Page 1: Ch11

Managerial Accountingby James Jiambalvo

Chapter 11:

Standard Costs and Variance Analysis

Slides Prepared by:

Scott Peterson

Northern State University

Page 2: Ch11

Objectives

1. Explain how standard costs are developed.

2. Calculate and interpret variances for direct material.

3. Calculate and interpret variances for direct labor.

4. Calculate and interpret variances for manufacturing overhead.

5. Calculate the financial impact of operating at more or less than planned capacity.

Page 3: Ch11

Objectives (Continued)

6. Discuss how the management by exception approach is applied to investigation of standard cost variances.

7. Explain why a “favorable” variance may be unfavorable, how process improvements may lead to “unfavorable” variances, and why evaluation in terms of variances may lead to overproduction.

Page 4: Ch11

Standard Costs

1. Standard cost refers to expected costs under anticipated conditions.

2. Standard cost systems allow for comparison of standard versus actual costs.

3. Differences are referred to as standard cost variances.

4. Variances should be investigated if significant.

Page 5: Ch11

Standard Costs and Budgets

1. Standard cost is the standard cost of a single unit.

2. Budgeted cost is the cost, at standard, of the total number of budgeted units.

Page 6: Ch11

Development of Standard Costs

1. Standard costs are developed in a variety of ways:

a. Specified by formulas or recipes.

b. Developed from price lists provided by suppliers.

c. Determined by time and motion studies conducted by industrial engineers.

d. Developed from analyses of past data.

Page 7: Ch11

Ideal Versus Attainable Standards

Two schools of thought:

1. Ideal standards (perfection standards): developed under the assumption that no obstacles to the production process will be encountered.

2. Attainable Standards: developed under the assumption that there will be occasional problems in the production process.

Page 8: Ch11

A General Approach To Variance Analysis

1. Direct material: materials price and materials quantity variance.

2. Direct labor: labor rate (price) and labor efficiency (quantity) variance.

3. Overhead: overhead volume variance and controllable overhead variance.

Page 9: Ch11

Material Variances

1. Differences between standard and actual material costs:

a. Material price variance.

b. Material quantity variance.

Page 10: Ch11

Material Price Variance

1. Material price variance:(AP – SP) x AQp

2. (AP) = actual price per unit of material.

3. (SP) = standard price per unit of direct material.

3. (AQp) = actual quantity of material purchased.

4. Actual price > standard price: unfavorable.

5. Actual price < standard price: favorable.

Page 11: Ch11

Material Quantity Variance

1. Material quantity variance: (AQu – SQ)SP

2. (AQu) = actual quantity of material used.

3. (SQ) = standard quantity of material allowed.

4. (SP) = standard price of material.

5. Actual quantity > standard quantity: unfavorable.

6. Actual quantity < standard quantity: favorable.

Page 12: Ch11

You Get What You Measure

Page 13: Ch11

Direct Labor Variances

1. Differences between standard and actual direct labor costs:

a. Labor rate (price) variance.

b. Material efficiency (quantity) variance.

Page 14: Ch11

Labor Rate Variance

1. Labor rate (price) variance: (AR – SR)AH

2. (AR) = actual wage rate (price).

3. (SR) = standard wage rate (price).

4. (AH) = actual number(quantity) labor hours.

5. Actual rate > standard rate: unfavorable.

6. Actual rate < standard rate: favorable.

Page 15: Ch11

Labor Efficiency Variance

1. Labor efficiency (quantity) variance:(AH – SH)SR

2. (AH) = actual number of hours worked.

3. (SH) = standard number of hours worked.

4. (SR) = standard labor wage rate.

5. Actual hours > standard hours: unfavorable.

6. Actual hours < standard hours: favorable.

Page 16: Ch11

Overhead Variances

1. Differences between overhead applied to inventory at actual overhead costs:a. Controllable overhead variance.

b. Overhead volume variance.

Page 17: Ch11

Controllable Overhead Variance

1. Actual overhead ($$) - flexible budget level of overhead ($$) for actual volume of production.

2. Referred to as controllable because managers are expected to control costs.

3. Actual > budget: unfavorable.

4. Actual < budget, then the variance is favorable.

Page 18: Ch11

Overhead Volume Variance

1. Overhead volume variance: flexible budget level of overhead for actual level of production - overhead applied to production using standard overhead rate.

