Capacity Planning Required Capacity Required Capacity -When manufacturing orders -When manufacturing orders are converted to measurable units of are converted to measurable units of capacity, such as standard hours, they can be capacity, such as standard hours, they can be used in predicting the need for capacity in used in predicting the need for capacity in different work centers over time. This different work centers over time. This statement of the resources needed to support statement of the resources needed to support the plan is called the REQUIRED CAPACITY the plan is called the REQUIRED CAPACITY Demonstrated capacity Demonstrated capacity - The current rate of - The current rate of output of a work center that is accepted by output of a work center that is accepted by the organization as its proven capability is the organization as its proven capability is called the demonstrated capacity called the demonstrated capacity
33
Embed
Capacity Planning Required Capacity-When manufacturing orders are converted to measurable units of capacity, such as standard hours, they can be used in.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Capacity Planning
Required CapacityRequired Capacity-When manufacturing orders are -When manufacturing orders are converted to measurable units of capacity, such as converted to measurable units of capacity, such as standard hours, they can be used in predicting the need standard hours, they can be used in predicting the need for capacity in different work centers over time. This for capacity in different work centers over time. This statement of the resources needed to support the plan is statement of the resources needed to support the plan is called the REQUIRED CAPACITYcalled the REQUIRED CAPACITY
Demonstrated capacityDemonstrated capacity- The current rate of output of a - The current rate of output of a work center that is accepted by the organization as its work center that is accepted by the organization as its proven capability is called the demonstrated capacityproven capability is called the demonstrated capacity
Planned CapacityPlanned Capacity - The predicted output of a - The predicted output of a work center in the future is called its planned work center in the future is called its planned capacity. The planned capacity is the capacity. The planned capacity is the demonstrated capacity plus or minus the expected demonstrated capacity plus or minus the expected results of known capacity adjustmentsresults of known capacity adjustments
Theoretical or Maximum CapacityTheoretical or Maximum Capacity-The -The maximum output a work center can achieve maximum output a work center can achieve assuming the current product specifications, assuming the current product specifications, product mix,plant, and equipment is its theoretical, product mix,plant, and equipment is its theoretical, or maximum, capacity or maximum, capacity
Work CenterWork Center-APICS defines a work center as a -APICS defines a work center as a specific production facility, consisting of one or more specific production facility, consisting of one or more people and/ or machines they can be considered as one people and/ or machines they can be considered as one unit for the purposes of capacity planning and detailed unit for the purposes of capacity planning and detailed scheduling.scheduling.
Capacity ManagementCapacity Management –The function of establishing , –The function of establishing , measuring, monitoring, and adjusting limits or levels of measuring, monitoring, and adjusting limits or levels of capacity in order to execute all manufacturing capacity in order to execute all manufacturing schedules;the production plan, master production schedules;the production plan, master production schedule, material requirements plan, and dispatch listschedule, material requirements plan, and dispatch list
Capacity ActionsCapacity Actions-When there is a discrepancy between -When there is a discrepancy between demonstrated capacity and required capacity, a capacity demonstrated capacity and required capacity, a capacity action is needed. The capacity action must be action is needed. The capacity action must be predictable, meaning that the outcome is fairly certain predictable, meaning that the outcome is fairly certain and measurableand measurable
Symptoms of Poor Capacity Planning
High costs resulting from poor utilization of resourcesHigh costs resulting from poor utilization of resources Over committed schedules causing missed deliveries and Over committed schedules causing missed deliveries and
poor customer servicepoor customer service Invalid priorities because more work is scheduled than can Invalid priorities because more work is scheduled than can
be accomplishedbe accomplished Excess work-in-process inventoryExcess work-in-process inventory Longer cycle timesLonger cycle times High raw materials and purchased components inventoriesHigh raw materials and purchased components inventories If resources are greater than required, excess idle time or If resources are greater than required, excess idle time or
poor efficienciespoor efficiencies
Tools for Solving Capacity Planning Problems Resources requirements plan Resources requirements plan Master production summariesMaster production summaries Capacity requirements plansCapacity requirements plans Finite capacity plansFinite capacity plans Capacity simulationsCapacity simulations Input-Output Controls Input-Output Controls
The Resource Requirements PlanThe Resource Requirements Plan is defined as is defined as the process of establishing, measuring , and the process of establishing, measuring , and adjusting limits of long range capacity. Resource adjusting limits of long range capacity. Resource requirement planning is based on the production requirement planning is based on the production planplan
Master Schedule SummaryMaster Schedule Summary- It assures that the - It assures that the master schedules sum up to management’s master schedules sum up to management’s production planproduction plan
Capacity Requirement PlanningCapacity Requirement Planning-It is the process -It is the process of determining in detail how much labor and of determining in detail how much labor and machines resources are required to accomplish the machines resources are required to accomplish the task of production task of production
Resources Requirement Planning HorizonHorizon ResponsibilityResponsibility Data Required-Select product families,Identify Data Required-Select product families,Identify
critical work centers,Calculate product load profiles, critical work centers,Calculate product load profiles, Calculate the resources requirement planCalculate the resources requirement plan
Selecting product familiesSelecting product families Identify critical work centersIdentify critical work centers Calculate product load profilesCalculate product load profiles Calculate the Resources Requirements PlanCalculate the Resources Requirements Plan
Characteristics of Critical Work Center
New equipment purchases is costly or require long New equipment purchases is costly or require long lead time to obtainlead time to obtain
Subcontracting is costly and difficult to arrangeSubcontracting is costly and difficult to arrange Skilled workers are not easily availableSkilled workers are not easily available Bottlenecks exist under normal conditionsBottlenecks exist under normal conditions Alternate routings are not available or very costlyAlternate routings are not available or very costly There is a proprietary or sole –source operation or There is a proprietary or sole –source operation or
processprocess
Product Load Profiles
FamilyFamily
Critical Work CenterCritical Work Center AA BB CC DD
BlendingBlending .03.03 00 .04.04 .012.012
PressPress .08.08 00 .12.12 .022.022
FinishFinish .05.05 .055.055 .23.23 .036.036
QC TestQC Test .021.021 .02.02 .07.07 00
PackPack .015.015 .015.015 .03.03 .01.01
Special processSpecial process .076.076 .055.055 .06.06 00
Routings
OperationOperation Work centerWork center Setup hoursSetup hours Run hoursRun hours
Master Schedule: Part No.R123, Safety Stock:1400, Lead Time:2 Weeks, Time Fence: 8 Weeks, Name: Master Scheduled End Items, On Hand:2900, Lot Size:4000, Family: D.
