Capital Improvements Program City Council October 14, 2014
78

Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Jul 28, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Capital Improvements

Program

City Council

October 14, 2014

Page 2: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Presentation Today • CIP Advantages/Process

• Approved CIP Program (FY14 - FY18 CIP)

• Financial Forecast

• Projects in CIP Database

• Other Projects

• Questions

Neighborhood Attendees ~15 (Paul Kaspar)

2

Page 3: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Capital Improvement Capital Improvement Project (CIP)

• $200,000 or more cost

• Non-recurring expense

• At least 5 year benefit

CIP Program Advantages

• Coordination of related projects

• Land acquisition ahead of construction

• Improved fiscal responsibility

• Maximizes staff time (provides focus)

• Higher priority projects done first

3

Page 4: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Goals • Objective project prioritizations

• Strategic direction incorporated in process

• Community buy-in

• Flexibility (for changes in process)

• Transparency

• Proactive vs. Reactive

4

Page 5: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

CIP Process • Resolution 3185

– CIP Process Adopted November 25, 2008

– Established Ranking System

• Resolution 3367

– Adopted a biennial process August 23, 2011

– Odd Fiscal Year

• Council Adopts 5 Year CIP

– Even Fiscal Year

• Update Database/Provide Update to Council

• Four CIP programs adopted since 2008:

– 2009, 2010, 2011, 2013

5

Page 6: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Biennial Process (Odd FY) • October – December

– Evaluate existing CIP bond funds to determine available savings

– Apply ranking criteria to Database projects – develop list of ranked

projects

• January – March – Obtain initial estimate of projected debt issuances for next 5 years

– Utilize ranked list of projects to draft a proposed CIP based on debt

issuances

• April – June – Review CIP with City Management

– Prepare City Council Presentation

• July – Discuss CIP with City Council

– Modify as needed

• August – September – Council adopts 5 year CIP

6

Page 7: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Biennial Process (Even FY) • October – March

– Present status update to City Council on active CIP projects

– Update the cost estimates for projects in the CIP database

– Evaluate the projects in the database to make sure still valid

– Enter new projects into the database, developing scope and cost

estimates

– Input citizen survey or other feedback into the database

– Apply ranking criteria to database projects – develop list of ranked

projects

• April – May – Review ranking criteria and develop recommended changes (if needed)

• June – September

– Present recommended changes (if any) to City Council for

consideration / adoption

• Issue Debt in Even Fiscal Year

7

Page 8: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY14 - FY18 CIP • Approved by Resolution 3506 on September 10,

2013

• Funding Sources

– Certificates of Obligation (Bond funds)

– Transportation Fee

– Drainage Fee

– Cemetery Funds

– Water and Sewer for the General Fund CIP projects

8

Page 9: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Funding Sources

• Certificates of Obligation (Bond Funds)

– Streets

– Buildings

– Sidewalks

– Drainage

– Fire Trucks

9

Page 10: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Funding Sources

• Transportation Fee

– Street Reconstruction

– Street Maintenance

– Traffic Signals

10

Page 11: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Funding Sources

• Drainage Fee

– Drainage Facilities

– Drainage Studies

11

Page 12: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Funding Sources

• Cemetery Funds

– Expansion of Cemetery Facilities

12

Page 13: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Funding Sources

• Water and Sewer Funds

– Water and Sewer Facilities

13

Page 14: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Other Sources

• TxDOT Funds

– Proposition 1 ballot

– If passes, may be eligible for State funds

– Funds funneled through MPO

• SH 6 Ramp Relocation from FM 158 to US 190/SH

21 – MPO #35 ($4 MM)

• SH 21 from approximately 2.32 miles E. of SH 47

to SH 47 reconstruct crossovers ($1 MM)

• Tarrow St. / Tarrow Dr. from FM 60 to Carter Crk.

