Initial Environmental Examination April 2018 CAM: Urban Water Supply Project - Siem Reap Subproject Prepared by the Siem Reap Water Supply Authority for the Asian Development Bank. This initial environmental examination report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. This is an updated version of the draft originally posted in September 2014 available on https://www.adb.org/projects/documents/urban-water-supply-project-siem- reap-iee. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
76
Embed
CAM: Urban Water Supply Project - Siem Reap Subproject
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Initial Environmental Examination
April 2018
CAM: Urban Water Supply Project -
Siem Reap Subproject
Prepared by the Siem Reap Water Supply Authority for the Asian Development Bank. This initial environmental examination report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. This is an updated version of the draft originally posted in September 2014 available on https://www.adb.org/projects/documents/urban-water-supply-project-siem-reap-iee. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Prepared by the Siem Reap Water Supply Authority for the Asian Development Bank
This is an updated version of the draft IEE originally posted in September 2014 available on https://www.adb.org/projects/documents/urban-water-supply-project-siem-reap-iee
ii
CURRENCY EQUIVALENTS
(as of March 24, 2018)
Currency unit – Riel
R1.00 = $0.00025
$1.00 = R4,000
ABBREVIATIONS
ADB – Asian Development Bank
AFD – Agence Francaise de Development
AP – Affected person
APSARA – Authority for the Protection and Management of Angkor
Appendix 5: Template of Semi-Annual Environmental Monitoring Report ............................ 63
Appendix 6: Approval Letter From Provincial Governor ........................................................ 65
Appendix 7: Standard Operating Procedure of Srwsa for Water Quality Tests ..................... 66
Appendix 8: Standard Operating Procedure of SRWSA for Pipe Laying/Installation............. 67
v
LIST OF TABLES
Table 1: Water supply distribution pipe specifications ............................................................ 3
Table 2: Size of trench for various pipe sizes ......................................................................... 3
Table 3: Drinking Water Quality Standards ............................................................................ 7
Table 4: List of Sensitive Receptors along Distribution Pipe Alignment ................................ 15
Table 5: Dates and venue of the public consultation meetings ............................................. 22
Table 6: Issues and concerns discussed during the public consultations ............................. 22
Table 7: Composition of the PMU ........................................................................................ 29
Table 8: Matrix of Environmental Management Plan ............................................................ 31
Table 9: Matrix of Environmental Monitoring Plan ................................................................ 39
LIST OF FIGURES
Figure 1: Soil filling after pipe laying ....................................................................................... 4
Figure 2: Location of pipe laying work .................................................................................... 5
Figure 3: Location of water supply distribution network improvement ................................... 10
Figure 4: Angkor Zones 1 and 2 .......................................................................................... 13
Figure 5: Map of Kouk Chak commune showing the service area and the Angkor Wat temples ........ 14
PHOTOGRAPH LOG
Photo 1: Example of household wells in Kouk Chak commune ............................................ 11
Photo 2: Typical land uses along the distribution pipe alignment.......................................... 12
Photo 3: Condition of affected roads and structures along the pipe alignment ..................... 15
Photo 4: Public consultation meetings.................................................................................. 24
vi
EXECUTIVE SUMMARY
Introduction
The Cambodia: Urban Water Supply Project is an approved loan from the Asian Development
Bank (ADB) which aims to improve water supply infrastructure and services in selected
provincial waterworks. The project consists of four main outputs, namely:
Output 1: Improvement of water supply systems in seven towns;
Output 2: New water supply system for Stung Treng;
Output 3: Expansion of water supply coverage in Siem Reap; and
Output 4: Project implementation support.
This updated Initial Environmental Examination (IEE) report is for the proposed Siem Reap
Water Supply subproject under Output 3. The updated IEE is prepared as per ADB’s Safeguard Policy Statement (2009) and the Royal Government of Cambodia (RGC) Law on
Environmental Protection and Natural Resource Management (December 1996).
Siem Reap Water Supply Sub-Project
Siem Reap has been selected as one of the subprojects where a new water distribution zone
will be provided under Output 3. This focuses mainly on the expansion of the water supply
coverage in Zone 1, to distribute water from the new water treatment plants (WTPs) of the
Siem Reap Water Supply Authority (SRWSA), a state-owned enterprise.
An IEE was prepared in 2014 as part of the Project Preparatory Technical Assistance (PPTA).
The original scope of the subproject in Siem Reap involves the improvement of the water
supply network for Zone 1 and a narrow section of APSARA area in Kouk Chak commune.
This includes a 6.5 km long 600mm HDPE transmission pipe from the existing water treatment
plant along National Road No. 6 (NR6) to connect to new and existing distribution pipe network
in Zone 1. HDPE distribution pipe network up to 250mm diameter will be installed to serve
8,000 households and businesses in Zone 1 and will extend to a strip of residential area in
APSARA zone that falls within the Kouk Chak commune. Other components of the project
include zone and household meters, valves and other appurtenance as needed to regulate the
system.
Updated Components of the Siem Reap Water Supply Sub-Project
The main transmission and the 15,000 m3/day WTP are already being implemented by
SRWSA through another funding source. The ADB loan package in Siem Reap will comprise
of procurement of pipes, valves, fittings and equipment. The SRWSA will make its own
arrangements for the project implementation under its Project Management Unit (PMU).
Although the works are excluded from ADB financing, the works are still considered an
associated facility under ADB Safeguard Policy Statement (2009) and the method statement
for works has been agreed with ADB is included in Appendix 8.
Based on the final detailed design, the target new distribution area will still be in Zone 1 and in
some areas in Zones 2 and 3 where new and replacement pipes will be installed. Overall, the
vii
pipe replacement will have a total length of 17.874 km while pipe expansion will cover 79.236
km. Based on the construction plan, the old pipes will not be removed but instead these old
pipes will be abandoned and new pipes will be laid out. These water supply distribution pipes
will be laid along roads.
Environmental Impacts and Mitigation Measures
Findings during the environmental due diligence confirm that the subproject is still Category B
for environment based on ADB Safeguard Policy Statement (2009). The pipe alignment will
remain on the side of existing roads. The identified impacts will primarily occur during
construction within a limited area along the pipe alignment. The adverse impacts are few,
temporary, generally site-specific, largely reversible, and can be readily addressed through
mitigation measures.
Flexible HDPE pipes will be used for the water distribution pipes which enables avoidance of
fences, electric poles and other structures along the pipe alignment. Works are restricted to a
section of pipe installation that can be completed in one day to avoid leaving excavated areas
open overnight. Should there be driveways, sidewalks and road sections that will be affected,
the SRWSA will ensure consultation with affected households and DPWT prior to works and
that there will be restoration of damaged areas to its original condition. Cost of restoration will
be shouldered by SRWSA. Proper coordination will also be undertaken prior to and during pipe
laying activities in identified sensitive receptors along the pipe alignment which consists of five
schools, seven pagodas and temple areas, and three hospitals/health centers. None of these
sensitive receptors are cultural heritage sites.
There will be no significant environmental impacts to the APSARA area in Kouk Chak
commune since the area is already characterized as a built-up area with houses, shops, and
access roads. The water supply pipe alignment is far from the Angkor Wat site and other
significant temples of the complex. During the meeting with the APSARA National Authority,
it was confirmed that there is no problem with the proposed water supply distribution project
since water is essential to the communities. The APSARA only requires a formal notice from
the SRWSA about the implementation of the project. Formal approval from the Provincial
Government was obtained and included in Appendix 6.
The environmental management plan (EMP) of the subproject is presented in Table 8.
Institutional Arrangement on Environment Safeguards
A PMU has been formally organized by the SRWSA by virtue of an office order issued in 2017.
The PMU is composed of 16 staff who will oversee the implementation of the project including
ensuring compliance with the ADB and MEF requirements.
The SRWSA has designated Mr. Meas. Sopheaktra as the focal person on environment,
health, safety, and social safeguards. Mr. Meas Sopheaktra will coordinate with the contractor
and the Project Implementation Assistance (PIA) consultants to ensure that the EMP is
implemented properly and that safeguards requirements of the subproject are met.
1
I. INTRODUCTION
The Cambodia: Urban Water Supply Project is an approved loan to the Royal Government of
Cambodia amounting to US$34.00 Million through the Ministry of Industry and Handicraft
(MIH). The Project will provide additional new and rehabilitated water supply infrastructure and
extension of system coverage to expand access to safe water in nine towns in Cambodia. The
Project aims to improve the performance of water utilities to give residents greater access to
safe piped water supply through the rehabilitation and improvement of existing water treatment
plants (WTPs), construction of new WTPs, and construction or replacement of distribution
pipelines to increase system pressure and improve service delivery. The Project targets to
reduce non-revenue water (NRW) levels to below 15% by using improved material and
construction practices in its works to complement ongoing non-revenue water (NRW) reduction
initiatives by the service providers and other development partners.
The Project consists of four main outputs, namely:
Output 1: Improvement of water supply systems in seven towns;
Output 2: New water supply system for Stung Treng;
Output 3: Expansion of water supply coverage in Siem Reap; and
Output 4: Project implementation support.
This updated Initial Environmental Examination (IEE) report is for Output 3 of the Siem Reap
Water Supply subproject. An IEE for the subproject was prepared in 2014 as part of the Project
Preparatory Technical Assistance (PPTA). This updated IEE report presents the findings of
the environmental due diligence based on the detailed plan of the distribution network
alignment. The due diligence aims to confirm whether there will be significant impacts in the
areas that will be bounded by the subproject, particularly at the APSARA Zone.
II. DESCRIPTION OF THE PROJECT
A. Existing Water Supply System
The Siem Reap water supply system utilizes groundwater as source of supply and has
undergone extensive improvements under previous projects. The current water supply system
was largely constructed by JICA in 2006, with a treatment capacity of 8,000 m3/day. Treatment
consists of chlorination, aeration and filtration. The current demand causes the system to
exceed its design capacity. More importantly, continued groundwater pumping is lowering the
groundwater table while the city faces severe shortage of water to serve the rapidly growing
tourism and allied industries.
