Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
Technical and financial Technical and financial management of the management of the
projectproject
Technical and financial Technical and financial management of the management of the
For a sound technical and financial management of your project you need:
1.a monitoring system
2.a financial plan
3.a project accounting system
4.a procurement plan
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
3
1. Monitoring system 1. Monitoring system
Why a monitoring system?
•To keep track of how a project is progressing in terms of resource use, implementation, delivery of results and the management of risks
•To support effective decision making with systematic and continual collection, analysis and use of management information
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
4
Monitoring system Monitoring system
Monitoring is:
•An information system
•Performed on a systematic, regular basis
•Based on indicators
•Concerned with the facts!
•Concerned with both financial and operational progress information
➪The information needed for monitoring should be identified when the project is first designed and/or when reviewed
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
Setting up the monitoring systemSetting up the monitoring system
Good monitoring depends on having reliable, relevant and timely information about the activities, outputs and outcomes of your project. This may be achieved by:
•Setting up a shared, internet-based (intranet), information tool including the control of deadlines, activities, deliverables and indicators using available project management software
•Requiring the project manager for each partner to submit a regular, short monitoring report to the Beneficiary providing information about the progress being made in implementing the project.
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
Sources of information for monitoringSources of information for monitoring
• The grant contract (your logframe, workplan…)
• Contracting information (sub-contracts)
• The record of project indicators at the levels of activities, outputs and results
• The financial records – bookkeeping system
• Special reports like quantitative surveys, questionnaires
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
Elements of Financial MonitoringElements of Financial Monitoring
• The value of the grant, the co-financing
• The expenditure and revenue budget and the actual financial position for the reporting period
– Expenditure & revenue
– Cash flows
– Cash flow forecast
– Bank balances
– Expected reimbursement claims for next period
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
Specific financial items to highlightSpecific financial items to highlight
• Actual expenditure significantly more than budget
• Actual expenditure significantly less than budget (eg savings on procurement)
• Delays in submitting payment requests
• Unexpected ineligible costs
• Significant change in exchange rates (effect on budget)
• Any other unexpected financial issues
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
Content of Operational MonitoringContent of Operational Monitoring
Is it not enough with the project budget approved?
Even though you prepared a budget including expenditure and sources of funding when preparing the application form, you have to take into consideration that:
•The budget doesn’t include an accurate monthly estimate for the whole project duration
•The approved budget does not have any forecast of the timetable for receipt of the sources of funding
•Not all expenditure imply an additional cash-flow, as they correspond, for example, to staff already working in your organisation
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
Why should you revise project Why should you revise project financial planning?financial planning?Why should you revise project Why should you revise project financial planning?financial planning?
Even though there is a 90% grant contribution, the balance will only be received after the project closure. The pre-financing may not avoid completely some cash deficits during project’s lifetime.
Therefore, it is important to make an accurate plan of receipts and payments in order to:
•Avoid any setbacks in project implementation due to cash shortage;
•Avoid misunderstandings among partners;
•Encourage partners to spend in time and contribute to a timely reporting and payment claim to JMA/JTS.
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
Steps for project financial planningSteps for project financial planningSteps for project financial planningSteps for project financial planning
1. Review your budget in detail to identify needs for minor adjustments in the initially estimated amounts;
2. Confirm your sources of funding and, in particular, the dates of expected receipt of contributions by external donors;
