Cable Rehabilitation at Oncor by Richie Harp – Distribution Standards Data provided by Mark Darilek – Maintenance Planning SWEDE 2009 – Tulsa, OK – Thursday, May 7, 2009
Feb 25, 2016
Cable Rehabilitation at Oncorby Richie Harp – Distribution StandardsData provided by Mark Darilek – Maintenance Planning
SWEDE 2009 – Tulsa, OK – Thursday, May 7, 2009
Cable Rehabilitation Overview
Rehabilitated cableCable repairs to facilitate future rehabilitation
Oncor requirements for rehabilitationFurther considerations2nd Responder processAnother technology
Amount of Rehabilitated Cable
Began in 1995420 cbl-mi rehabilitated8,000 cbl-mi in service – Pre-1993 cable
22,000 cbl-mi total cable
Amount of Rehabilitated Cable
URDCable size – Less than #4/0 AWG(#2 and #1/0 AWG, and minimalamount of #2/0 AWG)
Began in 1995405 cbl-mi rehabilitated17,000 cbl-mi in service2% of URD cables
Amount of Rehabilitated Cable
FeederCable size – #4/0 AWG and larger (up to 1000 kcmil)
Began in 200815 cbl-mi rehabilitated3,400 cbl-mi in service0.4% of feeder cable
Cable Repairs
Standard cable (Began purchasing in 1990)#1/0 Al 19-StrandsStrand-filled conductors25 kV, 260-mil TRXLPE16-#14 AWG Concentric Neutral Wires (Full neutral)
Jacketed
Cable Repairs (Cont)
Only for cable repairs (2-ft pieces) for future injection#1/0 Al 19-StrandsStrands not filled25 kV, 260-mil TRXLPE8-#14 AWG concentric neutral wires(1/2 neutral)
UnjacketedOn 1000-ft composite reel
Oncor Requirements for Rehabilitation
Do not rehabilitate: Cable installed in conduit 175-mil or 220-mil cable operating
at 14.4 kV Butyl rubber cable Cable with tape conductor shield Corroded concentric neutral
Do not rehabilitate cable if… Corroded center conductor Loss of insulation shield
conductivity Insulation shield with no adhesion Failures due to dig-ins or debris in
trench There is a chance the cable will be
converted to 14.4 kV in the future
Oncor Requirements for Rehabilitation (cont)
Other Requirements
There must be more than 25% concentric neutral remaining.
There cannot be more that one joint per 100 feet of cable.
The faulted cable section must not have been de-energized more than six months.
Comments:
We tried to rehabilitate some open loops that had been de-energized for up to 2 yearsVery little successWe quit rehabilitating open loops that had been de-energized for more than 6 months.
More comments:
2006 and 2007 ProcessesLeft URD loops open after failures (direct buried cables)
Only repaired cable to get customers’ lights back on.
More comments:
Dec 2007 ProcessBegan repairing failed loops again.Caught up with open loops (Feb 2009)–Inject cables or–Replace cable if not able to inject
More comments:
Dec 2008 Process ChangeInstall joint to repair cableTry to inject the cableAfter the repair, if the cable is not able to be injected, then just leave energized.
Defer replacement of the cable until the next fault.
2nd Responder Process
System-Wide ProcessRepair failures on direct buried cable (not in conduit)
Must be able to switch around to get lights back on.
Not normally feeder exits (Only non-critical cables)
2nd Responder Decision Process Flow Chart
Available by request
2nd Responder Process
1868 sections of failed cables came through the process since 2008
749 sections of cable were injected1119 sections were not able to be injected922 due to process requirements197 not related to the process (already energized when arrived, in conduit, etc.)
2nd Responder Process – Injected/Not Injected
922749 Injected
Non-Injected
2nd Responder Process
12 cause codes for not being able to inject the 1119 sections of cableAge of fault (> 6 months)Could not flow (Blocked strands or joints) Inaccessible fault or joint locationDeteriorated neutral (< 25% remaining)Previously injected, non-warranty or otherPreviously injected, warranty
2nd Responder Process
12 cause codes for not being able to inject the cable (Cont)Corroded conductorNumber of joints (> than 1 joint per 100 ft)UnknownCable is in conduitAlready energized upon arrivalOther–These last three represent the 197.
2nd Responder Process – Causes
11%
11%
20%
16%
5%18%
1%3%
1%2%
4%8%
Age of fault
Could not flow
Inaccessible fault or joint
Deteriorated neutral
Number of splices
Previously injected, non-warrantyPreviously injected,warrantyCorroded conductor
Unknown
Cable in conduit
Energized upon arrival
Other
Another technology
Different formulations for injection fluid
Formulation tailored to operating environment
Tailored more for feeder cables with higher operating temperatures (»45°C)
No soak tanks requiredPut back into service immediately after injection
Another technology (Cont)
Must replace all jointsHigher pressures for injection