Top Banner
Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.
23

Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Dec 17, 2015

Download

Documents

Posy Morris
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Ch 9 Learning Goals

1.Calculate, interpret, and evaluate:

payback period.

net present value (NPV).

internal rate of return (IRR).

2. Ranking conflicts.

Page 2: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Ch 9 Learning Goals

3. The importance of risk in capital budgeting.

4. Methods of evaluating project risk.

5. Determination and use of risk-adjusted

discount rates (RADRs).

6. Capital rationing.

Page 3: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

CB Evaluation Techniques

Techniques used to evaluate capital outlays

include:

Payback

Net present value (___________)

Internal rate of return (___________)

Page 4: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

CB Evaluation Techniques • Not all evaluation techniques are equally valid. The

best rely on:

– Cash Flows (rather than accounting values)

– Time value of money

• Techniques that do these two things are _________

_________________________________________

(DCF) methods (called “sophisticated” in your text).

Page 5: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Payback Period• The payback method measures how many years it

takes to recover the initial investment.

• The maximum acceptable payback period is

determined by management.

• Decision rule: accept if the payback period is _______

___________________________ the maximum

acceptable payback period.

Page 6: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Pros and Cons of Payback Periods

• Payback is simple, intuitive, and considers cash flows

rather than accounting profits.

• Payback is widely used by large firms to evaluate

small projects and by small firms to evaluate most

projects.

• It is also used to supplement other methods such as

NPV and IRR.

Page 7: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Pros and Cons of Payback Periods• Weaknesses of Payback:

– Does not consider all CFs

– Does not consider TVOM

– The appropriate payback period is

__________________________ determined

It is not a ___________________ method (it is

unsophisticated)

Page 8: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Pros and Cons of Payback Periods

Page 9: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Net Present Value (NPV)

• Net Present Value (NPV). Net Present Value is found

by subtracting the initial investment from the present

value of the after-tax inflows.

Decision Criteria

If NPV > 0, _______________ the project

If NPV < 0, _______________ the project

If NPV = 0, indifferent

Page 10: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

• The Internal Rate of Return (IRR) is defined as the

discount rate that causes NPV to _____________

________________.

• The IRR measures the annual percentage return on

funds invested in the project.

Internal Rate of Return (IRR)

Page 11: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

• To interpret IRR, we compare it to “k,” the required

return, or “cost of capital” for the project.

Decision Criteria

If IRR > k, __________________ the project

If IRR < k, __________________ the project

If IRR = k, indifferent

Internal Rate of Return (IRR)

Page 12: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Capital Budgeting Techniques

• NPV and IRR are both _____________ (sophisticated) methods of evaluating capital budgeting projects. They are not interchangeable, however.

Page 13: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Conflicting Rankings

• A ranking conflict exists if:

– Project A has higher NPV than Project B

but:

– Project B has higher IRR than A

• Mutually exclusive projects should be ranked by

__________ (not IRR) when a ranking conflict occurs.

Page 14: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Which Approach is Best?• On a theoretical basis, NPV is better than IRR:

– NPV assumes that cash flows are reinvested at the cost of

capital whereas IRR assumes they are reinvested at the

IRR,

– A project with non-conventional cash flows might have zero

or multiple IRRs.

• Despite that, more firms use the IRR because of

management preference for rates of return.

Page 15: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Risk in Capital Budgeting

• Different projects have different levels of risk.

Analysis of the project must consider that risk

(acceptance of the project affects the firm’s

future ____________________).

Page 16: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Approaches for Dealing with Risk

• Techniques for evaluating risk of a capital budgeting project include:– Scenario analysis– Sensitivity analysis– Simulation– Decision trees

Page 17: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Approaches for Dealing with Risk

• Each of the techniques considered gives insight into project risk, but none of them provide a _________________.

• Ultimately, the decision is based on a combination of analysis and judgment.

Page 18: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Assessing Project Risk: Scenario Analysis

• Scenario analysis involves identifying 3 or more possible outcomes. Normally, the probability of each outcome is also estimated.

Page 19: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Approaches for Dealing with Risk

• Once the risk level is determined, it is incorporated into the analysis by either:– Adjusting cash flows, or– Adjusting the required return to get the risk

adjusted discount rate (______________)

_______________ is more often used in practice.

Page 20: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Risk-Adjusted Discount Rates

• The risk-adjusted discount rate is the rate of return

that must be earned on a project to compensate for

the additional risk.

• The higher the risk of a project, the ______________

the RADR – and thus the __________________ a

project’s NPV.

Page 21: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Approaches for Dealing with Risk

• CAPM could be used to determine a project’s RADR. However, most firms use project characteristics to classify projects as low, average, or high risk.

Page 22: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Risk Adjusted Discount Rates

• Examples of Project Classification– Low risk: replacement existing assets without

adding capacity or changing technology– Average risk: expanding capacity without changing

products or technology– High risk: changing product line or technology

Page 23: Ch 9 Learning Goals 1.Calculate, interpret, and evaluate: payback period. net present value (NPV). internal rate of return (IRR). 2. Ranking conflicts.

Capital Rationing

• Capital rationing exists if a firm lacks sufficient

financing to undertake all acceptable projects.

• The firm should adopt the set of projects that provides