Top Banner

of 32

Cec Case Study of 20 Marks

Apr 03, 2018

Download

Documents

Ajay Gohil
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/29/2019 Cec Case Study of 20 Marks

    1/32

    Front page will be declared later:

    CEC case study of 20 marks.

    There will be 10 questions per group and each question will carry

    2 marks.

    That means 10 * 2 = 20marks

    CEC case study declaration date 13th of March 12, 2013

    CEC case study submission date 30th of March 12, 2013,

    After last date no case study will be accepted.

    They will be given zero marks in their assignment submission of

    10 marks.

    Viva of the above question will be declared later on.

  • 7/29/2019 Cec Case Study of 20 Marks

    2/32

    Questions for group number 1

    1. Samsnit Ltd. uses process cost system to manufacture a special type of kit for the

    textile industry. The company has furnished the following information pertaining tooperations for the month of June 2004:

    Particulars Units

    Opening work-in-process (June 01, 2004) 650

    Introduced in production during June2004 7,800

    Closing work-in-process (June 30, 2004) 580

    There is no loss in the manufacturing process. The opening inventory was 80% complete for

    materials and 60% complete for conversion costs. The closing inventory was 75% complete for

    material and 65% complete for conversion costs.

    Costs pertaining to the month of June 2004 are as follows:

    Opening work in process:

    Materials Rs. 19,850

    Conversion Rs. 21,250

    During the month:

    Materials Rs.4,98,240

    Conversion Rs.5,49,990

    The total cost of closing work-in-process on June30, 2004, using FIFO method,

    2. Mani Ltd. has 3 identical machines manned by 4 operators. The operators are fully

    engaged on machines. The total original cost of these 3 machines is Rs.12,00,000. The

    company has furnished the following information pertaining to operations for 1st quarter

    ending

    June 30, 2004:

    Normal available hours per month per operator 500 hours

    Absenteeism (without pay) 50 hours

    Leave (with pay) 70 hours

    Normal idle time (unavoidable) 10 hours

    Average rate of wages per hour Rs.20

    Estimated production bonus 8% on wages

  • 7/29/2019 Cec Case Study of 20 Marks

    3/32

    Value of power consumed Rs.28,500

    Supervision and indirect labor Rs.42,400

    Electricity and lighting Rs.19,600

    Repairs and maintenance per quarter 1% on value of machines

    Depreciation per annum 10% on original cost

    Miscellaneous expenses per annum Rs.48,000

    General management expenses per annum Rs.80,000

    The comprehensive machine hour rate for the machine shop for the quarter ending June 30,

    2003 is

    3. Plastic Furniture Ltd. manufactures plastic TV stands. The company is working at

    80% capacity level, which represents 24,000 units per month. The cost break-up per

    TV stands is as under:

    Materials Rs.140

    Labor Rs. 60

    Overheads Rs. 80 (50% fixed)

    The selling price is Rs.360 per unit. The company is planning to produce at 90% capacity

    level. At 90% capacity level the selling price falls by Rs.20 accompanied by 5% fall in the

    price of materials.

    The break-even point in units and profit at 90% level of capacity of the company are

    4. XY Ltd. wants to buy a new machine to replace the old one, which is having frequent

    breakdowns. The company received offers for two models M1 and M2. The details of

    the two models are as under:

    Particulars Model M1 Model M2

    Installed capacity in units 25,000 25,000

    Fixed overhead expenses per annum Rs.6,00,000 Rs.2,50,000

    Estimated profit at the above capacity Rs.4,00,000 Rs.2,50,000

    The sale price per unit of product manufactured by these types of machines is Rs.80.

    The level of sales at which both the models will earn the same profit

    5. Mohan Constructions undertook a contract for construction of a large complex in

    Secunderabad. The construction work commenced on April 01, 2003 and the

    following data are available for the year ended March 31, 2004:

  • 7/29/2019 Cec Case Study of 20 Marks

    4/32

    Particulars Rs.

    Total contract price 1,25,00,000

    Work certified 79,00,000

    Progress payment received 62,50,000

    Material issued to site 40,80,000

    Direct wages paid 16,50,000

    Materials returned from site 51,500

    Plant hire charges 1,25,000

    Wage related costs 99,500

    Direct expenses incurred 63,500

    Work not certified 11,11,500

    Materials at site 40,500

    Accrued wages 34,000

    The contractors own a plant which originally cost Rs.12,00,000 and has been continuously in

    use in this contract throughout the year. The salvage value of the plant after 10 years is nil.

    The company uses the straight-line method of depreciation. The total of work-in-process and

    plant at site to be shown in the balance sheet as on March 31, 2004 is

    6. Thaparia Ltd., using process costing, manufactures a single product, which passes

    through two processes process 1 and process 2, the output of process 1 becoming

    the input to process 2. The company has furnished the following information relatingto the product for the month of June 2004:

    I.Raw material issued to process 1 was 4,500 units at a cost of Rs.11.80 per unit.

    II. There was no opening or closing work-in-progress but opening and closing stocks

    of finished goods were Rs.15,130 and Rs.14,500 respectively.

    III. Normal losses and abnormal losses are defective units having a scrap value and

    cash is received at the end of the period for all such units.

    Other information:

    Particulars Process 1 Process 2

    Normal loss as a percentage of input 10% 5%

    Output in units 4,200 3,970

    Scrap value per unit (Rs.) 3.80 2.90

    Additional components introduced (Rs.) 1,800 1,150

  • 7/29/2019 Cec Case Study of 20 Marks

    5/32

    Direct wages incurred (Rs.) 6,500 7,250

    Direct expenses incurred (Rs.) 3,235 3,799

    Production overhead as a % of direct

    wages

    60 40

    The cost of goods sold of the product for the month of June 2004 is

    7. A product, which uses 100 tons as input per month, passes through two processes

    Process 1

    and Process 2. The details of cost of process 1 for the month of June 2004 are as

    follows:

    Process 1 Cost per ton (Rs.) of input

    Direct material cost 1,550

    Direct labor cost 1,200

    Overhead costs 1,349

    The total loss in process 1 is 2% of input and the scrap is 6% of the input with a value of

    Rs.850 per ton. The material is transferred to process 2 at cost. The direct labor cost of

    Process 2 is Rs.1,250 per ton of input. The overhead is 60% of direct labor cost. The scrap

    at process 2 is 10% of input with a value of Rs.850 per ton.