WeekWeek HoursHours Part No.Part No. Order No.Order No. TypeType
5/205/20 16.916.9 10011001 M1011M1011 RR
5/205/20 16.816.8 81628162 M4234M4234 RR
5/205/20 11.311.3 21522152 M6185M6185 RR
5/205/20 19.219.2 38943894 M5344M5344 RR
5/205/20 14.614.6 98339833 M7150M7150 RR
5/205/20 16.016.0 84908490 M7757M7757 RR
5/205/20 23.123.1 12951295 M2120M2120 PP
5/205/20 14.714.7 14431443 M2875M2875 PP
5/205/20 8.58.5 60106010 M7271M7271 PP
Critical Data Elements to Support Capacity Requirements Planning Complete and accurate routingsComplete and accurate routings Good work center definitionsGood work center definitions Accurate move, queue,setup, and run timesAccurate move, queue,setup, and run times Good shop schedulingGood shop scheduling Accurate demonstrated capacitiesAccurate demonstrated capacities Timely and accurate shop reportingTimely and accurate shop reporting
Once a capacity plan is approved and Once a capacity plan is approved and implemented, it can often change. implemented, it can often change. Manufacturing may not always perform as Manufacturing may not always perform as scheduled, or the requirement can change. scheduled, or the requirement can change. There is a need to regenerate capacity plans There is a need to regenerate capacity plans on a regular basis. Manually this becomes on a regular basis. Manually this becomes impossible.impossible.
Finite Capacity Planning
Finite capacity planning is a method of planning capacity Finite capacity planning is a method of planning capacity that assumes capacity is fixed. that assumes capacity is fixed.
Horizon-Finite capacity planning is limited to shorter time Horizon-Finite capacity planning is limited to shorter time frames than resources requirements planning.Adding frames than resources requirements planning.Adding equipment, expanding a plant, or adding a new facility are equipment, expanding a plant, or adding a new facility are long term capacity decisions.In short term the long term capacity decisions.In short term the demonstrated capacity is nearer to the maximum demonstrated capacity is nearer to the maximum capacity , no action is needed for capacity action.capacity , no action is needed for capacity action.
Loading capacity finitely is more problematic.Forward Loading capacity finitely is more problematic.Forward scheduling is used in finite capacity planning. First to load scheduling is used in finite capacity planning. First to load method is adoptedmethod is adopted
Input – Output Control
It is used for capacity control where planned and It is used for capacity control where planned and actual inputs and planned and actual outputs of a actual inputs and planned and actual outputs of a work center are monitored.It is a measure of work work center are monitored.It is a measure of work center performance.center performance.
