RTIO Rail System Rail Safety Conference, Sydney Australia, March 2012 Sid Hay, Manager Rail Development
Jan 19, 2015
RTIO Rail SystemRail Safety Conference, Sydney Australia, March 2012Sid Hay, Manager Rail Development
Contents
2
• Introduction to RTIO Rail System
• Characteristics of RTIO Rail System that create rail safety challenges
• Rate of change
• Long trains
• Heavy trains
• High axle loads
• 24hr x 365 day operation
• Remote location, challenging climate
• Community interfaces
• Future developments that further reduce risk
3
Railway network – one of the largest privately owned railways in Australia
Mine
Deposit
Port
Conveyor
Railway
Proposed Railway
RP113915v 2 April 2006
0
SCALE
MGA94 Zone 50
50 100km
Cape Lambert80 Mt/aDampier
150 Mt/a
Marandoo �
~15 Mt/a
� Paraburdoo
� Eastern RangeChannar �
� Nammuldi~5 Mt/a
West Angelas �
~28.5 Mt/a
Yandicoogina �
~52 Mt/a
Hope Downs 1 �~30 Mt/a
� Mt Tom Price~28 Mt/a
Mesa J �
~7 Mt/a
� Brockman #2~8 Mt/a
ORE-TYPE
� Brockman
� Marra Mamba
� Pisolite
ORE-TYPE
� Brockman
� Marra Mamba
� Pisolite
Dampier
Cape Lambert
ParkerPoint
EastIntercourse
Island
Dampier
Perth
Sydney
A U S T R A L I A
~20 Mt/a
� Brockman #4~22 Mt/a
Mesa A �
up to 25 Mt/a
Robe Valley
Pooled
Fleet
Integral part of the production network
Rail is the key to the logistics chain
• Ore is railed from 10 mine locations to 5
dumpers (3 at Dampier and 2 at Cape
Lambert).
• The current schedule (~230Mt/a.) is
– Pooled Fleet: 19 - 24 trains per day
– Robe Valley: 5 - 7 trains per day
A 353 Mt/a system means;
• Railing from 12 mine locations to 7 dumpers
(3 at Dampier and 4 at Cape Lambert)
• 40 loaded trains per day
• Finish dumping a train every 36 minutes
• Train movement every 20 minutes in dual
track
4
5
Train configuration (pooled fleet)
• Trains consist of 3 locomotives hauling 234 ore cars
• Banker locomotives (2 or 3) used for uphill gradients from some mines
• Average payload of 112 tonnes of ore per car ~ 33 tonne average axle load. Upper control limit is 36 tonne axle load.
• Each train has a gross mass of approx 32,000 tonnes and is 2.25 km long
Tonnes Railed
0
100
200
300
400
1966
1968
1970
1972
1974
1976
1978
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
2010
2012
2014
2016
Mtp
a
Pooled Fleet Robe Valley PF Plan RV Plan
Separate Hamersley Iron and
Robe River rail systems
RTIO rail
system
Rate of change
Note: Plan from 2013 to 2016 is an approximation.
6
• 30 years of slow growth
• 10 years of relatively rapid growth
– Combination of two rail systems, expansion of track and fleet, more
loadout and dumper interfaces, replacement of old fleet, increased
investment in technology
Ore cars (pooled fleet) – growth in fleet size
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
11000
12000
13000
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
• In addition to growth we
have replaced the original
2,464 ore cars
• Planned increase to
~12,000 ore cars by 2015
50 m3
55 m3
� 50 m3 ore car
55 m3 ore car �
(prototype)
7
Locomotives
0
50
100
150
200
250
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
DC Traction
- 72 GE Dash 9's
- balance GE Evolution Series
AC Traction ?
Dash 9 replacements due to start ~2015
• 15 DC Evo’s due 1H 2012
(completes 283 and fuel project)
• Now in negotiation with GE to
develop AC locomotive for 353
project
– testing of impact on signalling
system
– Specification of AC loco for the
Pilbara conditions
• Hybrid not currently viable due to
battery technology
8
Managing rate of change risk
9
• Must have strong change management processes
• Separate but aligned functions and resources for
– Working in the business
– Working on the business
• Capability of leaders
– Managing change
– Understanding of business fundamentals
Long Trains
10
• Empty train derailment risk through buckling of long lightweight empty
trains
– 2.3 km long train, 5000 tonnes mass, brake application takes time to
propagate along the train.
– An event causing emergency air brake application can buckle the
train causing derailment
– Strong or sudden application of locomotive dynamic braking can
cause first ore car behind locomotives to lift and derail
3 ore cars derailed in tangent track
10 ore cars derailed in a curve
First ore car behind locos derailed
Managing empty derailment risk today
11
• Change to ATP software
• Driver training
– Limitation on dynamic braking use on
empty trains
• Limit wheel sizes on first car behind
locomotive
– ‘white triangle cars’
Managing empty derailment risk – Future controls
12
• Electronically controlled pneumatic (ECP)
braking
– Fitout of pooled fleet commenced
• Driver Assist
– ‘Leader’ technology being installed on
locomotives to provide advice to
drivers on optimum throttle and brake
setting to achieve a ‘golden run’.
• AutoHaulTM
– In-train force limits configurable to
include empty train compression limit
Heavy loaded trains
13
• 32000 tonnes and 2.3km long with ~ 20 metres of free slack
• Kinetic energy @ 75 km/hr = 7 GJ (~2 tonnes of TNT !)
