Ch 6 Ch 6 1 IT-390 Preliminary and Detail Methods
Jan 04, 2016
22
Design and EvaluationDesign and Evaluation
Preliminary Estimate requested during the Preliminary Estimate requested during the initial evaluation for several reasons:initial evaluation for several reasons:
1) Investigate the validity of the project1) Investigate the validity of the project 2) Clarify direction or change direction2) Clarify direction or change direction 3) To allow proper preparation3) To allow proper preparation
33
Design and EvaluationDesign and Evaluation
Preliminary Estimates - limited facts Preliminary Estimates - limited facts specificsspecifics
ROM (Rough Order of Magnitude)ROM (Rough Order of Magnitude) Methods used are:Methods used are:
1) Rules of thumb (heuristic approach)1) Rules of thumb (heuristic approach) 2) Simple calculations2) Simple calculations
44
Design and EvaluationDesign and Evaluation
Preliminary EstimatesPreliminary Estimates less than accurateless than accurate Dollarless in valueDollarless in value No substantial foundationNo substantial foundation Invaluable to continuing or terminating the Invaluable to continuing or terminating the
operation, project, product, or system estimate operation, project, product, or system estimate in whole or part.in whole or part.
55
Design and EvaluationDesign and Evaluation
Detail Estimates are normally a "re-Detail Estimates are normally a "re-estimate”estimate” Re-estimate of the Preliminary EstimateRe-estimate of the Preliminary Estimate More discrete informationMore discrete information Increased accuracyIncreased accuracy Greater legitimacy of analysis Greater legitimacy of analysis
(Mathematical/Factual)(Mathematical/Factual)
66
OpinionOpinion
Opinion - judgment or belief stronger than a Opinion - judgment or belief stronger than a perception, but weaker than positive perception, but weaker than positive knowledge.knowledge. 1) Natural part, but not uneducated ones1) Natural part, but not uneducated ones 2) Capable, experienced engineer - good 2) Capable, experienced engineer - good
working knowledge working knowledge 3) Natural/Planned experiences3) Natural/Planned experiences
common sense, judgment, observations, gut feelings, all common sense, judgment, observations, gut feelings, all of which can also be done collectively (with others).of which can also be done collectively (with others).
77
ConferenceConference
Conference is formulating an educated Conference is formulating an educated opinion collectively with "others".opinion collectively with "others". A consensus (agreement) reachedA consensus (agreement) reached "others" - knowledge in specific areas"others" - knowledge in specific areas engineers only - individual designs (model of engineers only - individual designs (model of
estimation)estimation) Downfall - lack of adequate analysis and Downfall - lack of adequate analysis and
verifiable factsverifiable facts
88
ComparisonComparison
Similar to "Conference" but uses formal Similar to "Conference" but uses formal "Logic”"Logic”
Compare to similar item(s)Compare to similar item(s)
99
UnitUnit
Most popularMost popular AverageAverage Rough Order of magnitude (ROM)Rough Order of magnitude (ROM) Lump sumLump sum Module estimatingModule estimating
Examples of unit estimates include:Examples of unit estimates include: $/sq. foot (the / means “per”)$/sq. foot (the / means “per”) $/pound$/pound $/machine shop man hour$/machine shop man hour
1010
LearningLearning
Idea - more often an operation is performed, Idea - more often an operation is performed, less time will be required to complete itless time will be required to complete it
Repetition results in less time or effort Repetition results in less time or effort expendedexpended
The improved performance is called The improved performance is called ""LearningLearning""
1111
LearningLearning
Identifying Situations for Use of LearningIdentifying Situations for Use of Learning
Not used in all situationsNot used in all situations
Must haveMust have opportunity for improvementopportunity for improvement reduction in labor hours per unitreduction in labor hours per unit
1212
LearningLearning
Use of the improvement curve should be Use of the improvement curve should be considered in situations where there is:considered in situations where there is: A high proportion of manual laborA high proportion of manual labor Uninterrupted productionUninterrupted production Production of complex itemsProduction of complex items No major technological changeNo major technological change Continuous pressure to improveContinuous pressure to improve
