BUNNYTHORPE-WILTON (JUDGEFORD TO WILTON … · The crossing over the State Highway 1 Johnsonville to Porirua motorway and the ... The unquantified assessment further strengthened
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
SDDP Stochastic Dual Dynamic Programming – a market dispatch model used to determine the optimal dispatch of hydro, thermal and other renewable generation.
TPM Transmission pricing methodology, defined in Schedule 12.4 of the Code
Transpower Transpower New Zealand Limited, owner and operator of New Zealand’s high-voltage electricity network (the national grid)
Table 2 Listed project capital allowance application
Cost distribution
Range of distribution
Point selected within distribution (probability)
Cost applied for ($000)
Capex (real 2017$) Triangle +30% / -30% P50 8,675
Inflation 190
Exchange rates -
IDC 30
Total LPCA (2020$) 8,894
Proposal at a Glance
What: Replace the existing conductors on the Judgeford to Wilton section of the Bunnythorpe to Wilton line with simplex Chukar, and reconfiguration to a ‘double tee’ connection at Judgeford.
When: Commence work in Q4 2019 and complete by Q4 2021
How much: Transpower is seeking approval to add $8.9 million to our base capex funding baseline for RCP2 to reflect the cost of assets commissioned before 1 July 2020. The remaining cost will be included as base capex in our RCP3 funding application.
In September 2016 we consulted on a draft long-list of options in our long-list
consultation. We have subsequently confirmed the long-list of options and reduced
the long-list to a short-list using the following short-listing criteria that we also
consulted on:
1. Fit for purpose 2. Technical feasibility 3. Practicability of implementing the option 4. Good electricity industry practice (GEIP) 5. System security (additional benefit resulting from an economic investment) 6. Indicative cost
The following table outlines our long-list options and our assessment of whether an
option is shortlisted. Options considered in the short-list are marked with a ✓. This
indicates the option forms part of a short-listed plan. It may not be the entire plan in
the short-list, i.e. a long-list option being short-listed does not mean it can by itself
completely resolve the need.
Table 3 Long-list Assessment
Longlist options Short-list?
Comments
Non-transmission options: Demand side
Load shedding SPS – post contingency
Fails criterion 1 – not fit for purpose. This component does not address the poor condition of the assets and does not present an entire solution. However, this could be used to defer investment in combination with other long-list components.
Load shifting Fails criterion 1 – not fit for purpose. As above
Demand Side Response (DSR) – pre contingency
Fails criterion 1 – not fit for purpose. As above
Non-transmission options: Supply side
New generation Fails criterion 1 – not fit for purpose. There is no indication from industry this is imminent. A range of generation scenarios will be considered in the options assessment.
Generation re-dispatch
Fails criterion 1 – not fit for purpose. This component does not address the poor condition of the assets and does not present an entire solution. This component is implicitly included in the short-list as it is covered in the Stochastic Dual Dynamic Programming (SDDP) analysis.
New distributed generation
Fails criterion 1 – not fit for purpose. There is no indication from industry this is imminent. A range of generation scenarios will be considered in the options assessment.
Short-listed. The Judgeford double tee option converts the loop-in, loop-out connection to Haywards and Wilton into a double tee at Judgeford.
HVDC runback This component does not address the poor condition of the assets and does not present an entire solution. This component is implicitly included in all development plans.
Fails criterion 1 – not fit for purpose. The circuit is currently under-utilised so additional capacity is not required.
Simplex: lower rated circuits
Fails criterion 1 – not fit for purpose. Configuring a Simplex circuit over the length of line involved will result in prohibitively high impedance. However, Simplex may be utilised in small sections of the line.
Patch fix Fails criterion 1 – not fit for purpose. The large amount of patch fixes required means the activity will be impractical to implement and prohibitively expensive. This could be used to defer investment in combination with other long-list components.
Dismantling Judgeford-Wilton
Short-listed
If we were to dismantle the JFD-WIL section of the line, load at WIL, CPK, KWA, TKR, and PNI would be supplied solely from the 110 kV double-circuit HAY-TKR-WIL line. A double circuit outage (planned or unplanned) would mean that any load at these GXPs could not be supplied. This option is short-listed to provide a reference point from which system benefits for other options are relative.
