Cal/Coronagraph Integration Lewis Roberts 2/25/2010
25

Cal/Coronagraph Integration

Jan 02, 2016

Download

Documents

pelagia-aradia

Cal/Coronagraph Integration. Lewis Roberts 2/25/2010. Agenda. Schedule Tasks Summary. High Level Schedule. 1 st week – Set up and integrate with Coronagraph 2 nd week – Integrate with AO system. Test system in lab 3 rd week – IFU detector is installed and tested. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Cal/Coronagraph Integration

Cal/Coronagraph Integration

Lewis Roberts2/25/2010

Page 2: Cal/Coronagraph Integration

Agenda

• Schedule• Tasks• Summary

Page 3: Cal/Coronagraph Integration

High Level Schedule

• 1st week – Set up and integrate with Coronagraph

• 2nd week – Integrate with AO system. Test system in lab

• 3rd week – IFU detector is installed and tested.• 4th week – 1 Engineering night and 2 science

nights.

Page 4: Cal/Coronagraph Integration

Detailed Week 1 Schedule(This is just the highlights, a more detailed schedule is available on the Twiki)

• March 1– Drive Equipment to Palomar– Start Dewar Pumping/Cooling

• March 2– Sasha Tutors Gautam/Lewis on Coronagraph operations– Install Calibration Bread Board

• March 3– Install & Align Dewar– Alignment

• March 4

• March 5– Install System on AO bench

Page 5: Cal/Coronagraph Integration

Detailed Week 2 Schedule(This is just the highlights, a more detailed schedule is available on the Twiki)

• March 8– Drive to Palomar– End-to-End Alignment

• March 9– AO Lab Tests Day 1

• March 10– AO Lab Tests Day 2

• March 11– AO Lab Tests Day 3

• March 12– AO Lab Tests Day 4

Page 6: Cal/Coronagraph Integration

Detailed Week 3 Schedule(This is just the highlights, a more detailed schedule is available on the Twiki)

• March 15– Install new connectors on Cal System Dewar at JPL

• March 16– Drive to Palomar– Install Cal System Dewar into Cal System before IFU is installed. Need to confer with IFU

team.

Page 7: Cal/Coronagraph Integration

Detailed Week 4 Schedule(This is just the highlights, a more detailed schedule is available on the Twiki)

• March 21– In lab testing of Coronagraph, IFU, AO and Cal System

• March 22– Install Instrument on Telescope (Morning)– Engineering Night (Night)

• March 23– Science Observations

• March 24– Science Observations

Page 8: Cal/Coronagraph Integration

StaffingWeek 1

Mon3/1

Tues3/2

Wed3/3

Thur3/4

Fri3/5

Lewis ? X X

Gautam ? X X X X

Rob X X X X

Tom ? ?

Iris ? ?

Sasha X

Page 9: Cal/Coronagraph Integration

StaffingWeek 2

Mon3/8

Tues3/9

Wed3/10

Thur3/11

Fri3/12

Sat3/13

Sun3/14

Lewis X X

Gautam X X X X

Rob X X X X

Tom X X X X

Mike X X X

Jenny X

Rick X X X

Sasha X X

Ben X X

Ian X X

Page 10: Cal/Coronagraph Integration

StaffingWeek 3

Mon3/15

Tues3/16

Wed3/17

Thur3/18

Fri3/19

Sat3/20

Gautam ? ? ? ? ?

Sasha X X X X X X

Ben X X X X X X

Ian X X X X X X

Page 11: Cal/Coronagraph Integration

StaffingWeek 4

Sun3/21

Mon3/22

Tues3/23

Wed3/24

Lewis X X X

Gautam X X X X

Iris X X

Tom X X X

Mike X X

Antonin ? X X X

Rick Day Day Day

Sasha X X X X

Ben X X X X

Ian X X X X

Rich ? ? ?

Page 12: Cal/Coronagraph Integration

Integration Tasks

• This section summarizes tasks that need to be done at the telescope and involve a modification to the existing instrument.

Page 13: Cal/Coronagraph Integration

Overall Image of Calibration System

Page 14: Cal/Coronagraph Integration

P1640 Cables emerge from the top of the enclosure here.

Cryotiger Lines

Cal WFS Leach Electronics Box (See next slide)

Enclosure Modifications

Page 15: Cal/Coronagraph Integration

Design of the Side Panel Missing Handle

Page 16: Cal/Coronagraph Integration

Interferes with AO Spit

Page 17: Cal/Coronagraph Integration

Need To redesign Vacuum gauge/valve holder

Page 18: Cal/Coronagraph Integration

~3”

10.715”

Leaving about 1/8” for the panel.

Needed to have a custom part made by Brooks Automation. To bring the end of the gas lines to the edge of the enclosure to allow for access to attach the gas lines to the dewar when the instrument is mounted to the telescope.

Part was ordered 2/19. Will arrive 1st week of march.

Page 19: Cal/Coronagraph Integration

Cut Rear Dewar Foot

Cut Here

Page 20: Cal/Coronagraph Integration

Reverse FPM Mount

Need to reverse the FPM Mount to put the long motors in the direction shown.

Also need to reverse the FPM in the mount.

Page 21: Cal/Coronagraph Integration

Lyot Stop Mount

Put the Lyot Stop Mount on a new baseplate, to make room for the P1640 breadboard.

Page 22: Cal/Coronagraph Integration

1) Temporarily reroute ADC Cables around Optical Stimulus, while its installed.2) Route New Cables, will tie them in similar places to existing cables.

Optical Stimulus

Page 23: Cal/Coronagraph Integration

80/20 Beamsplitter was replaced with a 50/50 beamsplitter.

For additional light during science observations, we can remove the beamsplitter.

Agilis tip/tilt stage will be controlled …

New Location of Quad-Cell for Coronagraph FSM

Page 24: Cal/Coronagraph Integration

Integration Tasks• Machine Enclosure to hold Cal Gold Box• Machine Enclosure/install Cal patch panel• Cut hole in enclosure for Cal cold lines• Modify Dewar stand for Cal breadboard• Reverse FPM Mount• Reroute Risley Prism cables• Route New Cables• Move Quad Cell• Relocate Lyot Stop or Swap Mirror for

beamsplitter

Page 25: Cal/Coronagraph Integration

Outstanding Questions

• Need to Confirm IFU integration schedule• Confirm hole pattern for Handle on Side Panel• Identify magnitude of AO Spit interference

problem. • Vacuum Valve/Gauge Fixture• Control of the Quad Cell Tip/Tilt mirror