Agenda
• Cedarvale Station Update
• Forest Hill Station Update
3
Cedarvale Station Updates – October 2017
Complete• Shoring for the east entrance (east of Allen Rd North, north of Eglinton Ave) • Everden Road utilities relocation works (sanitary sewer & water main) • 3/3 invert concrete pours in the launch shaft (east of the Allen)• Invert tunnel concrete pour • Utilities relocation works (Sanitary sewer & water main) across the Toronto Police
parking lot • Excavation for the east entrance• Utilities relocation works on Winnett Avenue• Roof slab concrete pour 1 of 3Ongoing• Waterproofing and formwork at the launch shaft• Noise and vibration monitoring• Shoring on the south side of Eglinton AveUpcoming• Roof slab concrete pour 2 and 3 • South Allen Road Diversion• Backfill of LS2 Crossover• Shoring on the north side of Eglinton Ave
4
Construction Progress Picture
First roof slab pour
5
Construction Progress Picture
Utility relocation under Eglinton Avenue at Winnett
6
Forest Hill Station Construction Update
Fall 2017
• Continue piling the south side of the station box
• Continue roof slab construction of the southwest side of the station box
• Continue piling at the Main Entrance
• Continue wet utilities relocation
7
Current Traffic Staging
Began September 2017 for approximately four (4) months
8
Forest Hill Station Concept Aerial View
Main Entrance
Secondary Entrance
*60% rendering
9
Forest Hill Station Construction Progress
9
DRILLING – MAIN ENTRANCE
10
Forest Hill Station Construction Progress
DRILLING – SOUTHWEST CORNER
11
Local Area Map