Construction of new water treatment plant (WTP) with capacity of 15,000 m3/day was
completed in May 2019. This new treatment plant was built with support from the Agence
Francaise de Development (AFD). The raw water source is the surface water from the canal
of West Baray reservoir. Treatment used is the conventional sedimentation/filtration system.
The new WTP is located next to the existing treatment plant of SRWSA which is located in
Sandan Village, Sangkat Tel Vil. It occupies a land area of 6000 square meters. The property
is owned by SRWSA.
2
Treated water from the new WTP will be channeled to the main transmission line along NR6.
A separate IEIA study was conducted on the new water treatment plant and transmission line
by SRWSA during detailed design to identify the adverse impacts during project
implementation. Water quality tests on the raw water source were conducted to determine the
feasibility of the source and level of treatment necessary to remove contaminants. The IEIA
developed an environmental management plan to address adverse impacts. Approval from
MoE on the IEE report is not required as the target population of this project is less than 10,000.
Cost of rehabilitation/restoration of affected facilities and sections of NR6 during pipe laying
has been included in the contract price.
In addition, JICA has conducted a feasibility study for another water treatment plant using
surface water from Tonle Sap Lake. Raw water would be extracted during high water periods
(generally July – December) to offset groundwater extractions and to augment supplies. The
WTP from JICA is expected to start construction in 2019. Treated water from the WTPs will
connect to the water supply network to provide potable piped water to the service areas of
SRWSA.
B. Original Project Scope
The original scope of the subproject in Siem Reap involves the improvement of the water
supply network for Zone 1 and a narrow section of APSARA zone. This includes a 6.5 km long
600mm HDPE transmission pipe from the existing water treatment plant that will run along
National Road No. 6 (NR6) to connect to new and existing distribution piping in Zone 1. HDPE
distribution piping up to 250mm diameter will be installed to serve 8,000 households and
businesses in Zone 1 and will extend to a strip of residential area in APSARA zone that falls
within the Kouk Chak commune. Other components of the project include zone and household
meters, valves and other appurtenance as needed to regulate the system.
C. Revised Project Scope
The main transmission and the 15,000 m3/day WTP are already being implemented by
SRWSA through another funding source. The ADB loan package in Siem Reap will comprise
of procurement of pipes, valves, fittings and equipment. The SRWSA will make its own
arrangements for the project implementation under its Project Management Unit (PMU).
Although the works are excluded from ADB financing, the works are still considered an
associated facility under ADB Safeguard Policy Statement (2009) and the method statement
for works has been agreed with ADB is included in Appendix 8.
The target new distribution area will be in the community areas in Zones 1, 2 and 3 of Siem
Reap city. Overall, the pipe replacement will have a total length of 17.874 km while pipe
expansion will cover 79.236 km. These distribution pipes will be laid along existing road right-
of-way (ROW). The sizes of the distribution network ranged from 63 mm – 225 mm. Details of
the distribution pipe network are presented in Table 1.
3
Table 1: Water supply distribution pipe specifications
Size of Pipe Type of Pipe Length, meters
A. Pipe Replacement
225 mm HDPE pipe 0D225 1,809
160 mm HDPE pipe OD160 9,126
110 mm HDPE pipe OD110 6,939
Sub-total (pipe replacement) 17,874 meters
B. Pipe Expansion
225 mm HDPE pipe OD225 10,125
160 mm HDPE pipe OD160 11,187
110 mm HDPE pipe OD110 52,245
63 mm HDPE pipe OD63 5,679
Sub-total (pipe expansion) 79,236 meters
TOTAL LENGTH 97,110 meters
D. Construction Activities and Schedule
1. Activities
All the distribution lines will be installed along existing roads within the designated area
reserved for water supply lines. Pipes will be laid along the sidewalk and close to the property
of the households to be connected to the water supply distribution line.
The construction activities will involve the excavation of the trench, pipe laying, soil filling and
covering, and restoration and finishing of ground. The width of the trench excavation ranges
from 0.4-0.6m while the depth ranges from 0.6-1.0m. The size of the trench will depend on the
size of the pipe to be laid. Majority of the excavation works will be done manually but there are
a few sections where an excavator will be needed to break the concrete pavement of sidewalks
and driveways. The sizes of the trench according to pipe size are outlined in Table 2.
Table 2: Size of trench for various pipe sizes
No. Pipe size (mm)
Trench size (mm)
Excavation (by hand) Excavation (by excavator)
Width (W) Depth (H) Width (W) Depth (H)
1 63 400 600 500 600
2 110 500 700 500 800
3 160 500 800 600 900
4 225 500 900 600 1000
Once the trench is excavated, about 0.1m layer of sand bedding will be placed on the trench
before pipe laying. After the pipes have been laid out, the trench will be covered with sand and
soil. The excavated soil from the trench will be used to backfill the trench. Upon completion of
a pipe section, leak tests will be undertaken within a few days before the final cover of either
laterite or concrete is placed. The final cover will depend on the original type of pavement of
the road/driveway, i.e. road shoulder, laterite, double bituminous surface treated (DBST) road,
asphalt or concrete. Figure 1 presents the soil filling on various types of road surface.
4
Figure 1: Soil filling after pipe laying
2. Construction Schedule
For every 500 meters, trench excavation up to pipe installation would take about 2 – 3 days
for earth roads and about 4 – 7 days for concrete or DBST road surface.
3. Manpower Requirements
Construction will be directly implemented by the SRWSA under the supervision of the PMU.
There will be four teams for construction, with each team composed of 7 – 8 people. Labor
contractors will be hired by SRWSA to assist the SRWSA construction team.
The SRWSA has a Standard Operating Procedure (SOP) for pipe laying which will be observed
by the construction teams as well as its labor contractors. The SOP includes methods and
measures to manage trench excavation, pipe laying activities, and until testing and operation
of the distribution network.
5
Figure 2: Location of pipe laying work
6
III. POLICY, LEGAL AND INSTITUTIONAL FRAMEWORK
The hierarchy of legislation in Cambodia includes the Constitution, laws issued by the National
Assembly, decrees/sub-decrees/implementing regulations issued by the Council of Ministers,
implementing legislation (Prakas) issued by ministries and decree laws, which are legal
instruments issued prior to the 1992 Constitution. Article 59 of the Cambodian Constitution
provides for the protection of the environment.
A. Environmental Impact Assessment
In November 1996, the Cambodian National Assembly passed the Law on Environmental
Protection and Natural Resource Management (the framework law). The objectives of this law
are to protect environmental quality through the prevention, reduction and control of pollution,
to establish an Environmental Impact Assessment (EIA) system, to ensure sustainable use of
natural resources, to encourage public participation and to suppress acts which are harmful to
the environment. The law calls for EIAs to be conducted for every private or public project, to
be reviewed by the Ministry of Environment before submission to the Government for a final
decision. All proposed as well as existing activities are to be covered under this requirement.
The EIA policy has been extended through the Sub-decree on Environmental Impact
Assessment Process passed by the Council of Ministers on 11 Aug 1999. Under the sub-
decree an Initial Environmental Impact Assessment (IEIA) report is required from a project
owner either private, joint-venture or public sector. A Project Owner must apply to the MOE
for reviewing the IEIA report or to the Provincial/Urban Environmental Office (PEO) if the
investment value is less than $2,000,000 and environmental impacts are not considered
severe. In the case of a project that causes serious impact, the Project Owner must prepare a
full EIA report and apply to the MOE for review. In practice, all IEIAs and related documents
are reviewed and approved by the Department of EIA in the MOE. Declaration No. 49 Guideline
for EIA Reports was issued in June 2000, and Declaration No. 745 Determination of Service
Charge for Environmental Impact Assessment Report Review and Follow-up and Monitoring
of Project Implementation was issued in October, 2000.
Annex of the sub-decree No. 72 ANRK.BK presents the list of projects that require an IEIA. In
accordance with the Sub-Decree No. 72 ANRK.BK (August 1999), water supply projects with
≥10,000 users, require an EIA/IEIA to be submitted to the Ministry of Environment (MOE) for approval of the project. The Siem Reap subproject is not required to secure an environmental
approval/clearance while the target number of household connections is only 5,000
households located in Zone 1 in Sangkat Svay Dangkom, Kouk Chak, Slor Kram, and
Salakamreuk. Majority of the connections will be in Sangkat Svay Dangkom and Kouk Chak.
B. Heritage Legislation
The APSARA, the Authority for the Protection and Management of Angkor and the Region of
Siem Reap (hereafter referred to as the APSARA Authority), was established in 1995. It is in
charge of research, protection and conservation of cultural heritage of the Angkor Protected
Landscape (APL), as well as urban and tourist development. In December of 1995 the World
Heritage Committee confirmed Angkor's permanent inscription on the List of World Heritage
Sites in Danger.
7
There are several royal decrees related to the establishment and authority of the APSARA
Authority and the protection of the cultural heritage of Angkor:
Royal Decree NS/RKT/0295/12 establishing a National Authority for the Protection and
Management of Angkor and the Region of Siem Reap, named APSARA (1995,
amended in 1998 by Decree NS/RKT/0199/18)1.
Royal Decree 001/NS establishing Protected Cultural Zones in the Siem Reap/Angkor
Region and Guidelines for their Management2. The decree establishes management
zones within Siem Reap.
In the process of pipe laying and installation, a chance find procedure will be in force that
complies with Articles 37-39 of the Law on the Protection of Cultural Heritage (1996) and such
finds should not be disturbed until assessed by an expert from the APSARA Authority or other
expert as approved by the APSARA Authority. The SRWSA has already acquired the approval
letter from the Provincial Governor for the pipe installation, copy furnished to relevant
authorities including APSARA (Appendix 6).
C. Drinking Water Quality Standards
The national water quality standards for drinking water are set out in Prakas No. 294 dated
April 27, 2004 which was issued by the Department of Potable Water Supply, Ministry of
Industry, Mines, and Energy (MIME). Table 3 presents the drinking water quality parameters
and the allowable limits.
