Centro International Conferencias Joaqium Chissano, Maputo, Mozambique June 9 th - 12 th , 2009 BY Ing A. T. Barfour FGhIE, FID Project Coordinator - GEDAP Ministry of Energy – Ghana June 2009
Centro International Conferencias Joaqium Chissano,
Maputo, MozambiqueJune 9th - 12th, 2009
BY
Ing A. T. Barfour FGhIE, FID
Project Coordinator - GEDAP
Ministry of Energy – GhanaJune 2009
PRESENTATION OUTLINE
• Overview of the Ghana / Power Sector
• Electricity Generation in Ghana
• Historical Background
• National Electrification Scheme
• Implementation Strategy & Schemes
• Financing RE
• Key Challenges
• Way Forward and Conclusion
GHANA
- Land Area: 238.5 km2
- Population: 18,845,265
(2000 Census)
-Electricity Access: 60%
-Consumption/Capita: 386kwh
- Av. GDP Growth Rate: 6.0%
Major Export: Cocoa, Gold,
Timber, Bauxite, Electricity
(Togo & Benin)
Oil & Gas
Overview of Ghana
STAKEHOLDERS IN THE POWER
SECTOR
Ministry of
Energy
Energy Commission
• Advice MoE• Tech. Policy
• Tech. Standard• Prepare Grid Code
• Policy FormulationAnd Direction
VRA ECG
NED
• Produce• Distribute
• Distribute
PURC• BGT • DSC
• DSC
• Regulates Economic tariff• Cust. Serv. Quality
GRIDCO • Transmit
• TSC
Generation Sources
Hydropower Thermal Power
Akosombo–1,012 MW
Kpong – 160 MW
TAPCO (Takoradi I) – 330 MW
TICO (Takoradi II) – 220 MW
Mines Reserve Plant – 80 MW
VRA Tema – 126 MW
ELECTRICITY SUPPLY INFRASTRUCTURE
Bui – 400 MW
Osonor Power – 126 MW
Asorgli Power – 220 MW
Power Barge – 125 MW
Tema 2 Plant – 49.5 MW
Kpone Thermal – 223.4 MW
HISTORICAL BACKGROUNDThe Rural Electrification Committee of 1970 –
Objectives & Recommendations
• Objective was to establish how to bring
electrification to rural areas, as a means of
reducing the urban-rural inequalities and
increase economic activity in the rural areas
Recommendations:
• Rural electrification could not be economically
self supporting at the time
• A rural electrification fund to be set up from ECG
dividends to the government and part of VRA's
surplus to be used for financing the running and
maintenance of electricity systems
Objectives &
Recommendations - Cont• A rural electricity department to be set up within
ECG
• A rural electrification commission under the
ministerial control of the prime minister
• Government to provide subsidy for the supply of
electricity to all towns/villages with population
between 1,000 and 5,000
• To reduce cost, local materials should be used
• Interest on foreign loans for power projects should
be paid into a rural electrification fund
• Communities were to contribute 1% capital cost
Rural Electrification-
The National Electrification Scheme
• National Electrification Policy instituted in 1989to replace the 1970 policy.
• National electrification access was then about25%.
• 46 out of the 110 district capitals existing thenwere connected to the grid.
• Less than 5% rural coverage estimated at thetime.
• National Electrification Levy was instituted andthe levies collected were paid into a NationalElectrification Fund established to supportimplementation of the rural electrificationprogramme.
National Electrification Scheme –Goal and Aims
• Goal of NES is to extend reliable electricity
supplies to all communities over a 30-year
period.
• Aims:
- to enhance socio-economic development
nationwide; and
- to reduce level of poverty nationwide,
particularly in the rural areas.
National Electrification Scheme –Specific Objectives
• Promote use of local and indigenous resources for a cost effective implementation of rural electrification.
• Create employment and increase productivity and wealth.
• Promote growth of agro-based & small scale industries.
• Reduce the rate of rural-urban migration.
• Improve information access and communication services nationwide.
• Improve the quality of life of rural folks.
National Electrification Scheme –Implementation Strategy
• Comprehensive National Electrification Planning Study undertaken between 1989-1991 by Acres International of Canada and Asare-Tsibu & Partners of Ghana.
• Developed a comprehensive National Electrification Master Plan for 4,221 communities.
• All possible options of electrification considered including grid extension and off-grid renewable energy-based solutions such as biomass, solar, wind & small hydro.