2. This variance is solely the result of a different number of units being produced than planned in the static budget.

3. Usefulness is limited.

Page 19: Ch11

Calculating The Financial Impact Of Operating At More or Less Than Planned Capacity

1. Operating at less than planned capacity results in an unfavorable variance equal to the number of units (less than planned) x the marginal cost per unit.

2. Operating at more than planned capacity results in a favorable variance equal to the number of units (more than planned) x the marginal cost per unit.

Page 20: Ch11

Comprehensive Example: Darrington Ice Cream

Standard Costs Per Unit:

Item Qty. x Price =Total

Direct Materials: .8 gal. 2.50 =$2.00

Direct Labor: .125 hrs. 12.00= $1.50

Mfg. Overhead:$ .75

Total Cost Per Unit (Standard)$4.00

Page 21: Ch11

Comprehensive Example: Darrington Ice Cream

Page 22: Ch11

Material Variances

1. Material price variance:(AP – SP) x AQp : ($2.72 - $2.50) x 810,000 = $178,200 unfavorable.

2. Material quantity variance: (AQu – SQ)SP: (809,000 – 800,000) x $2.50 = $22,500 unfavorable.

Page 23: Ch11

Labor Variances

1. Labor rate (price) variance: (AR – SR)AH: ($12.10 - $12.00) x 130,000 = $13,000 unfavorable.

2. Labor efficiency (quantity) variance:(AH – SH)SR: (130,000 – 125,000) x $12 = $60,000 unfavorable.

Page 24: Ch11

Overhead Variances

1. Controllable overhead variance: Actual overhead ($$) - flexible budget level of overhead ($$) for actual volume of production: $680,000 - $700,000 = $20,000 unfavorable.

2. Overhead volume variance: flexible budget level of overhead for actual level of production - overhead applied to production using standard overhead rate: $700,000 - $750,000 = $50,000 favorable.

Page 25: Ch11

Investigation of Standard Cost Variances

1. Standard cost variances are not a definitive sign of good or bad performance.

2. Variances are merely indicators of potential problems which must be investigated.

3. There are many plausible explanations for them.

Page 26: Ch11

Management By Exception

1. Investigation of standard cost variances is a costly activity

2. Management must decide which variances to investigate.

3. Most managers practice management by exception.

4. What is “exceptional?” Usually an absolute dollar amount or a percentage dollar amount.

Page 27: Ch11

“Favorable” Variances May Be Unfavorable

1. A “favorable” variance does not mean that it should not be investigated.

2. Raw materials are good examples of this phenomenon.

3. Consider inferior, low-priced materials.

4. A favorable price variance may result, but there may also be substantially more scrap and rework, and thus a higher quantity variance.

Page 28: Ch11

Can Process Improvements Lead to “Unfavorable” Variances?

1. Process improvements frequently lead to unfavorable variances.

2. Process improvements often lead to increased productivity.

3. Therefore fewer hours may be required to produce a unit of output.

4. But actual hours will remain unchanged unless the firm terminates the workers to became “more productive.”

Page 29: Ch11

Beware-Evaluation in Terms of Variances Can Lead To Excess Production

1. A department in front of another (bottleneck) department should not produce more than the bottleneck department can handle.

2. If it cuts back, it will idle workers.

3. If it doesn’t there will be excess work in process and a negative effect on shareholder value.

Page 30: Ch11

Responsibility Accounting and Variances

1. Managers should be held responsible only for costs they can control.

2. This is also true in the area of variance analysis.

3. A purchasing agent may be held responsible for direct material price variances, but certainly not direct material quantity (usage) variances.

Page 31: Ch11

Appendix: Recording Standard Costs

1. Material

2. Labor

3. Overhead

4. Finished goods

5. Cost of goods sold

6. Closing variance accounts

Page 32: Ch11

Recording Material CostsPurchase of raw materials inventory:Account dr. cr.Raw Material Inventory (std.) xMaterial Price Variance x

Accounts Payable (actual) x

Usage of raw materials inventory:Account dr. cr.Work in Process Inventory xMaterial Quantity Variance x

Raw Material Inventory x

Page 33: Ch11

Recording Labor Costs

Recording Labor Cost:

Account dr. cr.

