Cancellation Process
There would be a provision to cancel the order till indoor task on new provision orders.
Cancellations also allowed at modify and delete orders from clarity.
Cancellation Process in Clarity:
Following are the common steps to cancel the order at any task in clarity.
1. Select one of the reasons from the LOV of “HALT REASON” attribute.
2. Fill the FEEDBACK attribute with proper comments.
3. Close the task.(If it is manual task then update the task status to COMPLETED else
update the task status to CLOSED.)
1. New Provision Landline, PCO, ISDN PRI, ISDN BRI and WLL services:
•Once the new provision order is submitted to clarity , the task flow would be as belowfor any wireline service (Landline, PCO, ISDN PRI, ISDN BRI):
For WLL Services(WLL_FIXED,WLL_MOBILE,WLL_EVDO,WLL_NIC):
OUTDOOR
MDF
INDOOR
FINAL TESTING
IDENTIFY
LINEMAN
FINAL TESTING
OUTDOOR
INDOOR
Page 2
8/3/2019 Cancellation Clarity User Manual
http://slidepdf.com/reader/full/cancellation-clarity-user-manual 2/11
• At IDENTIFY LINEMAN in progress:
o At IDENTIFY LINEMAN task, the JTO/SDE can initiate cancellation due to
reasons like Wrong Sublocality, Wrong Address, Customer Initiated, Change in
Urban/Rural and defaulter premises. Please refer the below screen shots.
Page 3
8/3/2019 Cancellation Clarity User Manual
http://slidepdf.com/reader/full/cancellation-clarity-user-manual 3/11
• At OUTDOOR in progress:
o At outdoor, the JTO can initiate cancellation due to reasons like Wrong
Sublocality, Wrong Address, Customer not Interested, Change in Urban/Rural,
customer premises too long and defaulter premises. Once the order is cancelled at
Clarity, the update goes to CRM and an alert is created for CO approval.
• At MDF in progress:
o At MDF, the JTO cannot cancel the service since there would be no reason of non
feasibility.
• At INDOOR in progress:
o At INDOOR, the indoor JTO can cancel the service order with Indoor not
feasible as a reason. Please refer to the below screen shots:
Page 4
8/3/2019 Cancellation Clarity User Manual
http://slidepdf.com/reader/full/cancellation-clarity-user-manual 4/11
o Rollback tasks would be generated for MDF and Outdoor activities.
• At FINAL TESTING in progress:
o Neither CRM nor Clarity can cancel the service order at this stage.
Note: For WLL cases, there would be no MDF task. CRM can initiate cancellation
only till Outdoor task in progress. Clarity can initiate cancellation till INDOOR in
progress.
2. New Provision order for Broadband over Landline and PCO services
Once the BB provision order is submitted to clarity , the task flow would be as below:
P2.2 P3
BB MDF
BB OUTDOOR BB FEASIBILITY
N/
W
Type
NIB ACTIVATIONP2.2 ACTIVATION
BB OUTDOOR
CLOSE SO
Page 5
8/3/2019 Cancellation Clarity User Manual
http://slidepdf.com/reader/full/cancellation-clarity-user-manual 5/11
• At BB MDF in progress:
o At MDF, the JTO can cancel the order due to reasons like technically not
feasible, prepaid not feasible and dslam ports not available.
• P2.2 - At BB Feasibility in progress:
o The Outdoor JTO can cancel the order with a valid reason. Once the order is
cancelled, an MDF work order would be generated to revert the MDF activity.
•P2.2 - At P2.2 Activation in progress:
o At P2.2 Activation, the SDE NIB can cancel the service order with “PLAN NOT
FEASIBLE” as a reason. He can enter the actual reasons in the FEEDBACK
attribute which is passed to CRM. Please refer to the below screen shots:
o Rollback task would be generated for BB MDF.
• P2.2 - BB Outdoor in progress:
o Neither CRM nor Clarity can cancel the service order at this stage.
Page 6
8/3/2019 Cancellation Clarity User Manual
http://slidepdf.com/reader/full/cancellation-clarity-user-manual 6/11
• P3 - BB Outdoor in progress:
o The Outdoor JTO can cancel the order with reasons like technically not feasible,
customer initiated, no stock of modems and cable pair faulty. Once the order is
cancelled, A MDF work order would be generated to revert the MDF activity.
• P3 - At NIB Activation in progress:
o Neither CRM nor Clarity can cancel the service order at this stage.
Note: For a service order with static ip request, a static ip allocation task would be
there after BB Feasibility for P2.2 and after MDF for P3 network. Order cannot be
cancelled at this point from Clarity.
3. Modify scenarios for Landline, PCO, ISDN BRI, ISDN PRI and WLL
services:
Following are the possible list of modify scenarios:
Accessory Provision.
Facility Provision
Combination of both Accessory & Facility
Change of Number
The taskflow for a typical modify order would be as below :
• At Outdoor task in progress:
o At Outdoor, the JTO can cancel the order due to reasons like technically not
feasible and customer initiated.
• At MDF task in progress:
o CRM can initiate customer initiated cancellation which would hit clarity and the
order would be cancelled. A rollback task would be generated for Outdoor.
OUTDOOR
MDF
INDOOR
FINAL TESTING
Accessory, Change of
Number scenarios
Change of Number
scenarios
Facility, Change of
Number
(IND)NUM_DEL(((scen
arios(IND)NUM
Change of Number
scenarios
Page 7
8/3/2019 Cancellation Clarity User Manual
http://slidepdf.com/reader/full/cancellation-clarity-user-manual 7/11
o At MDF, the JTO cannot cancel the service since there would be no reason of non
feasibility.