• 69 grid-based electrification project packages identified and prioritized for implementation over six 5-year phases major output of NEMP.
National Electrification Scheme –Implementation Strategy (Contd.)
• Connection of district capitals given first priority(64 district capitals in total) and completion ofalready ongoing projects - Phase One
• Subsequent phases prioritized based on:economic, political, traditional & historical factors:
- potential for small-scale industry activity;
- status as commercial market center;
- tourism potential;
- political dispensation; and
- historical importance of area.
National Electrification Scheme –Self-Help Electrification Programme
(SHEP)• SHEP is complementary electrification programme
instituted to support the main NES.
• Rationale: To accelerate the connection ofcommunities to the national electricity grid.
• Introduced by government to encourage (ratherthan dampen) the self-help developmental initiativesof communities.
• Communities that initiate their townshipelectrification projects receive government supportfor completion of the projects earlier than thescheduled date of connection under the NEMP.
SHEP Criteria for joining SHEP
• Community must be within 20 km of an
existing 11kV or 33kV network suitable for
further extension.
• Community must procure and erect all the
low voltage electricity poles required for the
local network.
• Evidence of a minimum of one-third of
houses in the community wired and ready to
receive electricity supply on arrival.
• Community must apply to join SHEP.
FINANCING RE
Name Role
Government of Ghana Consolidated Fund
Levy on consumers
Through Utilities/Agencies
Suppliers Credit
Local Government
Direct through provision of wood poles
MP’s Common Fund
Communities Provision of LV poles & communal labour
Development Partners Bilateral
Multilateral
RE Projects are financed through a mixture of Local
and External Sources (grants and soft loans from a
consortium of financing institutions including the DFIs &
bilateral funding agencies).
Government of Ghana / ECG /
VRA Contributions
Project Cost
(Million)Area Base Period Remarks
Grid Extension to Keta I ¢2192 Volta 11 1990 – 91
Grid Extension to Keta II ¢ 800 15 1992
Juabeso Bia
Electrification Western 41 1992 – 96
Electrification of Volta
Lake Resettlement
Townships
USD 32.8 Volta 144 2002 -2003
Suppliers
Credit from
Chinese Ex-
Im Bank
Bobikuma Electrification ¢ 1178 Central 11 1993 – 95
Agomeda – Kordiabe
Electrification ¢ 77.6 Gt. Accra 8 1993 – 95
Government of Ghana / ECG /
VRA Contributions
Project Cost
(Million)Area Base Period Remarks
Self Help Electrification
Project (SHEP)
SHEP 2 ¢ 2610 National 42 1992 – 94
Emergency SHEP ¢ 4520
Ashanti,
Central &
Volta
50 1994 – 96
SHEP 3 phase 1
USD 130
+ ¢900,000National
170 1996 – 98
phase 2 480 1998 – 2000
phase 3 700 2000 – 2005
SHEP 4 phase 1 & 2USD 45.0
+ ¢270,000National 193 2005 - 2008
MultilateralsProject Donors Area Period
National Electrification Project
- Rural
IDA
USD 77.8M
Western – 97
Eastern – 42
Volta – 56
Gt. Accra – 15
Ashanti – 15
Central – 66
NED/VRA - 155
1993 – 98
Dutch Government
USD 31.0M(40% Grant & 60%
concessionary loan)
Norwegian (Nordic Fund)
USD 6.88M
Swedish SIDA
SEK 68MDanish Govt (DANIDA).
USD 24.35M
GoG(Counterpart fund)
¢2,804M
Western Region Electrification EU €10.0M Western – 108 2002 – 2005
Project Cost
(Million)Area
Beneficiary
Communities Period Remarks
JICA I ¥ 780
Ashanti,
Central &
Gt. Accra
37 1989 – 90
GoG
contribution
¢50M
Lower Volta
Electrification JICA II¥ 1,876
Volta & Gt.