Table 3: Drinking Water Quality Standards
No Parameter Unit Standard Value
Bacteriological Quality for Drinking Water
1 Fecal Coliforms Count/100ml 0 per 100 ml
2 Total Coliforms Count/100ml 0 per 100 ml
Inorganic Constituents that affect health in drinking water
1 Arsenic mg/L, (ppm) 0.05
2 Barium mg/L, (ppm) 0.7
3 Cadmium mg/L, (ppm) 0.003
4 Chromium mg/L, (ppm) 0.05
5 Cyanide mg/L, (ppm) 0.07
6 Fluoride mg/L, (ppm) 1.5
7 Lead mg/L, (ppm) 0.01
8 Mercury mg/L, (ppm) 0.001
9 Nickel mg/L, (ppm) 0.02
10 Nitrate as NO3 mg/L, (ppm) 50
11 Nitrite as NO2 mg/L, (ppm) 3
12 Selenium mg/L, (ppm) 0.01
1 See http://www.autoriteapsara.org/en/apsara/about_apsara/legal_texts/decree1.html and
http://www.autoriteapsara.org/en/apsara/about_apsara/legal_texts/decree2_text.html for English translations. 2 See http://www.autoriteapsara.org/en/apsara/about_apsara/legal_texts/decree3_text.html for an English translation.
8
No Parameter Unit Standard Value
Physical, chemical and aesthetic quality of drinking water
1 Taste - Acceptable
2 Odor - Acceptable
3 Color - 5 TCU
4 Turbidity mg/L 5 NTU
5 Residual chlorine mg/L 0.2-0.5
6 Aluminum mg/L 0.2
7 Ammonia mg/L 1.5
8 Chloride mg/L 250
9 Copper mg/L 1
10 Hardness mg/L 300
11 Hydrogen Sulfide mg/L 0.05
12 Iron mg/L 0.3
13 Manganese mg/L 0.1
14 pH - 6.5-8.5
15 Sodium mg/L 200
16 Sulfate mg/L 250
17 Total dissolved solids mg/L 800
18 Zinc mg/L 3
D. ADB Safeguard Policies on Environment
The environment safeguards requirement of ADB is outlined in the Safeguard Policy Statement
(SPS 2009) and detailed in the Operational Manual Section F1/BP3. The requirements follow
ADB’s Strategy 20204, which emphasizes the pursuit of environmentally sustainable and
inclusive economic growth for developing member countries (DMCs). ADB outlines a set of
requirements for borrowers/clients in addressing environmental and social impacts of projects.
Based on the SPS 2009, all ADB-financed projects must undergo an environmental
assessment to ensure the environmental soundness and sustainability of projects. It also aims
to support the integration of environmental considerations in the project decision-making
process by developing safeguards to avoid adverse impacts of projects on the environment
and affected people, minimize, mitigate, and/or compensate for adverse project impacts when
avoidance is not possible, and help borrowers/clients to strengthen their safeguard systems
and develop the capacity to manage environmental and social risks.
When a Project has been identified for ADB financing and/or administration, environmental
screening and categorization is undertaken to determine the (i) significance of potential
impacts or risks of the project to the environment, (ii) level of assessment and institutional
resources required to address the safeguards issues, and (iii) information disclosure and
consultation requirements of the project. This is done through the use of environment
screening checklists that have been developed by ADB, whereby the project is initially
categorized for potential environmental impacts and risks. During the screening process, a
3 Operations Manual Bank Policies (BP) issued on 1 October 2013, based on ADB Safeguard Policy Statement, 2009. 4 ADB. 2008. Strategy 2020: The Long-Term Framework of the Asian Development Bank 2008-2020. Manila
9
category is assigned to the project depending on the significance of the potential environmental
impacts and risks.
Category A are those which are large and most complex and requires a full-blown
environmental impact assessment (EIA); Category B has environmental impacts which are site
specific, less adverse than those of Category A and which requires an initial environmental
examination (IEE); and Category C are the smallest and least complex and does not require
an EIA or IEE but environmental implications are still reviewed.
The subproject has been evaluated as Category B for environment. The adverse
environmental impacts of the project are considered site-specific and reversible.
1. Environmental Impact Assessment and Public Consultation
ADB also requires public consultation in the environmental assessment process and that the
borrower/client must consult with stakeholders affected by the proposed project. The
consultation should be carried out as early as possible in the project cycle so that views of the
affected groups are taken into account in the design of the project and in the development of
the environment mitigation measures.
2. Disclosure of IEE Document
Upon approval of the EIA or IEE by the borrower/client, the document is disclosed at the ADB
website in accordance with the ADB Public Communications Policy.
3. Environment Monitoring
The monitoring of implementation of the EMP by the borrower/client is reported to ADB. A
simplified environmental monitoring checklist has been developed in Appendix 4 for use of the
PMU during the regular inspection of construction areas. These completed inspection
checklists will be compiled and reviewed by the PIA in the preparation of the semi-annual
environmental monitoring reports to be submitted to ADB. The reports will include a summary
of the results of site inspections and will focus on key issues of concern that need to be
resolved. The template of the semi-annual environmental monitoring report is presented in
Appendix 5.
IV. DESCRIPTION OF THE ENVIRONMENT
A. Physical Resources
Geography. Siem Reap Province is located north of the Tonle Sap Lake. The province is
composed of 12 districts or srok. The most famous of these districts is the Siem Reap district
which is sub-divided into 10 communes, namely, Sla Kram, Svay Dongkum, Kouk Chak, Sala
The proposed distribution network will provide water supply to the communes in Kouk Chak,
Sla Kram, Sala Kamreuk, and Svay Dongkum. There is a small area in Kouk Chok which is
5 Source: siemreap.net. Date accessed: 03April2018
10
located in APSARA Zone but the pipe alignment is located about 2.2 km from the Angkor Wat
site. The proposed distribution network improvement project will be concentrated on the built-
up and populated areas within Siem Reap town. Figure 3 presents the location map showing
the communes, location of pipe network in Siem Reap town and the APSARA Zone.
Figure 3: Location of water supply distribution network improvement
Geology. The local geology consists of unconsolidated sediments of Quaternary age under
the geomorphology of swamps and deep soils of alternating sand and clay that make up the
Tonle Sap depression. The geology is characterized as alluvial deposits with thickness of 10–
20m; Pleistocene deposits with thickness of 10 – 30m; Pliocene formation with thickness of 20
– 50m; and bedrocks in upper Jurassic to tertiary composed of sandstone, siltstone and shale.
Topography. The areas of the proposed distribution network improvement are characterized
as flat land. There are no natural hazards such as steep slopes and unstable soils along the
distribution line routes. The Siem Reap town is located on the lake terrace with elevations
ranging from 10 to 15 m.
The isolated peaks are located at Phnom Bok (El 212 m), Phnom Baken (El. 90m) at Angkor
area, Phnom Croom (El 140 m) from north to south in the area. The Kulen Mountain range (El.
420m) in the northern area of Angkor Heritage area runs in the east west direction.6
Hydrology. The distribution networks will not traverse any river. The Siem River is the nearest
waterbody to the water distribution network which can be found at the communes in Sla Kram
6 Annex 3.3.1 – Geology. The Study on Water Supply System for Siem Reap Region in Cambodia. Final Report
11
and Sala Kamraeuk. It drains the Siem Reap town. Flooding has not been reported by
stakeholders in the project areas. On raw water source for the new WTP, West Baray will be
used. Though ancient, it is filled with water year round. The water comes from two main
sources: the Siem Reap and Puok Rivers. West Baray is a rectangular reservoir approximately
7.8 by 2.1 kilometers with a current maximum capacity of 12 to 14 billion gallons of water (53
million m3).
Hydrogeology. In the study conducted by JICA in 2006 to 2008, land displacement has been
observed in both deep aquifer and shallow aquifer with patterns of land displacement
fluctuations being almost the same for both aquifers. The land displacement fluctuation
coincided with the groundwater level fluctuation which changes according to the changes in
season. Calculations from the JICA study indicated that maximum displacement range from
18.96 – 17.06 = 1.9 mm for the deep aquifer and 16.31 – 13.86 = 2.45 mm for shallow aquifer.7
Simultaneous groundwater observations were conducted twice in the rainy season of
September 2009 and dry seasons of April 2010. Higher water level drawdown in the dry season
was observed with a lot of private wells using groundwater for users such as hotels and guest
houses.
Photo 1: Example of household wells in Kouk Chak commune
B. Ecological Resources
The areas for the proposed improvement of the distribution network are not located in
ecologically sensitive areas. The Tonle Sap Biosphere Reserve (TSBR) is located about 300
m from the town. Other water source for the existing WTP is from the existing 16 boreholes
along National Road No.6. There are also no trees that will be affected by the project. Pipe
laying activities can avoid cutting of trees since HDPE pipes are flexible and can be easily
adjusted to avoid trees and other structures.
C. Socio-Economic Development
Population. Siem Reap province covers a total land area of 10.299 km2. It has a population
of 1,042,286 people and a population density of 101.2 per km2. The total household population
of the province is 206,385 households. Population growth is at 3%. The Siem Reap town has
a population of 256,018 and household population of 50,824. Average size of household is 5.
7 Hydrological conditions in Siem Reap. http:// http://open_jicareport.jica.go.jp/pdf/12034724_02.pdf
12
Economy. The main industries contributing to the provincial economy are agriculture and
tourism. The province has favorable landscape, appropriate rainfall and irrigation systems
capable of supporting rice and crop production. Tourism is the second priority economic sector
in the province because of abundant tourism resources such as cultural and historical temples
and natural parks which includes the Angkor Temple complex. About 5,000,000 tourist arrivals
annually have resulted in the burgeoning tourism industry with hotels, restaurants, service
providers of all types and secondary commerce and industries that support tourism.
Land Use. Land uses in the project area consists of residential, commercial, and institutional
establishments with agricultural fields in the outlying areas from the Siem Reap town. Land
use is undergoing rapid change in the vicinity of Siem Reap town, especially along highways
and in the direction of the Angkor Temple complex. Establishments that can be found along
the pipe alignment consists of residential areas, shops, hotels, market, schools, and some
temples.
Residential houses in APSARA Zone
in Kouk Chak commune
Houses in APSARA Zone in Kouk Chak commune
Shops along the road
Market area
Residential house and office along the alignment.
A hotel and restaurant along the alignment.