Work in Process Inventory (std.) x

Labor Rate Variance x

Labor Efficiency Variance x

Wages/Sal. Payable (actual) x

Page 34: Ch11

Recording Manufacturing Overhead: Step 1

To record actual overhead cost:

Account dr. cr.

Manufacturing Overhead x

*Various Accounts x

Page 35: Ch11

Recording Manufacturing Overhead: Step 2

To apply overhead cost to work in process inventory at cost:

Account dr. cr.

Work in Process Inventory x

Manufacturing Overhead x

Page 36: Ch11

Recording Manufacturing Overhead: Step 3

To close out manufacturing overhead cost to work in process inventory at cost:

Account dr. cr.

Manufacturing Overhead x

Overhead Volume

Variance x

Controllable Overhead

Variance x

Page 37: Ch11

Recording Finished Goods

To record completed units sent to finished goods:

Account dr. cr.

Finished Goods Inventory x

Work in Process

Inventory x

Page 38: Ch11

Recording Cost Of Goods Sold

To apply overhead cost to work in process inventory at cost:

Account dr. cr.

Cost of Goods Sold x

Finished Goods

Inventory x

Page 39: Ch11

Closing Variance Accounts

Temporary variance accounts must be closed at the end of the period. Account dr. cr.Cost of Goods Sold xOverhead Volume Variance xControllable Overhead Variance x

Material Price Variance xMaterial Quantity Variance xLabor Rate Variance xLabor Efficiency Variance x

Page 40: Ch11

Quick Review Question #1

1. What does an unfavorable overhead volume variance mean?

a. Overhead costs are out of control.

b. Overhead costs are under control.

c. Production was greater than anticipated.

d. Production was less than anticipated.

Page 41: Ch11

Quick Review Answer #1

1. What does an unfavorable overhead volume variance mean?

a. Overhead costs are out of control.

b. Overhead costs are under control.

c. Production was greater than anticipated.

d. Production was less than anticipated.

Page 42: Ch11

Quick Review Question #2

2. Standard material costs per unit are $3.50. Actual costs per unit are $3.80 Actual quantity is 3,000. Standard quantity is 2,800. Material price variance is:a. $900 favorableb. $900 unfavorablec. $700 favorabled. $700 unfavorable

Page 43: Ch11

Quick Review Answer #2

2. Standard material costs per unit are $3.50. Actual costs per unit are $3.80 Actual quantity is 3,000. Standard quantity is 2,800. Material price variance is:a. $900 favorableb. $900 unfavorablec. $700 favorabled. $700 unfavorable

Page 44: Ch11

Quick Review Question #3

2. Standard material costs per unit are $3.50. Actual costs per unit are $3.80 Actual quantity is 3,000. Standard quantity is 2,800. Material quantity variance is:a. $900 favorableb. $900 unfavorablec. $700 favorabled. $700 unfavorable

Page 45: Ch11

Quick Review Answer #3

2. Standard material costs per unit are $3.50. Actual costs per unit are $3.80 Actual quantity is 3,000. Standard quantity is 2,800. Material quantity variance is:a. $900 favorableb. $900 unfavorablec. $700 favorabled. $700 unfavorable

Page 46: Ch11

Quick Review Question #4

4. What does a favorable labor efficiency variance mean?a. Labor rates were higher than called

for by standards.b. Inexperienced labor was used,

causing the rate to be lower than standard.

c. More labor was used than called for by standards.

d. Less labor was used than called for by standards.

Page 47: Ch11

Quick Review Answer #4

4. What does a favorable labor efficiency variance mean?a. Labor rates were higher than called

for by standards.b. Inexperienced labor was used,

causing the rate to be lower than standard.

c. More labor was used than called for by standards.

d. Less labor was used than called for by standards.

Page 48: Ch11

Copyright

© 2004 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in Section 117 of the 1976 United States Copyright Act without the express written permission of the copyright owner is unlawful. Request for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information contained herein.