Central-Wan Chai Bypass and Island Eastern Corridor Link Island Eastern Corridor Link - Causeway Bay T yphoon Shelter (Contract No. HY/2009/15) Tim Leung Singapore – 11 November 2016 Mr. Tim Leung
Central-Wan Chai Bypass and Island Eastern Corridor LinkIsland Eastern Corridor Link -
Causeway Bay Typhoon Sheltery y yp(Contract No. HY/2009/15)
Tim Leung
Singapore – 11 November 2016 Mr. Tim Leung
Client
Highways Department, Hong Kong GovernmentHighways Department, Hong Kong Government
Engineering Firm
AECOM Asia Co LtdAECOM Asia Co. Ltd.
Contractor
China States Construction Engineering (Hong Kong) Ltd
Contractor
Singapore – 11 November 2016
China States Construction Engineering (Hong Kong) Ltd.
2
Contract InformationOverall Cost for Tunnel Civil Works Cost:
€ 614 million (HK$ 5.37 billion)
Length of Drive:
Mined Tunnel = 167 metresCut-and-Cover Tunnel = 598 metres
Duration:
27 S t b 2010 31 M h 2016 (5 5 )27 September 2010 – 31 March 2016 (5.5 yrs)Date of Completion of Tunnelling Civil Works:
31 March 2016
Singapore – 11 November 2016
31 March 20163
Central – Wan Chai Bypass and Island Eastern Corridor Link
Brief Description
Central, Wan Chai and Causeway Bay lie inCentral, Wan Chai and Causeway Bay lie inthe heart of Hong Kong and are heavilytrafficked. The existing roads along thenorthern shore of Hong Kong Island is
tl ti b d it d i itcurrently operating beyond its design capacity.Hence there is a compelling need to provide anew trunk road – a 4.5 km dual 3-lane “Central
Wan Chai Bypass (CWB)” to relieve the– Wan Chai Bypass (CWB) to relieve theexisting traffic congestion and cater for theanticipated traffic growth. The CWB, consistsof 3.7 km tunnel, will be an expressway, p yrelieving the congestion between the east-west along the northern shore of Hong KongIsland and coping with the predicted trafficflow
Singapore – 11 November 2016
flow.
4
Scope and Type of Works
To meet requirements of the Protection of the Harbour Ordinance (PHO) least intrusion into the Victoria Harbour the minimum extent of permanent/temporary reclamation
Singapore – 11 November 20165
Scope and Type of WorksScope and Type of Works
• Construction of Cut‐and‐Cover tunnel below sea bed• Construction of Mined Tunnel underneath the existing Cross Harbour Tunnel
Singapore – 11 November 20166
g
Scope and Type of Works• Temporary reclamation (and its removal) after the completion of the tunnel
Construction Method for CWB – Cut-and-
Temporarily reclaimed area
for CWB Cut andCover Tunnel and Installation of Diaphragm Wall
Construction sequence of Cut‐and‐Cover Tunnel and construction of Diaphragm W ll i f h
Temporary ReclamationOriginal View of Site Area TS2
Wall is one of the most common methods of construction of tunnel. This method is adopted in the CWB Project. The brief construction procedures are shown in the diagrams.
Construction of Cut and Cover Tunnel Seabed Reinstated after Completion
Singapore – 11 November 20167
of Cut-and-Cover Tunnel
Scope and Type of WorksEx‐Wan Chai Public Cargo
Working AreaCross Harbour Tunnel
Causeway Bay Typhoon Shelter
Cut‐and‐Cover Tunnel being constructed
Mined Tunnel to be constructed by Drill‐and Break method
Cut‐and‐Cover Tunnel being constructed
Ex‐Wan Chai Public Cargo Working Area
Causeway Bay Typhoon Shelter
Cross Harbour Tunnel
Completed Cut‐and‐Cover Tunnel
Completed Cut‐and‐Cover Tunnel
Mined Tunnel being constructed
Singapore – 11 November 20168
Scope and Type of Works
Moorings and Anchorages
Singapore – 11 November 20169
Design & Construction Innovations Developed for and during the Project
Major tunnel plant in operation No.