Photo 2: Typical land uses along the distribution pipe alignment
13
Social and Cultural Resources. The project will not traverse any of the important temples in
the Angkor Wat complex. A section in Kouk Chak commune forms part of the communities to
be served by the distribution network. This area is characterized with settlements, shops, and
roads and is within the delineated APSARA Zone 2. As defined by the 1994 Royal Decree
establishing the Protected Cultural Zones at Angkor, Zone 2 covers “areas rich in archaeological remains which need to be protected from damaging land use practices and
inappropriate development.” APSARA Zone 1 covers the core areas of Angkor, and other zones are defined successively up to Zone 5, which covers the whole of the province including
the municipality of Siem Reap. The following are the designated zones:
o Zone 1 - for the Monument sites;
o Zone 2 - Protected archaeological reserves;
o Zone 3 - Protected cultural landscapes;
o Zone 4 - Sites of archaeological, anthropological or historical interest; and
o Zone 5 - Socio-economic and cultural development zone of the Siem Reap/ Angkor
Region.
Figure 4: Angkor Zones 1 and 2 Source: ICC-ANGKOR, www.http//apsaraauthority.gov.kh
The Angkor Wat complex is the central feature in Siem Reap. The historical/cultural areas
consist of the Angkor Wat Temple, Bayon Temple, and Ta Prom Temple. The Angkor Wat
V. POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
This chapter presents the potential environmental impacts in relation to the construction and
operation of the water supply distribution network. The potential impacts are analyzed and
necessary mitigation measures are proposed to reduce the overall magnitude of the impact.
The assessment of impacts was based on the inspection of the detailed pipe alignment and
from consultations and interviews with stakeholders and relevant Government agencies.
A. Project Benefits
The proposed Siem Reap water supply improvement project involves the replacement and
expansion of the water supply distribution network within the Siem Reap town. By extending
water supply service coverage, the project will reduce dependence of communities to
groundwater which are sourced through individual household or communal bore holes and
tube wells. Well water is used for washing, cooking, and drinking. If communities continue the
uncontrolled abstraction from groundwater sources, negative effect on the lowering of the
water table level would occur in the long term and which would cause land subsidence and
damage to structures, particularly of the important archaeological sites in Siem Reap.
During the public consultations, the villagers disclosed that groundwater quality is
deteriorating. The villagers said that water from their wells are brownish and smells like iron.
When washing laundry, the clothes have yellow stain. Skin diseases and diarrhea are common
most especially in children. For drinking, the communities either boil the well water or buy
bottled water. Through the project, the communities hope to get potable and clean water. The
communities also anticipate convenience in having piped water directly from faucets rather
than the current practice of fetching water from wells.
Expected positive benefits of the project are: (i) improvement of health and sanitation, (ii) less
expenses in buying bottled water and in operating water pumps to abstract from wells; (iii)
convenient access to clean piped water, and (iv) less dependence of communities on
groundwater abstraction.
B. Affected Areas
The pipe replacement and expansion will be along existing roads. The affected area is
relatively small, ranging from 0.4 – 0.6 m in width and 0.6 – 1.0 m in depth. Majority of the
activities will be done manually except in sections requiring an excavator to break the
pavement. Construction works also occur within a short period of time of about one week for
every 500 meters of pipeline segment. After each segment, the team moves to the next
segment to limit the construction period and minimize disturbances and impacts to the
surrounding areas.
For the pipe replacement, the old pipelines that are located beneath existing roads will be
abandoned and new pipelines will be installed on the road shoulder. However, there are
structures such as sidewalk, driveways, fences, street lamps, communication cables, trees,
and landscaped areas along the pipe alignment. The fences, street lamps, communication
cables, trees and landscaped areas can be readily avoided because flexible water pipes will
be utilized.
17
For the sidewalks and driveways, owners and government authorities of these structures will
be notified prior to start of construction activities. The affected road easements consist of
laterite roads and some asphalt-paved roads. The laterite roads can be found in road sections
in Kouk Chok commune.
C. Impacts during Construction
The pipe laying works may cause the following impacts:
Disruption and damage to existing community structures and facilities.
Dust and air emissions from excavation and movement of vehicles.
Noise and vibration.
Sediment runoff.
Generation of excavated soil and other construction debris.
Hazards to workers.
Risks to community health and safety.
Traffic congestion.
Mitigation measures are outlined in Table 8 to address the potential impacts during pipe laying.
Damage to community facilities. The installation of water supply distribution lines will be
along public road easements within semi-urbanized areas. This is the main item of work, along
with valves, fittings, installation of service connections and meters for homes and businesses,
and other appurtenances needed to complete the pipeline installation.
Prior to commencement of construction activities, the SRWSA shall consult in advance of
works with affected persons where houses, driveways and other structures will be affected. All
damage will be restored to pre-project conditions. The cost of restoration will be shouldered by
SRWSA. In addition, SRWSA shall coordinate with the Provincial Government and relevant
Government authorities such as the Department of Public Works and Transport (DPWT), and
APSARA Authority at least one month prior to pipe laying works.
The mitigation measures to address the impacts on community facilities include the following:
Coordinate with the Provincial Department of Public Works and Transport (DPWT),
local authorities, and owners of affected properties prior to commencement of pipe
laying works.
The Contractor is required to replace structures that may be damaged such as roads,
canals, driveways, and paths. Any damage to community structures will be restored at
pre-project condition at the cost of SRWSA.
Occupational health and safety. The SRWSA will deploy four construction teams with each
team composed of 7 – 8 workers. There will be no construction camp along the pipe distribution
network. However, there should be onsite portable sanitation facilities for workers to avoid
indiscriminate waste disposal at the construction sites. Solid waste should be collected at
waste bins and disposed properly offsite.
The SRWSA will provide the basic safety and health measures for workers such as personal
protective gear suitable to the type of work being performed. Emergency care will be available
on call.
18
Runoff of sediments. The excavation works are expected to generate sediments and cause
soil runoff during rain events. Given that excavations will not be deep, pipe diameters relatively
small, and that excavated materials will be used as backfill, the quantity of spoil will be minimal.
However, during rain events, runoff may still cause impacts to residential areas and drainage
in the immediate vicinity. Appropriate mitigation measures to prevent soil runoff will be
implemented that includes:
Excavation activities will be scheduled during the dry season as much as possible.
Stockpiles of excavated soil from the trench excavation will be located in areas that will
avoid blocking of drainage lines.
Stockpile of excavated soil will be covered and stabilized to prevent runoff.
Sediment trenches or barriers around stockpiles of materials will be provided to block
runoff water and catch sediments and other debris entering the drain.
Dust and air emission. Wind-blown dust may be generated due to presence of loose soil and
movement of vehicles at the work areas. The Contractor will establish the detailed measures
to address impacts to control dust and air emission from earthworks and movement of vehicles.
Measures to be applied includes the following:
Cover and keep excavated soil and stockpiles moist.
Conduct water sprinkling in areas prone to airborne dust.
Cover materials for excavated soil and stockpiles at the end of the day’s work. Regularly clean and sweep dust and accumulated soil at roadsides at the end of the
day’s work. Maintain vehicles and equipment to ensure that emissions comply with the
Government’s standards. Prohibit open burning of waste materials.
Instruct delivery trucks to cover materials with tarpaulin or other suitable materials
during hauling of materials.
Impose speed limits on construction vehicles.
Regularly clean and sweep dust in the work area.
Inform and educate workers on the implementation of air emission and dust control
measures.
Noise. There will be minimal noise to be generated during construction works except in areas
where there is a need to break the concrete or asphalt pavement. Noise levels ranging from
82 to 88 dBA may be experienced in areas at the distance of 15 to 30 meters from the source.
To avoid nuisance to adjacent establishments, pavement breaking activities will not be
undertaken at nighttime hours of 22:00 to 06:00. Coordination with the affected establishments
will be undertaken on the schedule of construction works.
Community health and safety. The laying of water pipes along existing road easements will
result to impacts to community health and safety, including traffic and restriction of community
access. Distribution pipes will be installed under a variety of local conditions including in front
of market areas, along asphalt-concrete roads, and along unpaved roads. Pipes will be
installed in the easements of paved roads to avoid cuts on road pavements.
19
Special precautions need to be taken in built up areas, for instance near schools, temples, and
hospitals/health centers where there are sensitive receptors. In areas that are busy during the
day, construction work may be conducted during nighttime to cause less disruption to traffic.
The SRWSA has a Standard Operating Procedure (SOP) which was issued through an office
order for pipe laying. These general guidelines of SRWSA on pipe installation will be applied.
The SRWSA will conduct pipe laying in a manner that will cause minimal impact on health,
safety and convenience of businesses, residents, and users of the roads. These measures
include the following:
a) Minimize the period of time that an excavation segment is kept open by not allowing
trenching and pipe-laying by more than a week for each 500-meter segment. Trenches
should be backfilled and ground leveled after installation of pipes.
b) Install signs at the beginning and end of section of works.
c) Provide the safety barriers to avoid conflict with live traffic.
d) Provide signs for works to indicate the GRM.
e) Place only bedding and pipe materials at the location that will be used within the next
few days’ work, well out of the line of traffic.
f) Clean up and remove from the site any excess spoil, wood used for shoring and
construction materials, upon completion of the segment.
g) Compact soil in trench and clean surrounding pavement areas to reduce blowing dust.
h) Provide temporary bridging across the trench at entries to residences and businesses.
Likewise, provide safety tape barriers to reduce the possibility of accidents.
i) Once work is complete on a segment, pavement surfaces and masonry works (curbs,
abutments, drains, driveways, and sidewalk will be repaired and returned to original
condition.
j) Provide advance notification of proposed pipe laying activities, locations and schedules
to local residents, hospitals, schools, businesses, and other institutions and
establishments. Regularly coordinate with affected parties during project construction.
k) Install safety barriers in open excavations to avoid unauthorized or accidental access
by the public.
Traffic. Pipe laying activities may potentially affect traffic movements and could result to
closure of a road section. There will be no need for traffic rerouting since the pipe installation
will require a small space at the road easement. A road lane may be blocked but not the entire
road. Mitigation measures to manage traffic will include the following:
Coordinate the proposed construction activities, schedules, and traffic management
plan with the local authorities and police.