1313
LearningLearning
Factors that Support ImprovementFactors that Support Improvement Job Familiarization by WorkersJob Familiarization by Workers Improved Production ProceduresImproved Production Procedures Improved Tooling and Tool CoordinationImproved Tooling and Tool Coordination Improved WorkFlow OrganizationImproved WorkFlow Organization Improved Product ProducibilityImproved Product Producibility Improved Engineering SupportImproved Engineering Support Improved Parts SupportImproved Parts Support
1414
LearningLearning
First application - manufacture of airframesFirst application - manufacture of airframes
Costs lowered with increasing quantity of production or Costs lowered with increasing quantity of production or experienceexperience
Rate of improvement is 20% between doubled quantitiesRate of improvement is 20% between doubled quantities
Therefore, learning curve is 80% or, 2nd unit will take Therefore, learning curve is 80% or, 2nd unit will take 80% labor of what it took on 1st unit80% labor of what it took on 1st unit
1515
LearningLearning
Other names for learning include:Other names for learning include:
Manufacturing progress functionManufacturing progress function
Experience or dynamic curveExperience or dynamic curve
1616
LearningLearning
The learning model is based on 3 The learning model is based on 3 assumptions:assumptions: 1) Amount of time or cost required to complete a unit of 1) Amount of time or cost required to complete a unit of
product is less each time the task is undertakenproduct is less each time the task is undertaken
2) Unit time will decrease at a decreasing rate (in other 2) Unit time will decrease at a decreasing rate (in other words, the time reduction will slow as time moves on)words, the time reduction will slow as time moves on)
3) Reduction in unit time follows the model y = ax3) Reduction in unit time follows the model y = axbb (curvilinear from Ch 5)(curvilinear from Ch 5)
1717
LearningLearning
The underlying hypothesis says: "The The underlying hypothesis says: "The direct labor man hours necessary to direct labor man hours necessary to complete a unit of product will decrease by complete a unit of product will decrease by a constant percentage each time the a constant percentage each time the production quantity is doubled."production quantity is doubled."
1919
LearningLearning
Several equations in this section are useful Several equations in this section are useful to us:to us: 1)1) Eq. Eq.
2)2) Eq. 6.9, pg. 259Eq. 6.9, pg. 259
3)3) Eq. 6.13, pg. 261Eq. 6.13, pg. 261
4)4) Eq.Eq.
s
Nj
Ni
Tj
Ti
2
log
Logs
NjNi
TjTis
loglog
loglog
sNK
NK
T
T
N
N 2)(
)2( 22
2020
LearningLearning
Where for each,Where for each, T = effort per unit of productionT = effort per unit of production N = unit numberN = unit number S = slope of improvement rate, a constantS = slope of improvement rate, a constant K = Constant, for unit 1, dimensions compatible to TK = Constant, for unit 1, dimensions compatible to T = the percent learning as a decimal= the percent learning as a decimal
These all assume that (Ni , Ti) and (Nj , Tj) are two points on a These all assume that (Ni , Ti) and (Nj , Tj) are two points on a log - log curve (straight line) of "N" vs "T"log - log curve (straight line) of "N" vs "T"
T
N
Effort. Labor Rate, etc.
Unit #
(Ti,Ni)
(Tj,Nj)
2121
LearningLearning
Problem 6.27, pg 294,Problem 6.27, pg 294, Supplemental ProblemSupplemental Problem
For the following problems, assume that the unit line is For the following problems, assume that the unit line is linear.linear. Find the first unit value when the 100Find the first unit value when the 100thth unit is 60 hours with unit is 60 hours with
81% learning.81% learning. Find the value for unit 6 when unit 3 is 1000 hours with 74% Find the value for unit 6 when unit 3 is 1000 hours with 74%
learning.learning. If the unit value at number 1 $2000, then find the unit dollars If the unit value at number 1 $2000, then find the unit dollars
for units 20 and 40 with learning rates of 93% and 100%.for units 20 and 40 with learning rates of 93% and 100%. If the cumulative average time at unit 100 is 100, then find the If the cumulative average time at unit 100 is 100, then find the
unit, cumulative, and average time at unit 101 for a learning unit, cumulative, and average time at unit 101 for a learning rate of 92%.rate of 92%.
