Page 1: Central Kitchen Stakeholder Meeting

Central Kitchen Stakeholder Meeting

June 7, 2017Hiram Johnson Cafeteria6879 14th Avenue

Page 2: Central Kitchen Stakeholder Meeting

Central Kitchen Stakeholder Meeting

Welcome and Introductions Project Scope / Central Kitchen Project Schedule Conceptual Design / Planning Options Community Input Session Additional Topic Development Breakout Discussion / Input / Priorities Dot Polling Exercise Next Steps

Page 3: Central Kitchen Stakeholder Meeting

Welcome and Introductions

Jessie Ryan1st Vice President, Board of EducationCo-Chair, Central Kitchen Taskforce

José L. BandaSuperintendent

Page 4: Central Kitchen Stakeholder Meeting

Central Kitchen Stakeholder Meeting

Project Scope / Central Kitchen Project Schedule Conceptual Design / Planning Options Community Input Session Additional Topic Development Breakout Discussion / Input / Priorities Dot Polling Exercise Next Steps

Page 5: Central Kitchen Stakeholder Meeting

San Joaquin Street

Redding Ave SiteWarehouseNutrition ServicesPrint ShopGroundsTransportationPurchasingLibrary Services10.2 Acres

Red

din

g A

ven

ue

Overall Project Scope / Central Kitchen

Page 6: Central Kitchen Stakeholder Meeting

• Kitchen Adjacent to Warehouse

• Transportation Relocated

• New Parking for all functions

• Storm water Treatment

• Community Garden

• CTE Opportunity

Overall Project Scope / Central Kitchen

Page 7: Central Kitchen Stakeholder Meeting

Programming Phase April – May ‘17

CEQA, CDE, DTSC Evaluations May ‘17

Design Process (P/SD/DD/CD) June ‘17 – June ‘18

Permitting July ‘18 – Jan ‘19

Bidding Jan – April ‘19

Phase 1 Construction (San Joaquin) May – Dec ‘19

Phase 2 Construction (Redding) Jan ‘20 – June ‘21

Schedule

Page 8: Central Kitchen Stakeholder Meeting

Conceptual Design / Planning Process

• Site Assessment• Bldg Assessment• Context• Space Inventory• Space Needs• Program Developed• Adjacencies• Relationships• Infrastructure• Cost • Prioritization• Design

Page 9: Central Kitchen Stakeholder Meeting

Community Input Session

Central Kitchen Transportation Community Questions / Concerns Sustainability Architectural Design Others?

Page 10: Central Kitchen Stakeholder Meeting

Dot Polling

Page 11: Central Kitchen Stakeholder Meeting

Next Steps

Review / Analyze Input Document Findings Schedule Follow-up Meetings Finalize Program Begin Design Continue Community Dialogue

Page 12: Central Kitchen Stakeholder Meeting

Central Kitchen Stakeholder Meeting

June 7, 2017Hiram Johnson Cafeteria6879 14th Avenue