3. Prepare a monthly (or bi-monthly) forecast of all project expenditure;
4. Estimate when you will be able to submit and receive further pre-financing;
5. Prepare a project cash flow forecast.
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
15
Let’s see a practical exampleLet’s see a practical exampleLet’s see a practical exampleLet’s see a practical example
Our simplified case study will be a project with:
• Beneficiary and one partner
• 24 months duration
• No additional donors, no direct revenue, no in-kind contribution
• A limited number of budget items
Let’s see the project budget
See tables annexed
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
16
Planning and adjusting Planning and adjusting expenditure expenditure Planning and adjusting Planning and adjusting expenditure expenditure Staff costs
• Confirm which persons will be working for the project and see if they are already contracted or they have to be recruited
• Confirm the estimated monthly cost (as “month” is the unit of time in budget)
• Find out in which month the persons will start working and on what basis, if not full time
Costs Assumption Initial dateDetailed description End date# of units Unit rateUnit
1. Human Resources1.1 Salaries (gross salaries including social security charges and other related costs, local staff) 1.1.1 Technical Technician 1 Beneficiary Month 12,00 3.000,00 Already in institution. 50% dedication Month 1 Month 24
Technician 2 Beneficiary Month 20,00 2.850,00 Recruited for the project. 100% dedication Month 4 Month 23Technician 3 Beneficiary Month 2,00 2.600,00 Recruited for the project. Half dedication 4 months for final event Month 19 Month 22Technician 1 partner 1 Month 5,50 2.000,00 Already in institution. 25% dedication Month 2 Month 23Technician 2 partner 1 Month 20,00 1.900,00 Recruited for the project. 100% dedication Month 4 Month 23Total technical staff 59,50 2.473,95
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
17
Planning and adjusting Planning and adjusting expenditure expenditure Planning and adjusting Planning and adjusting expenditure expenditure Staff costs
• Calculate the monthly cost
1. Human Resources1.1 Salaries (gross salaries including social security charges and other related costs, local staff) 1.1.1 Technical Technician 1 Beneficiary
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
18
Planning and adjusting Planning and adjusting expenditure expenditure Planning and adjusting Planning and adjusting expenditure expenditure Other categories
• Revise the estimated amounts and other necessary assumptions
• Identify when invoices for services and goods will be paid, according to the delivery dates and credit terms (usually X days after delivery)
• Make a monthly estimate of paid expenditure for each categories
• Exclude “contingency reserve” and “administrative costs” from these estimations
Let’s see a couple of examples
➙ See tables annexed
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
19
Planning and adjusting Planning and adjusting expenditure expenditure Planning and adjusting Planning and adjusting expenditure expenditure Other categories
Costs AssumptionDetailed description # of units Unit rateUnit
2. Travel2.1. International travel Kick-off meeting:
3 persons from partner 1 Per diem 6,00 250,00 Beneficiary's placeMeeting # 23 persons from Beneficiary Per diem 6,00 250,00 Partner 1 placeMeeting # 33 persons from partner 1 Per diem 6,00 250,00 Beneficiary's placeFinal conference5 persons from Beneficiary Per diem 10,00 400,00 Partner 1 placeTotal international travel 28,00 303,57
5. Other costs, services5.1 Publications Documents 1,00 300,00 Cost of printing the study5.2 Studies, research Studies 1,00 20.000,00 Paid 50% in 3 months; 50% 60 days after delivery5.3 Expenditure verification Reports 3,00 3.000,00 Paid 30 days after delivery5.4 Evaluation costs Reports 1,00 5.000,00 Paid 60 days after delivery
5.5 Translation, interpretersDocuments/
studies 2,00 2.000,00 Paid 60 days after delivery 5.7 Costs of conferences/seminars Conferences 1,00 5.000,00 Paid 30 days after delivery
5.8. Visibility actions Web site Web site 1,00 10.000,00Development (8.000 €) paid 60 days after delivery; maintenance paid 12 months later
Total other costs, services
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
20
Planning and adjusting Planning and adjusting expenditure expenditure Planning and adjusting Planning and adjusting expenditure expenditure Other categories
Costs Detailed description
2. Travel2.1. International travel Kick-off meeting:
3 persons from partner 1Meeting # 23 persons from BeneficiaryMeeting # 33 persons from partner 1Final conference5 persons from BeneficiaryTotal international travel
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
23
Planning of cash flowsPlanning of cash flowsPlanning of cash flowsPlanning of cash flows
Prepare a final table with:
• The revenues and their month of receipt;
• “Additional” foreseen expenditure paid for the project;
• Monthly and cumulative cash flow and surplus/deficit taking into account the “additional” expenditure;
• Other payments already budgeted in your organisation, such as permanent staff or administrative costs;
• Monthly and cumulative cash flow and surplus/deficit taking into account all expenditure
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
24
Final remarks on financial planningFinal remarks on financial planningFinal remarks on financial planningFinal remarks on financial planning
• As with all estimates, the financial forecast is only useful if reviewed and updated on a regular basis
• Discuss the planning with your partners, get information from them and reach a consensus on commitment for expenditure and payments
• Cash forecasts tend to be optimistic; revenues arrive later and expenditure on time or earlier
• Be prudent and ensure that no partner is blocked in their contribution to project implementation for lack of liquidity of funds
The tables and assumptions shown in this presentation
are just an example
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
25
3. Accounting system requirements3. Accounting system requirements3. Accounting system requirements3. Accounting system requirements
Art. 16.1 of General Conditions (annex II to the contract):
The Beneficiary and partners shall keep accurate and regular accounts of the implementation of the project, using an appropriate accounting and double-entry bookkeeping system. The system:
• May be either part of the beneficiary’s and partners’ regular system or an adjunct to that system
• Shall be run in accordance with the accounting and bookkeeping policies and rules that apply in the country concerned
• Accounts, expenditure and revenue relating to the project must be identifiable and verifiable
• Details on interest accruing on funds paid by EC have to be provided
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
26
What is an accounting system?What is an accounting system?What is an accounting system?What is an accounting system?
