Case Study of Roadmap to Case Study of Roadmap to Tokamak Demo Reactor in Tokamak Demo Reactor in Japan Japan International Workshop MFE Roadmapping in the ITER Era September 7, 2011 Princeton, New Jersey, USA Kunihiko OKANO Japan Central Research Institute of Electric Power Industry Graduate School of Frontier Sciences, The University of Tokyo,
24
Embed
Case Study of Roadmap to Tokamak Demo Reactor in Japan
International Workshop MFE Roadmapping in the ITER Era September 7, 2011 Princeton, New Jersey, USA. Case Study of Roadmap to Tokamak Demo Reactor in Japan. - PowerPoint PPT Presentation
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Case Study of Roadmap to Case Study of Roadmap to Tokamak Demo Reactor in Tokamak Demo Reactor in
JapanJapan
International WorkshopMFE Roadmapping in the ITER Era
September 7, 2011 Princeton, New Jersey, USA
Kunihiko OKANOJapan
Central Research Institute of Electric Power IndustryGraduate School of Frontier Sciences, The University of
Tokyo,
A request to Fusion Energy Forum from MEXT (October 2007 )MEXT: Ministry of Education, Culture, Sports, Science and Technology
To show a roadmap to finish the preparation for commercial use of fusion,@ before the middle of this Century@ assuming Tokamak plants
OKANO, K (Chair)OKANO, K (Chair) Cent. Res. Inst. Elec. Power. Ind. (CRIEPI)Cent. Res. Inst. Elec. Power. Ind. (CRIEPI)
Hasegawa, M.Hasegawa, M. Japan Atomic Industrial Forum (Japan Atomic Industrial Forum (from MITSUBISHI Electric corp.)from MITSUBISHI Electric corp.)
HORIIKE, H.HORIIKE, H. Osaka UniversityOsaka University
IMAGAWA, S.IMAGAWA, S. National Institute of Fusion Science (NIFS)National Institute of Fusion Science (NIFS)
KONISHI, S.KONISHI, S. Kyoto UniversityKyoto University
MORI, S. MORI, S. Japan Atomic Industrial Forum (Japan Atomic Industrial Forum (from Kawasaki Heavy Industry. Ltd.)from Kawasaki Heavy Industry. Ltd.)
OGAWA, Y. OGAWA, Y. University of TokyoUniversity of Tokyo
TANIGAWA, H. TANIGAWA, H. Japan Atomic Energy Agency (JAEA)Japan Atomic Energy Agency (JAEA)
TOBITA, K. TOBITA, K. Japan Atomic Energy Agency (JAEA)Japan Atomic Energy Agency (JAEA)
Members of the working group for roadmap study
This roadmap study was done in 2007-2008. The roadmap was submitted to the MEXT (Ministry of Education, Culture, Sports, Science and
Technology), then they took note it.
As this roadmap was not revised after that time, any recent changes in the ITER schedule have not been reflected in this roadmap.
The revision of roadmap is in progress by the committee organized by the MEXT.
Thursday, Perspectives III H.Yamada, “Current Status of Discussion on Roadmap of Fusion Energy Research and Development in Japan”.
# Commercial use of fusion should be ready before the middle of this Century → The commissioning of Demo should be finished by ~2040, because we will need DEMO operation for over 10 years in order to demonstrate the reliability of fusion plant.
# Steady state operation should be demonstrated.Output of commercial plants should be steady state. Then, a steady state plasma operation will be desirable.If not, a kind of energy storage is required for the commercial plants with additional cost. From a view point of the reliability as well.
Basic agreements of WG Basic agreements of WG members -1members -1
#Plasma in the commissioning phase @The commissioning phase will start with inductive
current or hybrid mode.
This means that a CS coil with a reasonable volt*sec is required for the DEMO design. The operation will shift toward full steady state with Q>20 gradually, during the several years in the commissioning phase.
Basic agreements of WG Basic agreements of WG members -2members -2
#Definition for “demonstration of electric power generation” @ Net electric output, in final stage of the commissioning @ Generator power in plant scale (>several hundred MWe) should be demonstrated.(Note: this is just a proposal by the roadmap working group).
This definition is different from the strategy decided by AEC in 2005*, where “1000MWe net electric output, certain economical cost and ITER-like size” have been required.
*Report on National Policy of Future Nuclear FusionResearch and Development, Atomic EnergyCommission Advisory Committee on Nuclear Fusion,26 October 2005.
Basic agreements of WG Basic agreements of WG members -3members -3
#Assumption about ITER project
@Assuming that the burning plasma of ITER will not be very different from our present knowledge, we carry forward the DEMO engineering design (EDA phase), before DT burning experiment in ITER (~2022).
@After the ITER DT (Q>10) operation, we will immediately move to a construction process (i.e. the design for construction by manufacturers).
#Strategy for blanket development by DEMO @Large test ports will be prepared for TBM of advanced concepts. New concept blankets can be developed throughout the Demo project to improve the reliability and efficiency. This is because blankets installed by the first day of DEMO operation should be very conservative one.
2027 in latest schedule
Basic agreements of WG Basic agreements of WG members -4members -4
Method to build up the Method to build up the roadmaproadmap
(1) Completion of breakdown list of works required toward the DEMO. The list should include whole R&D issues, required to construct the DEMO. Note: This list must not be “a list of the existent R&D issues”. It is very important to find issues or works indispensable for constructing the DEMO but missing in the existent R&D issues.