    The cost per unit of finished goods in process 2 is

    8. Shiv Sankar Ltd. manufactures four products A, B, C & D, which emerge from a

    particular process of operation. The total cost of input for the period ended March 31,

    2004 is Rs.4,80,000. The details of output, additional cost after split-off point and

    sales value of the products are as follows:

    Product

    s

    Output

    (Kg.)

    Additional processing

    cost

    after split-off point (Rs.)

    Sales value after

    further process

    (Rs.)

    A 12,000 22,000 2,40,000

    B 6,000 20,000 1,44,000

    C 8,000 4,000 1,44,000

    D 4,000 18,000 80,000

    If the products are sold at split-off point without further processing, the sales value would

    have been:

    A Rs.2,16,000

    B Rs.1,26,000

    C Rs.1,40,000

  • 7/29/2019 Cec Case Study of 20 Marks

    6/32

    D Rs. 56,000

    The maximum amount of profit of the company from the four products is

    9. Kappa Ltd. uses a process cost system to manufacture product - K. The company has

    furnished the following information pertaining to operation for the month of June

    2004:

    Particulars Units

    Opening work-in-process inventory, June 1, 2004 5,500

    Unit introduced during June 2004 29,000

    Unit completed during June 2004 32,500

    Closing work-in-process inventory, June 30, 2004 2,000

    The opening inventory was 60% complete for materials and 50% complete for conversion

    costs. The closing inventory was 80% complete for materials and 60% complete for

    conversion costs.

    Costs pertaining to the process for the month of June 2004 were as follows:

    I) Opening inventory costs are: Materials Rs.22,500, Labor cost Rs.16,200

    Factory Overhead Rs.7,500

    II) Costs incurred during the month: Materials used Rs.1,65,000, Labor cost

    Rs.1,10,000

    Factory overhead Rs.62,500

    Using the weighted average method, the equivalent unit cost of material for the month of

    June2004 is

    10. Consider the following data pertaining to inventories of CBX Ltd. for the month of

    June 2004:

    Particulars Opening inventory

    (Rs.)

    Closing inventory

    (Rs.)

    Raw materials 16,330 18,540

    Work-in-process 9,320 6,520

    Finished goods 4,300 4,440

    Other information:

  • 7/29/2019 Cec Case Study of 20 Marks

    7/32

    i. Raw materials used Rs.78,390

    ii. Total manufacturing costs charged to product

    (it includes raw materials, direct labor and

    factory overheads applied at the rate of 50%

    of direct labor cost) Rs. 2,85,960

    iii. Cost of goods available for sale Rs.3,25,600

    iv. Selling and general expenses Rs.6,300

    The costs of raw materials purchased and the direct labor are

    Group number 2

    11. The budgeted working conditions of a cost center of Super T Ltd. are as follows:

    Normal working per week 42 hours

    No. of machines 8

    Normal weekly loss of hours on

    maintenance etc 4 hours per machine

    No. of weeks worked per year 50

    Estimated annual overheads Rs.3,04,000

    Estimated wage rate Rs12 per hour

    Actual results in respect of a 4 week period are:

    Wages incurred Rs.17,000

    Overheads incurred Rs.23,300

    Machines used 1,200 hours

    The amount of under or over absorption of wages and overheads respectively are

    12. Moonstar Ltd. had the following inventories at the beginning and end of the month of

    June 2004:

    Particulars June 1, 2004 (Rs.) June 30, 2004 (Rs.)

    Finished goods 85,000 81,000

    Work-in-process 72,000 63,500

    Direct materials 90,000 82,500

    The following additional manufacturing data were available for the month of June 2004:

    Particulars (Rs.)

    Direct materials purchased 2,93,400

    Purchase returns and allowances 2,600

  • 7/29/2019 Cec Case Study of 20 Marks

    8/32

    Transportation 2,900

    Direct labor 2,68,000

    Actual factory overhead 1,65,000

    The company applies factory overhead at a rate of 40% of direct labor cost, and any over

    applied or under applied factory overhead is deferred until the end of the year 2004-05.The manufacturing cost of the company for the month of June 2004 was

    13.Bismat Ltd. manufactures and sells a special type of product K. Presently, the

    company manufactures 8,000 units, which is 80% of the potential capacity. The

    present cost structure per unit of the product K is given below:

    Direct materials Rs.200

    Direct labor Rs.150

    Factory overhead Rs. 100 (40% fixed)

    Selling overhead Rs. 80 (50% fixed)

    The company estimates to produce the same number of units of the product during the

    following year and anticipates that fixed cost will go up by 10% while the rates of direct

    materials and direct labor will increase by 8% and 6% respectively. The company has no

    intention to increase its present sale price of Rs.580 per unit. Under these circumstances,

    the company obtained an offer to supply 1,000 units of the product to a special customer.

    The minimum sale price per unit of additional order of 1,000 units to be quoted to the

    customer if the company desires to earn an overall profit of Rs.2,50,000 is

    14. Santaram Ltd. manufactures a single product at the operated capacity of 20,000

    units while the normal capacity of the plant is 25,000 units per annum. The

    company has estimated 20% profit on sales realization and furnished the followingbudgeted information:

    Particulars25,000 units

    (Rs.)

    20,000 units

    (Rs.)

    Fixed overheads 2,00,000 2,00,000

    Variable overheads 4,00,000 3,20,000

    Semi-variable overheads 2,50,000 2,20,000

    Sales realization 15,00,000 12,00,000

    The company has received an order from a customer for a quantity equivalent to 10% of

    the normal capacity. It is noticed that prime cost per unit of product is constant. If the

    company desires to maintain the same percentage of profit on selling price, the minimum

    price per unit to be quoted for new order is

    15. Jyothi Ltd. is attempting to compute costs for its three products for pricing

    purposes. The company has annual fixed manufacturing costs of Rs.5,32,000. The

  • 7/29/2019 Cec Case Study of 20 Marks

    9/32

    variable costs of the companys products are as follows:

    ProductVariable costs of manufacture

    (per unit) (Rs.)

