Calculate Total Cost And Incremental Costs Principles of Cost Analysis and Management © Dale R. Geiger 2011 1
Dec 24, 2015
© Dale R. Geiger 2011 1
Calculate Total Cost And Incremental Costs
Principles of Cost Analysis and Management
© Dale R. Geiger 2011 2
What if?
• Relationship between cost and unit of output is neither fixed nor variable?
• There are multiple elements that affect the cost of an output?
• A different type of cost relationship is relevant to the decision at hand?
© Dale R. Geiger 2011 3
Terminal Learning Objective
• Task: Calculate Total Cost And Incremental Costs Given Various Production Volumes
• Condition: You are a cost advisor technician with access to all regulations/course handouts, and awareness of Operational Environment (OE)/Contemporary Operational Environment (COE)
• Standard: With at least 80% accuracy: • Describe multivariate (mixed) and incremental costs• Express total multivariate cost in an equation• Graph total multivariate cost over a relevant range• Express incremental cost in an equation
© Dale R. Geiger 2011 4
Cost Definitions
• Mixed Costs - A combination of fixed and variable costs
Total Cost = Variable Cost + Fixed Cost
• Also known as multivariate costs
© Dale R. Geiger 2011 5
Multivariate Cost Expressions
• Variable component:• Variable $Cost per Unit * # Units
-Plus-• Fixed component:• Sum of relevant costs that remain the same
regardless of units of output
© Dale R. Geiger 2011 6
Multivariate Cost Example
• Relevant cost of transporting a unit for on-location training is $350,000.
• Cost of training operations on-location runs $20,000 per day.
• What is the unit of output?• Days of training
© Dale R. Geiger 2011 7
Multivariate Cost Example
• Relevant cost of transporting a unit for on-location training is $350,000.
• Cost of training operations on-location runs $20,000 per day.
• What is the unit of output?• Days of training
© Dale R. Geiger 2011 8
Multivariate Cost Example
• Relevant cost of transporting a unit for on-location training is $350,000.
• Cost of training operations on-location runs $20,000 per day.
• What is the cost expression for Fixed cost?• Fixed cost = $350,000
© Dale R. Geiger 2011 9
Multivariate Cost Example
• Relevant cost of transporting a unit for on-location training is $350,000.
• Cost of training operations on-location runs $20,000 per day.
• What is the cost expression for Fixed cost?• Fixed cost = $350,000
© Dale R. Geiger 2011 10
Multivariate Cost Example
• Relevant cost of transporting a unit for on-location training is $350,000.
• Cost of training operations on-location runs $20,000 per day.
• What is the cost expression for Variable Cost?• Variable cost = $20,000/day * # of days
© Dale R. Geiger 2011 11
Multivariate Cost Example
• Relevant cost of transporting a unit for on-location training is $350,000.
• Cost of training operations on-location runs $20,000 per day.
• What is the cost expression for Variable Cost?• Variable cost = $20,000 per day * # of days
© Dale R. Geiger 2011 12
Multivariate Cost Example
• Relevant cost of transporting a unit for on-location training is $350,000.
• Cost of training operations on-location runs $20,000 per day.
• What is the cost expression for Total Cost of on-location training?
© Dale R. Geiger 2011 13
Multivariate Cost Example
• Relevant cost of transporting a unit for on-location training is $350,000.
• Cost of training operations on-location runs $20,000 per day.
• What is the cost expression for Total Cost of on-location training?
• Total Cost = Variable cost + Fixed Cost• Total Cost = $20,000 per day * #days +
$350,000
14
Graph of Mixed Cost
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 150
100
200
300
400
500
600
700
Fixed Cost
X Axis = Number of DaysAs Number of Days increases, Fixed Cost does not change
$K
$350K
© Dale R. Geiger 2011
15
Graph of Mixed Cost
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 150
100
200
300
400
500
600
700
Fixed CostVariable Cost
X Axis = Number of DaysAs Number of Days increases, Variable Cost increases
$K
Variable cost for 10 days =
$20K per day * 10 days = $200K
© Dale R. Geiger 2011
16
Graph of Mixed Cost
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 150
100
200
300
400
500
600
700
Fixed CostVariable CostTotal Cost
X Axis = Number of DaysAs Number of Days increases, both Variable Cost and Total Cost increase
$KTotal cost for 10 days =
$20K per day * 10 days + $350K
or $550K$550K
© Dale R. Geiger 2011
© Dale R. Geiger 2011 17
Questions
• What is the cost expression for Cost per Day?
