Validware € Calculation Cost Model: Area Oriented Approach Manual Version 2.0, 1 February 2013
Validware
€
Calculation Cost Model: Area Oriented Approach Manual Version 2.0, 1 February 2013
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 2
Summary
This manual describes how to use the Cost Calculation Model: Area Oriented Approach (CCM: AOA) software. The
software can be downloaded from http://www.citychlor.eu/sites/default/files/installer_2.0_english.zip
The Cost Calculation Model: Area Oriented Approach (CCM: AOA) is a standardized method that allows an objective
assessment for organization and implementation of an area oriented approach. The model supports the financial
consideration in decisions about multiannual AOA both in the planning phase and during transfer to the management
phase.
This application was developed by a consortium of organizations under SKB project PP 5304. Extension of the model for
AOA was developed by Interreg IVB NWE CityChlor. Technical realization: Valid Ware
The Cost Calculation Model: AOA provides a standard to assist in an objective consideration of the costs for an Area
oriented Approach. The model assists the financial consideration in decisions about AOA locations, both in planning
phase and during transfer to management phase. Besides the import of regular cost the model also includes a method
on how to deal with financial windfalls or setbacks in decision making.
AgencyNL and its Dutch partner the Municipality of Utrecht participate in the European CityChlor project, operating under
the INTERREG IV B program for Northwest Europe. The Utrecht remediation approach for an AOA – the
“Biowasmachine” – is a pilot in this CityChlor project. From this position the initiative for a cost calculation model is
initiated as a part of the “Socio economic” work package; giving financial preconditions for a AOA and support to design
and implementation phase of an AOA approach.
The report “Cost Calculation Model Area Oriented Approach - tool for financial management” can be used as an
introduction for new users of the model. The scope of this report is to give a short presentation the CCM: AOA and
background readings to the building process of the model.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 3
Table of content
Summary .................................................................................................................................... 2
Table of content ......................................................................................................................... 3
1 Introduction ........................................................................................................................ 5
1.1 Background ................................................................................................................. 5
1.2 Objective ..................................................................................................................... 5
1.3 Execution .................................................................................................................... 6
1.4 Description of the application ...................................................................................... 6
1.5 Version history ............................................................................................................ 7
1.6 Manual contents ......................................................................................................... 7
2 Initial familiarisation ........................................................................................................... 8
2.1 Introduction ................................................................................................................. 8
2.2 Installation .................................................................................................................. 8
2.3 Select application language ....................................................................................... 8
2.4 Let's get started .......................................................................................................... 8
2.5 Making changes ....................................................................................................... 10
2.6 Adding and deleting ................................................................................................. 10
2.7 Reports ..................................................................................................................... 11
2.8 Important guidance for use ...................................................................................... 11
3 Installation and data management .................................................................................. 12
3.1 System requirements ............................................................................................... 12
3.2 Installation ................................................................................................................ 12
3.3 Data storage and exchange ..................................................................................... 12
4 Program manual .............................................................................................................. 14
4.1 Opening an estimate ................................................................................................ 14
4.2 Creating an estimate ................................................................................................ 15
4.2.1 Create new estimate .......................................................................................... 15
4.2.2 Explanation of the main screen .......................................................................... 16
4.2.3 Objects ............................................................................................................... 16
4.2.4 Costs structure sub-screen ................................................................................ 17
4.2.4.1 General ............................................................................................................... 17
4.2.4.2 Tree structure menu options .............................................................................. 18
4.2.4.3 Copy and paste actions ...................................................................................... 18
4.2.5 Costs list sub-screen ...................................................................................... 18
4.2.5.1 General ............................................................................................................... 18
4.2.5.2 Assessing the net present value ........................................................................ 19
4.2.5.3 Alternative display .............................................................................................. 19
4.2.6 Detail information sub-screen ............................................................................. 20
4.2.6.1 General ............................................................................................................... 20
4.2.6.2 Estimate details screen ...................................................................................... 20
4.2.6.3 Cost group details screen ................................................................................... 21
4.2.6.4 General settings details screen .......................................................................... 22
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 4
4.2.6.5 Financial settings details screen ........................................................................ 23
4.2.6.6 Phasing settings details screen .......................................................................... 24
4.2.6.7 Cost item details screen ..................................................................................... 25
4.2.6.8 Aggregation item details screen ......................................................................... 28
4.2.6.9 Risk/financial windfall details screen .................................................................. 29
4.3 Basic key figures ...................................................................................................... 30
4.3.1 General ............................................................................................................... 30
4.3.2 Creating lists of basic key figures ....................................................................... 31
4.3.3 Application of basic key figures .......................................................................... 32
4.3.4 File management ................................................................................................ 33
4.4 Calculation and reporting ......................................................................................... 35
4.4.1 Calculation of Net present value: ....................................................................... 35
4.4.2 Reports ............................................................................................................... 35
4.5 Sensitivity analysis ................................................................................................... 36
4.5.1 General ............................................................................................................... 36
4.5.2 Setting sensitivity analysis parameters .............................................................. 36
4.5.3 Interpretation of the results of the sensitivity analysis.......................... 37
4.6 Multilingual estimates ............................................................................................... 38
4.6.1 Introduction ......................................................................................................... 38
4.6.2 Choice of the language to be used..................................................................... 38
4.6.3 Multilingual input during set-up ........................................................................... 39
4.6.4 Input a translation retrospectively....................................................................... 39
4.6.5 Selection of the language that is currently active ............................................... 40
5 Account ............................................................................................................................ 41
Appendix 1 Risks and financial windfalls ............................................................................ 42
Appendix 2 Risks : example and check list ......................................................................... 47
Appendix 3 Calculation of NPV ........................................................................................... 49
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 5
1 Introduction
1.1 Background
The CCM: AOA is a standardized method that allows an objective assessment for organization and implementation
of an area oriented approach. The model supports the financial consideration in decisions about multiannual AOA
both in the planning phase and during transfer to the management phase.
This application was developed by a consortium of organizations under SKB project PP 5304. Extension of the
model for AOA was developed by Interreg IVB NWE CityChlor. Technical realization: Valid Ware
As a result of the developments in the soil policy in recent years in the Netherlands, contamination is remaining in
the soil for longer and more residual contamination is being left behind following remediation. The scope of the
(after) care task is thus expanding. Modification to the Soil Protection Act means than aftercare is now also better
embedded in legislation as a result of which the aftercare/management task is better safeguarded.
A often recurring stumbling block with respect to aftercare/management/management is the need for good cost
estimates and any potential financial risks. There is no standard and broadly supported method of determining and
quantifying the (after) care costs and risks of soil remediation. However various models have been developed on an
ad hoc basis (mostly for own use and also partly for other types of for aftercare/management/management, each
with its own method, set up and specific objective as well as specific flaws.
The absence of an effective and broadly supported costs and risks model results in inaccurate and unreliable
estimates (they can too low as well as too high) of and discussions regarding the aftercare/management costs.
Possible consequences in practice include: a wrong variant is selected in the evaluation phase of the remediation
process, difficult takeover procedure from aftercare/management locations because uncertainty is translated into
(probably too) high premiums, problems in budgeting operating costs and stagnation on projects/developments.
In short; a standard calculation model will mark a major step forward in safeguarding the continuity and quality of
soil remediation aftercare/management.
1.2 Objective
The objective of the SKB project 'Area Oriented Approach Cost Calculation Model (AOA:CCM') is to create a widely
supported and freely available calculation model for the aftercare/management costs of soil remediation sites. The
calculation model could set a solid financial basis for aftercare/management and enable soil quality processes to
be further optimised.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 6
1.3 Execution
This initiative has been executed as SKB Project PP5304. Various organisations have come together to form a
consortium to help to finance and execute the project:
Public Works Department (Gemeentewerken) Rotterdam – Pipeworks and underground management
department (Leidingenbureau en Beheer ondergrond) (main contractor)
Grontmij Nederland BV
Public Works Department Engineering Agency (Ingenieursbureau Gemeentewerken Rotterdam)
Rotterdam Development Agency (Ontwikkelingsbedrijf Rotterdam)
Province of Zuid-Holland aftercare/management agency
Province of Utrecht
Limburg aftercare/management (Nazorg/beheer Limburg)
SBNS
Municipality of Dordrecht
A&G milieutechniek
DCMR Environmental Protection Agency
Soil+
As part of an exploration and definition phase, a quick scan was carried out of the existing relevant information
while the consortium determined the required functionalities during brainstorm sessions. Next, they selected which
calculation modules should be built.