Pkwy. Construct bike/ped facilities w/ bridge over

Burton Crk. – MPO #313 ($1 MM)

14

Page 15: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

CIP Process

15

Project Database

Public Input

Financial Reality

Ranking

CIP

Page 16: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Current Ranking Criteria

16

Page 17: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Typical Large CIP Schedule

Design Services ~ 15 months

Land Acquisition ~ 12 months

Year 3 Year 2 Year 1

Utility

Relocation

~ 6- 8 months

Construction ~ 12 months

Design Services Land Acquisition Utility Relocation Construction

Bid

Award

2 mo.

Year 4

17

Page 18: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Typical Design Phase MONTH

Design Services Surveying City Review

2 1 3 4 5 6 9 8 7 10 11 12 13 14 15 16 17 18

Sc

hem

ati

c

Des

ign

Survey Schematic

Design

Cit

y

Revie

w

Preliminary

Design

Cit

y

Revie

w

Final Design

Cit

y

Revie

w

Advertise & Award

Bid & Council Award

18

Page 19: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Typical Land Acquisition Phase

Initial Contact Land Acquisition / Appraisals / Negotiation Condemnation

MONTH

12 8 4 3 2 1 5 6 7 11 10 9

Intr

od

uc

tory

Lett

ers

Title Reports, Contact w/ Owners, Make Offers

Condemnation

19

Page 20: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY14 CIP FY14 Debt Issuance = $7,815,000

• 28th Street Reconstruction - $3,925,000

• Old Hearne Rd / Wilkes St - $3,125,000

• Fire Truck - $765,000

• Cemetery Expansion – Phase 1 - $700,000

– Not a part of GF Debt

20

Page 21: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY14 CIP

• Old Hearne Rd – $650,000

– ($78k Design, $3.3 MM TF, $250k DF)

• West Fork Stillcreek Drainage Study - $75,000

• Traffic Signal (Old Hearne Rd/Texas Ave) -

$250,000

• Ettle St Overtopping - $300,000

21

Page 22: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY14 CIP Cemetery Expansion

• Cemetery

Endowment Fund

• $980,000 available

• Estimated Cost:

Phase 1 - $700,000

Phase 2 - $400,000

22

Page 23: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY14 CIP Cemetery Expansion Preliminary Layout

23

Washington / Old Kurten Re-alignment

875 - 20’x30’ Plots

Page 24: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY15 CIP

• Traffic Signal (S College/Carson St) - $300,000

• West Fork Drainage (Design) - $200,000

• West 17th St Box Culvert (Design) - $80,000

24

Page 25: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY16 CIP FY16 Debt Issuance = $7,000,000

• Fire Station 2 Design & Construct - $4,520,000

• Old Hearne Rd South Design (to Texas Ave) -

$1,600,000 ; ($1,800,000)

– Construction planned for FY20, giving time for ROW

acquisition

• Fire Truck - $880,000

25

Page 26: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY16 CIP

• West Fork Stillcreek Drn Const (Ph 1) - $400,000

• West 17th St Box Culvert (Const) - $500,000

($630,000)

26

Page 27: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY17 CIP

• Traffic Signal (S. College/Villa Maria) - $300,000

• West Fork Stillcreek Drn Const (Ph 2) - $600,000

27

Page 28: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY18 CIP FY18 Debt Issuance = $7,100,000

• S. College Ph. 2 (Villa Maria Rd to Sulphur Springs

Rd) - $4,750,000

• Sadie Thomas Splashpads - $380,000

• 29th Street Sidewalks - $500,000

• Broadmoor Dr Sidewalks - $250,000

• Rustling Oaks Dr Sidewalks - $270,000

• Fire Truck - $950,000

28

Page 29: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY18 CIP

• West Fork Stillcreek Drn Const (Ph 3) - $450,000

29

Page 30: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY19 Proposed CIP

• Miscellaneous Drainage Projects - $300,000

• Street Maintenance - $3,000,000

• Traffic Signal Replacement - $610,000

30

Page 31: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY20 Proposed CIP FY20 Debt Issuance = $7,442,000

