Caltrain EMU Update Citizens Advisory Committee May 20, 2020 Agenda Item #8
Caltrain EMU
Update
Citizens Advisory Committee May 20, 2020Agenda Item #8
Caltrain is procuring 19, 7-Car Trainsets
2
Emergency Exits
9
Vehicle Features and
Passenger Amenities
Amenities and Features• Passenger emergency intercom
• Emergency brake lever
• Emergency exit windows – both levels
• Automatic passenger counter
• Accessible toilet (“C” Car)
• Bike storage in bike cars
• Passenger Information Display (Destinations)
• Passenger Brochures
• Public Announcement System
• Under-seat electrical outlets
• Interior LED lighting and temperature control
• Passenger WiFi provisions
12
Accessible Toilet
13
Bike Car
14
Bike Car
15
Passenger Information Display (PIS) and
CCTV Camera
16
CCTV
PIS
Passenger Information Display and
Brochures
17
Emergency Exit Window – Upper Level
18
Emergency Brake Lever
19
Passenger Emergency Intercom
20
Underseat Charging Outlets
21
Add slide of Console Layout Drawing
22
23
24
25
Automatic Passenger Counter
26
Interior LED Lighting and Temperature
27
Production Activities
Car Shells in Switzerland Ready for Painting
29
Painted Car Shell in Switzerland
30
Car Shell Painted Interior
31
Car Shell Arriving In Salt Lake City
32
Cars Being Moved in Salt Lake City Facility
33
Trainset No. 1 in Salt Lake City
Undergoing Testing
34
Trucks (bogies) Assembled in Salt Lake City
Ready for Installation Under a Car
35
Upper Level
36
Cab Console Under Construction
in Salt Lake City
37
Front Destination Sign
38
Side Destination Sign
39
Destination Announcements
40
Schedule
- Trainset No. 1 Assembly Nearing Completion and Being Prepared for
Testing in Salt Lake City
- Trainset No. 2 – 4 in various stages of completion in Salt Lake City
- Trainset No. 1 to commence testing in Railcar Testing facility in Pueblo,
Colorado – Fall of ‘2020. Testing Duration 7 months
- First Trainset to be delivered to Caltrain – Spring of ‘2021.
41
Questions?
42