In the research and construction phase, the necessary information was collated and the calculation modules were
created in a software application.
1.4 Description of the application
The AOA:CCM calculation model creates a standard to support objective consideration of aftercare/management
variables. The model helps with financial considerations with respect to decisions concerning
aftercare/management sites both during the planning phase and when handing over to the management phase.
The model also includes an approach for dealing with setbacks/windfalls in financial decision-making.
The model is designed to develop both simple as well as complex estimates/budgets. While in principle focused on
use for 'genuine' aftercare/management locations, the model could also be used for former landfill aftercare or
industrial area soil remediation locations, for example.
As well as the input of standard cost items, the application also supports the input of risks and financial windfalls.
For recording and quantifying risks to be entered in the application, please see paragraph 4.2.6.9.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 7
1.5 Version history
Version 1 was the original release of the application (2010). This was followed by two bug fix releases in 2011.
Version 2 included extensions to make the software suitable for international use. In addition to the existing Dutch
user interface, an English version has been made available. Furthermore, users can now input estimates in four
languages (Dutch, English, German, French)
A more detailed description of the application version history can be found on the AOA:CCM website.
Since version 2, the application has been called:
Dutch: Rekenmodel Nazorg/beheer en Beheer (abbreviated as: RNB)
English: Cost Calculation Model: Area Oriented Approach (abbreviated as: CCM AOA)
The set-up of version 2 includes two standard estimates for area oriented groundwater management: a short and
an extended version. These two estimates are available in two languages (English and Dutch). They can also be
downloaded separately from http://www.citychlor.eu/sites/default/files/installer_2.0_english.zip
The following versions of the manual have been published:
Version 1.0 is the version supplied with application version 1.0.
Version 2.0 is (this) version which is supplied with application version 2.0. It is available in both Dutch and English.
1.6 Manual contents
The follow-up to this manual deals with each of the following subjects in order. Chapter 2 is a familiarisation with the
application so that you can get started quickly. Chapter 3 explains how to install the application and proposes how
the manage the data (basic key figures and estimates). In chapter 4 there is a detailed look at all the application's
functionalities.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 8
2 Initial familiarisation
2.1 Introduction
The aim of this chapter is to help you get started working with the software quickly. You will find a more detailed
description in chapter 4.
Broadly speaking, working with the application comes down to the following:
Opening an existing or new estimate;
Adding/editing cost items;
Reporting to Excel.
2.2 Installation
The software first needs to be installed. In the majority of organisations, user rights for doing this are restricted and you
will need to contact your systems administrator. The installation procedure is described in more detail in paragraph
3.2.
2.3 Select application language
You can select the application language to be used. The application language determines the standard text on
buttons, screen, reporting windows etc.
The latest version supports the English and Dutch languages.
You can change the application language at any time by using the ‘App. language' button in the toolbar. If you
change the application language, the application will be restarted.
2.4 Let's get started
The installation procedure creates quick links in your start-up menu and on your desktop. You can start the application
by double clicking on the quick link.
After starting the application, the first screen you will see is ‘Estimates file management’. This shows the various
estimate projects which are available in the estimates file to which there is a link at the top of this screen. Two
standard estimates are provided during installation.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 9
The screen shows which language the estimate was input in using flag icons.
Select the estimate you want and click on 'Open'.
The estimate will be uploaded and displayed in the application main screen:
To become familiar with this screen, click on something in the costs structure on the left. Detailed information for the
elements you have clicked in the costs structure is displayed in the sub-screen on the bottom right.
Click on an item for each element type (indicated by the various icons) and view the detailed information.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 10
2.5 Making changes
In this paragraph, we are going to make a change.
Click on the top item ('Sample estimate 1').
Enter something in the comments field. The save button will now be activated.
Click on this save button (or: use Ctrl+S) to save your change.
This system is used in every details screen.
Try to make a change to another item, for example a cost item (indicated by the icon ).
2.6 Adding and deleting
You can add and delete by right clicking on the costs structure menu. For
example, right click on the 'Manage' costs group. The menu will open.
We can now select 'Add cost item' for example.
In the cost item details screen, you can enter the name of the cost item
and the properties such as frequency, amount etc.
You can delete via the 'delete' option from the right-hand mouse button
menu.
Also explore the other options under the right-hand mouse button menu.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 11
2.7 Reports
You can export your estimate to Excel by using the report button in the
main menu. Click on this button. You will now see a window where you
can enter certain specifications. For now, you can use the standard
settings.
Click on ‘OK’. The application will now export the estimate to Excel.
The Excel report will display a table showing the calculation on the net
present value (NPV) and of the estimate.
So you have now had a brief view of how the application works. We
have looked at the application only in broad terms. You can find a full
description of the functionalities in chapter 4.
2.8 Important guidance for use
Although the model offers flexibility in terms of retrospectively move cost items, create a new type of classifications or
apply other changes to structure, it is advisable - particularly in the case of larger projects - to think about:
logical and consistent classification into cost groups (see paragraph 4.2.6.3). For example, you can classify
by type of activity (maintenance, inspection, replacement), by the type of facility (groundwater extraction
system, cover sealing), by sub-sector, etc. Consistent classification provides you with a solid overview during
operations and the same for readers of the Excel reports that will be generated.
phasing (see paragraph) 4.2.6.6). The use of 'phasing settings' is not mandatory but it is recommended. If
you input one or more phasing settings you will add structure to the 'time' factor and save on inputting time.
This is explained further in paragraph 4.2.6.6.
Another important observation concerns the security of the data you have input. The application saves what you have
input in databases. You can choose the file location where you want to save databases and you can apply different
principles (see paragraph 3.3 for further explanation).
In this paragraph, you are advised that the file location you select should be included in your network's daily back-up.
We strongly advise that you should not place databases on a local hard drive.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 12
3 Installation and data management
3.1 System requirements
The application works on the Windows XP, Windows Vista, Windows 7 and Windows 8 operating systems and uses
Microsoft.NET Framework version 3.5. Depending on the Windows installation history on your computer, this will
already be installed or will be installed as part of the software installation process. To save data, the program uses
Microsoft SQL Server Compact Edition. This (free) package is also installed during the installation process.
3.2 Installation
The software can be downloaded from http://www.citychlor.eu/sites/default/files/installer_2.0_english.zip
Download and unzip the file: installer 2.0 english.zip
From the unzipped files use the standard msi installer.
During installation, a quick link is created on your desktop and in the start menu (Programs Validware AOA:CCM
calculation model).
3.3 Data storage and exchange
The structure of the calculation model is shown in the figure below.
The application includes the user screens and the program code for calculations/operations. The data (details you
have input and basic key figures) are saved separately in databases. There is a database for the estimates (file
extension .rnbR) and for key figures (file extension .rnbK). The databases are of the type Microsoft SQL Server
Compact Edition.
Application
Data file estimates
(*.rnbR)
Data file key
figures
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 13
The arrows in the diagram show that the databases can be linked to the calculation model application. In the
application, you can indicate which estimates database and which key figures database you want to link to, similar to
how you would open a spreadsheet in Microsoft Excel or a Word file in Word.
The application does not dictate where you must locate the estimates and key figures databases. However it is
recommended that you agree strategy in this respect within your organisation/with your colleagues.
Possible strategies for data storage:
1. Fully centralised
All estimates are saved in a single estimates database on the network. All key figures are saved in a single
key figures database on the network. All the users within an organisation use the same databases
2. Semi-centralised
In this version, an estimates database is used per estimate/location. The subsequent estimates databases
are saved in separate project directories. The key figures database is saved centrally so that all users use the
same key figures.
3. Fully centralised
All estimates databases and key figures databases are created per user per project.
4. Per user
Every user uses his own estimate databases and key figures databases.