Post informational boards in case of temporary lane closures.
Employ trained flaggers to direct traffic movements in areas with lane closures.
Use traffic control and warning devices such as lights, signs, traffic cones, flashing
board, bollards, and barricades to alert vehicles and pedestrians about lane closures,
equipment use, excavations, and other potential hazards.
Impact on cultural heritage sites. A portion of the pipe expansion will be for communities in
Kouk Chak in the APSARA zone. These areas have been subject to human disturbance as
evidenced by the presence of houses, shops, roads and other community structures.
20
According to the APSARA Authority regulations, the villagers who have homes and live in the
Angkor area can continue to live there and that villagers can demolish old houses or build new
ones with a request to get permits from APSARA Authority. The villagers have the right to
manage their own land such as giving their land possession to their relatives or selling it to
neighbors but it is forbidden to buy and sell for the purpose of making profitable business for
companies to build hotels, restaurants and other businesses.
Considering that the proposed extension of the service area is already characterized with
settlements, there is low likelihood of finding archaeological artifacts because these areas have
been subject to previous road development works and that the trench excavation are relatively
shallow and small.
The SRWSA will coordinate with the APSARA Authority prior to commencement of works in
accordance with the Law on the Protection of Cultural Heritage (1996). A chance find
procedure will be implemented in the event that cultural property such as ancient objects,
remains of inhabited sites, ancient burial sites, engravings or any property likely of interest is
discovered.
The following procedure will be observed by SRWSA to comply with the intents of the law in
case of chance find:
If physical cultural resources are encountered during the construction phase, all works
at the chance find site should be immediately halted.
The chance find should be assessed by a competent expert from the APSARA National
Authority.
Work should not begin until the procedures to avoid, minimize or mitigate impacts to
the physical cultural resource have been implemented.
Removal of the chance find should be conducted in accordance with national heritage
protection decrees and regulations.
All workers and staff should be made aware of the chance find procedure.
UXO contamination. On UXO/land mine, the DPWT said that UXO/land mine clearance was
already completed within Siem Reap City when the roads were constructed. Chance discovery
of UXO during trench excavation is not foreseen since the areas where the pipes will be laid
have been subject to disturbance during the construction of roads, houses, and other
structures.
Residual chlorine during pipeline disinfection. When the pipes are already laid out, the pipe
work will be hosed down with chlorine solution on the interior to prevent any contaminated
material into the water pipe and to protect and disinfection the water line’s sanitary condition. This is typically done after the completion of the leak and pressure tests. During this process,
extra caution will be necessary to avoid disposing water with excessive chlorine residuals. The
pipe disinfection process should observe the recommended dosage of chlorine and allowable
residual chlorine of 0.1 – 0.2 mg/l as prescribed by international standards.
D. Operational Phase
Poor water quality. Impacts during the operational phase concern environmental or public
health. Broken lines and low pressure provide means for entry of pathogens into the distribution
21
system. Maintaining chlorine residual in the system is one way to guard against cross-
contamination, as is sustaining adequate pressure in the system.
Generation of wastewater. With the improvement in the water supply system, there will be
incremental wastewater that will be generated. Households are likely to use more water for
bathing, cooking and washing. This may lead to more grey water or sullage as the population
increases and as more people have access to piped water supply. Without appropriate
wastewater treatment systems, the disposal of wastes will have significant effect on the
pollution load into rivers. Eventually, the wastewater management system should be
developed for Siem Reap to protect the environment from incremental wastewater that will be
generated.
VI. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE
Information disclosure and public consultations were conducted to inform stakeholders about
the proposed water supply improvement project. Meetings were held in Siem Reap with key
provincial agencies, commune leaders, and community members. SRWSA organized the
meetings which were announced through invitations letters direct communication with
communes/villages and Government leaders.
A. Public Consultations
A general description of the project was prepared in Khmer language. Hand drawn/lettered
poster boards and large scale prints of drawings were prepared for the presentation. The
environmental and social impacts were identified by the SRWSA through the Project
Implementation Consultants. The minutes of the public consultation meetings, attendance lists
and project information booklet (PIB) are included in Appendix 2.
The first public consultation was held in 07 June 2013 during the project preparatory technical
assistance (PPTA) while the follow-up consultations were held on August 2017 in Trapeang
Ses village, Veal village, and Teak sen Khang Thbong village and 17 August 2017 in Sala
Kanseng village, Sangkat Svay Dong Koum and at Sangkat Sla Kram was prepared the
meeting with commune councils on August 17, 2017 at 14:30pm in Slakram commune center.
There were a total of 227 participants, of which 132 are female, during the public consultations
held from 16 – 17 August 2017. Sangkay Kouk Chok has eight villages but there are three
villages within the pipe expansion network. These are: (i) Trapeang Ses, (ii) Veal, and (iii)
Teaksen Thbong. Five separate meetings were conducted with villagers and stakeholders.
The first public consultation was held in Trapeang Ses village, the second meeting in Teak
Sen Thbong village, the third was in Veal village, and the fourth in Sala Kansemg village,
however; dung that time the stakeholder meeting was also arranged the meeting with Sla Kram
Commune Councils at Sla Kram Commune Center. All of these villages are within Sangkat
Kouk Chok where Zone 1 of the APSARA Authority region is located. Table 5 presents the
dates and locations of the follow-up public consultations.
22
Table 5: Dates and venue of the public consultation meetings
Date
Time
Location Number of
participants Sangkat
(Commune) Village
Meeting
venue
Aug 16, 2017 08:00-09:30 Kouk Chork Trapeang Ses Wat Thmei 54/F=38
Aug 16, 2017 10:00-11:00 Kouk Chork Teak Sen
Thbong
Prasat Kouk
Chork
33/F=14
Aug 16, 2017 14:00-16:00 Kouk Chork Veal Prasat Kouk
Chor
104/F=64
Aug 17, 2017 08:30-10:00 Svay Dong
Koum
Sala Kanseng Village Chief’s house
30/F=15
Aug 17, 2017 14:30-15:30 Sla Kram Sla Kram Commune
center
6/F=1
Total 3 5 4 227/F=132
Prior to the public consultation meetings, the PMU of SRWSA and the PIA met to arrange the
schedule of the consultation meetings with the villages, local authorities, and agencies. The
village authorities in Sangkat Kouk Chok were met on 14 July 2017 and 15 August 2017 and
positive benefits were primarily raised about the project by the village representatives. They
said that the people have been clamoring for piped water supply for a long time.
During each public consultation meeting, the project and proposed alignment of the pipe
network were presented. The presentation also included the identified environmental and
social issues and the proposed mitigation measures to be implemented during pipe laying.
The grievance redress mechanism was also presented. This is followed by an open discussion
of issues and concerns from the stakeholders. Project information booklets were also
distributed for reference of the public. The following presents the issues that were raised during
the public consultation meetings:
Table 6: Issues and concerns discussed during the public consultations
Issue raised and perceived
environmental issues
Approach to addressing the issue
- There is strong support to the project.
The villagers and local authorities
welcome the project and they would like
to implement the project as soon as
possible.
- Noted.
- The PIB was disseminated to the
participants. The location of the pipes in
relation to the private properties was
raised.
- PIB and information related to the water
supply project within the project area were
provided.
- The right-of-way (ROW) is 15m to 25m from
the center of the road. The pipe alignment
will be basically on the edge of existing
road and will avoid any private properties.
In case there will be any affected structure
along the ROW, the SRWSA will consult
23
Issue raised and perceived
environmental issues
Approach to addressing the issue
with the affected person prior to any works
to explain the temporary disturbance and
restoration to pre-project condition to be
undertaken by SRWSA.
- The project might affect structures like
electric poles, telecommunication
cables. There are some private
properties within the APSARA Authority
zone.
- The SRWSA will discuss with EDC,
telecommunication company and APSARA
Authority to avoid damage to properties.
- The project will minimize the impacts as
much as possible in the urban areas
(mostly in and nearby markets).
- Construction will be on the road right of
way.
- The people are willing to connect to the
piped water supply. They are willing to
contribute and closely cooperate with
the authorities in providing land and
trees that may be affected along the
project route for the installation of the
pipe network.
- Noted
- Safety plan should be developed in
order to avoid traffic accidents,
especially at road crossing and
intersections before commencement
work.
- SRWSA will cooperate and provide all
necessary information to the local
authorities about working places, project
sites, and routing of alignment of the pipe
network, and schedule before
commencement of works in order to ensure
safety and security.
- A traffic management plan will be
implemented in coordination with the local
authorities.
- The time for construction should be not
delay for long time (at replacement pipe
network areas).
- There will have small impact of the
subproject at Sangkat Slakram and
Sangkat Svay Dong Koum. In Sangkat
Kouk Chok, there are illegal shelters
(96HHs) that were built on the road
No.22 (V20C).
- Impacts to these settlers will be avoided.
Coordination with these shelters and
Sangkat council and Provincial Government
will be undertaken prior to start of pipe
laying activities.
B. Key Informant Interviews
Key informant interviews were conducted with Sangkat Councils of Sangkat Kouk Chok and
Sangkat Sla Kram on 14 July 2017 and 15 August 2017. The following issues were raised by
the council members:
a) The villagers currently take water by pumping from well or ring well. During the rainy
season, the water is not clean while during the dry season, water cannot be abstracted
24
because there is not enough water to pump. In the dry season, most of the people buy
bottled water (20 liters at R3,000 per jar) at least twice per week for drinking and also
from water trucks for washing and bathing. The houses in the villages have large jars
where they store water.
b) During the rainy season, the people collect rain water which they also use for drinking,
washing, and other households needs.
c) For cooking and drinking, the villagers have two options: (i) buy water from delivery
truck, (ii) use stored rainwater.
d) The Sangkat Council said that the elderly people and children usually get sick during
the dry season which they attribute to the hot weather. Common diseases are stomach
ache, intestinal tract infection, and diarrhea. The villagers go to the health center near
the Commune for consultation and at the Siem Reap Referral Hospital. Medical
consultation fee ranges from US$5 – 10.
e) The Sangkat Council said that most of the people who are living within the Sangkat are
willing to connect to the proposed water supply project and that they are very happy
that the project will be implemented soon. They added that their lives will be more
convenient if there is piped water connection.
f) Based on the proposed location of pipe replacement and expansion, the pipes will be
installed along road structure alignment which belongs to public land.
g) The Sangkat Chief said all residential land in Kouk Chak are already registered and
recognized by the APSARA Authority.
h) Some physical concrete properties of people may be affected by the project such as
sidewalk but the people are willing to donate these properties to the project. It is
important to get piped water connection for houses.