• Old Hearne Rd Ph. 2 - $3,343,000

• South Coulter Dr – $3,199,000

• Fire Truck - $900,000

31

Page 32: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

FY20 Proposed CIP

• Old Hearne Rd Ph 2 - $1,000,000

• S. Coulter Dr (S. College Ave /29th St) - $500,000

• Miscellaneous Drainage Projects - $300,000

• Street Maintenance - $3,000,000

• Traffic Signal Replacement - $780,000

32

Page 33: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Other Projects

• Projects to be added

– First Street

– Skate Parks

– St. Joseph

• 29th St/Memorial Dr

• 29th St/Villa Maria Rd

– West 26th St

– Highway Safety Improvement Program

33

Page 34: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Questions

34

Project Database

Public Input

Financial Reality

Ranking

CIP

Page 35: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

City of Bryan

Financing Picture

Page 36: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Debt Considerations

• Revenues Come from Property Taxes

– About 1/3 of tax rate goes to pay debt

– Remainder goes to General Fund

– Adjusted periodically

– As property values increase, revenues

increase and ability to borrow increased

– Creates a steady steam of revenue

36

Page 37: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Projected Debt Service Revenues (in millions)

37 $-

$1

$2

$3

$4

$5

$6

$7

$8

$9

$10

FY2015 FY2016 FY2017 FY2018 FY2019 FY2020

Page 38: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

• Existing debt plus new debt must fit in this

revenue stream

38

Debt Considerations

Page 39: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Existing Annual Debt Service (in millions)

39

$-

$1

$2

$3

$4

$5

$6

$7

$8

$9

Page 40: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Current CIP Budget

• FY 14 $7.8 mm

• FY 16 $7.0 mm

• FY 18 $7.1 mm

40

Page 41: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Existing and New Debt Service (in millions)

41

$-

$1

$2

$3

$4

$5

$6

$7

$8

$9

$10

FY2015 FY2016 FY2017 FY2018 FY2019 FY2020

Page 42: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Borrowing Outlook

The City’s capacity to borrow has increased

in recent years due to:

– Property Value Increases

– Lower Cost of Interest

– Refinancing of higher cost older debt

42

Page 43: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Lenders Viewpoint

Lenders want to see:

• Growth in property values – ability to pay

• Borrowing for major projects

• Execution a plan

City of Bryan has an “AA” rating – S&P ‘AA’—Very strong capacity to meet financial commitments.

43

Page 44: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Financial

Questions

Page 45: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

CIP Database

Page 46: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

CIP Database • Input from Citizens, Council, Staff, Citizen

Surveys

• Includes projects for Parks, Streets, Traffic

Signals, Fire Stations, Drainage, Sidewalks,

Facilities, Information Technology

46

Page 47: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Review CIP

Database Projects

47

Page 48: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Other Projects

Page 49: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Old Hearne Road

August 7th

City Council

August 7, 2014

Page 50: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Old Hearne Road

• In current CIP for design in FY16 CIP

• Estimated design cost is $1,800,000

• Recommended by Staff to construct in

FY20 CIP

• Estimated cost is $4,343,000 for

construction

50

Page 51: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Peale Street

August 7th

City Council

August 7, 2014

Page 52: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Peale Street

• South side

– 525 feet long

– Open ditch

– 2009: Reconstructed in place with the addition

of limestone base and overlaid

• North side

– 190 feet long

– Open ditch

– 2011: Overlaid

52

Page 53: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Peale Street (South)

53

Page 54: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Peale Street (South)

54

Page 55: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Peale Street (North)

55

Page 56: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Pavement Preservation

56

Page 57: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Pavement Condition

57

Page 58: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Woodville Road

Page 59: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Woodville Road

• In current CIP database ST_09_002

• Entered into the database in 2009

• Current CIP ranking is 13

• Estimated future cost ~ $ 11.4 million

59

Page 60: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

West 17th Street Culvert

Page 61: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

West 17th Street Culvert

• Ranked high in Stormwater Masterplan

• In current FY14-18 adopted CIP

• Est. cost (design and construction) - $580k; ($710k)