Accra19 1994 – 95
GoG
¢ 561M
Electrification of
Asesewa & Yeji Area
JICA III
¥ 826
Eastern &
Brong
Ahafo
44 1996 – 97 GoG
¢ 503.20M
Electrification of
Nyinahin and
Amansie West
District JICA IV
¥ 890 Ashanti 34 2003 -2004GoG
¢ 7,500M
JICA V Upper
Denkyira & West
Akim
¥1,088Central &
Eastern47 2006 - 2009
GoG
¢ 29,300M
Bilateral
-Japanese Government through JICA
Project Cost
(Mill)Area
Beneficiary
Communities Period Remarks
Volta Electrification
phase 1DM 7.7 Volta 44 1982 – 84
Residual Works Volta
Electrification Phase 1DM 1.0 Volta 16/9
1982 – 84 GoG
¢ 246M
Bilateral
- German Government through KfW
Project Cost
(Mill)Area
Beneficiary
Communities Period Remarks
Eastern Region District
Capital Electrification SEK 52.5 Eastern 22 1994 – 95 GoG
¢465.7M
Ashanti Region District
Capital Electrification US$ 9.98(Finish Gov’t)
Ashanti 52 1993 – 95 GoG
¢ 530.33M
BilateralSwedish/Finish Government through SIDA
Spanish Government
Project Cost
(Mill)Area
Beneficiary
Communities Period Remarks
Upper East
Electrification Project USD10.0
Upper
East 51
1999 –
2000
Project Cost
(Mill)Area
Beneficiary
Communities Period Remarks
Upper East
Electrification Project USD10.0
Upper
East 51 1999 – 2000
BilateralSpanish Government
Project Cost
(Mill)Area Base
Beneficiary
Communities Remarks
Electrification of Jasikan
Kadjebi & othersCAD10 Volta 38 1991 – 92
GoG
¢ 869M
BilateralCanadian Government through CIDA
Project Cost (Mill) AreaBeneficiary
Communities Period Remarks
SHEP I Rp10 National 150 1989 – 93
Government
bears local
expenses
Indian Government
Source of
funding
Beneficiary
Communities
Foreign
(million)
Local
(million)
Bilateral 422 USD 102.58 ¢40,025.23
Multilateral 554 USD 163.03 ¢2,804.00
Government of
Ghana1,865 USD 207.80 ¢1,181,377.6
TOTAL 2,841 USD 473.41¢1,224,206.83
(USD 122.42)
Summary
Capital Cost/ Communities Electrified
•All local currencies were funded by the Government of Ghana
USD 1.00 = ¢10,000.00
Summary
- Capital Cost
Bilateral 18%
Multilateral 27%
Government of Ghana55%
Financing Ongoing RE Projects
Project 2Cost
(Million)Source Area
Beneficiary
Communitie
s
Period
GEDAP Grid
ExtensionUSD 58.40
IDA
ACGF
SECO
ECG
operational
Area
420 2007 – 12
GEDAP
IntensificationUSD 24.60 IDA National 570 2007 – 12
SHEP - 4USD 90
CIWE -1
(Suppliers
Credit)
National 580 2007 – 09
SHEP - 4USD 170
US17(GOG)
CIWE -2
(Suppliers
Credit)
National830
2009 – 12
Financing Ongoing RE Projects
Project 2Cost
(Million)Source Area
Beneficiary
CommunitiesPeriod
SHEP - 4 USD 30 EBIDAshanti,
BA106 2009 – 12
SHEP - 4 EURO 10Eltel Network
(Finland)
Ashanti,
Eastern79 2009 – 12
SHEP - 4USD 5.5
MCA National 45 2008 – 12
SHEP - 4
USD 350
US50(GOG)Suppliers Credit:
US ExIm BankNational 1200 2009 -13
TOTALUSD
7423830
Next 5
Years
KEY CHALLENGIES
• Poverty level of the Rural People
• Inadequate RE levy (0.017 cent/kwh)
• Government Budget Support – inadequate &
not reliable
• Strict conditionalities of Development
Partners
• Lack of Private Capital
• Lack of commitment of the Utilities
WAY FORWARD / CONCLUSION
• Financing RE Projects is a daunting task for
developing countries
• Government Policy Towards Poverty
Alleviation/Wealth Creation in Rural Areas
must be pursued vigorously
• REA and REF must be established
• Local Government, Communities and
Consumers should continue to contribute to
the RE Fund
WAY FORWARD / CONCLUSION
• The RE Levy should be made a percentage
of Energy Consumption
• Government Budgetary Allocation should be
adequate and released timely
• A portion of Utilities profit must be channeled
to the RE Fund
• Development Partners should continue to
assist RE with lesser conditionalities
• Private Investors should be encouraged to
fund RE Projects through franchise/
concession