• At Indoor task in progress:
o At INDOOR, the indoor JTO can cancel the service order with technically not
feasible/Indoor not feasible as a reason. He can enter the actual reasons in the
FEEDBACK attribute which is passed to CRM. Rollback task would be
generated for Outdoor and MDF activities.
• Final Testing task in progress:
o Neither CRM nor Clarity can cancel the service order at this stage.
Additional Details:
o For scenarios like Add/Del DIDs and Add/Delete from Centrex or CH group,
no cancellation option would be available.
o Except for the fact that WLL service does not have MDF task in any case, all
other scenarios hold good for cancellation.
o In case of Change of number MDF,IND_NUM_DEL ,IND_NUM_ADD &
INDOOR tasks would be inserted on the order. Cancellation is allowed at
IND_NUM_DEL tasks . If IND_NUM_DEL task is completed then
cancellation is not allowed from the remaining tasks in clarity(i.e cancellation
not allowed at IND_NUM_ADD,INDOOR tasks)
Cancellation is allowed at all INDOOR tasks. In case of change of number if
IND_NUM_DEL task is completed then cancellation is not allowed at INDOOR task
4 Modify orders for BB Over Landline and PCO services:
• Following are the possible list of modify scenarios:
Change in Acquisition type
Accessory(Change of Modem)
Change of Plan
Add IP
Delete IP
Broadband Static IP change
Broadband Network Change
Change in EMAIL-ID
Combination of Modem & Acquistion type Change
Combination of Plan & IP requests
• The taskflow for a typical modify order would be as below :
Page 8
8/3/2019 Cancellation Clarity User Manual
http://slidepdf.com/reader/full/cancellation-clarity-user-manual 8/11
• At BB Outdoor task in progress:
o Same as BB Outdoor in broadband provision order.
• At IP Allocation in progress:
o CRM can initiate customer initiated cancellation which would hit clarity and theorder would be cancelled. A rollback task would be generated for Outdoor if
applicable.
o Clarity cannot initiate cancellation at this stage.
• P2.2 - Activation task in progress:
o Same as P2.2 Activation in BB provision order. There would be rollback task
created for BB Outdoor if applicable.
• P3 NIB Activation or Indoor task in progress:
o Neither CRM nor Clarity can cancel the service order at this stage.
Note: In case of network change, cancellation is allowed at Clarity at MDF task
which is the first task. Later cancellation is allowed from neither CRM nor Clarity.
5. Broadband Disconnection Over Landline and PCO services:
Accessory, Acquisition
type change
Add/Delete/Change in
Static IP
BB OUTDOOR
IP ALLOCATION
P2.2Or P3
NIB ACTIVATIONP2.2 ACTIVATION
INDOOR
CLOSE SO
Change of Plan/Email
ID
Facility change
scenarios
Page 9
8/3/2019 Cancellation Clarity User Manual
http://slidepdf.com/reader/full/cancellation-clarity-user-manual 9/11
• The taskflow for a BB disconnection order would be as below :
• At P2.2 Deactivation task, the order can be cancelled by the SDE NIB with customer
initiated reason.
• Once the P2.2 deactivation task is completed, there would not be any provision for
further cancellations.
• IN P3 service disconnection flow, we cannot cancel at any stage since the very first
task is a system task sent to NIB system for profile deletion.
6. Permanent Disconnection for Landline (having BB), PCO (having BB),
ISDN BRI, ISDN PRI and WLL services
Clarity:
• The taskflow for a permanent disconnection order for LL and PCO services having
BB would be as below :
P2.2Or P3
NIB DEACTNP2.2 DEACTN
BB DEL MDF
BB OUTDOOR
CLOSE SO
P2.2 P3
P2.2Or P3
NIB
DEACTNP2.2
DEACTN
MDF
OUTDOOR
CLOSE SO
P3P2.2
INDOOR INDOOR
Page 10
8/3/2019 Cancellation Clarity User Manual
http://slidepdf.com/reader/full/cancellation-clarity-user-manual 10/11
• The taskflow for a permanent disconnection order for LL, PCO, ISDN and WLL
services would be as below :
• In case of LL+BB disconnection, cancellation is possible from Clarity only for P2.2
network at P2.2 Deactivation task/Indoor task. Further to this there is no cancellation
possible at Clarity.
Note: 1. While cancelling at P2.2 deactivation, there would be a check if Indoor
task is also in progress. If it is completed then cancellation is not allowed at P2.2
deactivation task from clarity.
2. While cancelling at Indoor task, there would be a check if P2.2 Deactivation
task is also in progress. If it is completed then cancellation is not allowed at Indoor
task from clarity.
3. Indoor JTO/SDE NIB can cancel the disconnection order with Customer
initiated as a reason. He can enter the actual reasons in the FEEDBACK attribute
which is passed to CRM.Please refer to the below screen shot:
INDOOR
MDF
OUTDOOR
FINAL TESTING
Would not be present in
case of WLL
Page 11
8/3/2019 Cancellation Clarity User Manual
http://slidepdf.com/reader/full/cancellation-clarity-user-manual 11/11
Additional Details:
• In case of only LL disconnection, order can be cancelled at Indoor task with customer
initiated reason.
• No cancellations are allowed in case of Shift Disconnections.
• No cancellations are allowed from CRM in (normal & Shift) disconnect orders.
• No cancellations are allowed for Suspend & Restore Orders.
• No cancellations are allowed for fault orders in clarity.
• No cancellations are allowed for OFFLINE orders in clarity.