Top Banner
Cast Iron Rene al Techniq es Cast Iron Renewal Techniques Katie Harkless Project Manager-Replacement Washington Gas
45

Cast Iron Rene al Techniq esCast Iron Renewal Techniques...ti itwin main • The pipeline after depressurizing was almost completely dry with ... Cured-in-place Lining Technology.

Jan 25, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • Cast Iron Rene al Techniq esCast Iron Renewal Techniques

    Katie Harkless

    Project Manager-Replacement

    Washington Gas

  • Washington Gas Overview

    • Serve D.C. and adjoining areas in MD and VA

    • Approximately 1.2M customers

    • 22 gate stations, 2 peak shaving plants, and 1 storage fieldand 1 storage field

    2

  • WG Cast Iron Piping

    DC 428 il• DC – 428 miles• MD- 75 miles• VA – 17 MilesVA 17 Miles• Total cast iron = 520 miles• Replace 5-6 miles annually

  • WG Cast Iron Renewal Techniques

    Li• Liners– Cured-in-place liner– U-liner

    • Joint sealants– Internal joint sealants

    External joint sealants– External joint sealants• Insertion

    – Plastic insertion

  • WG Cast Iron Renewal Techniques – Cured-In-Place Liner

    C d I Pl Li• Cured-In-Place Liners– WG primarily uses on 12” and larger diameters due to

    thicker pipe wall– Example project – Anacostia river rehab project

    • Used liner because wanted to directionally drill but couldn’t obtain permit from National Park Service.

    • Remediated 1800’ (2-900’ lengths)

  • Cured-In-Place Anacostia River Rehab Project

    C d i l• Cured-in-place process– Disconnect pipe– Clean pipe– Pre-lining inspection (CCTV)– Lining process– Post-lining inspection– Post-lining inspection– Pressure test– Activate the line

  • Anacostia River Rehab Project

    B k d f th P j t• Background of the Project– 16-inch cast iron pipes leaking under river Winter 2009

    • Replace Option p p– Drill new lines– Install new lines through Anacostia Park

    Complete line replacement– Complete line replacement • Rehabilitation Options

    – Insertion– Lining – selected as best option

  • River Crossing Location

  • Project Design Concerns

    C l t d t d i i f th i d ibl t• Concerns related to depressurizing of the main and possible water infiltration

    • Double lining considered, first lining to stop water infiltration & d f isecond for gas carrier

    • Obtaining Permits from Parks Dept• Working from Vault Side without dismantling the vault• Environmental issues related to dewatering of park side pit

  • Pipeline Inspection

    D i i f th Fi t L f T i 16 I h iDepressurizing of the First Leg of Twin 16-Inch main –Phase I

    • Consideration was given to live camera inspect while simultaneously l i th t it t i filt tilowering the gas pressure to witness any water infiltration

    • WGL opted not to live camera inspect and depressurized first leg of t i itwin main

    • The pipeline after depressurizing was almost completely dry with l th fi t t t i j i t i littl tonly the first two cast iron joints weeping a little water

  • Cured-in-place Lining Technology

  • Pipeline Before Cleaning to Final Product

  • Camera Inspection

    W ki f th k id f th j t th fi t i ti f th• Working from the park side of the project, the first camera inspection of the pipeline revealed a clean main, except for the last 100ft or so before the drip

    • The debris found was “sand like”, the amount of debris became greater the closer it came to the drip p

    valve

    Debris

    Drip

  • Blast Hose from Vault Side

  • Pipeline Cleaning

  • Cleaning Process

  • Filling the Drip

    Valve

    Drip filling Methodology

    • Inserted 2-14-Inch pigs into the bottom of the drip Camera

    • Inserted 90ft of 2-Inch PVC pipe

    • Mixed and poured adhesive into 2-Inch pipe and fill drip (27 Cans used)

    2-14” Pigs

    • Observed process through camera

  • Lining Process

  • Lining Process

    PressureDrum

    Concrete Vault Sub Station Side

    Drum

    P k Sid With St l

    Direction of Lining

    Drip filled with2-Pigs & Adhesive

    Park Side With SteelSheeting Box

  • Lining Process

  • Clearance Concerns

    Important: For every two feet (2ft) of additional cover, top of main,The cut-out section of space between the mains MUST increaseBy one additional foot (1ft) for example, a pipe with 6 feet (6ft) of