Other strategies are also possible. Every organisation can select its own policy. Estimates databases can be linked in
the same way as you would save Word and Excel files, for example. Key figures databases can be linked in in the
same way as you handle standard documents, templates etc.
In any case, it is recommended that you place the databases on the network and not on a locale PC for the following
reasons:
If the databases are on the network, they will be included in the daily back-up. In the case of disaster, you can then get
your system administrator to restore a backup.
If you are working from a different PC, you can also connect to the files.
The sdf files can be exchanged between users in the same way as you are able to exchange Word and Excel files.
An import function has also been implemented in the application to allow estimates or lists of basic key figures to be
imported from another sdf filed in the linked sdf file.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 14
4 Program manual
4.1 Opening an estimate
When you start the application, the 'Manage estimates' screen will be opened, see figure below. This shows the
estimates from the database to which the application is linked (see paragraph 3.3). The estimates are indicated by
their name and one or more flag icons which show which language the estimates were entered in.
If the application is not able to establish the database it needs to link to, you will be given the option to select a
database.
Use the 'change…' button to link to a different database. You can do this only if you have not yet opened an estimate.
Use the 'new…' button to create a new database and save it in the file location of your choice.
The buttons beneath the screen have the following functions:
Delete: delete the estimate selected; this cannot be undone;
New: Create a new estimate which will then be displayed in the main screen (see paragraph 4.2.2);
Cancel: the screen is closed with no further action;
Open: the estimate selected is opened in the main screen;
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 15
If you click on the 'exchange' button you can link to a second database, the so-called 'exchange database'.
See the figure below. You can select an exchange database of your choice. Use the '>>' and '<<' buttons to copy
estimates from one file to another.
The exchange databases are full databases. You can use an exchange database as an archive or backup, but as a
means of e-mailing multiple estimates to another user of the AOA:CCM application.
4.2 Creating an estimate
4.2.1 Create new estimate To make the application accessible to beginners, a distinction is made
between simple and complex estimates.
A number of functionalities are available only for 'complex' estimates. These
functionalities relate to:
Phasing;
Aggregation items;
Sensitivity analysis;
Price level correction;
You can change an estimate from simple to complex at any time. However
you cannot change an estimate from complex to simple.
You need to provide a name of the estimate and the price level in which you want to enter the prices.
When you click on OK, the main screen will be displayed in which you can further populate the estimate which has
been created.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 16
4.2.2 Explanation of the main screen The main screen is shown in the figure below:
The main screen comprises 3 parts:
left: sub-screen with costs structure shown hierarchically;
top right: sub-screen with the costs list;
bottom right: sub-screen with detail information.
The size of the sub-screens can be changed by dragging the vertical and horizontal borders between the sub-screens.
4.2.3 Objects The model assumes a hierarchical allocation of cost items into cost groups. Cost items and cost groups are the two
most important objects in the model.
The overview below provides a complete summary of all the model objects:
General settings: settings and data which provide information to the user but which do not influence the calculation result. See paragraph 4.2.6.4.
Financial settings: settings and data which apply to all cost items in an estimate and which relate to the calculation method/parameters of the net present value calculation. See paragraph 4.2.6.5.
Cost group: a group of associated cost items. See paragraph 4.2.6.3.
Estimate. An estimate is the cost group at the highest level in the hierarchy. An estimate is a cost group which has only child but no parent cost groups.
Cost item. An activity/facility with which costs are associated. See paragraph 4.2.6.7. If the amount or the
Cost structure Cost list
Detailed information
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 17
frequency of a cost item changes over time, this is a phased cost item ( ).
Risk/financial windfall: an item entered as a net present value.
Aggregation item (only for 'complex' estimates: a cost item whose value is calculated from the value of the other cost items within the same cost group. One example of this is the item 'Unforeseen', the value of which is equivalent to 10% of the value of a number of other cost items. For more detailed explanation, see paragraph 4.2.6.8.
Phasing settings (only for 'complex' estimates): settings which apply to phased cost items ( ). See paragraph 4.2.6.6.
4.2.4 Costs structure sub-screen
4.2.4.1 General The costs structure sub-screen is on the left and shows the hierarchy of the cost groups and child cost items. It gives a
complete overview of all the objects that are present. By clicking on the plus and minus buttons you can expand and
collapse a cost group. If you left click on the name of a item,the other two sub-screens will be activated with the
information that belongs to the item selected.
Right clicking on an item from the tree structure opens a menu with the actions which may be performed. See the
example below.
The options are explained in the following section.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 18
4.2.4.2 Tree structure menu options
The following options are available:
Expand all child nodes
Collapse all child nodes
Open current estimate. This opens an estimate from the active database. Multiple estimates can be shown at the same time in the tree structure.
Add new estimate. This adds a new estimate to the active database.
Add cost group to the selected cost group
Add cost group to the selected cost group Shortcut key: Ctrl+N
Risk/add financial windfall to the selected cost group
Copy the selected item. See explanation in paragraph 4.2.4.3
Paste the item that is in the copy buffer. See explanation in paragraph 4.2.4.3
Delete the selected item. All child items in the hierarchy are automatically deleted.
Add aggregation item to the selected cost group (only for 'complex' estimates)
Add phasing settings to the selected cost group (only for 'complex' estimates)
Close the estimate.
The options which are active depend on the item you have right-clicked on.
4.2.4.3 Copy and paste actions The application supports the copying and pasting of objects in the tree structure. However there are limitations to
some actions. For example, phased cost items cannot be copied to a cost group where other phasing settings apply. If
specific actions are not permitted, the options in the menu will be deactivated (grey coloured) or if you try to perform
the action a message will be displayed showing more information.
4.2.5 Costs list sub-screen
4.2.5.1 General This sub-screen is found to the top right. The aim of this screen is to provide an overview of the most important
properties (start year, end year, costs) of all the cost items in the cost group selected. This screen cannot be edited.
Each un-phased cost items occupies one row in this screen. If a cost group is phased, each phase occupies a row.
The detailed information is displayed for each row along with the calculated (or in the case of a risk/financial windfall:
the input) net present value. Finally, the 'Check' column indicates whether the net current value calculation has been
successfully completed.
If you click on a row in this sub-screen, the item in question will also be selected in the costs structure sub-screen (on
the left in the image). The item will also be displayed in the detail information sub-screen (in the bottom right of the
image). If you select an un-phased cost item, the 'details' tab will be displayed. If you select a phase from a phased
cost item, the tab associated with the phase in question will be displayed.
Double clicking on a cost group in this sub-screen enables you to 'enter' the costs groups so that the child cost items
are displayed.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 19
4.2.5.2 Assessing the net present value The net present value (NPV) is the capitalised value of (on or multiple) expenditure items. The method of calculating
the NPV is explained in appendix 3.
The NPV of the item displayed has been calculated.
The NPV of the item displayed has not been calculated.
This assessment is recursive and pessimistic.
Recursive means that it relates to the item displayed and, if it relates to a cost group, all the child items, as well as the
items below these, etcetera.
Pessimistic means that if all the child items in a cost group except one have the result then the cost group will have
the result .
In other words: if somewhere deep in the hierarchy, one cost item shows an error when determining the NPV, then at
the estimate level ( ) the result will also be . Therefore the estimate is not suitable for a formal report if at the
estimate level, the result is .
4.2.5.3 Alternative display Checking 'sort by NPV' and 'show child cost items' allows different costs list displays to be set.
Sort by NPV
The cost items are displayed as standard in the same order as in the costs structure on the left of the image. However
you can request a different order of sorting by selecting the 'sort by NPV' check box.
If you check this box, the cost items will be sorted in descending order according to net current value (NPV). This
enables you to see at a glance which cost items are determinative.
Show child cost groups
As standard, cost groups are also included in the costs list. You can double click on a cost group to 'go into' it.
However in some cases, it may be more transparent to view all the child cost items in the costs list without having to
click through to child cost groups. You can do this by using the 'show child cost items' box. If you have selected the
highest level (the estimate ) in the costs structure and selected the option 'show child cost items', the costs list will
display all the cost items from the whole estimate.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 20
4.2.6 Detail information sub-screen
4.2.6.1 General The sub-screen showing detail information is at the bottom right of the image and shows, depending on the type of
object (see paragraph 4.2.3) a different screen. The details screen displays all the data for a single object and is also
where changes can be made.