Meeting at Trapeang Ses village, Kouk Chok Sangkat in Thmei pagoda
Meeting at Veal village, Kouk Chok Sangkat in Prasat Kouk Chor pagoda
Meeting at Teak Sen Tbong village in Prasat Kouk Chok pagoda
Meeting at Sala Kanseng village, Svay Dong Koum Sangkat in Village’s house
Photo 4: Public consultation meetings
25
VII. GRIEVANCE REDRESS MECHANISM
Grievances related to both environmental and resettlement issues are addressed through the
Grievance Redress Mechanism (GRM). In order to ensure that complaints from all affected
persons (APs) on any aspect of environment, land acquisition, compensation and resettlement
are addressed in a timely and satisfactory manner, and that all possible avenues are available
to APs to air their grievances, a well-defined grievance redress mechanism will be established.
All APs can send any questions to the SRWSA about their rights in relation with redress of
environmental problems and entitlement under the resettlement plan. APs are not required to
pay any fee in order to file a complaint at any level. The GRM has been explained in the public
information booklet distributed to all APs, and is explained here in relation to complaints related
to environmental impacts.
A Grievance Redress Committee (GRC) shall be established before commencement of site
works and shall be chaired by SRWSA-PMU. The GRC shall have members from the SRWSA-
PMU, commune councils, and village chiefs. Grievances can be filed verbally or in a written
form with any member of the GRC. The committee will have 20 days to respond with a
resolution. If unsatisfied with the decision, the existence of the GRC shall not impede the
complainant’s access to the Government’s judicial or administrative remedies.
Stage 1 - Complaints from APs on any aspect of environmental impacts shall first be
lodged verbally or in a written form with any SRWSA-PMU representatives at the
construction site or through telephone numbers provided on the signboard placed
outside the construction site. The SRWSA-PMU will decide on a course of action within
5 days from the day it is lodged. Usually complaints about environmental impacts are
resolved at this stage.
Stage 2 - If no understanding or amicable solution can not be reached, or if no response
from the SRSWA-PMU is received by the AP within 5 days of registering the complaint,
he/she can appeal directly to the commune or village chiefs concerned. The commune
or village chiefs will coordinate with the SRWSA-PMU to decide on a course of action.
The complaint must be settled within 5 days of registering the original complaint.
Stage 3 - If the AP is not satisfied with the actions made by the commune or village
chiefs, or in the absence of any response, the AP can appeal to the District GRC. The
District GRC will coordinate with SRWSA-PMU and relevant commune or village chiefs
to resolve the complaint, which must be settled within 5 days of registering the original
complaint.
Stage 4 - If the AP is not satisfied with the actions made by the District GRC, or in the
absence of any response, the AP can appeal to the Provincial GRC which must make
a written decision and submit copies to the SRWSA-PMU and AP.
Stage 5 - If the AP is still not satisfied with the decision of the Provincial GRC on appeal,
or in absence of any response from the SRWSA-PMU within the stipulated time, the
AP, as a last resort, may submit his/her case to court of law, whose judgment is final.
APs may also ask for resolution from ADB’s responsible project officer consistent with the provision of the ADB’s accountability mechanism. They can file their complaint through the ADB resident mission in Phnom Penh for transmittal to the ADB
headquarters in Manila.
26
At each stage, the governing official is responsible for recording the minutes of meetings,
maintaining files on all complaints, and for distributing copies of all decisions to the SRWSA-
PMU and lower level bodies, including commune/village officials and affected parties and
households.
The SRWSA-PMU shall make public the existence of this grievance redress mechanism
through public awareness campaigns. They shall set-up a hotline for complaints and the hotline
shall be publicized through the media and numbers placed on the notice boards sited outside
the construction site and at subnational level of local government offices (e.g., provincial,
district, commune levels). Locally affected people will still be able to express grievances
through the commune councils and these would be referred through the usual channels in
those committees.
The SRWSA-PMU will be responsible for checking the procedures and resolutions of
grievances and complaints. The PIA consultant may recommend further measures to be taken
to address unresolved grievances.
VIII. ENVIRONMENTAL MANAGEMENT PLAN
The rehabilitation and expansion of water supply systems will entail the replacement of existing
water supply pipelines within the Siem Reap town and the expansion to unserved areas in
Kuok Chak Sangkat and Svay Dongkun commune. The proposed mitigation measures to
address adverse environmental impacts during pipe laying have been compiled into a matrix
and is presented in Table 8. The matrix summarizes the anticipated environmental impacts
and its mitigation measures during pre-construction, construction, and commissioning phases.
Prior to commencement of construction activities, the SRWSA shall survey and determine loss
or damage to community assets such as roads, shops, fences, gates, driveways, portions of
houses, and other structures. Affected persons will be consulted in advance of works to explain
the temporary disturbance that will occur during pipe installation and the restoration that will
be undertaken by SRWSA. It will be explained that any damage to community structures will
be restored at the cost of SRWSA. The SRWSA shall coordinate with the relevant Government
authorities such as the Department of Public Works and Transport (DPWT), APSARA
Authority, local authorities, commercial establishments, and affected households prior to pipe
laying works.
The SRWSA will make sure that applicable prohibited activities as stipulated in Appendix 5 of
the ADB SPS (2009) and the ADB Reference Guidelines on Environmentally Responsible
Procurement are not undertaken. These include:
Activities involving harmful or exploitative forms of forced labor or child labor9.
Production of or trade in any product or activity deemed illegal under the Cambodia’s laws and regulations and international conventions and agreements or subject to
international phase outs or bans such as (i) pharmaceuticals10, pesticides, and
9 Child labor means the employment of children whose age is below the country’s statutory minimum age of employment or
employment of children in contravention of the International Labor Organization Convention No. 138 “Minimum Age Convention” (ww.ilo.org)
10 A list of pharmaceutical products subject to phase outs or bans is available at http://www.who.int.
27
herbicides11, (ii) ozone-depleting substances12, (iii) polychlorinated biphenyls13 and
other hazardous chemicals14, (iv) wildlife or wildlife products regulated under the
Convention on International Trade of Endangered Species of Wild Fauna and Flora15,
and (v) transboundary trade of waste or waste products16.
Trade or use of un-bonded asbestos fibers.17
Marine and coastal fishing practices, such as large-scale pelagic drift net fishing and
fine mesh net fishing that are harmful to vulnerable and protected species in large
numbers and damaging to marine biodiversity and habitats.
A. ENVIRONMENTAL MONITORING PLAN
A matrix of the Environmental Monitoring Plan is presented in Table 9. The main components
of the monitoring plan include the following:
Environmental parameters to be monitored and means of verification.
Locations where monitoring will be conducted.
Applicable standards and criteria.
Duration, frequency and estimated monitoring costs.
Institutional responsibilities for monitoring and supervision.
In addition, the SRWSA is required to establish a complaint recording system which would
contain details on the type and nature of complaint, location where complaint occurred, time
the complaint was received, remedial actions to address the complaint, and the final outcome
leading to the resolution of the complaint.
1. Compliance Monitoring
Compliance monitoring will be required to assess the overall implementation of the CEMP.
Selected indicators of major components of the environment that will be affected by the
construction phase are drawn from the EMP. The SRWSA through the PMU’s Environment,
Health, Safety and Social Safeguards Officer will conduct visual inspection and monitoring,
review of construction records, and meetings with stakeholders when necessary. Compliance
monitoring will involve regular checks on waste management, dust and noise control
measures, construction safety measures, community health and safety measures and
community coordination. The daily or weekly spot checks on site operations will be undertaken
through a checklist of activities and measures that needs to be complied during the
construction. Completed daily and weekly checklists will be filed for records purposes.
Appendix 4 presents the inspection checklist to be used during monitoring.
The following lists the monitoring parameters and time of monitoring:
Excessive soil runoff from construction sites must be checked during the rainy season.
11 A list of pesticides and herbicides subject to phase-out or ban is available at http://pic.int. 12 A list of chemical compounds that react with and deplete the stratospheric ozone resulting in the ozone holes is listed in the
Montreal Protocol, together with the target reduction and phase-out dates. Information is available at http://www/unep.org/ozonaction.
13 A group of highly toxic chemicals, polychlorinated biphenyls are likely to be found in oil-filled transformers, capacitors, and switchgear dating from 1950 to 1985.
14 A list of hazardous chemicals is available at http://www.pic.int. 15 A list is available at http://www.cites.org. 16 As defined by the Basel Convention; see http://www.basel.int. 17 This does not apply to the purchase and use of bonded asbestos cement sheeting where the asbestos content is less than 20%.
28
Dust emissions at construction sites and pipe laying activities must be checked daily
by visual inspection particularly during the dry months and by examining records of
water spraying.
Noise levels must be checked at 100 meter from sensitive receptors and in the event
of a complaint.
Rehabilitation of road shoulder and driveways after pipe laying must be checked.
Proper removal of wastes must be checked weekly by visual inspection and by
checking records from waste disposal contractors.
EMP measures must be checked daily or weekly by visual inspection of the
construction camps and construction sites.
During the operational phase, water quality tests will be carried out on a daily basis for residual
chlorine and on a monthly or annual basis for other parameters in accordance to the Standard
Operating Procedure (SOP) of SRWSA. The tests aim to ensure that treated water to be
supplied to the community is potable and meets the National Drinking Standards as well as
the WHO standards.
2. Reporting
The PMU will compile the results of the implementation of the EMP measures and monitoring
checklists on a monthly basis to be sent to the PIA. The designated Environment, Health,
Safety and Social Safeguards Officer of the PMU with assistance of the PIA will review the
reports. The PIA Environment Safeguards Specialists will make spot visits to the site to check
the reports and to validate the implementation of the mitigation measures.
