CASE STUDY NUVIA ROSYTH
6

CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down

Sep 27, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down

CASE STUDYNUVIA ROSYTH

Page 2: CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down

• High security site – limited access for personnel

• Location of final installation remote for tradesmen

• Limited lay down available for site access

RESTRICTIONS

Page 3: CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down
Page 4: CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down
Page 5: CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down

• Onsite time reduced from 16 weeks to 1 day

15.8 weeks on site saving

• Overall cost of prelims on site 15.8 weeks saved

£79k saving to client

• Mechanical & Electrical equipment tested and assured

offsite prior to installation

• Modules could be removed from inside the dock & re

installed within 3 days

IMPACT OFMODULAR CONSTRUCTION

Page 6: CASE STUDY NUVIA ROSYTH - NEPIC€¦ · NUVIA ROSYTH •High security site –limited access for personnel •Location of final installation remote for tradesmen •Limited lay down

• Modules construction at ground level

• Modules fitted out & tested prior to delivery

• Mock up of submarine tested adjacent to modules

• Offsite construction local to specialist trades

• Installation of 5 modules completed in 1 working day

BENEFITS OFMODULAR CONSTRUCTION