To the top right of the details screen is the menu bar with the following buttons:
Undo changes to an item. Shortcut key: Ctrl+Z
Save changes to the item. Shortcut key: Ctrl+S
Copy the item
Delete the selected item.
If the screen is in 'read mode' (the standard mode), the and buttons are activated whereas the and
buttons are deactivated. Once the screen is in 'change mode' (because you have started to make a change), the
situation is reversed.
If the screen is in 'change mode', you must first click on or before you can select another item.
Tip to make your work easier
It is recommended that you use the available shortcut keys:
- use Ctrl+Z instead of the button
- use Ctrl+S instead of the button
- use Ctrl+N to create a new cost item.
The paragraphs below look at the details screen for each object.
4.2.6.2 Estimate details screen The estimate is the highest level in the
costs structure. See figure. In addition to
the name of the estimate and any
comments, you can change the estimate
type from simple to complex in the details
screen. This change cannot be undone.
Simple estimates can be changed to
'complex' but not the other way round.
Since version 2.0 of the application, this screen includes the functionalities which relate to the multilingual character of
an estimate.
Via the 'Current language' pull down box, you can set which translation you want to see displayed on the screen at the
current moment.
Use the 'language selection' link to indicate which languages you want to input your estimate in.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 21
Use the 'open translation form' to view and update all the multilingual texts available in the estimate. We look at this in
more detail in paragraph 4.6.
You can also manage the locking of an estimate in this details screen. A locked estimate cannot be edited. You can
use locking to, for example, 'close off' a final estimate, or to e-mail an estimate file to third parties who are permitted to
view the estimate but not to make changes to it.
Locking: To lock an estimate, you must enter a password.
After locking, the program uploads the estimate again. The details screen displays the symbol and the input boxes
and button can no longer be used until the estimate is unlocked again.
Unlocking:
When unlocking, you can choose between two options.
Unlock session: the unlock is effective for as long as you are working on the estimate but as soon as the
estimate is closed and re-opened, it will be locked again.
Permanently delete unlock: the password is erased and the estimated can again be modified by anybody.
4.2.6.3 Cost group details screen A cost group may form part of a parent cost group and in turn have its own child cost groups. The aim of cost groups is
to give structure and transparency to the estimate, just as chapters and paragraphs do for a text. You can determine
the structure to be applied yourself.
Some examples of grouping:
by the nature of the physical facility ('Cover sealing', 'Groundwater extraction', 'Monitoring well measurement
network', etc.);
by provider/responsible body ('Contractor X', 'Agency Y', etc.);
by cost item type ('Replacements'”, 'Maintenance', 'Monitoring', etc.);
in accordance with the classification of headings in the remediation plan/specifications/aftercare/management
document;
by geography ('Segment A', 'Segment B', etc.).
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 22
See the figure below. In this screen, you enter the name of the cost group and any comments.
4.2.6.4 General settings details screen In this screen, you enter general details. Some details are pre-defined (location name, Globis code (Dutch), etc.) and
you can also enter your own data. See the figure below.
Participants
Use the button to create tabs to add participant details. A participant can be an organisation or an individual who
plays a role in the estimate. For example municipal authority/province/consultancy/residents' representative groups,
etc.
A participant tab looks like this:
The role that you enter in the top input field becomes the title of the tab.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 23
4.2.6.5 Financial settings details screen In this screen, you enter the calculation parameters needed to calculate the NPV. See the figure below.
At the top of the screen, you enter the interest rate to be used for the capitalisation calculation.
Below this is the price level of the amounts which you enter under the cost items. You can now change the price level
by using the 'Change' button (only for 'complex' estimates).
The NPV calculation will be performed with effect from the calendar year which you enter under
'aftercare/management start year'. If you have defined cost items which begin prior to this year, the NPV calculation
will use only the incidents of expenditure which fall in the years from the 'aftercare/management start year'.
The inflation percentages are used for:
discounting of the inflation effect in the capitalisation calculation
adjusting the price level of an estimate (using the 'Change…' button);
converting basic key figure amounts which are applied to estimates with a different price level than the list of basic key
figures.
If you assume constant inflation when performing the calculation, one row will be sufficient. As
standard, the application enters an inflation percentage of 2%, applicable from 1 January 1980.
Price level change (only for 'complex' estimates)
If you press the 'Change…' button under the 'Price level' section, the following screen will be displayed:
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 24
Here, you can indicate what the new price level/year should be. If you have already entered cost items in the budget in
question, you can adjust the amounts in these cost items to the new price level. Checking the 'Correct amounts
already entered' option means that existing amounts are adjusted by the correction factor shown. The correction factor
is calculated on the basis of the inflation percentages you have entered. For display on the screen, the factor is shown
with maximum 4 decimal points.
Notes with regard to changing the price level;
1 The price level correction changes all amounts entered by the correction factor given. This update cannot
be undone. It is advisable to create a backup of the of the estimate before performing such an update;
2 The price level correction cannot be performed on items of the type 'Risk/financial windfall'. Given that the
interest/inflation effect is discounted in these amounts, you need to check for yourself whether they need to
be (manually) adjusted. In such cases, the application gives you a reminder via a notice on the progress
screen.
3 The formulae which you have entered in the aggregation items include possible numerical values which are
related to a price level (although this is best avoided). If the price level is changed, the application indicates
a that you must check whether the adjustment or the formula is necessary.
4.2.6.6 Phasing settings details screen This screen is available only for 'complex' estimates.
A phasing setting can be entered per cost group. The setting applies to all cost items in that group. If no phasing
setting has been created in a cost group, the phasing setting from the cost group above will be applied. If your entire
estimate is based on the same phasing, you need to create a phasing setting only at the estimate level ( ).
Use of the phasing functionality is not mandatory. An estimate can also be created without this functionality. However
working with phasing brings the following added value:
Explicit designation of dynamics:
In more complex remediation cases, the activities generally change over time. For example groundwater
remediation is completed within a number of years, or a location gets another use over time. Making explicit
reference in the estimate to these changes over time provides a clearer relationship between the concrete
remediation act and the estimate.
This offers the following benefits:
o While inputting the estimate in the application: if there is a time dynamic this generally has an effect
on multiple cost items. By anchoring the dynamic in a phasing setting, you will encourage the
originator to think about which cost items change over time in the same way when inputting the cost
items.
o In the report (print-out) it is clearer when what happens because a specified time span is easier to
interpret than a litany of separate years.
Simplified updating of the estimate:
Because the 'time' aspect is not entered separately for every cost item, but only in a few places (the phasing
settings) the time dynamic can be changed quickly in the interim. Imagine that after one year's groundwater
remediation, it emerges that the targeted final objective can be achieved sooner, the duration only needs to
be modified in one place in the estimate, i.e. in a 'groundwater remediation' phase. All the cost items related
to this phase are thus updated automatically.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 25
Simpler variants analysis:
Connects to the previous point. If multiple variables need to be compared on costs, it is easier if the onus of
inputting is kept to a minimum for comparing variables. Variable in the 'time' aspect can be compared more
quickly when working with phasing settings.
A phasing settings has three options (see the screenshot above)
'There is no phasing ': this option means that the cost items in this group cannot/may not be phased;
'Use phasing from parent cost group'. This is implicitly also the setting used if you do not create a phasing
setting in a cost group.
'The following phasing applies'. With this option, you can enter a series of phases used in this cost group. Per
phase you enter:
o The name of the phase;
o The duration of the phase in years. If the final phase is perpetual, you can enter '-1' there.
The table displays the following information (not editable)
'From-to': This is the timespan of the phase calculated on the basis of the 'financial settings' on the screen
(see paragraph 4.2.6.5) 'start of aftercare/management' year entered;
'applied'. This indicates at how many points in your estimate a cost item refers to this phase. Phases applied
once or more in a cost items may not be deleted.
You can change the order of the phases by using the arrow buttons ( and ) to the right of the table. You can
delete the phases by using the and buttons.
4.2.6.7 Cost item details screen This details screen is where you enter the properties of the cost items used in the NPV calculation.