Accounting IS NOT a list of expenditure and revenue. Accounting IS NOT a list of expenditure and revenue.
An excel file is not an accounting system.An excel file is not an accounting system.
General definition of accounting
The systematic recording, reporting and analysis of the financial transactions of an entity.
Common provisions on accounting by Financial Regulation (Article 132 of EC Regulation 1605/2002)
1. The institution’s accounting system is the system serving to organise the budgetary and financial information in such a way that figures can be input, filed and registered
2. The accounts shall consist of general accounts and budgetary accounts
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
27
General requirements on General requirements on accountingaccountingGeneral requirements on General requirements on accountingaccounting
All partners need to have a general accounting in All partners need to have a general accounting in conformity with national rulesconformity with national rules
The project accounting has to be organised as a The project accounting has to be organised as a budgetary accounting in all partnersbudgetary accounting in all partners
The project accounting has to be kept in the national currency, as the translation to Euro will only be necessary for the financial report to JMA/JTS.
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
Use of exchange rates in the projectUse of exchange rates in the projectConversion:
Purpose Which exchange rate
Bank transfer Actual rate applied by bank
Reimbursement of subsistence costs to staff
National bank daily rate
Payment of invoices in foreign currency Actual rate applied by bank
Translation:
Purpose Which exchange rate
Reporting Average of monthly rates for the reporting period from Inforeuro
Decision on procurement procedure (verification of threshold)
Inforeuro rate of the month of launch of the procedure
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
29
What is double-entry bookkeeping?What is double-entry bookkeeping?What is double-entry bookkeeping?What is double-entry bookkeeping?
Definition of double-entry bookkeeping
An accounting technique which records each transaction in at least two different accounts, as a credit and as a debit. Credit entries represent the sources of financing, while debit entries represent the use of this financing.
Let’s see an example of expenditure in a project-dedicated accounting:
•The debit will indicate to which category of expenditure the invoice has to be imputed
•The credit will indicate if the invoice was paid by the beneficiary or a partner. In case of non-dedicated bank accounts, the entry should also indicate which one was used.
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
30
Reconciliation with reportsReconciliation with reportsReconciliation with reportsReconciliation with reports
Article 16.1. of General Conditions also indicates that:
The financial report has to be properly and easily reconciled to the accounting and bookkeeping system and to the underlying accounting and other relevant records.
For this purpose, the beneficiary shall prepare and keep appropriate reconciliations, supporting schedules, analyses and breakdowns for inspection and verification.
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
31
Setting up your accounting systemSetting up your accounting systemSetting up your accounting systemSetting up your accounting system
•Ensure that it is in conformity with the requirements of art. 16.1 of General Conditions
•Design it to provide the necessary information for the interim and final reports
•Use it periodically to allow a proper follow-up of the project budget and enable you to identify any major deviations beforehand
•Ensure that there is shared understanding by all partners. If it is a separate system, use the same for all the partnership; if it is included in the partners’ accounting, check its adequacy
•Ask support to the auditors on the conformity of the system by all partners several months before the first reporting
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
32
Archiving of supporting documentsArchiving of supporting documentsArchiving of supporting documentsArchiving of supporting documents
Requirements of your archiving system
•All transactions in accounting are referred to the necessary supporting documents (see presentation on eligible expenditure)
•The originals of the supporting documents have to be kept by each partner institution, but copies (either scanned or physical) are easily available by the Beneficiary in order to facilitate the financial controls by authorized bodies. A web-based document repository shared by all partners may be very useful for this purpose.
•The documents have to be archived in a way that they are easily accessible after the project closure. (7 years after receiving the balance payment)
Ce projet est financé par l’UE et mis en œuvre par un consortium dirigé par MWH
33
4. Procurement plan4. Procurement plan4. Procurement plan4. Procurement plan
Delays in procurement procedures is one of the main risks for not keeping the working plan. Therefore:
•Identify which are the procurement procedures to be launched during the project implementation and who is the responsible partner
•Identify the applicable legislation and specific procedures and deadlines
•Insert the timing of the procedures in the working plan and ensure that no activity will be delayed for this reason
•Include the procurement plan in your monitoring system