    Cover requires a 7 foot (7ft) cut-out

    6ft SectionRemoved

    2-Foot

    Section to be Lined

    Utility Requirement

    Removed@ 4FT cover

    1-Foot

    be Lined

  • Clearance Requirements

    Side View

    PressureDrum

    Approx 40ft LongIncluding Trucks4ft

    DirectionOf Lining

    Approx 10-12ft Long

    Including Trucks

    1ft

    Approx 10 12ft Long

  • Consequences of Misalignment

    • Misalignment at the inversion point creates unsupportedliner within the rehabilitated pipeline and a

    “Spot Repair” is required after curing

    Unsupported liner

    liner

    Not enoughSpace to properlyAlign hose fittingAlign hose fitting

    Unsupported liner

  • Loading the Lining

  • Inversion Cone Being Connected to Liner

  • Lining

  • Line Complete

    Valve

    Half/Pig to support Liner

    Cast iron Joint

    Half/Pig to support Liner

    • Liner was installed and held pressure • PPM maintained positive pressure all night and next day to allow

    Lineradhesive proper time to fully cure• Re-pressurized and tested pipeline• Cut open fish mouth valve position

    Adhesive filled DripStarline-1000

  • Pipeline Lining Completed

  • Other Challenges - Flooding

  • Other Challenges – Freezing and Blizzard

  • Area Restored – Liner Project Complete

  • WG Cast Iron Renewal Technique- Other Liners

    U li• U-liner– Internal sealing

    technique used in the l t 1990’late 1990’s

    – U shaper liner that expands in pipe

    – Useful on straight pipe with no service connections

    – Remediated about 1000’ of main

  • WG Cast Iron Renewal Techniques –Internal Joint Sealant

    I t l j i t l t• Internal joint sealants– Only plausible on 16” diameter and up– More cost effective than external joint sealant because

    don’t have to excavate every joint– Projected savings of up to 60% over conventional repair

    methods – Example project – Embassy Row internal sealing rehab

    • Remediated about 3,300’ of 20” cast iron main

  • WG Cast Iron Renewal Techniques –Embassy Row Internal Sealing Rehab

    Hi t f b ll d i t j i t l k• History of bell and spigot joint leakage• Main in good condition

    – Pipe wall thickness = .71” thicknessp• Less expensive than direct bury• 11 customer included

    E b id– Embassy residences– Textile museum– Large homes

  • WG Cast Iron Renewal Techniques –Embassy Row Internal Sealing Rehab

    Sequence of WorkSequence of Work

    • Temporarily transfer services to low pressure main

    • Install new 2” main - transfer services• Excavations• Gas stop-offs• Disconnects• Disconnects• Internal sealing• Air test main • Reconnect pipe segments• Stop-off to reconnect last segments• Service transfers• Additional work

  • WG Cast Iron Renewal Techniques –Embassy Row Internal Sealing Rehab

    Pl

    Ave

    e24th

    St

    23rd

    St

    Phe

    lps

    P

    X

    Mas

    s A

    Fla

    Ave2 2 P

    S STX X X X X X X X

    X – Stop-off – (7’ x 8’)

    X - Disconnect – (7’ x 20’)

    X – Entry/Exit – (7’x 10’)

  • WG Cast Iron Renewal Techniques –Georgetown Internal Sealing Rehab

    I t l S liInternal Sealing– Seals

    Nitrile rubber• Nitrile rubber• Steel retaining bands

    – Process• Internal inspection/count• Clean/grout joints• Put seals and bands in place• Expand steel bands• Air test each seal

    Crews worked inside 20” main for 7 days– Crews worked inside 20 main for 7 days

  • Construction

  • WG Cast Iron Renewal Techniques –Embassy Row Internal Sealing Rehab

    Return To ServiceReturn To Service

    • Air test at 25 psig for 1 hour

    • Return to pressure at 5-psig increments

    • Leak survey between increments

  • WG Cast Iron Renewal Techniques –External Joint Sealant

    E t l j i t l t• External joint sealants– Same concept as

    encapsulation kit – Considered a repair, not a

    renewal– Not used for mass

    replacement, but more for big diameter joint repairs

    – Not as cost effective as internal joint sealants

  • WG Cast Iron Renewal Techniques –Plastic Insertion

    Pl ti I ti• Plastic Insertion– Used mostly for small, 8”

    and below diameter• Have done some 16”

    diameter– Convert LP to MP after

    i tiinsertion– Practice is to purge before

    insertion, so not done on lilive gas

    – Complete about 5 miles of replacement annually using th i ti th dthe insertion method

  • Questions?