An example of a cost items is 'monitoring observation wells', [replacement of dam wall', or 'inspection of top layer'.
Characteristics of cost items in the calculation model are that they have a start year, end year, a fee and a specific
frequency of repetition.
Cost items may change over time: these are phased cost items. One example of this is 'monitoring groundwater
quality' which is intensive during the first 15 years and then becomes more extensive, for example.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 26
Tab 1: General
See the figure below.
Under this tab, you enter:
The name of the cost item;
The concurrence percentage. There is concurrence if a cost item is fully paid for within your estimate. For
example, if your estimate includes costs for a top layer construction where it is agreed that 45% will be
financed by the municipal authority in the context of redevelopment plans (and therefore does not need to be
paid for out of the remediation/aftercare/management budget for which you are creating an estimate), you will
enter '45%' here.
o 0% means: no concurrence: the costs are fully met by this estimate. This is the standard setting;
o 100% means: the costs are not charged to this estimate. You can complete this if you want to
include a specific cost item for the sake of completeness, although the costs de facto do not need to
be included.
Or if this is a phased cost item. It it is: you need to indicate which phases this cost item applies to. This option
is available only for 'complex' estimates.
An explanatory comment. You can provide an explanation of the content or refer to a source document
(remediation plan/aftercare/management plan/specifications)
Depending on whether you indicate in this tab that the cost item is phased, one or more of the following tabs will be
displayed.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 27
Tab 2: Details of the cost item (un-phased)
If the cost item is un-phased, the tab will be laid out as per the figure below.
Under this tab, you enter:
The frequency, i.e. how often the cost item occurs
The costs each time there is expenditure on this cost item.
The start year in which this cost item will first play a role. Here, you can choose to enter the start year as a
calendar year or as the year of the start of the aftercare/management (start year of the NPV calculation).
Aftercare/management year 1 is the first year of the aftercare/management phase.
The end year. This is the last year in which the cost item occurs. In addition to the options
aftercare/management year/calendar year, here you are also given the option to indicate the end year
(perpetual).
One comment.
The 'Basic key figure' box is dealt with further under working with basic key figures, see paragraph 4.3.3.
Tab 2 and beyond: Details of a cost item (phased cost items)
Several tabs are available only for phased cost items under 'complex' estimates.
If the cost item is phased, a tab will be displayed for each phase which you have checked under the 'General' tab. See
the figure below.
For each 'phase tab', you enter the frequency and the costs per occurrence. You do not need to enter the start and
end year which come from the duration of the phases.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 28
4.2.6.8 Aggregation item details screen An aggregation item is a cost item which is determined via arithmetic processing of other cost items. The aggregation
items re in particular designed to create allowances per cost group on the sub-total of the cost group. Examples:
Definition of the item 'unforeseen' of which the amount is a percentage of the sum of a number of other cost
items;
Definition of general costs (insurance, supervision) as a percentage of the sub-total.
Definition of the costs of management, design etc.
See the screen below. In that example, an aggregation item is used to define an 'Unforeseen' item. The cost item is
derived by adding together a number of costs and multiplying the total by 0.10.
A formula editor is implemented in this screen. You can use the following algebraic operators: + - / * and then use of
real figures (negative and positive whole values and decimal values). The use of brackets is permitted.
Method:
In the 'Available cost items' option list you will see the cost items in the current cost group. These are the cost items
you can select from when creating an aggregation formula. You can include a cost item in the formula as follows:
Double click on the cost item in the option list. The cost item is entered in the formula editor at the position of
the cursor;
Click on the cost item and then press the button. The cost item is entered in the formula editor at the
position of the cursor;
Click on the cost item then right click in the right-hand window on the position where you want to enter the
cost item.
In addition to the individual cost items, there is an option 'ALL COST ITEMS IN THIS COST GROUP'. With this option,
you can quickly make updates to the sum of all cost item. Only standard cost items are included in this. Risks/windfalls
and other aggregation items are not included.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 29
The use of tabs, enters and spaces is recommended to increase legibility of the formulae.
It is recommended that you do not use prices or price level-dependent values in aggregation formulae to avoid having
to update the formula if the price level changes (see paragraph 4.2.6.5).
When you save the cost item, the bar below the formula editor indicates whether the formula contains any errors.
View costings
If you click on the 'view costings' button,the
screen below is displayed.
The aim of this screen is to give you insight into
the way in which the model calculates the
annual costs for an aggregation item over the
whole aftercare/management period. Because
the various cost items to which the aggregation
item formulae refers may have different start
and end years, the aggregation item may have
different values in different years.
You indicate an aftercare start/management
end year and the number of years you want
insight into in the calculation. You then click on
'Show calculations'. The application displays your formula (with the same spacing, line breaks etc.) and instead of the
name of the cost items, the number of euros applicable in the year in question.
4.2.6.9 Risk/financial windfall details screen In this screen, (already capitalised) values for risks/financial windfalls can be entered.
When determining the risk costs, the roadmap in appendix 1 can be used. The roadmap includes a chart in which the
risks can be classified. For outcomes of two types of risk (squares II and III) can be processed in the model.
For the risks in square II, a cost item risk allowance can be added to the relevant risk item. Another option is to add an
aggregation item (see paragraph 4.2.6.8).
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 30
In addition to the overview provided by appendix 1, appendix 2 includes a sample calculation and a check list which
may help when determining the risk amounts to be entered in the application. The probability and cost savings for
financial windfalls can be entered per event in the same way as the risk costs calculation. An example is included in
appendix 2. This item must be entered as a negative number (negative costs = revenue).
NB: when entering a capitalised amount always ensure that the capitalised amount is calculated with the same
parameters (interest, inflation, aftercare/management start year) as you entered under the 'Financial settings' tab.
4.3 Basic key figures
4.3.1 General The screen for maintaining the basic key figures is opened using the 'Basic key figures' button. See the figure below.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 31
Basic key figures are your archive of values for frequencies, life spans and prices of cost items. The aim of the basic
key figures functionality is:
To be able to put together an estimate in a shorter time.
Because the application can make direction use of a list of prices, life spans and, you can create cost items
quickly;
Grouping of knowledge/experience. If employees within your organisation use the same key figures file (see
paragraph 3.3), the knowledge/experience accumulated by employees is made accessible to other
employees in various estimates.
Encouraging standardisation of prices, frequencies and life spans in estimated created by your organisation.
The use of basic key figures is an optional functionality. Estimates can also be created without using basic key figures.
When the calculation model is launched, a list of basic key figures is provided which is derived from the IPO check list
for landfill sites (source: www.nazorg/beheerstortplaatsen.nl).
This list cannot be edited. The lists created by users can be edited.
4.3.2 Creating lists of basic key figures The way of changing basic key figures is comparable with changing an estimate.
Just as costs are accommodated in cost groups, basic key figures are also accommodated in groups. The following
model objects and their symbols play a role:
/
List of basic key figures, editable/uneditable
Basic key figures group, designed to bring order to the basic key figures
/
Basic key figure, editable/uneditable
A list of basic key figures is always found in a specific price level. This price level applies to all minimum and maximum
prices in the list in question.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 32
Each basic key figure is characterised by 4 variables which ultimately determine the NPV value, i.e.:
frequency;
costs per occurrence
start year;
end year.
These variables are entered as bandwidth, i.e. with a minimum and maximum value or a total of 8 variables.
It is not compulsory to enter all these 8 variables for every figure. By checking or unchecking the check box next to the
name of the variable, you can indicate whether the variable applies.
For example if you want to enter basic key figures for life spans of vertical dam walls, you will probably use only the
frequency (e.g. 1x every 75 years).
However it is recommended that you include as much information as possible per basic figure.
For example a value for 'lifespan' is not very informative from a costs perspective if it is not clear what the replacement
operation will cost.
This is especially the case because 'frequency' and 'costs per occurrence' in particular are usually logically connected.
have a longer lifespan but will also have higher costs per occurrence than equipment with a shorter lifespan.
So although the model allows you to input, for example, only life spans (replacement frequencies), it also possible to
attach other variables which determine costs, such as frequency, where such information is desirable and available.
If you enter figures for costs, you must do this in the list of basic key figures price level.
