Top Banner
Central-Wan Chai Bypass and Island Eastern Corridor Link Island Eastern Corridor Link - Causeway Bay T yphoon Shelter (Contract No. HY/2009/15) Tim Leung Singapore – 11 November 2016 Mr. Tim Leung
30

Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Jul 21, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Central-Wan Chai Bypass and Island Eastern Corridor LinkIsland Eastern Corridor Link -

Causeway Bay Typhoon Sheltery y yp(Contract No. HY/2009/15)

Tim Leung

Singapore – 11 November 2016 Mr. Tim Leung

Page 2: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Client

Highways Department, Hong Kong GovernmentHighways Department, Hong Kong Government

Engineering Firm

AECOM Asia Co LtdAECOM Asia Co. Ltd.

Contractor

China States Construction Engineering (Hong Kong) Ltd

Contractor

Singapore – 11 November 2016

China States Construction Engineering (Hong Kong) Ltd.

2

Page 3: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Contract InformationOverall Cost for Tunnel Civil Works Cost:

€ 614 million (HK$ 5.37 billion)

Length of Drive:

Mined Tunnel = 167 metresCut-and-Cover Tunnel = 598 metres

Duration:

27 S t b 2010 31 M h 2016 (5 5 )27 September 2010 – 31 March 2016 (5.5 yrs)Date of Completion of Tunnelling Civil Works:

31 March 2016

Singapore – 11 November 2016

31 March 20163

Page 4: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Central – Wan Chai Bypass and Island Eastern Corridor Link

Brief Description

Central, Wan Chai and Causeway Bay lie inCentral, Wan Chai and Causeway Bay lie inthe heart of Hong Kong and are heavilytrafficked. The existing roads along thenorthern shore of Hong Kong Island is

tl ti b d it d i itcurrently operating beyond its design capacity.Hence there is a compelling need to provide anew trunk road – a 4.5 km dual 3-lane “Central

Wan Chai Bypass (CWB)” to relieve the– Wan Chai Bypass (CWB) to relieve theexisting traffic congestion and cater for theanticipated traffic growth. The CWB, consistsof 3.7 km tunnel, will be an expressway, p yrelieving the congestion between the east-west along the northern shore of Hong KongIsland and coping with the predicted trafficflow

Singapore – 11 November 2016

flow.

4

Page 5: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Scope and Type of Works

To meet requirements of the Protection of the Harbour Ordinance (PHO) least intrusion into the Victoria Harbour the minimum extent of permanent/temporary reclamation

Singapore – 11 November 20165

Page 6: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Scope and Type of WorksScope and Type of Works

• Construction of Cut‐and‐Cover tunnel below sea bed• Construction of Mined Tunnel underneath the existing Cross Harbour Tunnel

Singapore – 11 November 20166

g

Page 7: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Scope and Type of Works• Temporary reclamation (and its removal) after the completion of the tunnel

Construction Method for CWB – Cut-and-

Temporarily reclaimed area

for CWB Cut andCover Tunnel and Installation of Diaphragm Wall

Construction sequence of Cut‐and‐Cover Tunnel and construction of Diaphragm W ll i f h

Temporary ReclamationOriginal View of Site Area TS2

Wall is one of the most common methods of construction of tunnel. This method is adopted in the CWB Project. The brief construction procedures are shown in the diagrams.

Construction of Cut and Cover Tunnel Seabed Reinstated after Completion

Singapore – 11 November 20167

of Cut-and-Cover Tunnel

Page 8: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Scope and Type of WorksEx‐Wan Chai Public Cargo 

Working AreaCross Harbour Tunnel

Causeway Bay Typhoon Shelter

Cut‐and‐Cover Tunnel being constructed

Mined Tunnel to be constructed by Drill‐and Break method

Cut‐and‐Cover Tunnel being constructed

Ex‐Wan Chai Public Cargo Working Area

Causeway Bay Typhoon Shelter

Cross Harbour Tunnel

Completed Cut‐and‐Cover Tunnel

Completed Cut‐and‐Cover Tunnel

Mined Tunnel being constructed

Singapore – 11 November 20168

Page 9: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Scope and Type of Works

Moorings and Anchorages

Singapore – 11 November 20169

Page 10: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Design & Construction Innovations Developed for and during the Project

Major tunnel plant in operation No.