Drilling Jumbo 6
Crawler Drill 3
Rock Splitter 3
Hydraulic Breaker 8
Backhoe 5
Singapore – 11 November 2016
Wheel Loader 3
Design & Construction Innovations Developed for and during the Project• Modification of Drilling Jumbo for Continuous Slot Holes (Free Faces) Drilling
Guide Plunger
Singapore – 11 November 2016
Drilling of continuous slot holes by modified drilling jumbo with guide plunger
11
Design & Construction Innovations Developed for and during the Project
• Diaphragm Wall Underwater Cutting
Split & Remove Cut Piece
Singapore – 11 November 201612
Design & Construction Innovations Developed for and during the Project
Singapore – 11 November 201613
Design & Construction Innovations Developed for and during the Project
1. Additional Steel Weight at CHT Portal To compensate the additional induced stress estimated in CHT anchors due to p
mined tunnel excavation
2. Standby Dewatering / Recharging Systemy g g g y Act as contingency measure against floatation during mined tunnel construction
3. Instrumentation Monitoring at CHT Portal3. Instrumentation Monitoring at CHT Portal To closely monitor the structural behavior of CHT portal
4 Magnetometry survey carried out in horizontal holes to4. Magnetometry survey carried out in horizontal holes to Confirm the existence of CHT anchors Check clearance between existing CHT ground anchors and the tunnel
Singapore – 11 November 2016
Additional Steel Weights
Singapore – 11 November 201615
Standby Dewatering /Recharging SystemDewatering Wells – 37 nos.Recharge Wells – 51 nos.Piezometers – 13 nos.
Singapore – 11 November 201616
Comprehensive Instrumentation Monitoring
L t Pl f ADMS P i Layout Plan of ADMS Prisms and Strain Gauges
Notification via e‐mail and SMSNotification via e‐mail and SMS
Convergence Monitoring in
Alert, Action and Alarm (AAA) Trigger Levels +/‐13, 18 and 22mm
Alert, Action and Alarm (AAA) Trigger Levels +/‐13, 18 and 22mm
Trigger Standby Dewatering / Recharging System
Trigger Standby Dewatering / Recharging System
Singapore – 11 November 2016
Two Major Stages
17
Overall Approach to Management of Construction (Methods and Schedule) to Successfully Complete the Excavation(s) within PlanSchedule) to Successfully Complete the Excavation(s) within Plan
Singapore – 11 November 201618
Overall Approach to Management of Construction (Methods and Schedule) to Successfully Complete the Excavation(s) within PlanSchedule) to Successfully Complete the Excavation(s) within Plan
Trinocular Tunnel
Singapore – 11 November 201619
Demonstrated Overall Owner Satisfaction with Completed Work, Including Safety and Quality PerformanceIncluding Safety and Quality Performance
• Meeting tight programme / milestone• Upon completion of Mined Tunnel, negligible displacement / deformation at the existing Cross Harbour
TunnelTunnel• Winning several safety & environmental awards• Speech of the Client, Director of Highways Department
of HKSAR, during the Breakthrough Ceremony at MinedT l ti fi d ith th tTunnel, was very satisfied with the outcome.