It is compulsory to enter the scope of application/limiting conditions before using the figure. For example if you give a
figure for the lifespan of an observation well and the observation well material is not resistant to specific chemicals, this
is relevant information which must be reported.
4.3.3 Application of basic key figures There are two functionalities built into the application for application of the basic key figures.
1 Drag basic key figures
In the basic key figures screen in the tree structure, you can select a figure and drag it to an item in the tree
structure of the screen with cost items.
1.1 Drag to cost item: If you drag the item to an existing cost item the figure's values are entered in the cost
item. If a minimum and maximum value for a figure have been entered, the application takes the average
of these two as the input value.
1.2 Drag to cost group: If you drag the item to a cost group, the application creates a new cost item based on
the figure in question.
2 button on the cost item details screen
If you are editing a cost item, on the 'Details' tab you will see button for that cost item with the symbol . If
you click on this, the 'basic key figures' screen will be opened. You can search on a basic figure there and
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 33
then click on the button 'Apply figure…' (symbol ). The basic figure is then applied to the cost item you
are editing.
Before the figure is actually edited, you will see a pop-up asking you to confirm:
If the basic figure includes price information and has a different price level from the estimate, you will be notified of this
in this pop-up. When the key figure is used, the application will first rework the amounts to the price level of your
estimate. For more information about price level reworking, see paragraph 4.2.6.5.
After a basic figure is applied, on the 'Details' tab of that cost group in the 'Basic figure' group will include information
about the name of the basic figure. See the figure below. Use the arrow ( ) to open and close information. The
following information is available:
The name of the figure
The file which the key figure came from;
The basic key figure group which the figure came from;
The date on which the figure was assigned to the cost item
The ID of the figure
4.3.4 File management When you start the application, the 'File management' screen will be opened, see figure below. This shows the lists of
basic key figures from the database to which the application is linked (see paragraph 3.3).
Use the 'change…' button to link to a different database. You can do this only if you have not yet opened a list of basic
key figures.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 34
Use the 'new…' button to create a new database and save it in the file location of your choice.
The buttons beneath the screen have the following functions:
Delete: delete the selected list of figures;
New: Create a new list of figures which is then opened for editing;
Cancel: the screen is closed with no further action;
Open: the selected list of figures is opened;
If you click on the 'exchange' button you can link to a second database, the so-called 'exchange database'.
See the figure below. You can select an exchange database of your choice. Use the '>>' and '<<' buttons to copy lists
of basic key figures from one file to another.
The exchange databases are full databases. You can use an exchange database as an archive or backup, but as a
means of e-mailing multiple lists of basic key figures to another user of the AOA:CCM application.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 35
4.4 Calculation and reporting
4.4.1 Calculation of Net present value: After saving a cost item, the NPV for the cost item in question is determined.
Calculation of the net present value (NPV) of the whole estimate occurs:
After completing a price level correction (see paragraph 4.2.6.5);
After clicking on the 'Calculate' button in the main menu;
After clicking on the 'Reports' button in the main menu;
While the NPV is being calculated, a progress screen is displayed which shows the calculation result per cost item. If
errors are encountered during the calculation, this is reported on the progress screen. This information is useful in
quickly identifying and changing cost items which are causing problems.
The NCW is calculated based on:
- the properties of the cost item;
- the parameters entered under 'Financial settings';
The NPV is not calculated for cost items of the type 'risk/windfall'; the value input is in this case itself the NPV.
The calculation method is further explained in appendix 3.
4.4.2 Reports Clicking on the 'Reports' button in the main menu brings up the following form:
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 36
In this form, you can choose which reports should be generated.
NPV report
This report shows the NPV per cost item (including the parameters and variables on which the calculation is
based). A sub-total is reported per cost group.
You can choose how you want to see the start and end years of the cost items reported: as
aftercare/management year, calendar year, both or as you have input them.
Budget report
This report shows the expenditure per cost item per budget year. You can put in what
(aftercare/management) year the report should start from and over how many years the report should be
generated. The amounts can be printed out in a fixed price level (price level input), or per estimate year in the
price level for that year.
If you click on OK, the application will first perform a (re-)calculation of the NPV (see paragraph 4.4.1). Excel will now
be started. Progression of the process is displayed in the progress information screen. Depending on the speed of
your computer, running reports may take some time.
4.5 Sensitivity analysis
4.5.1 General Open the screen to calculate a sensitivity analysis via the 'Sensitivity analyse' button on the main menu. The sensitivity
analysis serves to provide insight into the impact on the target equity of changing certain parameters.
4.5.2 Setting sensitivity analysis parameters To perform a sensitivity analysis, you need to set a number of parameters in the left-hand side of the screen (see the
figure below).
First specify whether you want to perform a sensitivity analysis for:
the whole estimate. All cost items are calculated;
only the selected cost group. This option is available only if you
have selected a specific cost item before opening this screen.
Use this option if you are interested in a sensitivity analysis for a
specific cost group and children cost groups. The impact on
parent cost groups up to the top level are not calculated.
You then indicate which scenarios should be calculated. You can select
between:
Change in frequencies. You can use this option to, for
example, determine the effect of lower maintenance
frequencies or to establish whether longer lifespans have a
significant effect on the total cash value. In the screen,
enter by what factor the frequency values input should be multiplied during the sensitivity analysis.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 37
o N.B. 1: Processing of the factor input:
Frequencies are input in the model as either n times per year or 1x per n years. If a value of 2
is entered, the model interprets this has: the cost item occurs 2x per so often. A cost item with
an input frequency of 2 times per year then becomes: 4 times per annum. A cost item with an
input frequency of 1 x per 10 years becomes: 1x every 5 years.
o N.B. 2: Rounding of frequencies:
The sensitivity analysis allows for real numbers (numbers with decimal places) to be input as
the factor. The frequencies to be investigated then also result in whole numbers in the first
instance. Before starting the sensitivity analysis, the model rounds this frequency down to the
nearest whole number. An example. If the frequency of replacement is 1x per per 5 years, and
you perform a sensitivity analysis at a frequency with factor 1.2, the model will calculate a
sensitivity analysis for 1x per 4 years (and not 1x per 5/1.2 = 4.years).
o N.B. 3: Interpretation of the outcome:
Cost items input as as 1x per n years and which have an established end year (i.e. they have
not been input with a 'perpetual' end year) will not only occur more/less often over time in the
frequency sensitivity analysis, they may also happen more/less frequently in totality. By way of
illustration: Ten-yearly replacement of a facility during the first 50 years of
aftercare/management means that the cost item will occur in year10, 20, 30, 40 and 50 (i.e. 5
times). If the frequency in the sensitivity analysis with factor 1.5 is equal to fifteen-yearly
replacement, this means that the cost item will occur in year 15, 30 and 45 (i.e. 3 times). The
NPV according to the sensitivity analysis is thus lower due to the fact that the replacement
takes place later in time, and there are 3 replacements rather than 5.
Change in interest rate/inflation
You can indicate by how many percentage points both the interest rate and inflation which have been
set should be modified.
4.5.3 Interpretation of the results of the sensitivity analysis The results are displayed in table form in the right-hand section of the screen (see the figure below).
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 38
The first four columns (standard font) show the details of the cost item, the standard NPV in euros and the standard
NPV as a percentage of the total NPV of the estimate (the target equity).
The other columns (in italics) show the results of the sensitivity analysis. The 'scenario' column shows which of the
parameters you have set relate to the calculations.
The 'NPV (€)' and 'NPV (%)' columns show the NPV for the scenario.
The 'Increase in NPV (€)' and 'Increase in NPV (%)' show the comparison between the standard NPV and the
sensitivity analysis scenario. The 'Increase in NPV (€)' is the most informative. The rows are therefore sorted in
descending order based on the values in this column. A sharp increase (negative or positive) in the NPV means that
the cost item/cost group in question has a significant impact on the NPV under the scenario calculated.
The 'Increase in NPV (%) column indicates by what how many per cent the NPV is higher in the sensitivity analysis
scenario than in the standard calculation. This relative indicator shows the sensitivity of a cost item to the scenario, but
this sensitivity does not necessarily have any impact on the total target equity of the estimate, which of course
depends on the absolute amount (€) of the cost item.
