Top Banner
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done : (1/2) Preliminary civil engineering drawing and Functional specification approved by CERN on 18/03/2014 (EDMS 1365362 and 1350076) Civil engineering Tender Design phase started on 2/04/2014 by ARCADIS Submission of the « Permis de construire » on 19/05/2014 Market survey issued to the firms on 11/06/2014 → Two work packages (WP1-Civil engineering & WP2-Steel structure and cladding) 02 October 2014 1 Extension of Building 887 - Neutrino Platform General Meetings N.Lopez – M.Manfredi
4

CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.

Jan 17, 2016

Download

Documents

Conrad Riley
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.

CENF – Civil Engineering Extension B887Status – 02 October 2014

Done: (1/2)

Preliminary civil engineering drawing and Functional specification approved by CERN on 18/03/2014 (EDMS 1365362 and 1350076)

Civil engineering Tender Design phase started on 2/04/2014 by ARCADIS

Submission of the « Permis de construire » on 19/05/2014

Market survey issued to the firms on 11/06/2014 → Two work packages (WP1-Civil engineering & WP2-Steel structure and cladding)

02 October 20141

Extension of Building 887 - Neutrino Platform General MeetingsN.Lopez – M.Manfredi

Page 2: CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.

Done: (2/2)

Tender documents ready and EDMS approval procedure launched on 10/07/2014 → 9 firms qualified for WP1, 7 firms for WP2 and 4 firms for WP 1+2

Specification Committee meeting held on 29/07/2014

Tender documents sent to the firms on 18/08/2014

Construction Design phase started on 18/08/2014 by ARCADIS

Bidders Conference held on 4/09/2014

Extension of Building 887 - Neutrino Platform General MeetingsN.Lopez – M.Manfredi

CENF – Civil Engineering Extension B887

02 October 20142

Page 3: CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.

Next steps:

Bids expected on 2/10/2014

Preparatory works to start on October 2014 (abattage, déviation de réseaux, etc)

Construction Design expected on November 2014

Adjudication foreseen on December 2014 FC

Contract signature

Start of the works expected on January 2015 (if possible, anticipate Excavation works as early as possible)

Extension of Building 887 - Neutrino Platform General MeetingsN.Lopez – M.Manfredi

CENF – Civil Engineering Extension B887

TODAY // Commercial Opening soon

02 October 20143

Page 4: CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.

Remarks: All material requiring CERN approval or distribution process is on EDMS (CERN-0000097536 v.0) Public documents available are the Preliminary Civil Engineering drawing (n°1365362) and Functional

specification (n°1350076)

Tender drawings and documents are «Released» but still with restricted access. Construction drawings will be «Under Approval» once received. As agreed, all the users request (i.e. general or specific information, coordination plan, etc..) concerning

the integration studies has to pass via Ilias Efthymiopoulos and his group.

Extension of Building 887 - Neutrino Platform General MeetingsN.Lopez – M.Manfredi

CENF – Civil Engineering Extension B887

02 October 20144