It is a short term capacity planning tool usually It is a short term capacity planning tool usually covering 6 to 8 weeks of the planning horizoncovering 6 to 8 weeks of the planning horizon
Data required is planned input , actual input and Data required is planned input , actual input and deviationdeviation
Capacity Simulation Implementation Issues
Defining where and when to use the toolDefining where and when to use the tool Identifying and collecting accurate dataIdentifying and collecting accurate data Developing interfaces for downloading and uploading information to other Developing interfaces for downloading and uploading information to other
systemssystems Determining whether to maintain two sets of data in both the MRPII and in the Determining whether to maintain two sets of data in both the MRPII and in the
capacity simulatorcapacity simulator Defining how often you need to regulate capacity plansDefining how often you need to regulate capacity plans Determine how to integrate it with MRPII and effectively communicate the new Determine how to integrate it with MRPII and effectively communicate the new
plan to manufacturing and purchasingplan to manufacturing and purchasing Specifying to what degree you can afford change and effectively manage it Specifying to what degree you can afford change and effectively manage it Defining hardware requirements Defining hardware requirements Selecting the capacity simulation softwareSelecting the capacity simulation software Developing education and training requirementsDeveloping education and training requirements Identifying the policies and procedures for operating and maintaining the system Identifying the policies and procedures for operating and maintaining the system Justifying how the system will pay for itselfJustifying how the system will pay for itself
Capacity Strategies Reserving capacity for a particular purpose or for a orderReserving capacity for a particular purpose or for a order Load levelingLoad leveling Rate-based planning-It is simply converting the Rate-based planning-It is simply converting the
requirements to an equivalent unit of measure that is requirements to an equivalent unit of measure that is accurate and fitting for the work centeraccurate and fitting for the work center
Capacity planning forum should meet regularly.Capacity planning forum should meet regularly. Long term capacity actions are made to assure that the Long term capacity actions are made to assure that the
resources are available to meet the planresources are available to meet the plan Maser schedulers review the current master schedules to Maser schedulers review the current master schedules to
assure that they are in line with production plan. Master assure that they are in line with production plan. Master schedule summary provides this informationschedule summary provides this information
CRP and input out controls are reviewed weekly and CRP and input out controls are reviewed weekly and actions taken by concerned manager on capacity actionsactions taken by concerned manager on capacity actions
Policies Procedures and Performance Measures
The goal of capacity planning The goal of capacity planning How to measure and maintain demonstrated capacity How to measure and maintain demonstrated capacity The predictable capacity actions that can be taken The The predictable capacity actions that can be taken The
time horizon of each of the capacitytime horizon of each of the capacity The frequency of each of the capacity planning meetingsThe frequency of each of the capacity planning meetings The attendees at each meetingsThe attendees at each meetings The responsibility for the accuracy of the capacity The responsibility for the accuracy of the capacity
information information The documentation and follow-up process to assure that The documentation and follow-up process to assure that
capacity planning is working effectivelycapacity planning is working effectively A good set of capacity performance measuresA good set of capacity performance measures
Performance Measures
No critical work center’s required varies from its planned No critical work center’s required varies from its planned capacity by more than plus or minus 10 percent on a capacity by more than plus or minus 10 percent on a monthly basismonthly basis
The MPS summary report shows the master schedules are The MPS summary report shows the master schedules are within plus or minus 7 % of the production plan for each within plus or minus 7 % of the production plan for each familyfamily
The CRP reports show no work center with past due The CRP reports show no work center with past due requirements greater than 1 week’s worth of demonstrated requirements greater than 1 week’s worth of demonstrated capacitycapacity
The CRP reports show no work center with overstated The CRP reports show no work center with overstated requirements over a period of 4 weeks or morerequirements over a period of 4 weeks or more
Input-output reports show less than 5 % of all work centers Input-output reports show less than 5 % of all work centers out of tolerance each week. out of tolerance each week.
Trading Partner
Trading Partner
Trading Partner
Collaborate
SUPPLIERS
CPFR
EDI
Internet
Promotions
Forecasts
Item Catalog
Orders
GenerateDemand
Determine
Reqts
Make toDemand
APS
CRM
ERP
CPFR Unplanned and uncoordinated events that distort smooth flow of Unplanned and uncoordinated events that distort smooth flow of
product through supply chainproduct through supply chain Channel participants fail to coordinate their individual forecasts of Channel participants fail to coordinate their individual forecasts of
final consumer demand and marketing events designed to stimulate final consumer demand and marketing events designed to stimulate demanddemand
Joint planning and information sharing would increase the likely Joint planning and information sharing would increase the likely hood of a successful relationshipshood of a successful relationships
CPFR is a process initiated by the consumer products industry to CPFR is a process initiated by the consumer products industry to achieve such a coordinationachieve such a coordination
It does not replace automatic replenishment strategies but It does not replace automatic replenishment strategies but supplements them by a cooperative processsupplements them by a cooperative process
CPFR coordinates the requirement plan for the demand creation and CPFR coordinates the requirement plan for the demand creation and demand fulfillment activitiesdemand fulfillment activities
In CPFR collaboratively developed information is used jointly and In CPFR collaboratively developed information is used jointly and iteratively by planners to generate demand, and match production to iteratively by planners to generate demand, and match production to demanddemand
CPFR
In this process joint business planning by retailer, supplier In this process joint business planning by retailer, supplier share , discuss, coordinate and rationalize their own share , discuss, coordinate and rationalize their own individual strategies to create a partnership strategyindividual strategies to create a partnership strategy
Joint plan offers common plan for promotion,sle of Joint plan offers common plan for promotion,sle of merchandisemerchandise
Joint calender is created to share information on a product Joint calender is created to share information on a product flowflow
Common sales forecast is created and shared among Common sales forecast is created and shared among membersmembers
Using consensus forecast, production, replenishment, and Using consensus forecast, production, replenishment, and shipment plans are developedshipment plans are developed
Such a close working arrangement reduces cost of doing Such a close working arrangement reduces cost of doing business for all channel mmbersbusiness for all channel mmbers