• Design Contract to Council – 2nd meeting in

October/First meeting in November

• Design (12 weeks) – March 2015

• Bidding – March/April 2015

• Council Award – April/May 2015

• Construction Start – May/June 2015

• Const. complete (5 mo) – October/November 2015

61

Page 62: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Martin Luther King Jr Blvd

Page 63: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

MLK Jr Blvd

• Planned to be resurfaced in 2015 year – Texas Ave

to SH6

• From Military Dr to SH6 in database. Project

ST_09_109 (9), ST_09_209 (8)

• New project added to database. Includes

redoing entire length of MLK. ST_14_011

– Estimated cost: $41 MM (today’s cost)

63

Page 64: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Sandy Point Road Sidewalks

August 7th

City Council

August 7, 2014

Page 65: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Sandy Point Rd - Timeline

• 12/11/2013 – Met with County staff to discuss sidewalk

and possibility of using trustee labor

• 1/21/2014 – Staff met with Council members Pena and

Saenz. Makes them aware we are already working with

County on Sandy Point Rd sidewalk

• Feb. 2014 – Staff met w/ County to discuss needs,

location and ILA

• Mar. 2014 – ILA is signed by both governmental

agencies

• 3/31/2014 – Staff asked County to provide officer and

inmates to construct the Apartment side also. They

agree with 50/50 of materials on their side only.

65

Page 66: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

• 4/1/2014 – COB staff made contact with TXDOT

staff

• 4/9/2014 – COB staff met with TxDOT staff and

they have utility easement concerns

• April 2014 – Contract with Jones & Carter to

survey TXDOT ROW

• 5/30/2014 – ROW was staked

• 6/2/2014 – TxDOT wants to leave utility corridor

open. Rural FM road. Saw the need for

curb/gutter. Called in for locates per TXDOT

request.

66

Sandy Point Rd - Timeline

Page 67: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

67

• Mid – June – TXDOT requested more in depth locates

(fiber line found running in the same area that we want

the sidewalks to be placed).

• 6/17/2014 – Met with TXDOT and we never received a

go ahead. We were told there were several challenges

on this project and that it would be costly.

• 6/24/2014 – Sent email to TXDOT that the remaining

locates (fiber) had been completed (no response from

TXDOT)

• 6/30/2014 – Sent email to TXDOT if they had a chance

to review the locates.

Sandy Point Rd - Timeline

Page 68: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

68

• 7/8/2014 – TXDOT responded with other questions –

Staff responded the same day to TXDOT…no response

on this since

• 7/10/2014 – Sent email to see if they could meet to

discuss

• 7/14/2014 – They responded that they would get back

with staff

• 7/28/2014 – Staff sent another email request to meet

• 7/31/2014 – Staff left phone message

• 8/1/2014 – Staff left phone message

• 8/6/2014 – Staff talks to TxDOT. Staff is waiting on

TxDOT to provide direction on Curb and Gutter and level

of design they will require.

Sandy Point Rd - Timeline

Page 69: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

69

• 8/8/2014 – TXDOT responded that the project will have

to go through the AFA process

• 9/11/2014 – Staff met with TxDOT to discuss AFA

requirements

• TxDOT to require

Scope of Work – (project limits, type of work, etc.)

Cost estimate – (provide breakdown of services)

Environmental Analysis (Study & Clearance)

Engineering (PS&E)

Construction

Sandy Point Rd - Timeline

Page 70: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Sandy Point Rd

70

Page 71: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Sandy Point Rd

71

Page 72: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Sandy Point Rd

72

Page 73: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Sandy Point Rd

73

Page 74: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

74

Page 75: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

75

Page 76: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Sandy Point Rd (County)

76

Page 77: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Sandy Point Rd (Apt Side)

77

Page 78: Capital Improvements Program Process - WTAWwtaw.com/wp-content/uploads/2014/10/BryCoun101414cip.pdf · Biennial Process (Odd FY) • October – December ... – Construction planned

Questions

78

Project Database

Public Input

Financial Reality

Ranking

CIP