We have surveyed the R&D issues carefully, and broken down over 1000 works.
(2) Completion of the time table for each work and check of the correlations to build our roadmap.
106
15
30
185
414
38
33
36
37
30
13
90
13
14
7
29
23
8
5
Total : 1127 issues
The number of Issues
185
Decision making for SC materials and Max field on coil.
If we chose a new type of SC coils beyond the ITER design, a lot of issues will appear.
414
Basic design will be based on the ITER-TBM proposed by Japan.We assume that it will be successful !!
Improved Li2TiO3 (2013)Decision on method for Li-6 enrich.(2014)
Advanced multiplier (-2021)Decision on breeder & multiplier (2022)
Blanket-3Tritium block coating on coolant channels
Decision on using of tritium block coat. (2015)
Blanket-4Adv. high temp. BLK
Choice of candidates for adv. BLK (2013)
Decision of a candidate of adv. BLK system (2016)
Initial spec. of adv. BLK (2022)
Final spec. of adv. BLK for replacement (2029)
Phase
Category
DEMO CDAand R&D
-2014
DEMO EDA Phase-1
-2018
DEMO EDAPhase-2
and Regulation-2022
DEMO Design forConstruction
Safety Review2031
Maintenance Decision of maintenance scheme (2016)
Plasma physics Decision of plasma configuration (2022)Provisional choice of operat. point (2022)
Final decision on operation point (2027)
Heating & Current Drive
Decision on method for H &CD (2014)
Decision of Beam energy, if used (2020)
Tritium Handling
Decision on method to secure initial Tritium inventory (import or DD-start)(2014)
Final spec. of-Treatment of exhaust gas (TEP)-Isotope separation-tritium storage-Air purification(ADSVDS)
etc. (2022)
start of cold test for water disposal system (WDS) (2031)
It has been pointed out that some issues are critical for DEMO while R&D project does not exist yet or is insufficient in Japan. The following issues are the examples. The R&D’s need starting in this decade.
NOTE!: These are not the most important issues, but are missing or insufficient issues in previous program.
Finding by the work breakdown studyFinding by the work breakdown study
(ex1) Mass production factory of 6-Li enriched litium
Except for designs with liquid Li breeder/coolant or LiO2 seramics breeder, the enrichment of 6-Li is indispensable to achieve reasonable TBR (local TBR > 1.3).
Requirement of 6-Li for DEMO will be ~100 ton for every set of blanket. No factory to provide such amount of 6-Li, at least, in Japan, (possibly in the world too? )
(ex2) Procurement of initial tritium inventory
Sufficient amount of tritium should be secured before the commissioning of DEMO. In order to decide to move to the DEMO construction phase, a reliable path or method for the procurement of this initial tritium should be shown.
Our possible choices:
1) Tritium production by fission reactors in Japan (but nearly impossible)2) Purchase from elsewhere (Who will be able to sell it us?)3) DEMO operation starts with a beam-driven DD operation, and shifts gradually to D/T=50/50 operation.
Our simulation has shown that full DT operation is attained within 6 months with continuous 100MW NB injection. (Cost of this electric power >> present T price)
S. Konishi et al., J. Plasma and Fusion Research, Vol.76 , No.12 (2000)p.1309.Y. Asaoka, S. Konishi et al., "Commissioning of a DT Fusion Reactor without External Supply of Tritium.", Proc. of The 18th IAEA Fusion Energy Conference, PDP-08, Sorrento, Italy, Oct. 2000.
Cont.
Finding by the working breakdown studyFinding by the working breakdown study
(ex3) Maintenance method
The maintenance concept should be fixed before stating the demo engineering design, because the maintenance method changes the overall design of the DEMOs. Our choice is extended widely between a full sector removal (like ARIES-RS, SLIM-CS, CREST) and a small module replacement (like ITER).ITER maintenance concept may not be acceptable from a view point of TBR.
Based on our roadmap, the time limit for our decision is ~2015.
Cont.
Finding by the roadmap & Working breakdown Finding by the roadmap & Working breakdown studystudy
(ex5) Anti tritium-transit technology for water cooling pipes
If we use a water cooled ferritic steel blanket, a large amount of tritium may transit to the secondary cooling loop from the primary. Development of anti-transit coating or 3rd water loop with heat exchanger will be required. The 3rd loop reduces the thermal efficiency.
Cont.
Finding by the roadmap & Working breakdown Finding by the roadmap & Working breakdown studystudy
(ex4) Divertor with Demo-relevant armor
If we want to test the new divertor in ITER, a high reliability will be required to install it in ITER. Therefore we should begin the R&D of the divertor with Demo-relevant armor as soon as possible.
@ Breakdown list of works which consists of over 1000 works for the DEMO construction, has been built.
@ The time schedules and a lot of decision points are defined on the working list.
@ The roadmap has been built based on the list of break down structure of works, and the break down schedules.
@ It has been pointed out that some issues are critical for DEMO while R&D project does not exist or is insufficient. We should begin those R&D’s during the next decade. Some example issues have been shown.
@ Investigation of the impact by the newest ITER schedule is in progress, but it has not be included in the present roadmap yet.
Summary on our roadmap studySummary on our roadmap study