    A

    B

    C

    20

    30

    40

    The company expects to produce and sell 5,000 units of A, 6,000 units of B, and 8,000

    units of C annually. The policy of the company is to add a markup of 25% to each

    products total manufacturing costs to compute the tentative selling price. The selling

    prices of product A, B and C, if fixed costs are allocated on the basis of number of units

    produced, are

    16. Motilal Ltd. manufactures and sells a single product. The estimated activity of the

    company for the month of June 2004 is as follows:

    Sales Rs.8,50,000

    Gross profit on sales 30%

    Increase in inventory during the month Rs.25,800

    Increase in sundry debtors Rs.19,500

    Total selling and administrative expensesRs.50,000 + 2.5% on

    sales

    Depreciation expenses which is included in

    fixed selling and administrative expenses Rs.20,000

    The net cash surplus or deficit for the month of June 2004 is

    17. Shira Ltd. pays commission to its salesmen in the month the company receives

    cash for sales, which is equal to 4% of the cash inflows. The company has

    budgeted sales of Rs.6,50,000 for July 2004, Rs.7,00,000 for August 2004 and

    Rs.7,50,000 for September 2004. 50% of the sales are on credit. Experience

    indicates that 70% of the budgeted credit sales will be collected in the month

    following the sales. 25% are expected to be realized in the second month following

    the month of sales and remaining 5% will be non-recoverable.

    The total amount of sales commission for the month of September 2004 is

    18. Tripty Ltd. has a policy of maintaining a minimum cash balance of Rs.50,000 at the

    end of each month. Any deficit below Rs.50,000 will be financed through bank

    borrowings and any surplus will be utlised to repay the outstanding bank borrowing

    and the balance will be invested in short-term securities. For this purpose, the

    company has an agreement with the bank to borrow in multiples of Rs.5,000

    whenever a need arises subject to a maximum of Rs.60,000. The rate of interest is

  • 7/29/2019 Cec Case Study of 20 Marks

    10/32

    12% per annum payable monthly on the amount borrowed.

    50% of the sales are on credit and is expected to be collected in the month following the

    month of sales. 25% of the purchases are on credit and will be paid in the month following

    the month of purchases. The salaries and other expenses are to be paid in the month for

    which they relate. The following is the budgeted information for the quarter ending

    September 2004:

    Particulars July 2004

    Rs.

    August

    2004

    Rs.

    September

    2004

    Rs.

    Sales 20,000 30,000 40,000

    Purchases 20,000 30,000 30,000

    Salaries 10,000 10,000 10,000

    Manufacturing and otheradministrative expenses

    10,000

    10,000

    10,000

    If the closing cash balance as on July 31, 2004 is Rs.50,000, the cash balance as on

    October 01, 2004 before borrowing will be

    19. XY Ltd. has prepared the following budget for the year 2004-05:

    Particulars Percentage to total sales(Rs.)

    Direct materials 40

    Direct labor 20

    Factory overheads Variable

    10

    Fixed 8

    Selling and administrative overheads Variable

    12

    Fixed 06

    Profit 04

    Total 100

    After evaluating the first quarter performance, it was observed that the company would be

    able to achieve only 80% of the original budgeted sales. The revised budgeted sales as

    envisaged above was estimated at Rs.2,400 lakh after taking into account a reduction in

    selling price by 20%.The original budgeted sales at original price is

  • 7/29/2019 Cec Case Study of 20 Marks

    11/32

    20. Sreyi Ltd. has furnished the following data relating to a product for the year 2003

    04:

    Units produced 4,000

    Direct materials

    (Rs.)5,20,000

    Direct labor (Rs.) 3,40,000

    Manufacturing overheads

    (Rs.)2,00,000 (25% fixed)

    Selling and administrative overheads

    (Rs.)1,50,000 (40% fixed)

    If the company manufactures 4,400 units in the next year, the total cost per unit would be

    Group number 3

    21.Leo Ltd. manufactures toy cats with moving parts and a built-in voice box.

    Projected sales for 5 months are as follows:

    Month Projected sales in units

    July 2004 3,500

    August 2004 3,900

    September 2004 4,200

    October 2004 4,500

    November 2004 4,800

    Each toy requires direct materials from a supplier at Rs.80 for moving parts. Voice boxes

    are purchased from another supplier at Rs.20 per toy. Labor cost is Rs.30 per toy and

    variable overhead cost is Rs.5 per toy. Fixed manufacturing overhead applicable to

    production is Rs.51,000 per month. It is the practice of the company to manufacture an

    output in a month which is equivalent to 1.2 times of the following months sales.

    The production budget for the month of August 2004 and the production cost budget for

    the month of September 2004 are

    22.The flexible budget for the month of July 2004 was for 12,000 units with direct

    material cost at Rs.25 per unit. Direct labor was budgeted at 45 minutes per unit

    for a total cost of Rs.1,44,000. Actual output for the month was 10,800 units with

    Rs.2,70,000 in direct material and Rs.1,30,000 in direct labor expenses. The direct

    labor standard of 45 minutes was maintained throughout the month. The variance

    analysis of the performance for the month of July 2004 would show a(n)

  • 7/29/2019 Cec Case Study of 20 Marks

    12/32

    23. Avoy Ltd. manufactures two products X and Y, using same facilities and similar

    process. The company has furnished the following information pertaining to two

    products for the year ending March 31, 2004.

    Particulars Product X Product Y

    Direct labor hours per unit 4 2.5

    Machine hours per unit 5 4

    Number of set ups during the period 22 18

    Number of orders handled during the period 16 19

    Production units 6,000 4,340

    Total production overhead costs for the period are as follows:

    Particulars Rs.

