Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department
27

Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Mar 28, 2015

Download

Documents

Eloise Haslip
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Capital Construction: NYS SBGA Fall Conference -

Buffalo, September 30, 2003

Curt Miller

Office of Facilities Planning

New York State Education Department

Page 2: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

The Capital Project

Who: identification of need for a capital project may come from many people.

Page 3: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

The Capital Project

What: Capital Projects Identified– Reconstruction: boiler and roof replacement,

walls, floors, ceilings, lighting, windows, etc.– Additions: construction of new space attached

to existing building– New Construction: construct a new building

Page 4: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

The Capital Project

How: the person delegated to initiate the project will follow the next steps...

Page 5: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

The Letter of Intent or “LOI”

Four flavors:– New Building,

Addition or Reconstruction

– Manufactured Building

– District-Wide– Leased Space or

Discovered Buildings

Page 6: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

LOIs continued...• Find blank LOIs on our web page• Mail or Fax to our office (But not both!)

Page 7: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Choosing an Architect or Engineer

• RFP - We recommend choosing the consultant using a request for proposal

• Choose carefully - an important link in the process• Must be NYS licensed• Will draft, sign, seal and certify plans and specs

Page 8: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Response (package) to the LOI

Facilities Planning sends:– Response letter, includes name of project

manager and 15-digit project control number, CSI codes and name of building

– Directions for submitting all forms necessary for a complete final submission or for a preliminary submission when a project involves new space

– Sent to the person on our computer system

Page 9: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Eligibility for Building Aid• Must be an instructional facility• Must have general construction costs of $10,000

or more• Must be legitimate capital construction• Funding sources must be aidable (e.g. federal and

state grants are NOT aidable sources)• Must have proper authorization• Must have SED building permit BEFORE going out

to bid• Building Aid Unit calculations are used to

determine aidable new construction and additions

Page 10: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

The Complete SubmissionRequires the following forms:

• Checklist• Application for Approval of Final Plans and Specs• Evaluation of Existing Building Form• Scope of Proposed Project (plus SHPO cover,

Board Resolution and SEQR Clarification Form)• Highway and Asbestos Letters• Floodplain Certification• NEW Code Compliance Checklist (now includes

the structural responsibility checklist)

Page 11: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Preliminary Submissions

• For projects involving new instructional space• Preliminary Submission must include:

– Application for Approval of Preliminary Plans (FP-P)

– Facilities Needs Assessment Summary– Enrollment projections– Instructional Space Review form (from VESID)– Scope of Proposed Project (SHPO cover)– Evaluation of Existing Building form (EEB)– Schematic Floor Plans– Site Plan

Page 12: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Final Submissions

• Very similar to documents needed for final submission of reconstruction projects, except...

• SEQRA documents, Scope of Proposed Project and Evaluation of Existing Building should already have been part of the preliminary submission

Page 13: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Reconstruction Projects

• Require only a final submission

• Package to FacPlan must include:– “Checklist”– Application form (FP-F)– Evaluation of Existing Building form (EEB)– SEQR documents as outlined above– Highway letter– Asbestos letter– Code Compliance Checklist

Page 14: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Reconstruction Projects, continued

– Plans and Specs, signed, sealed and certified– Must paperclip these items in spec book:

• non-collusive bidding certification• “equivalency clause” (You may check the

“Instruction Guide” on our website for a sample of an equivalency clause. They are a frequent cause of confusion!)

• wage rates• Rescue 155.5 items

Page 15: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

SEQR (State Environmental Quality Review)

New Process implemented September 1, 2001• District takes “lead agency” status• Paperwork to complete:

– “Scope of Proposed Project” (find this on our website)

– Determination document(s) (i.e., such as a board resolution declaring a “Type II project”

– Copy of “SHPO letter” (State Historic Pres. Office) for new space or 50+ y/o building

– SEQR Clarification form, if needed

Page 16: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Discovered Buildings

• Includes shipping containers and tool sheds and any other lockable building, regardless of size

• Requirements for submission:

- Form FP-AU- certification by architect- architectural drawings- Fire Safety Report- AHERA management plan

Page 17: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Temporary Quarters (leased space)

• Requires same paperwork submission as Discovered Building with the addition of a local Certificate of Occupancy

• For lease aid, additional documentation (including the lease) will be needed

Page 18: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Safety During Construction, Remodeling and Maintenance

Page 19: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Please know these sections!

• § 155.2 Construction and remodeling of school district facilities.

• § 155.5 Uniform Safety Standards for School Construction and Maintenance Projects

Page 20: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Addenda and Change Orders

• Addenda alter Plans and Specs BEFORE the project is bid

• Change orders alter Plans and Specs AFTER bid process, contract signing and work begun

• A new “Change Order Certification” form is now required with all change orders (and must be submitted with the change order or the change order will be returned!)

Page 21: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.
Page 22: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

Bits ‘n Pieces

FP-FI forms and financial revision

• Available on our website

• Total of all projects done under a referendum must never exceed authorization $

Page 23: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

FP-FI form

• FP-FI forms and financial revision

Page 24: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

More Bits ‘n Pieces• Emergencies are repairs

– Board declares “Ordinary Contingent Expense”

– Repairs made may become incidental to a subsequent capital project of which it becomes a part

• The capital project will require a Building Permit (which will be expedited)

Page 25: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

What’s New at FacPlan

• International Building Code: all projects now must follow the International Building Code.

• Minor Maintenance and Repair Aid is available for 2003-04. Must claim by August 1, 2004.

• Chromated Copper Arsenate (CCA) Playgrounds Prohibition took effect on March 15, 2003

• Know the definition of “emergency project” - must be unforeseen, not due to neglect or age

• Electrically operated partitions were require to be compliant by June 1, 2003 or made inoperable

Page 26: Capital Construction: NYS SBGA Fall Conference - Buffalo, September 30, 2003 Curt Miller Office of Facilities Planning New York State Education Department.

“Fill for Fields”