The quarterly project progress reports to be submitted to ADB will include a summary of the
implementation of the EMP and the semi-annual environmental monitoring reports will provide
the details of the EMP implementation, results of water quality tests, GRM, and other follow-
up consultations.
B. INSTITUTIONAL ARRANGEMENT
The SRWSA has organized the PMU of the subproject by virtue of an office order issued in
2017 as shown in Appendix 3. The PMU has the following tasks:
a) Manage related documents of the project in cooperation with the technical consultant
and ADB and the Ministry of Economy and Finance (MEF).
b) Manage, lead, and be responsible in the day-to-day activities of the subproject to
ensure compliance to ADB and MEF requirements.
c) Cooperate with the technical consultant of the project in procurement management
after the agreement has been signed.
d) Monitor the construction of the project, installation, material supply, machineries, and
equipment as stated in the contract.
e) Oversee financial management and related expenses in compliance with MEF.
f) Ensure quality control of machineries and equipment and supervise construction
activities.
g) Document reports on progress of works through monthly and quarterly reports to be
submitted to MEF and ADB to illustrate progress of project implementation.
h) Attend meetings required by the director of the project.
29
The PMU is composed of 15 members, as follows:
Table 7: Composition of the PMU
Name Concurrent Assignment Project Position
Khut Vuthiarith Director Project Director
Chan Sengla Deputy Director Project Manager
Seak Pengkheang Assistant Director Deputy Project Manager
Yay Monyroth Deputy Director, Business Division Technical Manager
Kut Nimol Director, Technical Department Technical Manager
Sok Hout Director, Finance & Accounting Finance
Touch Ratha Deputy Director, Technical
Department
Technical
Chan Sereyroth Chief, Procurement Unit Procurement
The SRWSA will hire labor contractors but the PMU will directly supervise the construction
activities. The EMP implementation will be monitored by the SRWSA-PMU through its
appointed EHS officer. Mr. Meas Sopheaktra has been designated as the focal person
environment, health, safety and social safeguards who will coordinate the activities between
the contractor and the PIA regarding the implementation of the project’s EMP as well as oversee the submission of semi-annual environmental and social monitoring reports to ADB.
C. CAPACITY DEVELOPMENT
Training on environment and social safeguards will be conducted by the PIA before the start
of construction works. As per request of SRWSA, the training will be delivered in Khmer by
the PIA national environment and social specialists. A resource person from the MOE will be
invited to give an orientation on the Government’s environmental requirements.
The orientation training aims to:
a) Orient the participants on the key requirements on environment and social
safeguards based on the ADB Safeguard Policy Statement (2009);
b) Enhance environmental management and monitoring of the Siem Reap water supply
project under Loan 3232;
c) Enhance the implementation of environmental management plan;
d) Orient the PMUs on the grievance redress mechanism; and
e) Explain the preparation of the environment and social safeguards monitoring reports.
30
The target participants are four staff from the PMU and the four construction teams of SRWSA
composed of 7 – 8 people per team. The total number of target participants is 36.
The orientation training will focus on the following topics:
ADB Safeguards Policy Statement (2009);
Importance of compliance monitoring;
Environmental monitoring parameters;
Grievance redress mechanism for environment-related complaints; and
Preparation of semi-annual environmental and social monitoring reports.
31
Table 8: Matrix of Environmental Management Plan
Environmental Impact Options for Prevention or Mitigation Responsible Entity Source of
Fund Implementation Monitoring
Pre-Construction Phase
Damage to community assets
such as roads, fences,
driveways, and other structures
due to pipe laying.
Survey the alignment of the water supply
pipelines and determine community assets
that will be affected.
Coordinate with the Provincial Department of
Public Works and Transport (DPWT) to
determine sections of roads that will be
affected prior to construction.
Coordinate with the Provincial Government
and local authorities so that interruption of
services will be at the minimum.
Notify affected households in advance on
the pipe laying works and any structures that
will be affected including information on the
schedule of construction activities. The
temporary disturbance and restoration after
pipe installation at pre-project conditions with
cost shouldered by SRWSA will be
explained.
SRWSA-PMU PMU-
Environment,
health, safety &
social safeguards
staff;
PIA
SRWSA-PMU
Impact on APSARA Zone 2 Notify APSARA Authority about the water
supply distribution pipe laying activities in
Kouk Chak commune.
SRWSA-PMU PMU-
Environment,
health, safety &
social safeguards
staff;
SRWSA-PMU
32
Environmental Impact Options for Prevention or Mitigation Responsible Entity Source of
Fund Implementation Monitoring
Seek approval of pipe laying plan at least
one month prior to start of works.
PIA
Construction Phase
Disruption and damage to
existing community structures
and facilities
Pipe laying will cause temporary
disruption of community
services and access to
properties.
Damage to community facilities
such as roads, driveways to
properties and pathways to
private and public areas during
pipe laying.
Particularly at pipe road
crossings, construction activities
along roads may lead to
temporary blockage of lane and
hamper movement of vehicles
and people in the community.
Provide temporary accesses to affected
properties using durable materials.
Particular attention will be given to ensuring
safety along roads and paths normally used
by school children.
Side street parking of construction vehicles
on prolonged basis will not be allowed.
Install barriers and safety warning signs on
road sections and if necessary deploy traffic
aides/flag persons at affected locations.
Provide information boards on the project
details, schedule and SRWSA contact
numbers.
Immediately rehabilitate the excavated areas
and any damaged structures such as roads,
driveways, gates, and paths. Ensure that
restoration is accepted by the affected
person.
SRWSA-PMU PMU-
Environment,
health, safety &
social safeguards
staff;
PIA
SRWSA-PMU
Air pollution
Require the contractor to cover materials with
tarpaulin or other suitable materials while in
transit to avoid spillage of materials.
SRWSA-PMU PMU-
Environment,
health, safety &
SRWSA-PMU
33
Environmental Impact Options for Prevention or Mitigation Responsible Entity Source of
Fund Implementation Monitoring
Dust and air emissions from
excavation and movement of
vehicles can pose nuisance to
nearby communities
Moisten earthen roads during dry and dusty
conditions, particularly roads near residences
and through the town core area.
Impose speed limits on construction vehicles.
Conduct maintenance on construction
equipment and vehicles to control air
emissions during vehicle operation.
social safeguards
staff;
PIA
Noise and Vibration
Operation of construction
equipment such as excavator
will cause excessive noise
resulting to nuisance to
communities.
Limit construction activities, particularly
operation of noise generating equipment at
night.
Position any stationary equipment that produce
high noise levels such as excavator as far as
practical from sensitive receptors.
Erect temporary walls around construction
sites especially near schools, hospitals, and
houses.
Install noise suppression devices to noise
generating equipment.
Require drivers to minimize blowing of horn
and to comply with speed limits
SRWSA-PMU PMU-
Environment,
health, safety &
social safeguards
staff;
PIA
SRWSA-PMU
34
Environmental Impact Options for Prevention or Mitigation Responsible Entity Source of
Fund Implementation Monitoring
Provide information to community on schedule
of construction activities through billboard/signs
and complaint hotline.
Sediment runoff
Sediment runoff undertaken
during excavation, earthworks
and grading in the rainy season
will cause siltation of rivers
Construct silt traps, deviation channels,
mounting barriers or trenches around the
stockpiles of materials
SRWSA-PMU PMU-
Environment,
health, safety &
social safeguards
staff;
PIA
SRWSA-PMU
Discharge of chlorine during
pipeline disinfection
Prior to commissioning,
disinfection will be undertaken
on the pipeline. Discharge of
chlorine above the allowable
limits is toxic to fish and other
aquatic life.
Follow the recommended dosage of chlorine
during the disinfection of pipes and reservoir.
Measure chlorine residual if within the
allowable limit of 0.2 – 0.5 mg/l before flushing,
otherwise, treat or dilute prior to disposal into
the environment.
SRWSA-PMU PMU-
Environment,
health, safety &
social safeguards
staff;
PIA
SRWSA-PMU
Generation of excavated soil
and other construction debris
Generation of excavated
materials during pipe laying.
During pipe laying, excavated material will be
utilized to cover back the trench. The
contractor will be required to properly reinstate
the excavated trench after completion of pipe
laying.
SRWSA-PMU PMU-
Environment,
health, safety &
social safeguards
staff;
PIA
SRWSA-PMU
35
Environmental Impact Options for Prevention or Mitigation Responsible Entity Source of
Fund Implementation Monitoring
Domestic solid wastes,
domestic wastewater, inert
construction wastes, and
hazardous wastes during
construction may result to
pollution of the environment.
Undertake segregation of hazardous and non-
hazardous wastes, including properly labeled
waste disposal bins.
Instruct workers not to indiscriminately dispose
wastes particularly at surrounding areas,
canals, rivers, field, and other public areas
All solid waste will be regularly collected and
removed from the work camps and disposed
to areas approved by local authorities.
Prohibit burning of wastes.
Site decommissioning and
rehabilitation of construction
sites
All construction sites and work areas will be
rehabilitated so that these can be returned
as close as possible to their previous use.
This includes the restoration and
stabilization of all of the construction sites.
No waste will remain at the site after work is
completed.
SRWSA-PMU PMU-
Environment,
health, safety &
social safeguards
staff;
PIA
SRWSA-PMU
Worker health and safety
Workers may be exposed to
risks to health and safety due to
physical hazards, exposure to
dust and noise, falling objects,
and ergonomic injuries.
Orient workers and implement measures to
ensure construction safety; fire prevention
and management; worker education and
awareness for HIV/AIDS and other sexually
transmitted diseases; and control strategy
for mosquito and other vector diseases.
SRWSA-PMU PMU-
Environment,
health, safety &
social safeguards
staff;
PIA
SRWSA-PMU
36
Environmental Impact Options for Prevention or Mitigation Responsible Entity Source of
Fund Implementation Monitoring
Potential conflict with local
people will occur if migrant
workers will be brought to the
site.
Require workers to adhere to guidelines
relating to minimum distances for
excavations, tools, vehicles, and other
activities in the ROW of the water distribution
lines.
Provision of first-aid facilities readily
accessible by workers.