    Machine activity costs 2,40,000

    Set-ups costs 56,000

    Order handling costs 52,500

    3,48,500

    The absorption of total production overheads of both the products on the basis of a

    suitable cost driver, using Activity Based Costing method, is

    Product X (Rs.) Product Y (Rs.)

    24.Acer Ltd. manufactures 6,000 units of Product PT at a cost of Rs.150 per unit.

    Presently, the company is utilizing 60% of the total capacity. The information

    pertaining to cost per unit of the product is as follows:

    Material Rs.80

    Labor Rs.20

    Factory overheads Rs.30 (40% fixed)

    Administrative overheads Rs.20 (50% fixed)

    Other information:

    i. The current selling price of the product is Rs.200 per unit.

    ii. At 70% capacity level Material cost per unit will increase by 2% and

    current selling price per unit will reduce

    by 2%.

    iii. At 90% capacity level Material cost per unit will increase by 5% and

  • 7/29/2019 Cec Case Study of 20 Marks

    13/32

    current selling price per unit will reduce

    by 5%.

    The profit per unit of the product of the company at 70% and 90% capacity levels will be

    25. Sri Ram Ltd. uses a Standard costing system. The following details have been

    extracted from the standard cost card in respect of direct materials for the monthof June 2004.

    Material usage per unit 5 kg at the rate of Rs.15 per kg

    Budgeted production 1000 units

    The company has furnished the following data relating to direct material for the month of

    June 2004:

    Materials purchased 5,400 kg at a price of Rs.86,400

    Materials issued to production 4,670 kgs

    Actual production 900 units

    The material price and material usage variances are

    26. Mina Processors Ltd. produces a commodity by blending two raw materials A and

    B. The following are the details regarding the raw materials:

    Material Standard mix Standard price per kg.

    A 60% Rs. 8

    B 40% Rs.10

    The standard process loss is 10%. During the month of June 2004, the company produced5,000 kg. of finished product. The position of stock and purchases for the month of June

    2004 is as under:

    Material Stock as on June

    01, 2004

    Kg.

    Stock as on June

    30, 2004 Kg.

    Purchases during June

    2004

    Kg. Rs.

    A 120 50 3,000 24,900

    B 80 30 2,500 24,000

    The material yield variance of the company is

    27. SD Ltd. uses a standard absorption costing system. The following data have been

    extracted from its budget for the month of June 2004:

    Fixed production overhead cost Rs.1,20,000

    Production 12,000 units

  • 7/29/2019 Cec Case Study of 20 Marks

    14/32

    In June 2004, the fixed production overhead cost was under absorbed by Rs.10,500 and

    the fixed production overhead expenditure variance was Rs.2,800 (Adverse).The actual

    number of units produced was

    28. VK Ltd. has furnished the following data pertaining to a product for the month of

    June 2004:Particulars Budget Actual

    Production units 10,000 10,400

    Labor hours 5,000 4,800

    Fixed overheads (Rs.) 85,000 87,200

    Number of working days 25 24

    The fixed overhead volume variance is

    29. Sri Durga Pump Ltd. manufactures water pumps and uses a standard cost system.The following standard factory overhead costs per water pump are based on direct

    labor hours:

    Variable overheads (40 hours at the rate of Rs.20 per hour) Rs.800

    Fixed overheads (40 hours at the rate of Rs.15 per hour) Rs.600

    The additional information is available for the month of June 2004:

    i. 4,000 pumps were produced although 4,200 had been scheduled for production

    ii. The normal capacity level was 1,68,000 direct labor hours per month

    iii. 1,59,000 direct labor hours were worked at a total cost of Rs.38,16,000

    iv. The standard direct labor rate is Rs.25 per hour

    v. The standard direct labor time per unit is 40 hours

    vi. Variable overhead costs were Rs.33,20,000

    vii. Fixed overhead costs were Rs.25,50,000

    The fixed overhead expenditure variance and direct labor efficiency variance are

    30. Consider the following data pertaining to overhead cost for the month of June 2004:

    i. Overhead cost variance Rs.5,200 (A)

    ii. Overhead volume variance Rs.3,800 (A)

    iii. Budgeted hours for the month 2,500

    iv. Budgeted overheads for the month Rs.20,000

  • 7/29/2019 Cec Case Study of 20 Marks

    15/32

    v. Rate of recovery of overheads Rs.20 per hour

    The actual overhead incurred by the company is

  • 7/29/2019 Cec Case Study of 20 Marks

    16/32

    Group number 4

    31. X Ltd. operates under a standard cost system. Factory overhead cost is applied to

    products on a direct labor hour basis. At normal operating level, the company

    utilizes 2,00,000 direct-labor hours per year. The budgeted overhead cost at normal

    capacity level is as follows:

    Variable Rs.6,50,000

    Fixed Rs.4,20,000

    During the year 2003-04, the actual labor hours were 2,20,000 to get production that

    should have required only 1,80,000 hours. The overhead efficiency variance is

    32. MN Ltd. uses standard process costing method. The standard process cost card per

    month shows that 4 hours of direct labor is required to produce one kg. of finished

    product and the fixed overheads, which are recovered on direct labor hours,amount to Rs.180 per kg. of output. The budgeted output is 4,000 kgs. per month.

    Actual production during the month of June 2004 is 3,800 kgs. and the direct labor hours

    utilized during the month were 14,800.

    The details of opening and closing work-in progress (WIP) are as under:

    Opening work-in-progress 300 kgs.(Degree of completion of labor and overheads 60%)

    Closing work-in-progress 480 kgs.(Degree of completion of labor and overheads 20%)

    The company uses FIFO method for evaluation of stocks.

    The fixed overhead efficiency variance is

    33. The standard labor component and the actual labor component for a job in a week

    are given below:

    ParticularsSkilled

    workers

    Semi-skilled

    workers

    Unskilled

    workers

    i. Standard number of workers in the

    gang40 30 20

    ii. Standard wage rate per hour (Rs.) 20 16 10

    iii. Actual number of workers employedin the gang during the week

    36 20 34

    iv. Actual wage rate per hour (Rs.) 32 23 8

    During the 40 hours working week, the gang produced 3,400 standard labor hours of work.