• How would the graph of Cost per Day look?• It should be a downward sloping curve that will
level out above $20K
© Dale R. Geiger 2011 18
Cost Definitions
• Semi-variable Cost - Costs that Increase as Unit of Output increases, but not in Direct Proportion
• Examples:• Hours worked by an employee• Miles driven• Students in a course
© Dale R. Geiger 2011 19
Semi-Variable Cost Example
• Sometimes the Variable Cost per unit remains the same only for a Relevant Range• Example: Employee Wages• Employee’s base wage is $15 per hour• If the employee works more than 40 hours in a
week we must pay time and a half
© Dale R. Geiger 2011 20
Cost Expression for Semi Variable
• The cost expression for Total Wage Cost is:
Straight Time Hours * Straight Time
$ per Hour + Overtime Hours *
1.5*
Straight Time $ per Hour
© Dale R. Geiger 2011 21
Cost Expression for Semi Variable
• If the total number of hours worked is 30 and straight-time rate is $15 per hour then:
= $450
30 Straight
Time Hours* $15 per Hour +
0 Overtime
Hours*
1.5*
Straight Time $ per Hour
© Dale R. Geiger 2011 22
Cost Expression for Semi Variable
• If the total number of hours worked is 44 and straight-time rate is $15 per hour then:
= $690
40 Straight
Time Hours* $15 per Hour +
4 Overtime
Hours*
1.5*
$15 per Hour
23
Graph for Total Wage Cost
0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 600
200
400
600
800
1000
X Axis = # of Hours WorkedAs # Hours Worked increases, total Wage Cost increases, but not uniformly
© Dale R. Geiger 2011
24
Graph for Wage Cost per Hour
0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 600
5
10
15
20
25
X Axis = # of Hours WorkedAs # Hours Worked increases, Wage Cost per Hour remains the same for the relevant range
This is known as a Step Function. Cost per Hour for Hours 0-40 = $15Cost per Hour for Hours 41-60 = $22.50
© Dale R. Geiger 2011
© Dale R. Geiger 2011 25
Questions for Thought
• What about a volume discount?• Units 1-20 cost $10 per unit• Units 21-50 cost $9 per unit• Units 51-100 cost $8 per unit
• How would you express this cost relationship• In total? On a per-unit basis?
• How would the graph of each look?• What is the cost of 16 units? Of 67 units?
© Dale R. Geiger 2011 26
Graph of Total Cost
1 10 20 30 40 50 60 70 80 90 1000
100200300400500600700800900
1000
20; 200
50; 470
100; 870
Total Cost
© Dale R. Geiger 2011 27
Graph of Unit Cost
0 4 8 12 16 20 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 961005
6
7
8
9
10
11
Unit cost
© Dale R. Geiger 2011 28
Check on Learning
• What is the generic cost expression for a mixed cost?
• A cost that increases as output increases but not in direct proportion is called a -
cost.
© Dale R. Geiger 2011 29
Cost Definition
• Incremental Costs - The increase in Total Cost caused by increasing output by ONE unit
• Reflects the Difference between the Total Cost for a given level of output and the Total Cost for that level plus one
• Cost Expression for Incremental Cost:(Total Cost of # Units + 1) – (Total Cost of # Units)
© Dale R. Geiger 2011 30
Relevant Range and Fixed Cost
• Sometimes Fixed Cost remains the same only for a relevant range• Example : Airline Flight• Fixed Cost of $15K per flight cover
fuel and crew regardless of number of passengers• The aircraft holds 150 passengers
31
Graph Airline Flight Cost
0 20 40 60 80100
120140
160180
200220
240260
280300
320340
05
101520253035404550
Fixed Cost$K
X Axis = Number of passengersAs number of passengers increases, Fixed cost increases in a step-wise fashion
© Dale R. Geiger 2011
© Dale R. Geiger 2011 32
Incremental Cost Example
• Our airline provides a $.50 bag of peanuts and a $.75 can of soda to each passenger
• Additional fuel cost per passenger is $8.75• What is the cost expression for Total Cost for a
single flight? Variable Cost $10 per passenger * # passengers
+ Fixed Cost $15,000
© Dale R. Geiger 2011 33
Incremental Cost Example
• Our airline provides a $.50 bag of peanuts and a $.75 can of soda to each passenger
• Additional fuel cost per passenger is $8.75• What is the cost expression for Total Cost for a
single flight? Variable Cost $10 per passenger * # passengers
+ Fixed Cost $15,000
© Dale R. Geiger 2011 34
Incremental Cost Example
• Our airline provides a $.50 bag of peanuts and a $.75 can of soda to each passenger
• Additional fuel cost per passenger is $8.75• What is Total Cost for 125 passengers?
$10 per passenger * 125 passengers+
$15,000= $27,500
© Dale R. Geiger 2011 35
Incremental Cost Example
• Our airline provides a $.50 bag of peanuts and a $.75 can of soda to each passenger
• Additional fuel cost per passenger is $8.75• What is Total Cost for 125 passengers?