Conduct training of workers in the
identification and management of
occupational hazards.
Post safety signs, reminders, or warning
notices at visible areas onsite.
Strictly implement a “No-Alcohol, No-
Gambling and No-Dangerous Drug Policy” at the construction site.
Provide PPEs such as hard hats, gloves,
safety boots, ear protection, breathing
masks, etc. Wearing of PPEs, while working
onsite will be a mandatory requirement for
workers.
Contractor should ensure that child laborers
and trafficked workers are not employed.
37
Environmental Impact Options for Prevention or Mitigation Responsible Entity Source of
Fund Implementation Monitoring
The contractor will be required to provide
priority hiring of qualified construction
workers from the villages and to consult with
the local to avoid conflict if migrant workers
will be brought to the site.
Community health and safety
Risks to community health and
safety due to pipe laying and
unauthorized entry of villagers
into dangerous working areas
Provide advance notification of proposed
pipe laying activities, locations and
schedules to local residents, hospitals,
schools, businesses, and other institutions
and establishments. Regularly coordinate
with affected parties during project
construction.
Install safety barriers and plates in open
excavations to avoid unauthorized or
accidental access by the public.
Provide safe access and passageways to
properties and establishments for
pedestrians affected by pipe laying works.
This will include temporary pathways and
crossings (e.g. metal or durable wooden
plates) over excavated areas or trenches.
Conduct daily cleaning of the work area and
sweeping of the road shoulder.
Backfill and cover the excavated areas after
pipe laying activities.
SRWSA-PMU PMU-
Environment,
health, safety &
social safeguards
staff;
PIA
SRWSA-PMU
38
Environmental Impact Options for Prevention or Mitigation Responsible Entity Source of
Fund Implementation Monitoring
Reinstate good quality permanent accesses
following completion of construction works.
Post informational boards with contact name
and numbers whereby local residents,
business operators, farmers and other
establishments can report issues related to
access restrictions.
Implement the Grievance Redress
Mechanism to manage complaints from the
community. Assign a focal person to receive
community complaints in accordance with
the Grievance Redress Mechanism (GRM).
Document all complaints received and
actions taken by the contractor to resolve the
complaint.
Physical cultural resources
Chance discovery of artifacts
and archaeological resources
Orient workers on procedures to employ
during chance discovery of artifacts. Any
chance find should be reported immediately
to proper authorities.
SRWSA-PMU PMU-
Environment,
health, safety &
social safeguards
staff;
PIA
SRWSA-PMU
39
Table 9: Matrix of Environmental Monitoring Plan
Aspects/Parameters to be
Monitored
Location Means of Monitoring Schedule/Frequency Responsibility Source of
Fund
Pre-Construction Phase
Survey of affected structures
(roads, shops, driveways,
fences, gates, portions of
houses, etc._
All project sites including
associated facilities
Site survey Prior to start of civil
works
PMU PMU
Construction Phase
Rehabilitation of road shoulder
and driveways after pipe laying
Areas with pipe laying
activities
Visual inspection Daily/weekly PMU PMU
EMP implementation All project areas
(construction sites, camp)
Visual inspection Daily/weekly PMU PMU
Direct effects on communities
from project impacts such as
damage to properties, dust
generation, noise and safety.
All project sites Gather views and
opinions of communities
through community
feedback and GRM
Weekly PMU PMU
Monitoring of EMP during
construction/excavation,
including compliance to traffic
management and road
restoration.
All roads, particularly at
road pipe crossings
Site inspection Daily/weekly PMU PMU
Residual chlorine during
pipeline disinfection prior to
commissioning
Pipeline Residual chlorine should
be 0.1 – 0.2 mg/l before
flushing.
Prior to
commissioning
PMU PMU
40
IX. CONCLUSION
Based on the updated IEE, the subproject is still classified as Category B because the identified
environmental impacts are temporary, reversible and will primarily occur during construction.
The water supply distribution pipe alignment is far from the Angkor Wat site and other
significant temples of the complex. There are no environmentally, ecologically sensitive or
culturally significant areas along the distribution network. The areas to be connected to piped
water supply in the APSARA Zone are characterized with built-up communities where land and
structures have already been registered and recognized by the APSARA Authority. The
provision of safe and potable piped water services to these communities is of primary
importance to protect the health and sanitation of the people living in the area.
Adverse impacts can occur due to damage to concrete driveways of houses and road sidewalk
pavements but these will be restored by the SRWSA after pipe laying. Affected persons will be
consulted in advance of works so that information on temporary disturbance, mitigation
measures, and restoration works are explained by SRWSA. The cost of restoration will be
shouldered by SRWSA. The SRWSA will coordinate with relevant authorities such as the
Department of Public Works and Transport (DPWT), Provincial Government of Siem Reap,
APSARA Authority, local government authorities, and affected stakeholders prior to start of
pipe laying activities.
The benefits of providing water supply to the households who are currently relying on
boreholes and unsafe and unsustainable groundwater supplies far outweigh any adverse
impact that may occur during construction. The mitigation proposals will be monitored during
the construction phase. Likewise, SRWSA will inform the APARA Authority and the Provincial
Government at least one month prior to pipe laying at APSARA Zone 2. The letters of approval
of these agencies will be submitted to ADB as part of the semi-annual environmental
monitoring report.
41
Appendix 1: Documentation of Consultation Meetings
1) Attendance list of public meeting at Trapeang Ses village, Kouk Chok commune
date 16 Aug 2017 (at 08:00am) at Wat Kouk Chok (Total: 54ps; F=38)
42
43
2) Attendance list for public meeting at Teak Saen Keng Tbong village, Kouk Chok commune
date 16 Aug. 2017 at 10:00am (Total: 33ps, F=14)
44
45
3) Attendance list for public meeting at Veal village, Kouk Chok commune
date 16 Aug. 2017 at 14:00pm (Total: 104ps, F=64)
46
47
48
49
50
51
4) Attendance list for public meeting at Sala Kanseng, Svay Dong Kom commune
date 17 Aug. 2017 at 08:30am (Total:30ps, F=15)
52
53
5) Attendance list for discussion meeting with commune council at Slakram commune,
date 17 Aug. 2017 at 14:30pm (Total: 6, F=1)
54
Public consultation meeting at Trapeang Ses village,
Sangkat Kouk Chok, Siem Reap,
Date 16 Aug. 2017
Public consultation meeting at Veal village, Sangkat
Kouk Chok, Siem Reap,
Date 16 Aug. 2017
Public consultation meeting atTeak Saen Tbong
village, Sangkat Kouk Chok, Siem Reap, Date 16
Aug. 2017
Discussion meeting with Commune Councils at Svay
Dong Koum commune, date 17 Aug. 2017
Siem Reap Water Supply Authority,
date 14 July 2017
Discussion meeting with SRWA,
Date 14 July 2017
Discussion meeting with Siem Reap Provincial
Department of Public Works and Transport, date 14
July 2017
Discussion meeting with Commune Council at
Sangkat Kouk Chok, Siem Reap, date 13 July 2017
55
Appendix 2: Public Information Booklet
56
57
58
59
Appendix 3: Organization of the Project Management Unit of SRWSA
a) Has the Provincial Government and local authorities been informed and given its consent of the project activities and schedule?
b) Has the APSARA Authority given its consent on pipe laying at APSARA Zone 2?
c) Has the DPWT been informed of road segments that will be affected?
d) Were affected households with driveways and sensitive receptors been informed of the project activities and schedule?
e) Was orientation training on environment safeguards undertaken for the PMU and construction team prior to start of construction activities?
f) Are workers informed of the chance find procedure for archaelogical artifacts?
Construction a) Are there barriers in the work area?
b) Are there safety warning signs?
c) Are workers wearing the appropriate personal protective gadgets applicable to type of work?
d) Are there flagmen/traffic aides in busy road lanes affected by pipelaying?
e) Are there information boards about the project, schedule, and SRWSA contact numbers?
f) Are there available temporary toilets/sanitation facilities for workers?
g) Are there garbage bins at the work area?
h) Is water sprinkling being undertaken to moisten earthen roads?
i) Are there silt traps, deviation channel or mounting barriers/trenches around excavated soils to prevent soil runoff?
j) Are there plates/cover and safe access or passageways for pedestrians in open excavations to avoid accidents?
k) Is daily cleaning of the work areas being undertaken?
l) Were there complaints received by communities?
m) Are there readily available first-aid facilities at the site?
n) Was the recommended dosage of chlorine during pipe disinfection and the resulting resdual chlorine of 0.1 – 0.2 mg/l followed?
63
Appendix 5: Template of Semi-Annual Environmental Monitoring Report
Summary: (to be included as part of the main Report)
Summary of EMMP Implementation
Description of monitoring activities carried out (e.g. field visits, community consultation meetings, site inspections, focus group discussions, etc)
Key issues, any corrective actions already taken, and any grievances
Recommendations Environment Safeguards Monitoring Report 1. Introduction and Project Overview Project Number and Title:
Reporting period:
This section can include, among others, the following: Activities of Proponent Progress of Work (% physical completion) Changes of Surrounding Environment Status of Permits
Monitoring period covered
Key sub-project activities since last report:
Report prepared by:
2. Environmental Performance Monitoring a. Status of Compliance with EMMP Requirements (Environmental Performance)
Environmental Impact
Options for Prevention or Mitigation
STATUS
Pre-Construction Phase
Construction Phase
Summary of EMMP Compliance Status: b. Results of Environmental Monitoring
Complaints resolution
Follow-up consultations EMMP implementation
Water quality at distribution network
Training/capacity building
64
c. Issues for Further Action
Issue Required Action Responsibility and
Timing Resolution
Old Issues from Previous Reports
List of EMMP measures or activities not completed (last column of previous table)
New Issues from This Report
3. Conclusion
Important results from the implementation of EMMP monitoring Recommendations to improve EMMP management, implementation, and monitoring
4. Attachments
Permits Monitoring data (water quality, etc.) Photographs Maps
65
Appendix 6: Approval Letter from Provincial Governor
66
Appendix 7: Standard Operating Procedure of SRWSA for Water Quality Tests
67
Appendix 8: Standard Operating Procedure of SRWSA for Pipe Laying/Installation