2222
LearningLearning
Calculated by regression models since data Calculated by regression models since data of many points are requiredof many points are required
There are two approaches to learning There are two approaches to learning curves:curves: 1) The 1) The WrightWright (cumulative average) system (cumulative average) system 2) The 2) The BoeingBoeing (unit) system (unit) system
2323
LearningLearning
Ostwald refers to the Crawford system as the Ostwald refers to the Crawford system as the "Boeing" system"Boeing" system
In Fig. 6.4 (pg. 258)In Fig. 6.4 (pg. 258) Two systems so it's important to know what data Two systems so it's important to know what data
has been collectedhas been collected Is it for unit cost or cumulative average cost?Is it for unit cost or cumulative average cost?
Each requires a different system and a different set Each requires a different system and a different set of equationsof equations
2424
LearningLearning
Wright SystemWright System Boeing SystemBoeing System cumulative average per unitcumulative average per unit cumulative averagecumulative average Tá = KNTá = KNss Ta = Ta = KNKNss / / (1+s)(1+s)
cumulative total effort from unit 1 - Ncumulative total effort from unit 1 - N cumulative totalcumulative total Tć= KNTć= KNs+1s+1 Tc = Tc = TTuu or Tc = ( or Tc = (TTaa))
(N)(N)
unit effortunit effort unit effortunit effort Tú = KNTú = KNs+1s+1 -K(N-1) -K(N-1) s+1s+1 Tu = KNTu = KNss
NotesNotes: Plot of Tá & Tu are assumed to be linear.: Plot of Tá & Tu are assumed to be linear. The “T” in Tá is for The “T” in Tá is for timetime. For . For costcost we could have used a “C” as in Cá, but for we could have used a “C” as in Cá, but for
simplicity, we will leave the equations as “T”s even when dealing with simplicity, we will leave the equations as “T”s even when dealing with costcost..
N = unit numberS = slope of improvement rate, a constantK= constant, for unit one
2525
LearningLearning
Values in Appendix 5, pg. 553Values in Appendix 5, pg. 553
Assumption - "cumulative average" data Assumption - "cumulative average" data have been collected and plotted to form the have been collected and plotted to form the straight line in regression analysis (Wright straight line in regression analysis (Wright system)system)
2727
LearningLearning
Slope - determined from Slope - determined from historical/predicted from experiencehistorical/predicted from experience
Minimal improvement in "hard" tooling VS Minimal improvement in "hard" tooling VS manual labormanual labor
2828
LearningLearning
Learning curve values typical of general Learning curve values typical of general industry groups as of 1995 were:industry groups as of 1995 were: AerospaceAerospace 85%85% ShipbuildingShipbuilding 80-85%80-85% Complex machine tools for new models Complex machine tools for new models 75-85%75-85% Repetitive electronics mfg.Repetitive electronics mfg. 90-95%90-95% Repetitive machining or punch-press oper.Repetitive machining or punch-press oper. 90-95%90-95% Repetitive clerical operationsRepetitive clerical operations 75-85%75-85% Repetitive welding operationsRepetitive welding operations 90%90% Construction operationsConstruction operations 70-90%70-90% Raw materialsRaw materials 93-96%93-96% Purchased partsPurchased parts 85-88%85-88%
2929
LearningLearning
Theoretical First Unit (TFU) Cost + an estimate of Theoretical First Unit (TFU) Cost + an estimate of the learning curve slope = a cost estimate in (Ch 8)the learning curve slope = a cost estimate in (Ch 8) 1) Risk Method - Both the TFU and learning curve slope are 1) Risk Method - Both the TFU and learning curve slope are
estimatesestimates 2) If slope of the curve is off only +/-5%, at the 1000th unit, 2) If slope of the curve is off only +/-5%, at the 1000th unit,
estimate is off by estimate is off by 68%68% 3) The TFU cost is the cost (in dollars or man hours) to produce unit 3) The TFU cost is the cost (in dollars or man hours) to produce unit
#1#1 4) "theoretical" since rarely will the cost of the first unit produced 4) "theoretical" since rarely will the cost of the first unit produced
match this figurematch this figure 5) Why? Because we typically build several prototypes before 5) Why? Because we typically build several prototypes before
reaching the 1st unit that have the effect of lowering its costreaching the 1st unit that have the effect of lowering its cost