Speech from Director of Highways Department of HKSAR on 15
Singapore – 11 November 201620
Speech from Director of Highways Department of HKSAR on 15October 2014
CSW 2015 – Competition Award “Zero Accident”
Public / Community Relations Programs to Bring Public Support to the Project and Mitigation of Construction Impactsto the Project and Mitigation of Construction Impacts
• Community Liaison Centre (CLC)
Singapore – 11 November 201621
Public / Community Relations Programs to Bring Public Support to the Project and Mitigation of Construction Impactsto the Project and Mitigation of Construction Impacts
• Community Liaison Centre (CLC)
• Using work barges for delivery of concrete trucks to avoid imposing additional traffic load to theexisting road network
Singapore – 11 November 201622
Public / Community Relations Programs to Bring Public Support to the Project and Mitigation of Construction Impactsto the Project and Mitigation of Construction Impacts
• Community Liaison Centre (CLC)
• Using work barges for delivery of concrete trucks to avoid imposing additional traffic load to theexisting road network
• Arranged site visits including collection of public views, consultation of Legislative Council,Harbour‐Front Commission and District Councils
Singapore – 11 November 201623
Public / Community Relations Programs to Bring Public Support to the Project and Mitigation of Construction Impactsto the Project and Mitigation of Construction Impacts
• Community Liaison Centre (CLC)
• Using work barges for delivery of concrete trucks to avoid imposing additional traffic load to theexisting road network
• Arranged site visits including collection of public views, consultation of Legislative Council,Harbour‐Front Commission and District Councils
Goh Chok Tong William H. Frist
Site Visit – Singapore Emeritus Senior MinisterG h Ch k T (22 J 2016)
Site Visit – US ex-Senator William H. Frist (19 Mar
Singapore – 11 November 2016
Goh Chok Tong (22 Jan 2016) 2015)
24
Public / Community Relations Programs to Bring Public Support to the Project and Mitigation of Construction Impactsto the Project and Mitigation of Construction Impacts
• Community Liaison Centre (CLC)
• Using work barges for delivery of concrete trucks to avoid imposing additional traffic load to theexisting road network
• Arranged site visits including collection of public views, consultation of Legislative Council,Harbour‐Front Commission and District Councils
• Appreciation and acknowledgment from various events and competitions• Appreciation and acknowledgment from various events and competitions
Singapore – 11 November 201625
Relevance of the Project and on the Tunnelling Solution
CWB CWB –– The Missing LinkThe Missing LinkCWB CWB –– The Missing LinkThe Missing LinkCWB CWB –– The Missing LinkThe Missing Link
Singapore – 11 November 201626
Interesting Features / Commercial ResolutionTo alleviate long traffic queue between east‐west along thenorthern shore of Hong Kong Island
From Central to North Point By 2017: 45 minutesBy 2017: 45 minutes
From Central to North Point
With CWB: 5 minutes
Singapore – 11 November 201627
Demonstrate “Value Added” by All of the Above• Four technical papers on this project were published and presented in the international conferences
Institute of Materials, Minerals and Mining (IOM3) in September 2015 World Tunnel Congress 2016 (WTC2016) in April 2016 I t ti l C f U d d C t ti P 2016 j i tl ith 3 d E t International Conference Underground Construction Prague 2016 jointly with 3rd Eastern
European Tunnelling Conference (EETC2016) in May 2016
• Selected to be the cover story of The Journal of the Hong Kong Institution of Engineers in September 2016
Singapore – 11 November 201628
Development of Cost Saving Underground Solutions
This project is designed for the rapid population growth andincreased urbanisation in the decades ahead, and will be onef h f d h d llof the major infrastructures in Hong Kong and such design will
surely wide use of underground solutions worldwide.
As the theme of WTC 2017, the project teamresolved “Surface Challenges” and provided“Underground Solutions” for this section ofCentral – Wan Chai Bypass Tunnel
Singapore – 11 November 201629
Why the Entry should be Selected for an AwardDespiteDespite thethe numerousnumerous challengeschallenges encountered,encountered, thethe teamteam werewere ableable totosuccessfullysuccessfully completecomplete thethe projectproject onon timetime andand withinwithin budget,budget, andand withwithsomesome costcost savingssavings.. OverallOverall thethe clientclient waswas veryvery satisfiedsatisfied withwith thethe outcomeoutcome.
Singapore – 11 November 201630