4.6 Multilingual estimates
4.6.1 Introduction
Version 2.0 supports multilingual estimates. This functionality enables you to create a single estimate for a project
which can then be reviewed/edited by people who speak different languages.
The following actions are involved in multilingual inputting:
Choice of the language to be used
Multilingual input when preparing the estimate
Translation once an estimate has been set up
Selection of the language that is currently active
Most of these actions are performed via the estimate details screen (paragraph 4.2.6.2). We look at these actions in
greater detail in the sub-paragraphs below.
4.6.2 Choice of the language to be used In the estimate details screen, click on the 'language selection' link to open the 'Translations' screen. By checking the
box, you can indicate which language from the choice of German, French, English and Dutch you want to use in your
estimate. You can change this selection at any time. If you uncheck a language for which you have already input
translations, the application will give you a warning that all your texts in that language will be deleted.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 39
4.6.3 Multilingual input during set-up When inputting the estimate, you can input the text in multiple languages. The text fields which support multilingual
input are indicated by a button with a globe icon ( ). If you click on one of these buttons, the online translation form
will be opened; see the figure below.
You can enter the translations in this form, 1 language per line.
4.6.4 Input a translation retrospectively You can also opt to first input the estimate in one language and then add the translations retrospectively. You can do
this by using the buttons with the globe icons as described in the previous paragraph. However you can also use the
special translation form. This allows you to view and edit all the translations of the entire estimate on a single screen.
Open the translation form via the 'open translation form' link on the estimate details screen (paragraph 4.2.6.2).
The following screen will then be opened:
The image above shows an overview of the items to be translated, 1 column per translation.
The list displays the items in the same order as in the costs structure sub-screen (paragraph 4.2.4) and is thus
synchronised. If you activate an item in the list (by clicking on it), this becomes the active element in the costs
structure.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 40
At the bottom of the image you will see 'editor translations'. Here, you can edit and save the active item from the
summary list.
This screen is particularly suited in situations where someone takes over the translation task but has limited
experience of working with the application. This individual can undertake translation of an estimate without a significant
learning curve.
4.6.5 Selection of the language that is currently active On the estimate details screen (paragraph 4.2.6.2) you can use the 'Current language' pull down box to select the
language to be activated. After you make your selection, the application immediately displays the multilingual texts in
the chosen language. You do not need to save this setting since it is not a property of your estimate, simply a display
option during your session.
The active language selected is also used for reports (paragraph 4.4.2).
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 41
5 Account
Title AOA:CCM Manual version 2
Date 1 Jan 2013 Project Area Oriented Approach Cost Calculation Model - PP5304
Consortium members Public Works Department (Gemeentewerken) Rotterdam,
Pipeworks and underground management department (Leidingenbureau en Beheer ondergrond) (main contractor) Grontmij Nederland BV Public Works Department Engineering Agency (Ingenieursbureau Gemeentewerken Rotterdam) Rotterdam Development Agency (Ontwikkelingsbedrijf Rotterdam) Province of Zuid-Holland aftercare/management agency Province of Utrecht Limburg aftercare/management (Nazorg/beheer Limburg) SBNS Municipality of Dordrecht A&G milieutechniek DCMR Environmental Protection Agency Soil+
Technical implementation Validware Groningen
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 42
Appendix 1 Risks and financial
windfalls
When determining the total aftercare/management costs associated with soil remediation, an allowance generally
needs to be included to cover the costs of risks or undesirable events.
The occurrence of unexpected events may lead to activities which differ from the expected aftercare/management
activities as described and budgeted for in an aftercare/management plan. This is not covered by the standard
bandwidth of aftercare/management costs. These are events which, although they are recognised, there is such
uncertainty as to whether measures or provisions are required to deal with them that they cannot be taken into account
in the aftercare/management plan.
In this paragraph, a roadmap is proposed for dealing with risks when estimating the aftercare/management costs of
soil remediation by constructing a calculation model.
Description of the problem
The AltVAR study reveals that we cannot quantify the long-term risks (sufficiently objectively). in the
aftercare/management market in general and to stagnation in the transfer of aftercare/management obligations in
particular.
The current (IPO) models used to calculate aftercare/management costs and risks are fine for Environmental
Management Act landfill sites (i.e. for well-defined IBC systems), but do not provide a solution for more complex
situations. This is because the technical risks are difficult to determine and to quantify and non-technical risks appear
to play a much greater part.
This situation concerning risks results in stagnation in aftercare/management; risks are not really dealt with effectively.
By developing a roadmap for risks, there is hope that this stagnation may be reduced.
This roadmap comprises 5 steps:
Before discussing this roadmap, we below take a brief look at the risks to be considered.
What are the risks?
What sort of risks are we talking about? The AltVAR study (Allocation of long-term responsibility, liability and (residual)
risks), SKB, June, 2005) differentiated between the following risk groups.
A. Technical risks, for example as the result of source and plume measures, systems failure or unfavourable
dispersion forecasts
B. Legal risks, for example as the result of valid or invalid claims by third parties
C. Operational risks, for example as the result of improper use of the location (by third parties or by the standard
operator)
D. Environmental risks, for example as the result of the impacts of (spatial) developments on or from the
environment
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 43
E. Administrative/legal risks, for example as the result of changes to legislations and regulations or government
decrees
F. Economic risks, for example as the result of changes in the investment climate or unfavourable economic
developments putting the aftercare/management budget under pressure
The AltVAR study examines these risks in greater detail. It also indicates which risks have low, moderate or significant
financial consequences.
The occurrence of an undesirable event (risk) results in a situation which is a threat to the environment. Remedying
the situation then incurs costs. These costs are known as ‘costs of repair’.
How is the roadmap?
Below we show a roadmap which can be used to make the risks of aftercare/soil remediation management
manageable.
This roadmap can be used not only in the preparatory phase (SO, SP or NZ plan) to reduce risk (where it is more a
case of risk management) but also to ensure they can be discussed in negotiating positions.
Using the roadmap for aftercare/soil remediation management risks
In developing this roadmap, use was made of experiences accumulated other fields of work facing similar issues
(commercial construction and civil engineering).
The roadmap comprises the following steps:
A. Risk identification
B. Prioritisation of the risks
C. Sorting of risks
D. Exclusion of risks
E. Discounting of risks
Step A – Risk identification
A risk analysis is the basis of ensuring risks are talked about and become manageable; it should at least facilitate open
and transparent communication on the subject.
First of all, the risks need to be identified – preferably classified according to the six risk types below.
Step B – Prioritisation of the risks
Once the risks have been identified, we can start to prioritise the risks.
One tool to help in doing this is by positioning the risks in the risks matrix. Risks are positioned within this matrix
according to the probability of them occurring and their consequences.
Below is an example of such a risks matrix.
IPO BO-19 report provides a structure for prioritising the risks. However the report is not comprehensive enough to
cover all the risks which may arise.
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 44
RISKS MATRIX Low probability of occurring
High probability of occurring
Minor effect
1. … 2. … 3. … 4. …
1. … 2. …
Major effect
1. … 2. … 3.
1. … 2. … 3. … 4. … 5. …
Step B – Prioritisation of the risks
Once the risks have been identified, we can start to sort them.
This is done using the four different squares I to IV in the risks matrix.
Square I (low probability – minor effect)
Risks in this square of the risks matrix are part of the ‘normal risk’ of a project. Examples include: the
probability that an observation well from a large monitoring and measurement network needs to be
replaced prematurely because of vandalism.
These risks are not normative. It is not productive to accord them extra attention.
Square II (high probability – minor effect)
Risk in this square of the risks matrix may be caused by a 'sensitive' aftercare/management system.
Examples include: the probability that an observation well from a large monitoring and measurement
network needs to be replaced on a regular basis because of vandalism.
These risks are not normative.
If the decision is taken not to reduce the probability, the risks in square II can be made manageable by
applying a low risk-allowance to those specific cost items with a high probability and minor effect. This
can be met with a previously established percentage allowance.
Square III (low probability – major effect)
Risks in this square of the risks matrix merit further consideration.