    The labor efficiency variance is

  • 7/29/2019 Cec Case Study of 20 Marks

    17/32

    34. The data relating to Sinha Ltd. for the month of June 2004 are as follows:

    Output (units)

    Wages paid for 4,850 hours

    Material purchased 2,500 kg

    5,000

    Rs. 87,300

    Rs. 40,000

    Variances:

    Variances Rs.

    Labor rate

    Labor efficiency

    Labor idle time

    Material price

    Material usage

    2,130 (A)

    2,250 (F)

    300 (A)

    2,560 (F)

    2,940 (F)

    The standard prime cost per unit is

    35. Consider the following details pertaining to Srikanth Ltd. for the month of June

    2004:

    Particulars Rs.

    Sales 60,000

    Direct materials 18,500

    Direct labor 14,000

    Variable overheads 8,000

    Capital employed 1,20,000

    The return on investment in June 2004 is 12.5%. In the month of July 2004, it is expected

    that the volume of sales will be increased by 15%, the selling price will be increased by 2%

    and there will be a reduction of all other costs by 2%. The change in the return on

    investment for the month of July 2004 will be

    36. Consider the following data of AB Ltd. for the quarter ending June 30, 2004:

    Projected sales 5,000 units

    Raw materials per unit of finished goods 4 kg

    Opening stock of finished goods 675units

  • 7/29/2019 Cec Case Study of 20 Marks

    18/32

    Closing stock of finished goods 850units

    Opening stock of raw materials 4,500 kg

    Closing stock of raw materials 6,200 kg

    The total quantity of materials purchased during the quarter is

    37. Siva Ltd. manufacturers cabinets and outsources handles of the cabinet. Eachcabinet requires four handles. The direct labor time for assembly work is 30

    minutes per cabinet. The closing stock of finished cabinets in a month is estimated

    to be 50% of projected unit sales for the next month. The closing stock of handles

    in a month is planned to be 60% of the requirement for the second following month.

    The company has furnished the following projected unit sales:

    July 2004 300 cabinets

    August 2004 310 cabinets

    September 2004 320 cabinets

    October 2004 350 cabinets

    The closing inventory of the company for the month of June 2004 are as follows:

    Cabinets 150

    Handles 800

    The number of handles to be purchased in the month of July 2004 is

    38. ABC Constructions Ltd. has taken two contracts on April 01, 2003. The position of

    the contracts as on March 31, 2004 is as follows:

    ParticularsContract A

    (Rs.)

    Contract B

    (Rs.)

    Contract price 54,00,000

    1,20,00,000

    Materials 11,60,00

    0

    21,60,000

    Wages paid 22,48,00

    0

    33,00,000

    Other expenses 56,000 1,20,000

    Plant at site 3,20,000 6,00,000

    Unused materials at site 80,000 1,20,000

    Wages accrued 72,000 1,08,000

    Other expenses due 8,000 18,000

    Work certified 32,00,00

    0

    60,00,000

    Cash received 24,00,00 45,00,000

  • 7/29/2019 Cec Case Study of 20 Marks

    19/32

    0

    Work completed but not yet certified 1,60,000 1,80,000

    The plant at site is to be depreciated at 12% per annum.

    The values of work in progress of each contract respectively are

    39. Aditya Ltd., using process costing, manufactures a single product, which

    passes through two processes process 1 and process 2, the output of

    process 1 becoming the input to process 2. The company has furnished

    the following information relating to the product for the month of

    September 2004:

    i) Raw material issued to process 1 was 3,000 units at a cost of Rs.5 per unit.

    ii) There was no opening or closing work-in-progress but opening and closing

    stocks of finished goods were Rs.20,000 and Rs.23,000 respectively.

    iii) Normal losses and abnormal losses are defective units having a scrap

    value and cash is received at the end of the period for all such units.

    Other information:

    Particulars Process 1 Process 2

    Normal loss as a percentage of input 10% 5%

    Output in units 2,800 2,600

    Scrap value per unit (Rs.) 2 5

    Additional components introduced (Rs.) 1,000 780

    Direct wages incurred (Rs.) 4,000 6,000

    Direct expenses incurred (Rs.) 10,000 14,000

    Production overhead as a % of direct

    wages

    75 125

    The cost of goods sold of the product for the month of September 2004 is

    40. Marphy Company manufactures radios, which are sold at Rs.1,600 per

    unit. The total cost consists of 30% for direct materials, 40% for directwages and 30% for overheads. An increase in material price by 30%

    and in wage rates by 10% is expected in the forthcoming year, as a

    result of which, the profit at current selling price may decrease by 40%

    of the present profit per unit. The future selling price to maintain same

    profit percentage is

  • 7/29/2019 Cec Case Study of 20 Marks

    20/32

    Group number 5

    41. The cost data pertaining to Product X of XL Ltd. are as follows:

    Maximum capacity 30,000 units

    Normal capacity 15,000 units

    Increase in inventory 1,880 units

    Variable cost per unit Rs.12

    Selling price per unit Rs.50

    Fixed manufacturing overhead

    costs

    Rs.3,60,000

    If the profit under Absorption costing method is Rs.1,01,000, the profit under

    Marginal costing method would be

    42. JIT Ltd. has a factory where four products are manufactured in a common

    process. During September 2004, the costs of the common process were

    Rs.1,60,000. The data pertaining to four products is as follows:

    Product

    Production

    SalesSales value per

    unit

    A 600 units

    B 400 units

    C 500 units400

    units

    Rs. 70

    D 600 units450

    units

    Rs.100

    Products A and B are further processed to make finished products X and Y

    respectively. The data relating to Products X and Y is given below.

    Product Production Sales Cost of furtherprocessing Sales value perunit

    X 600 units600

    units

    Rs.10,000 Rs.100

    Y 400 units 300unit

    Rs.25,000 Rs.200

  • 7/29/2019 Cec Case Study of 20 Marks

    21/32

    s

    There was no opening stock. Company uses sales value at split off point as basis

    for apportionment of common costs.