Drilling Jumbo 6

Crawler Drill 3

Rock Splitter 3

Hydraulic Breaker 8

Backhoe 5

Singapore – 11 November 2016

Wheel Loader 3

Page 11: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Design & Construction Innovations Developed for and during the Project• Modification of Drilling Jumbo for Continuous Slot Holes (Free Faces) Drilling

Guide Plunger

Singapore – 11 November 2016

Drilling of continuous slot holes by modified drilling jumbo with guide plunger

11

Page 12: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Design & Construction Innovations Developed for and during the Project

• Diaphragm Wall Underwater Cutting

Split & Remove Cut Piece

Singapore – 11 November 201612

Page 13: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Design & Construction Innovations Developed for and during the Project

Singapore – 11 November 201613

Page 14: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Design & Construction Innovations Developed for and during the Project

1. Additional Steel Weight at CHT Portal  To compensate the additional induced stress estimated in CHT anchors due to p

mined tunnel excavation

2. Standby Dewatering / Recharging Systemy g g g y Act as contingency measure against floatation during mined tunnel construction

3. Instrumentation Monitoring at CHT Portal3. Instrumentation Monitoring at CHT Portal To closely monitor the structural behavior of CHT portal

4 Magnetometry survey carried out in horizontal holes to4. Magnetometry survey carried out in horizontal holes to Confirm the existence of CHT anchors Check clearance between existing CHT ground anchors and the tunnel

Singapore – 11 November 2016

Page 15: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Additional Steel Weights

Singapore – 11 November 201615

Page 16: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Standby Dewatering /Recharging SystemDewatering Wells – 37 nos.Recharge Wells – 51 nos.Piezometers – 13 nos.

Singapore – 11 November 201616

Page 17: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Comprehensive Instrumentation Monitoring

L t Pl f ADMS P i Layout Plan of ADMS Prisms and Strain Gauges

Notification via e‐mail and SMSNotification via e‐mail and SMS

Convergence Monitoring in

Alert, Action and Alarm (AAA) Trigger Levels +/‐13, 18 and 22mm 

Alert, Action and Alarm (AAA) Trigger Levels +/‐13, 18 and 22mm 

Trigger Standby Dewatering / Recharging System

Trigger Standby Dewatering / Recharging System

Singapore – 11 November 2016

Two Major Stages

17

Page 18: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Overall Approach to Management of Construction (Methods and Schedule) to Successfully Complete the Excavation(s) within PlanSchedule) to Successfully Complete the Excavation(s) within Plan

Singapore – 11 November 201618

Page 19: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Overall Approach to Management of Construction (Methods and Schedule) to Successfully Complete the Excavation(s) within PlanSchedule) to Successfully Complete the Excavation(s) within Plan

Trinocular Tunnel

Singapore – 11 November 201619

Page 20: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Demonstrated Overall Owner Satisfaction with Completed Work, Including Safety and Quality PerformanceIncluding Safety and Quality Performance

• Meeting tight programme / milestone• Upon completion of Mined Tunnel, negligible displacement / deformation at the existing Cross Harbour

TunnelTunnel• Winning several safety & environmental awards• Speech of the Client, Director of Highways Department

of HKSAR, during the Breakthrough Ceremony at MinedT l ti fi d ith th tTunnel, was very satisfied with the outcome.

Speech from Director of Highways Department of HKSAR on 15

Singapore – 11 November 201620

Speech from Director of Highways Department of HKSAR on 15October 2014

CSW 2015 – Competition Award “Zero Accident”

Page 21: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Public / Community Relations Programs to Bring Public Support to the Project and Mitigation of Construction Impactsto the Project and Mitigation of Construction Impacts

• Community Liaison Centre (CLC)

Singapore – 11 November 201621

Page 22: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Public / Community Relations Programs to Bring Public Support to the Project and Mitigation of Construction Impactsto the Project and Mitigation of Construction Impacts

• Community Liaison Centre (CLC)