Examples include: the probability of groundwater contamination caused by unfavourable delivery from
the source.
These risks may be normative. In terms of the aftercare/management location's risk profile, it is
productive to accord attention to this; after all the consequences are major and therefore potential
normative for the total risk amount. There are several ways of tackling these risks:
Reducing the consequences;
Limiting the risk;
Taking out insurance.
I II
III IV
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 45
Square IV (high probability – major effect)
In principle, the risk can be determined in exactly the same way as with square III (risk = probability x consequence).
Given that this generally leads to unacceptable risks, we may quickly conclude that risks which appear in this square
of a risk matrix should really not be allowed to occur; not only in terms of stability of the technical solution but also
stability of the management organisation.
They warrant special attention because they are normative.
There are multiple solutions for dealing with these risks; one obvious solution is adapt the aftercare/management
measures: to adopt an approach of 'consequence reduction' and 'probability reduction. This would quickly prove cost-
effective. The risk needs to be shifted to squares I, II or III. See the text to each square for how to subsequently deal
with the residual risk.
RISKS MATRIX Low probability of occurring
High probability of occurring
Minor effect
1. … 2. … 3. … 4. …
1. … 2. …
Major effect
1. … 2. … 3.
1. … 2. … 3. … 4. … 5. …
Figure 2 Probability reduction and consequence reduction
Step D - Exclusions of risks
In addition to the events described in step C, which are classified as foreseeable risks, a distinction can also be made
between unforeseeable risks.
If these events are within the scope of the aftercare/management – of buyout payment – they can be excluded from
settlement in the risk amount.
Consideration can also be given to excluding the risks in square IV and not including them in the cost estimate. If the
aftercare/management is transferred, such risks fall outside the buyout payment and remain with the recipient of the
disposition on the aftercare/management.
Step E - Discounting risk
Step C indicated how risks can be discounted. Figure 3 is provides a summary of how risks can be included in an area
oriented approach cost calculation model .
The figure assumes that measures such as probability and consequence reduction or additional remediation measures
have already been completed.
Measure involving consequence reduction
Measure involving probability reduction
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 46
RISKS MATRIX Low probability of occurring
High probability of occurring
Minor effect
Included in the standard 'profit/risk' item of the aftercare/management estimate
apply a low risk-allowance to risky item which for example fall under 'maintenance'
fixed percentage based on, for example, rule of thumb, check list or empirical figures
Major effect
exclude conduct an extended risk
analysis per item (risk = probability x consequence).
Rules of thumb for fixed set of 'consequences'?
Additional tools: see the summary of step A
Input insurance policies and the insurance premium into the calculation model
Static underpinning?
Exclude Input insurance policies and
the insurance premium into the calculation model
N.B. the risks in this square should
not generally be allowed to occur with
appropriate risk management
(consequence and probability
reduction)
Figure 3 Method of discounting risk
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 47
Appendix 2 Risks : example and check list
Calculation of risk costs
project
file
date:
failure event probability costs risk (probability x costs) Note
1 monitoring system
unforeseen substances 0.5 50000 25000
wrong lay-out of monitoring system 0.25 100000 25000
wrong frequency monitoring 0.01 100000 1000
2 extraction wells
well obstruction 0.25 15000 3750
wrong dimensioning 0.25 25000 6250
foundation damage (gw extraction) 0.01 200000 2000
3 water purification
technical failures 0.5 50000 25000
capacity too low 0.1 200000 20000
energy outage 0.01 80000 800
increased competition. Influent 0.5 100000 50000
more stringent discharge standards 0.25 100000 25000
longer maintenance of water
purification 0.25 200000 50000
4 Cover sealing
cover sealing structurally damaged 0.01 200000 2000
5 vertical
pile in barrier 0.1 80000 8000
screen leak/design error 0.01 200000 2000
6 extraction system drainage area
delivery pipe explosion, recontamination 0.25 0.25 20000 5000
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 48
Calculation of financial windfall
project:
file:
date:
failure event probability cost saving windfall Note
1 monitoring system
contamination not measured 0.1 100000 10000
substantial proportion (25%) of location =clean)
2 extraction wells
cleaning less frequently 0.1 15000 1500 clean wells 1 x 4 years instead of 1x every 2 years
3 water purification
shorter maintenance of water purification 0.1 200000 20000
maintain 1 less water purification
4 Cover sealing
use cover sealing for longer 0.01 2000000 20000
6 ha sand betonite sealing
to last 5 years longer
5 vertical barrier
use cover sealing for longer 0.1 80000 8000 100 m foil barrier 6m to last 5 years longer
6 extraction system drainage area
delivery pipe explosion, recontamination 0.25 0.25 20000 5000 50 m3 of ground recontaminated
total cost saving (financial windfall) 64500
the opportunities below may result in lower aftercare/management costs (check list)
more flexible policy;
stable situation (already reached);
redevelopment..core is removed;
new remediation techniques (more effective);
new concentrations/circumstances for remediation (w.r.t. cold and heat storage));
more flexible return remediation value;
area-oriented approach
dilemma of infinity (if you wait long enough, some problems resolve themselves);
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 49
Appendix 3 Calculation of NPV
General description of the capitalisation method
Formula (1) describes the effect of inflation (=price increase) on a cost item which at the point in time
tp is equivalent to Ktp. At a later point in time tu, a higher amount Ktu is needed as a result of inflation
in order to finance this cost item.
In which: Ktu: calculated cost item at t=tu [€] Ktp: input cost item at t=tp [€] i: inflation [as a per cent /100]
tp: calendar year price level of input cost items [calendar year] tu: calendar year in aftercare/management phase in which the cost item applies.
[calendar year]
The half-yearly correction ensures that all expenditure in the middle of the year is assumed.
Formula (2) describes the effect of the interest rate on formation of the funds. To have available on tu funds to the
amount of Ftu, a lower amount Fts is needed at an earlier point in time.
In which: Fts: fund size on t=ts [€] Ftu: fund size on t=tu [€] r. interest rate [as a per cent /100] ts: calendar year of start of aftercare/management [calendar year]
tu: calendar year in aftercare/management phase in which the fund is approached to finance expenditure. [calendar year] The half-yearly correction ensures that all expenditure in the middle of the year is assumed.
In order to finance a cost item Ktu at a point in time tu in the aftercare/management phase, the size of the fund Ftu at
that time must be equivalent to the amount of the cost item.
In formula:
)5,0()1(
tptu
tptuiKK
)5,0()1(
1
tstututsr
FF
tutuKF
(1)
(2)
Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013 50
Combination of formula (1) and (2) then results in:
Formula (3) establishes the required size of the fund at the start of the aftercare/management, Fts, which is necessary
at a moment in time tu to finance a cost item Ktp which is expressed in a price level for calendar year tp.
The size of the total fund calculated is derived from the sum of the contributions Fts from the individual cost items.
There are also cost items (risks/windfalls) already input as net present value which are added to the capitalised
standard cost items.
In which: D: target equity [€]
NPVr,m risks input as NPV, windfalls [€]
Use in the application
The formulae above are translated into programming code.
The following are calculated per cost item, and per aftercare/management year:
an inflation factor in that year which is a result of all the inflation percentages from the year's price level input;
the level of expenditure in that year based on the value input and the inflation factor (formula 2);
the number of euros needed for that expenditure year at the start of aftercare/management (formula 3) based on the
(fixed) rate of interest;
All these outgoings per cost item are added together and allocated to the cost item's total NPV. The net present value
(NPV) of the cost item is thus determined. The NPV of the estimate as a whole is a sum of these sub-totals.
)5,0(
)5,0(
)1(
1)1(
tstu
tptu
tptsr
iKF
(3)
mrts
NCWFD, (4)
Validware
Document description
Title: Calculation Cost Model: Area Oriented Approach - Manual Version 2.0, 1 February 2013
Deposit number: -
Number of Pages: 51
Editor: Jan Frank Mars
Date of publication: February 1, 2013
Contact: Floris de Jong
Key words: CCM: AOA
Translations:
Summary: The CCM: AOA is a standardized method that allows an objective assessment for
organization and implementation of an area oriented approach. The model supports the financial
consideration in decisions about multiannual AOA both in the planning phase and du