    The profits of product Y and product C are

    43.Bharti Ltd. has furnished the following data pertaining to manufacturing

    operations for the month of September 2004:

    Particulars Rs.

    Raw materials (September

    1,2004)

    6,000

    Direct labor cost 25,000 (125% of factory

    overhead )

    Work-in-progress (September

    1,2004)

    7,000

    Finished goods (September

    1,2004)

    12,000

    Cost of goods sold 88,000

    Selling expenses 8,500

    Raw materials (September

    30,2004)

    6,800

    Work-in-progress (September

    30,2004)

    6,500

    Finished goods (September

    30,2004)

    12,800

    Sales for the month 1,12,500

    The materials purchased and profit earned by the company for the month of

    September 2004 are

    44. Two manufacturing companies AB Ltd and XY Ltd. have decided to merge

    their business operations. They have furnished the following operation details:

    Particulars AB Ltd XY Ltd

    Capacity utilization (%) 90 60

    Sales (Rs. in lacs) 540 300

    Variable costs (Rs. in

    lacs)

    396 225

    Fixed costs (Rs. in lacs) 80 50

  • 7/29/2019 Cec Case Study of 20 Marks

    22/32

    The profitability of the merged plant at 80% capacity level is

    45. XLNT Ltd. has furnished the following information pertaining to the

    forthcoming year:

    Budgeted Variable

    costs

    60% of sales

    value

    Budgeted Fixed costs

    20% of salesvalue

    If the company increases the selling price by 10% but the fixed costs, variable cost

    per unit and sales volume remain unchanged, the effect on contribution would be

    46. Quadila Ltd. has furnished the following information pertaining to its product

    for the period ended September 30,2004:

    Selling price perunit

    Rs.80

    Variable cost perunit

    Rs.35

    Fixed cost Rs.5,96,000

    The company plans to improve the quality of its sole product by

    i. Replacing a component that costs Rs.6.25 with a higher-grade unit that costs

    Rs.8.00.

    ii. Acquiring a packing machine of Rs.80,000.

    The company will depreciate the machine over a period of 10 years with no

    estimated salvage value by the Straight Line Method of depreciation. The income tax

    rate is 40%. If the company desires to earn a post-tax profit of 10% on sales in the

    next period, the units to be sold by the company in the next period are

    47. Sams Ltd. manufactures and sells two products M and N. The following data

    are estimated for the quarter ending September 30, 2004 .

    ParticularsProduct

    M

    Product

    N

    Sales (Units) 80,000 1,20,000

    Sale price per unit

    (Rs.)20 16

    Variable cost per unit 12 10

  • 7/29/2019 Cec Case Study of 20 Marks

    23/32

    (Rs.)

    The annual fixed costs are estimated at Rs.8,16,000. The break-even point in sales

    value with the current sales mix is

    48. ACD Ltd. has been approached by a foreign customer who wants to place an

    order for 1,500 units of Product C at Rs.22.50 a unit although the company

    currently sells this item for Rs.39 a unit, and the item has a cost of Rs.29 per

    unit. Further analysis reveals that the company will not pay sales

    commission of Rs.2.50 a unit on these sales and its packaging requirement

    will save an additional amount of Rs.1.50 per unit. However, the additional

    graphics required on this job will cost Rs.3,000. The fixed costs amounting to

    Rs.4,00,000 for the production of 50,000 units of such products by the

    company will not change. Accepting this job by the company will

    49. Ponchu Das Pvt.Ltd. of Kolkata is currently operating at 80% capacity. The

    following is the income statement furnished by the company:

    Particulars Rs. in lakh Rs. in lakh

    Sales 640

    Cost of sales:

    Direct materials

    200

    Direct expenses 80

    Variable

    overheads

    40

    Fixed overheads 260

    Total cost 580

    Net income 60

    The Managing Director has been discussing an offer from Middle East of a quantity,

    which will require 50% capacity of the factory. The price is 10% less than the current

    price in the local market. Order cannot be split. The capacity of factory can be

    augmented by 10% by adding facilities at an increase of Rs.40 lakh in fixed cost. If

    the proposal is accepted with the increased facilities, the profit will be increased by

    50. PQR Ltd. manufactures three components P, Q, and R. The company has

    furnished the following information pertaining to the cost per unit of threeproducts:

    Particulars P (Rs.) Q (Rs.) R (Rs.)

    Fixed cost 7.00 5.00 4.50

    Variable cost 8.00 6.00 6.00

    Total cost 15.00 11.00 10.50

  • 7/29/2019 Cec Case Study of 20 Marks

    24/32

    Alwin Company has offered to supply the components to PQR Ltd at the following

    prices:

    P Rs. 10.00 per unit

    Q Rs. 5.00 per unit

    R Rs. 7.50 per unit

    Which of the following decisions should be considered by PQR Ltd.?

    Group number 6

    51. MNR Ltd. has furnished the following information for two years:

    Particulars 2002-03 (Rs.) 2003-04 (Rs.)

    Sales 8,00,000 ?

    P/V Ratio 50 % 37.5%

    Margin of safety as % of Sales 40 21.87

    There has been substantial saving in the fixed cost for the year 2003-04 due to

    restructuring of process. The companys sales quantities of both the years are same.

    Selling price for the year 2003-04 is reduced. The fixed cost for the year 2003-

    04 is

    52. Bhavani Ltd.is operating at 80% capacity has a sales value of Rs.8,00,000 at

    Rs.25 per unit. The cost data are as under:

    Material cost Rs.7.50 per unit. Labour Rs.6.25 per unit. Semi variable cost (including

    variable cost of Rs.3.75 per unit) Rs.1,80,000. Fixed cost Rs1,90,000 up to 80% level

    of output, beyond this an additional cost of Rs.20,000 will be incurred. The activity

    level at break even point is

  • 7/29/2019 Cec Case Study of 20 Marks

    25/32

    53. The comparative profit statement of two quarters is as below:

    Particulars 1st quarter 2nd quarter

    Units sold 2,500 3,750

    Direct Material (Rs.) 87,500 ?

    Direct wages (Rs.) 62,500 ?