• Using work barges for delivery of concrete trucks to avoid imposing additional traffic load to theexisting road network

Singapore – 11 November 201622

Page 23: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Public / Community Relations Programs to Bring Public Support to the Project and Mitigation of Construction Impactsto the Project and Mitigation of Construction Impacts

• Community Liaison Centre (CLC)

• Using work barges for delivery of concrete trucks to avoid imposing additional traffic load to theexisting road network

• Arranged site visits including collection of public views, consultation of Legislative Council,Harbour‐Front Commission and District Councils

Singapore – 11 November 201623

Page 24: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Public / Community Relations Programs to Bring Public Support to the Project and Mitigation of Construction Impactsto the Project and Mitigation of Construction Impacts

• Community Liaison Centre (CLC)

• Using work barges for delivery of concrete trucks to avoid imposing additional traffic load to theexisting road network

• Arranged site visits including collection of public views, consultation of Legislative Council,Harbour‐Front Commission and District Councils

Goh Chok Tong William H. Frist

Site Visit – Singapore Emeritus Senior MinisterG h Ch k T (22 J 2016)

Site Visit – US ex-Senator William H. Frist (19 Mar

Singapore – 11 November 2016

Goh Chok Tong (22 Jan 2016) 2015)

24

Page 25: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Public / Community Relations Programs to Bring Public Support to the Project and Mitigation of Construction Impactsto the Project and Mitigation of Construction Impacts

• Community Liaison Centre (CLC)

• Using work barges for delivery of concrete trucks to avoid imposing additional traffic load to theexisting road network

• Arranged site visits including collection of public views, consultation of Legislative Council,Harbour‐Front Commission and District Councils

• Appreciation and acknowledgment from various events and competitions• Appreciation and acknowledgment from various events and competitions

Singapore – 11 November 201625

Page 26: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Relevance of the Project and on the Tunnelling Solution

CWB CWB –– The Missing LinkThe Missing LinkCWB CWB –– The Missing LinkThe Missing LinkCWB CWB –– The Missing LinkThe Missing Link

Singapore – 11 November 201626

Page 27: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Interesting Features / Commercial ResolutionTo alleviate long traffic queue between east‐west along thenorthern shore of Hong Kong Island

From Central to North Point By 2017: 45 minutesBy 2017: 45 minutes

From Central to North Point

With CWB: 5 minutes

Singapore – 11 November 201627

Page 28: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Demonstrate “Value Added” by All of the Above• Four technical papers on this project were published and presented in the international conferences

Institute of Materials, Minerals and Mining (IOM3) in September 2015 World Tunnel Congress 2016 (WTC2016) in April 2016 I t ti l C f U d d C t ti P 2016 j i tl ith 3 d E t International Conference Underground Construction Prague 2016 jointly with 3rd Eastern

European Tunnelling Conference (EETC2016) in May 2016

• Selected to be the cover story of The Journal of the Hong Kong Institution of Engineers in September 2016

Singapore – 11 November 201628

Page 29: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Development of Cost Saving Underground Solutions

This project is designed for the rapid population growth andincreased urbanisation in the decades ahead, and will be onef h f d h d llof the major infrastructures in Hong Kong and such design will

surely wide use of underground solutions worldwide.

As the theme of WTC 2017, the project teamresolved “Surface Challenges” and provided“Underground Solutions” for this section ofCentral – Wan Chai Bypass Tunnel

Singapore – 11 November 201629

Page 30: Central-Wan Chai Bypass and Island Eastern Corridor ... · Central-Wan Chai Bypass and Island Eastern Corridor LinkCorridor Link - Causeway Bay Typhoon Shelter (Contract No. HY/2009/15)

Why the Entry should be Selected for an AwardDespiteDespite thethe numerousnumerous challengeschallenges encountered,encountered, thethe teamteam werewere ableable totosuccessfullysuccessfully completecomplete thethe projectproject onon timetime andand withinwithin budget,budget, andand withwithsomesome costcost savingssavings.. OverallOverall thethe clientclient waswas veryvery satisfiedsatisfied withwith thethe outcomeoutcome.

Singapore – 11 November 201630