WATER & ENVIRONMENT CPS INFRAESTRUCTURAS MOVILIDAD Y MEDIO AMBIENTE, S.L. CHANNEL REPAIR AND AUTOMATION OF THE MAIN CANAL OF THE TURIA CONTRACT INFORMATION ADMINISTRATIVE INFORMATION TECHNICAL INFORMATION CONTRACT TYPE: Technical Assistance to the Work Management. CONTRACT NAME: Technical Assistance to the Work Management included in the Urgent Action 3.2.j “Channel Repair and Automation of the Main Canal of the Turia (Valencia), Collection in Law 11/2005” LOCATION: Valencia (Spain) BUDGET: 1,248,374.03 € WORK BUDGET: 18,159,732.27 € CLIENT: ACUAMED S.A. DATE (BEGINNING – END): August 2007 – October 2012 Length of Canal 70,044.00 ml Covered irrigation Surface 24,500.00 ha Clean residuals from area 33.656,00 m 3 Covering cannel with slab 7,365.00 m 2 Waterproofing 4,700,00 ml Floodgate types Narcy, Narbio y Narmil… 14.00 units Flat guard gates 12.00 units Beacons with mask modules 23.00 units Flat folding gates 2.00 units Ultrasonic flowmeter 3.00 units Bubbling measurement equipment 4.00 units Parshall type gauging sections 4.00 units Remote control system 1.00 units Mariana Fountain Tunnel 1,616.75 ml Weir Outlet Benageber - Flow Rate 72.00 m 3 /s - Height 3.00 m Draining of “El Romano” - Flow Rate 19.50 m 3 /s - Wall of gabions in slope 5,038.00 m 3 WORK OBJECTIVE The works have the objective to guarantee the correct functioning of the canal, giving a solution to the different structural problems of stability, filtration, draining, etc. that are present. DEVELOPED TASKS Geometric Control Economic Control Quality Control of Materials Initial and Final Project Repot Monthly Reports Liquidation Project of the Work Price Revisions PROJECT LOCATION