    Fixed and variable factory overheads

    (Rs.)

    75,000 95,000

    Sales (Rs.) 2,75,000 ?

    Profit (Rs.) 50,000 40,000

    In 2nd quarter, direct material price has increased by 20%. There was a saving of

    Rs.5,000 in fixed overhead in the second quarter. The other costs remained same.

    The quantity that should have been sold in the second quarter to maintain the profitof 1st quarter is.

    54.. Delta Ltd. manufactures four products P,Q,R & S, which emerge from a particular

    process of operation. The total cost of input for the year ended March 31, 2004 is

    Rs.2,80,000. The details of output, additional cost after split-off point and sales value

    of the products are as follows:

    Product

    s

    Output

    (Kg.)

    Additional processing

    cost

    after split-off point

    (Rs.)

    Sales value after further

    process

    (Rs.)

    P 10,000 20,000 2,20,000

    Q 3,000 20,000 1,15,000

    R 6,000 17,000 1,05,000

    S 4,000 50,000 1,70,000

    If the products are sold at split-off point without further processing, the sales value

    would have been:

    Rs.1,90,00

    0

    Rs.1,00,00

    0

    Rs.

    85,00

    0

    Rs.1,05,00

  • 7/29/2019 Cec Case Study of 20 Marks

    26/32

    0

    The maximum amount of profit of the company from the four products is

    55. Ajex Ltd. had the following inventories at the beginning and end of the month

    of March 2005:

    Particulars March 1, 2005 (Rs.) March 31, 2005 (Rs.)

    Finished goods 1,25,000 1,17,000

    Work-in-process 2,35,000 2,51,000

    Direct materials 1,34,000 1,24,000

    The following additional manufacturing data were available for the month of March

    2005:

    Particulars (Rs.)

    Direct materials

    purchased1,89,000

    Purchase returns 1,000

    Transportation 3,000

    Direct labor 3,00,000

    Actual factory overhead 1,75,000

    The company applies factory overhead at a rate of 60% of direct labor cost and anyoverapplied or underapplied factory overhead is deferred until the end of the year

    2004-05.

    The manufacturing cost of the company for the month of March 2005 was

    56. For a department, the standard overhead rate is Rs.2.50 per hour and

    overhead allowances are as follows:

    Activity level

    (hours)

    Budgeted overhead

    allowance (Rs.)

    3,000 10,000

    7,000 18,000

    11,000 26,000

    The normal capacity level, on the basis of which the standard overhead rate has

    been worked out, is

    57. Sai Plastics Ltd. manufactures plastic chairs. The company is working at 60%

  • 7/29/2019 Cec Case Study of 20 Marks

    27/32

    capacity level, which represents 4,800 chairs per month. The cost break-up

    per chair is as under:

    Materials Rs.62

    Labor Rs.32

    Overheads Rs.40 (60% fixed)

    The selling price is Rs.180 per chair. The company is planning to produce at 80%

    capacity level. At 80% capacity level the selling price falls by 5% accompanied by a

    similar fall in the price of materials.

    The break-even point in units and profit at 80% level of capacity of the company are

    58. A machine shop has 5 identical machines manned by 3 operators. The

    operators are fully engaged on machines. The total original cost of these 5

    machines is Rs.8,00,000. The company has furnished the following

    information pertaining to operations for the last quarter ending March 31,

    2005:

    Normal available hours per month peroperator

    200 hours

    Absenteeism (without pay) 12 hours

    Leave (with pay) 20 hours

    Normal idle time (unavoidable) 8 hours

    Average rate of wages per hour Rs.8

    Estimated production bonus 10% on wages

    Value of power consumed Rs.7,265

    Supervision and indirect labor Rs.4,100

    Electricity and lighting Rs.3,800

    Repairs and maintenance per quarter 1% on value of machines

    Depreciation per annum 10% on original cost

    Miscellaneous expenses per annum Rs.7,200

    General management expenses per annum Rs.45,800

    The comprehensive machine hour rate for the machine shop for the quarter ending

    March 31, 2005 is

    59. Monark Ltd. has undertaken to supply 2,000 units of product MONO per

    month for the months of April, May and June 2005. Every month a batch order

    is opened against which materials and labor cost are booked at actual.

    Overheads are absorbed at a rate per labor hour. The selling price is

    contracted at Rs.15 per unit. The company has furnished the following data

  • 7/29/2019 Cec Case Study of 20 Marks

    28/32

    pertaining to the costs for 3 months:

    MonthBatch

    Production(Units)

    Material

    cost

    (Rs.)

    Labor

    cost

    (Rs.)

    Overhead

    cost

    (Rs.)

    Total

    labor

    hours

    April 2005 2,500 12,5005,00

    024,000 8,000

    May 2005 3,000 18,0006,00

    018,000 9,000

    June 2005 2,000 10,0004,00

    030,000 10,000

    The rate per labor hour is Rs.2. The overall profit of the order of 4,400 units is

    60. HP Ltd. has furnished the following information pertaining to its 3 products:

    Department Allocation BaseProduct

    A

    Product

    B

    Product

    C

    Overhead

    costs

    Production Machine Hours 1,000 2,000 500 Rs.14,00,000

    Purchasing Purchase Orders 100 300 150 Rs. 5,00,500

    Inspection Labor Hours 200 200 200 Rs. 3,00,000

    Assuming overhead is allocated based on activities, using ABC basis, how much

    would be allocated to Product B?

    Group number seven

    61. AB Ltd. has furnished the following information for its product:

    Direct material - Rs.10 per unit

    Direct labor - Rs. 6 per unit

    Variable overhead - Rs. 3 per unit

  • 7/29/2019 Cec Case Study of 20 Marks

    29/32

    Fixed overhead - Rs. 4 per unit

    Budgeted production - 12,000 units

    Actual production - 10,000 units

    There is no overhead spending variance

    Sales - 9,000 units

    Selling price - Rs.28 per unit

    Using Absorption costing, what is the cost per unit based upon actual costs?