$10 per passenger * 125 passengers+
$15,000= $16,250
© Dale R. Geiger 2011 36
Incremental Cost Example
• Our airline provides a $.50 bag of peanuts and a $.75 can of soda to each passenger
• Additional fuel cost per passenger is $8.75• What is the Incremental cost of increasing
from 125 to 126 passengers?• Incremental cost =
Cost of 126 psgrs – Cost of 125 psgrs($10 * 126 + $15,000) - ($10 * 125 + $15,000)
= $10
37
Incremental Cost Example
• Our airline provides a $.50 bag of peanuts and a $.75 can of soda to each passenger
• Additional fuel cost per passenger is $8.75• What is the Incremental cost of increasing
from 125 to 126 passengers?• Incremental cost =
Cost of 126 psgrs – Cost of 125 psgrs($10 * 126 + $15,000) - ($10 * 125 + $15,000)
= $10© Dale R. Geiger 2011
38
Graph Airline Flight Cost
115117
119121
123125
127129
131133
135137
139141
143145
147149
16.00
16.05
16.10
16.15
16.20
16.25
16.30
16.35
16.40
16.45
16.50 $K
X Axis = Number of passengersAs number of passengers increases, Total Cost increases
Total Cost at 125 passengers = 125 * $10 per passenger + $15,000= $16,250
Total Cost at 126 passengers = 126 * $10 per passenger + $15,000= $16,260
Incremental cost = $16,260 – $16,250 = 10
© Dale R. Geiger 2011
© Dale R. Geiger 2011 39
Incremental Cost Example
• Our airline provides a $.50 bag of peanuts and a $.75 can of soda to each passenger
• Additional fuel cost per passenger is $8.75• What is the Incremental cost of increasing
from 150 to 151 passengers?• Incremental cost =
Cost of 151 psgrs – Cost of 150 psgrs($10 * 151 + $30,000) - ($10 * 150 + $15,000)
= $15,010
© Dale R. Geiger 2011 40
Incremental Cost Example
• Our airline provides a $.50 bag of peanuts and a $.75 can of soda to each passenger
• Additional fuel cost per passenger is $8.75• What is the Incremental cost of increasing
from 150 to 151 passengers?• Incremental cost =
Cost of 151 psgrs – Cost of 150 psgrs($10 * 151 + $30,000) - ($10 * 150 + $15,000)
= $15,010
41
Graph Airline Flight Cost
135137
139141
143145
147149
151153
155157
159161
163165
167169
15.00
17.00
19.00
21.00
23.00
25.00
27.00
29.00
31.00
33.00 $K
X Axis = Number of passengersAs number of passengers increases, Total Cost increases
Total Cost at 150 psgrs = 150 * $10 per psgr+ $15,000Or $16,500
Total Cost at 151 psgrs = 151 * $10 per psgr + $30,000Or $31,510
Incremental cost = $16,500 – $31,510 = $15,010
© Dale R. Geiger 2011
© Dale R. Geiger 2011 42
Check on Learning
• What is the generic cost expression for incremental cost?
• If the relevant range for fixed cost is not exceeded, incremental cost is equal to
.
© Dale R. Geiger 2011 43
Other Multivariate Cost Expressions
• Some cost expressions consist of multiple components
• Example: Cell phone planBase plan $35 for 500 minutesAdditional minutes $.25 per minuteData plan $10 for 200 MBAdditional MB of data $.50 per MB
© Dale R. Geiger 2011 44
Cell Phone Plan Example
Base plan $35 for 500 minutesAdditional minutes $.25 per minuteData plan $10 for 200 MBAdditional MB of data $.50 per MB• What is the cost expression? • Base plan $35 + $.25/min * additional minutes
+ data plan $10 + $.50/MB * additional MB
© Dale R. Geiger 2011 45
Cell Phone Plan Example
Base plan $35 for 500 minutesAdditional minutes $.25 per minuteData plan $10 for 200 MBAdditional MB of data $.50 per MB• What is the cost expression?
Base plan $35 + ($.25 per min * add’l mins) + data plan $10 + ($.50 per MB * add’l MB)
© Dale R. Geiger 2011 46
Cell Phone Plan Example
Base plan $35 for 500 minutesAdditional minutes $.25 per minuteData plan $10 for 200 MBAdditional MB of data $.50 per MB• What is the cost if 400 minutes and 250 MB
are used?$35 + ($.25/min * 0 additional minutes) +
$10 + ($.50/MB * 50 additional MB)
© Dale R. Geiger 2011 47
Cell Phone Plan Example
Base plan $35 for 500 minutesAdditional minutes $.25 per minuteData plan $10 for 200 MBAdditional MB of data $.50 per MB• What is the cost if 400 minutes and 250 MB
are used?$35 + ($.25 per min * 0 additional minutes) +
$10 + ($.50 per MB * 50 additional MB)= $70
© Dale R. Geiger 2011 48
Graph of Cell Phone Cost
400 min/ 250 MB
600 min/ 100 MB
500 min/ 200 MB$0
$10
$20
$30
$40
$50
$60
$70
$80
$35 $35 $35
$10
$10
$10
25
$25 Add'l MBData PlanAdd'l minutesBase Plan
© Dale R. Geiger 2011 49
Check on Learning
• You are planning a one-week vacation for you and your significant other. How would you define the cost expression for the trip?
© Dale R. Geiger 2011 50
Practical Exercises