• Large braking distances, particularly on downhill gradients
�Low tolerance for human error
– Overspeed or exceed LOA through misjudgement of brake
application timing or amount
– Drawgear failures due to misjudgement of driving strategy
• Very high momentum means a single derailed wheelset will not be
noticed by the driver
• A derailment caused by track failure can escalate rapidly
Heavy loaded trains – managing risk
14
• Existing Controls
– Automatic Train Protection (ATP) prevents overspeed or LOA breach
in mainline
– Instrumented ore cars provide
feedback on driving strategy
effects on in-train forces
– Wayside dragging equipment
detectors (DED’s). Average
DED spacing ~3km.
• Future controls
– ECP Braking, Driver Assist,
AutoHaul
High axle loads
15
• Average axle load = 33 tonnes, Upper control limit = 36 tonnes
• These loads create potential for failures of above and below rail
components:
– Sleepers, rails, rail welds, wheels, bearings, axles
– Currently rail welds and bearings suffer from failures
High axle loads – managing risk
16
• Weigh scales installed at loadouts
– overloaded cars are corrected
before departure.
• Track monitoring through use of
instrumented ore cars
– detect areas of high dynamic
forces
– application of speed restrictions
– correct track geometry.
• Use of wheel impact detectors
High axle loads – managing risk
17
• Hot bearing detectors at an average ~25km
spacing, conservative setpoint
• Acoustic bearing condition monitoring
• Investment in premium track materials
(concrete sleepers, high strength rails,
conservative wear limits)
• Conservative ultrasonic inspection
frequency for defects
• Eliminating lower quality rail welds
– Increased use of mobile flashbutt
welders
24 hour x 365 day operations
18
• Managing the track maintenance - operations interface;
– Working in relatively small maintenance windows
– Some tasks with lookout protection
• Commissioning brownfields track upgrades requires existing cab-code
based signalling (ICSS) to be shutdown
– Use lesser systems (train orders, hirails checking track integrity)
24 hour x 365 day operations – managing risk today
19
• Perth Operations Centre,
centralised 24hr management
of the integrated production
process
• Maximise commissioning train
free windows, better planning
and coordination of events
across the integrated
production process
Whole of System Visibility
Improved access to
information
Collaboration
Operations Support
Asset MgtMining Whole of Business Planning
Logistics
Utilities
Train control & Scheduling
Port Ops & Scheduling
Pit Control & Mine care
Crushers & Plant Control
Mines
Power Stations & Network
Plants Rail Port
s
Quality
Centralised
Control Room
BENEFITS
Integrated Planning
Scheduling
Better, smarter, faster decisions
Operational excellence
OPERATIONS CENTRE
Whole of System Visibility
Improved access to
information
Collaboration
Operations Support
Asset MgtMining Whole of Business Planning
Logistics
Utilities
Train control & Scheduling
Port Ops & Scheduling
Pit Control & Mine care
Crushers & Plant Control
Mines
Power Stations & Network
Plants Rail Port
s
Quality
Centralised
Control Room
BENEFITS
Integrated Planning
Scheduling
Better, smarter, faster decisions
Operational excellence
OPERATIONS CENTRE
24 hour x 365 day operations– future controls
20
• Eliminating lookout protection for work
in the danger zone
• SIL rated warning systems for work
near the danger zone
– Trial of SIL3 rated system
• Overlay coloured light signalling system
being developed for commissioning
activities
– Recent comparative analysis
showed OSS system 1.5-1.7 times
safer then paper based train order
working system
Remote locations and challenging climate
21
• Flooding events
• Lightning storms – damage signalling system
� Degraded mode operation
• Managing risk today
– Stream flow detectors
– Lightning protection upgrades
• Potential future move away from track circuit based signalling and asset
protection – reduce field hardware.
Community interfaces
22
• Existing controls
– Awareness campaigns
– Design assessments (ALCAM)
– Application of active protection to all
approved public level crossings
• Future controls
– Level crossing upgrades as part of
AutoHaulTM project
At over 2.5km in length and weighing more than
29,000 tonnes, a loaded train takes over 2
kilometers to stop. Please remember, never take
risks at rail crossings and always obey the signs
and signals
23
AutoHaulTM
• Scope of current project is pooled fleet ore train operations, the Deepdale line will still run manned trains.
• Train Drivers still required for
• service trains in the mainline, ore trains from Western Creek to Robe Valley (Deepdalemainline)
• AutoHaul trains in a failed state
• operating port yards, driving trains through loadout at non-automated mines.
• New specialist roles will be created, covering geographical sections and requiring driving competence.
• Significant organisational change project, affects every team in the railway directly or indirectly
• Technology components
• Locomotive and Operations Centre systems changes
• Wayside signalling configuration changes and extensions
• Data communications to support autonomous functions
• Level crossing protection upgrades
• AutoHaul TM will be implemented in two stages, with first autonomous trains to be implemented in the latter half of 2014.
24
Future developments to further reduce risk
1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2015 2020
Train Orders
Track Circuits
Coloured Light Signals
Integrated Control and Signalling System (ICSS)
Driver Assist, ECP Brakes, AutoHaulTM
, Overlay Signals
GPS Tracking System linked to block protection
Hi-rails, trackside workers
Trains & track machines
Trains
Track
machines
Verbal Authority
2 way GPS system - pseudo ICSS
Le
ve
l o
f E
ng
ine
eri
ng
Co
ntr
ol
Communications based control
SA
FE
TY
Questions ?