    62. Baisakhi Ltd. has 3 production departments P1, P2 and P3 and 2 service

    departments S1 and S2. The company has furnished the following overhead

    costs of production as well as service departments:

    Departmen

    t

    Overhead costs (Rs.)

    P1 13,600

    P2 14,700

    P3 12,800

    S1 9,000

    S2 3,000

    The company has provided the expenses of service departments which are charged

    to production as well as service departments on the following percentage basis:

    Department

    P1 P2 P3 S1 S2

    S1 40% 30% 20% - 10%

    S2 30% 30% 20% 20% -

    The total overhead expenses of P1 and P3 are

    63. Mahan Ltd. uses a historical cost system and applies overheads on the basis

    of predetermined rates. The following data are furnished by the company for

    the year ended March 31,2005:

    Particulars Rs.

    Manufacturing overheads 13,84,000

    Manufactured overheads

    applied

    14,00,000

    Work-in-progress 3,00,000

    Finished goods 8,00,000

    Cost of goods sold 9,00,000

  • 7/29/2019 Cec Case Study of 20 Marks

    30/32

    The amount of under absorbed overheads to be adjusted to work-in-progress, using

    supplementary rate, is

    64. ADC Ltd. has furnished the following data pertaining to its business:

    DepartmentEmployee

    s Sq.ft

    Costs

    Rs.

    Direct

    Hours

    Allocation

    Base

    Personnel 3 1,00

    0

    1,80,000 Employees

    Cleaning 5 2,22,750 Square

    feet

    Operating Dept.

    A

    30 3,75

    0

    25,00,00

    0

    45,00

    0

    Hours

    Operating Dept.

    B

    10 3,00

    0

    30,00,00

    0

    27,00

    0

    Hours

    Using the Step Method to allocate Personnel Department and Cleaning Departmentcosts, what is the appropriate overhead allocation rate to Department B?

    65. APW Ltd. uses process cost system to manufacture Dust Density Sensors for

    the mining industry. The following pertains to operations for the month of

    March 2005:

    Particulars Units

    Opening work-in-process (March 01, 2005)1,28

    0

    Introduced in production during March 20057,20

    0

    Closing work-in-process (March 31, 2005) 950

    There is no loss in the manufacturing process. The opening inventory was 60%

    complete for materials and 50% complete for conversion costs. The closing inventory

    was 80% complete for material and 60% complete for conversion costs.

    Costs pertaining to the month of March 2005 are as follows:

    Particulars Rs.

    Opening work in process:

    Materials 20,500

    Conversion 16,350

    During the month:

    Materials1,12,83

    0

  • 7/29/2019 Cec Case Study of 20 Marks

    31/32

    Conversion 89,520

    The total cost of closing work-in-process on March 31, 2005, using FIFO method, i

    66. During the month of March 2005, Murphi Ltd. manufactured 5,000 units of

    product P at a cost of Rs.60,000, exclusive of spoilage allocation. The

    company sold 2,500 units of product P during the month. An additional 1,000

    units, costing Rs.8,000, were completed to the extent of 50% by March 31,

    2005. All units were inspected between the completion of manufacturing and

    transfer to finished goods inventory. Normal spoilage for the month was

    Rs.2,000 and abnormal spoilage of Rs.5,000 was also incurred during the

    month. The portion of total spoilage that should be charged against revenue in

    the month of March 2005 is

    67. Sigma Chemicals Ltd. produces high-quality plastic sheets in a continuous

    manufacturing operation. All materials are introduced at the beginning of the

    process. Conversion costs are incurred evenly throughout the process. A

    quality control inspection occurs when units are 80% through with themanufacturing process, when some units are separated out as inferior quality.

    The following data are available for the month of March 2005:

    Material costs Rs.36,000

    Conversion costs Rs.19,500

    Units introduced 8,000

    Units completed 7,000

    There is no opening or closing work-in-progress. Past experience indicates that

    approximately 8% of the units introduced are found to be defective on inspection byquality control.

    The cost of abnormal loss for the month of March 2005 is

    68. Anjani Ltd. makes one model of a product known as Brand D. The company

    has provided the following balances as on October 01, 2004:

    Finished goods 500 units

    Work-in-process Rs.7,450

    Raw materials Rs.16,120

    The following data are available as on March 31, 2005

    Indirect labor Rs.16,100

    Freight in Rs.7,500

    Direct labor Rs.43,240

    Raw material Rs.6,490

    Factory overhead expenses Rs.31,300

  • 7/29/2019 Cec Case Study of 20 Marks

    32/32

    Work-in-process Rs.6,800

    Sales (15,000 units) Rs.3,60,000

    Indirect material Rs.25,500

    Total manufacturing costs incurred Rs.2,15,500

    There were 1,500 units of finished goods of Brand D as on March 31, 2005.

    The amount of raw materials purchased during the half-year ended March 31, 2005

    was

    69. Srirupa Ltd. manufactures a single product at the operated capacity of 8,000

    units while the normal capacity of the plant is 10,000 units per annum. The

    company has estimated 25% profit on sales realization and furnished the

    following budgeted information:

    Particulars 10,000 units (Rs.) 8,000 units (Rs.)

    Fixed overheads 1,50,000 1,50,000

    Variable overheads 50,000 40,000

    Semi-variable overheads 1,00,000 88,000

    Sales realization 8,00,000 6,40,000

    The company has received an order from a customer for a quantity equivalent to

    10% of the normal capacity. It is noticed that prime cost per unit of product is

    constant.

    If the company desires to maintain the same percentage of profit on selling price,

    the minimum price per unit to be quoted for the new order is

    70. Dcent Ltd. pays commission to its salesmen in the month the company

    receives cash for sales, which is equal to 5% of the cash inflows. The

    company has budgeted sales of Rs.4,25,000 for April 2005, Rs.5,25,000 for

    May 2005 and Rs.5,85,000 for June 2005. 60% of the sales are on credit.

    Experience indicates that 60% of the budgeted credit sales will be collected in

    the month following the sales. 35% are expected to be realized in the second

    month following the month of sales and remaining 5% will be non-

    recoverable.

    The total amount of sales commission for the month of June 2005 is