

    4 weeks 9 weeks

    11 weeks

    1 week

    Move

    in

    Deterministic

    time estimates

    Figure 17.5

    17-22 Project Management

  • 7/28/2019 Chap017 Project Management

    22/43

    17-22 Project Management

    Example 1 Solution

    Path Length(weeks)

    Slack

    1-2-3-4-5-61-2-5-61-3-5-6

    182014

    206

    Critical Path

    17-23 Project Management

  • 7/28/2019 Chap017 Project Management

    23/43

    17 23 Project Management

    Network activities ES: early start

    EF: early finish

    LS: late start LF: late finish

    Used to determine

    Expected project duration

    Slack time

    Critical path

    Computing Algorithm

    17-24 Project Management

  • 7/28/2019 Chap017 Project Management

    24/43

    17 24 Project Management

    Probabilistic Time Estimates

    Optimistic time Time required under optimal conditions

    Pessimistic time

    Time required under worst conditions

    Most likely time

    Most probable length of time that will berequired

    17-25 Project Management

  • 7/28/2019 Chap017 Project Management

    25/43

    17 25 Project Management

    Probabilistic Estimates

    Activity

    start

    Optimistic

    time

    Most likely

    time (mode)

    Pessimistic

    time

    to tptm te

    Figure 17.8

    17-26 Project Management

  • 7/28/2019 Chap017 Project Management

    26/43

    17 26 Project Management

    Expected Time

    te =to + 4tm +tp

    6

    te = expected time

    to = optimistic time

    tm

    = most likely time

    tp = pessimistic time

    17-27 Project Management

  • 7/28/2019 Chap017 Project Management

    27/43

    j g

    Variance

    2 =(tp to)

    2

    36

    2= variance

    to = optimistic time

    tp = pessimistic time

    17-28 Project Management

  • 7/28/2019 Chap017 Project Management

    28/43

    j g

    Example 5

    3-4-5

    d

    3-5-7

    e

    5-7-9

    f

    2-4-6

    b

    4-6-8

    h

    Optimistictime Most likelytime Pessimistictime

    17-29 Project Management

  • 7/28/2019 Chap017 Project Management

    29/43

    j g

    Path Probabilities

    Z =Specified time Path mean

    Path standard deviation

    Z indicates how many standard deviations

    of the path distribution the specified tine

    is beyond the expected path duration.

    17-30 Project Management

  • 7/28/2019 Chap017 Project Management

    30/43

    j g

    17

    Weeks

    Weeks

    Weeks

    Weeks

    10.0

    16.0

    13.5

    1.00

    1.00

    a-b-c

    d-e-f

    g-h-i

    Example 6

    17-31 Project Management

  • 7/28/2019 Chap017 Project Management

    31/43

    j g

    Time-cost Trade-offs: Crashing

    Crashshortening activity duration Procedure for crashing

    Crash the project one period at a time

    Only an activity on the critical path

    Crash the least expensive activity

    Multiple critical paths: find the sum ofcrashing the least expensive activity on each

    critical path

    17-32 Project Management

  • 7/28/2019 Chap017 Project Management

    32/43

    Time-Cost Trade-Offs: CrashingTotal

    cost

    Shorten

    Shorten

    Cumulative

    cost ofcrashing

    Expected indirect costs

    Optimum

    CRASH

    Figure 17.11

    17-33 Project Management

  • 7/28/2019 Chap017 Project Management

    33/43

    4d

    2f

    Example 7

    17-34 Project Management

  • 7/28/2019 Chap017 Project Management

    34/43

    Advantages of PERT Forces managers to organize Provides graphic display of activities

    Identifies

    Critical activities

    Slack activities1

    2

    3

    4

    5 6

    17-35 Project Management

  • 7/28/2019 Chap017 Project Management

    35/43

    Limitations of PERT Important activities may be omitted Precedence relationships may not be correct

    Estimates may include

    a fudge factor

    May focus solely

    on critical path 1

    2

    3

    4

    5 6

    142 weeks

    17-36 Project Management

  • 7/28/2019 Chap017 Project Management

    36/43

    Computer aided design (CAD) Groupware (Lotus Notes)

    Project management software

    CA Super Project Harvard Total Manager

    MS Project

    Sure Track Project Manager

    Time Line

    Technology for Managing Projects

    17-37 Project Management

  • 7/28/2019 Chap017 Project Management

    37/43

    Imposes a methodology Provides logical planning structure

    Enhances team communication

    Flag constraint violations

    Automatic report formats

    Multiple levels of reports Enables what-if scenarios

    Generates various chart types

    Advantages of PM Software

    17-38 Project Management

  • 7/28/2019 Chap017 Project Management

    38/43

    Risk: occurrence of events that haveundesirable consequences

    Delays

    Increased costs

    Inability to meet specifications

    Project termination

    Project Risk Management

    17-39 Project Management

  • 7/28/2019 Chap017 Project Management

    39/43

    Identify potential risks Analyze and assess risks

    Work to minimize occurrence of risk

    Establish contingency plans

    Risk Management

    17-40 Project Management

  • 7/28/2019 Chap017 Project Management

    40/43

    Summary

    Projects are a unique set of activities Projects go through life cycles

    PERT and CPM are two common techniques

    Network diagrams

    Project management software available

    17-41 Project Management

  • 7/28/2019 Chap017 Project Management

    41/43

    Additional PowerPoint slides

    contributed byGeoff Willis,

    University of Central Oklahoma.

    CHAPTER

    17

    17-42 Project Management

  • 7/28/2019 Chap017 Project Management

    42/43

    Project Crashing

    Crashing a project involves paying moremoney to complete a project more quickly.

    Since the critical path determines the length of

    a project, it makes sense to reduce the lengthof activities on the critical path.

    CP activities should be reduced until theproject is reduced to the desired length or youare paying more per day than you save.

    If you have multiple CPs, they should beshortened simultaneously.

    17-43 Project Management

    j

  • 7/28/2019 Chap017 Project Management

    43/43

    ProjectsConcepts

    PM1