Business Affairs Committee Office of Facilities July 16, 2020
Business Affairs CommitteeOffice of Facilities
July 16, 2020
Page 2Dobo Hall: Phase III Restoration (Dobo Proper)
Dobo Hall, a 110,000 GSF laboratory facility, was significantly damaged by Hurricane Florence, September 14, 2018
An entire new roof system was installed in addition to the replacement of all exterior windows and doors.
Interior renovations included the following:
• Mechanical: duct work, exhaust systems, chillers, boilers, etc.• Electrical: new distribution panels, branch circuits, lighting, and generator• Fire Safety: upgraded fire suppression and new fire alarm• Casework: all new laboratory casework and hood systems
The laboratory facility’s return to use is nearly complete. Beneficial Occupancy was granted Jul 7, 2020; 662 days after Hurricane Florence. Departmental moves and laboratory equipment calibration is in progress and will be complete for the fall semester of 2020.
Page 3Dobo Hall: Phase III Restoration (Dobo Proper)
Before
Page 4Dobo Hall: Phase III Restoration (Dobo Proper)
After
Page 5Dobo Hall: Phase III Restoration (Dobo Proper)
Lecture Hall
Page 6Dobo Hall: Phase III Restoration (Dobo Proper)
Laboratory
Page 7
Dobo Hall: Phase III Restoration (Dobo Proper)
Laboratories
Page 8Dobo Hall: Phase III Restoration Status (Dobo Proper)
CM@R: Balfour BeattyDesigner: Mosley ArchitectsBeneficial Occupancy Received 7/7/2020Moves are In-Progress
Page 9Veterans Hall
Budget: $66M CM@R: Balfour BeattyDesigner: EYP ArchitectsBeneficial Occupancy Received 6/26/2020. Moves are In-Progress
Page 10Veterans Hall
Laboratories
Page 11Veterans Hall
Laboratories
Page 12Veterans Hall
Laboratories
Page 13Veterans Hall
Teaching and Collaborative Spaces
Page 14Central Parking Deck
Budget: $24M Design-Builder: Balfour Beatty ConstructionBeneficial Occupancy Received: 06/09/2020
Page 15Central Parking Deck
Budget: $24M Design-Builder: Balfour Beatty ConstructionBeneficial Occupancy Received: 06/09/2020
Page 16
Housing Village
CHF (Collegiate Housing Foundation)Developer: Balfour Beatty Campus Solutions
Occupancy:Phase I Fall 2020 Bldgs. 3&4 (1000 Beds)Phase II Fall 2021 Bldgs. 1&2 (800 Beds)
Phase I Status:
Building 4 (Name)Beneficial Occupancy Received 7/9/20Move-In Beginning 8/10/20
Building 3 (Name)Beneficial Occupancy Inspection Scheduled 7/22/20Move-In Beginning 8/10/20
Galloway Belk
Bldg. 1
Hewlett
Graham
Bldg. 2
Bldg. 3
Bldg. 4
HUB
Page 17
Housing Village –Buildings
Page 18
Housing Village –Buildings
Page 19
Housing Village –Buildings
Page 20
Housing Village –Buildings
Page 21
Student Village Dining Facility
Budget: $14M Designer: Perkins EastmanCMR: Monteith Construction Estd. Comp.: Summer 2021
Page 22Student Village Dining Facility – Site Plan
Budget: $14M Designer: Perkins EastmanCMR: Skanska Estd. Comp.: Spring 2021
Page 23Student Village Dining Facility – Floor Plan
Budget: $14M Designer: Perkins EastmanCMR: SkanskaEstd. Completion: Spring 2021
Page 24
Student Village Dining Facility
Culvert and Utility Crossing
Page 25Film Studies Facility
Budget: $3.5M Designer: Becker Morgan GroupContractor: Thomson Estd. Occupancy: Fall 2020
Page 26Film Studies Facility
Budget: $3.5M Designer: Becker Morgan GroupContractor: Thomson Estd. Occupancy: Fall 2020
Page 27
CIS/Congdon Modernization and Expansion
Budget: $2.5M (Philanthropic Gift)Designer: LS3PStatus: Out for BidEstd. Construction: Summer 2020
Page 28Coastal Engineering Facility
COASTAL ENGINEERING
Budget: $6MDesigner: SGA/Narmour Wright Design, PA Contractor: TBD Estd. Occupancy: Fall 2021
Page 29Randall Library Renovation and Expansion
Budget: $5.5M (Design Only) (Estd. Total $62M)Designer: LS3P CM@R: Skanska Estd. Construction: TBD
Conceptual Rendering
Page 30Randall Library Renovation and Expansion
Budget: $5.5M (Design Only) (Estd. Total $62M)Designer: LS3P CM@R: Skanska Estd. Construction: TBD
Conceptual Rendering
Page 31Campus Development Impact Map
Questions