Options 3 – 6 in the table below explore different conductor technologies and sizes
while maintaining the same rating as the existing design. Different conductor sizes
were selected to compare the wind loadings, operating temperatures, and the cost of
structure and clearance modifications required.
Option 2 is like-for-like conductor with a reduced rating to investigate possible cost
savings.
Option 1 is significantly different in that it requires the dismantling of the existing circuit
(and continuing power system operations in its absence permanently).
Option 7 is significantly different again as it changes the circuits to a double tee
connection, improving the distribution of power across the circuits. This option would
utilise a simplex conductor configuration as opposed to the existing duplex conductor
configuration.
Table 4 Short-list of options
Option
#
Option Description
1 Dismantling JFD-WIL and create a 2nd BPE-LTN-HAY circuit
• Remove JFD-WIL section of circuits and jumper across at Judgeford
2 Duplex Zebra ACSR Option A - Reduced rating
• Replace assets with modern equivalent of the existing Duplex Zebra ACSR/AC
• 65°C (reduced rating)
3 Duplex Zebra ACSR Option B - Existing rating
• Replace assets with modern equivalent of the existing Duplex Zebra ACSR/AC
• 75°C (existing rating)
4 Duplex Goat ACSR Existing rating
• Replace assets with Duplex Goat ACSR/AC
• 94°C ( existing rating)
5 Duplex Selenium AAAC Existing rating
• Replace assets with Duplex Selenium AAAC
• 70°C (existing rating)
6 Duplex Sulphur AAAC Existing rating
• Replace assets with Duplex Sulphur AAAC
• 57°C (existing rating)
7 Double tee connection • Reconfigure circuits at the Judgeford deviation to create a ‘double tee’ connection at Judgeford and reconductor the JFD-WIL section with simplex Chukar. See Figure 6 below.
Based on our analysis we intend to develop an application to the Commerce
Commission for:
Proposal at a Glance
What: Replace the existing conductors on the Judgeford to Wilton section of the Bunnythorpe to Wilton line with simplex Chukar, and reconfiguration to a ‘double tee’ connection at Judgeford.
When: Commence work in Q4 2019 and complete by Q4 2021
How much: Transpower is seeking approval for up to $8.9m additional base capex in RCP2 to cover the cost of assets commissioned before 1 July 2020. The remainder of the project cost will be included as base capex in our RCP3 funding application
Grid Outputs Replace the existing conductors on the Judgeford to Wilton section of the Bunnythorpe to Wilton line with simplex Chukar, and reconfiguration to a ‘double tee’ connection at Judgeford, and associated works. Obtaining property rights and environmental approvals as required.
Our cost estimate for the project, while we consider appropriate for option analysis, is
currently being further refined through additional investigation. Assuming the updated
cost does not change our conclusions, we intend to make our application to the
Commerce Commission. We are targeting making an application in June 2018 and do
not intend to consult further on this project before our application.
Table 13 summarises our Listed Project Capital Allowance application of $8.9m
million. Note that this figure covers only the portion of the project commissioned in
RCP2. The remainder of the capital will be recovered through RCP3 base capex.
Table 13 Listed project capital allowance application
Cost distribution Range of
distribution Point selected within distribution (probability)
Cost applied for ($000)
Capex (real 2017$) Triangle +30% / -30% P50 8,675
Inflation 190
Exchange rates -
IDC 30
Total LPCA (2021$)
8,894
The table below provides an indicative timing of the total capital spend over the
project. We will refine these timings and include confirmed schedules in our
In the below table we outline how this proposal meets the requirements to be
approved by the Commerce Commission under the Capex IM.
Table 17 - Capex IM checklist
Capex IM section Report cross reference
2.2.3 Listed Project
(2) Listed project definition (a) (i) capex > $20 million
(ii) to be commissioned in the regulatory period (b) replacement/ refurbishment (c) commencement date within the regulatory period (d) not already in base capex
4.3 Costs
3.2.4 Approval of base capex in addition to the base capex allowance
(1) Due by June twenty-two months before the end of a regulatory period
Submission expected in June 2018 (due before Aug 2018)
(2)(a) reason for project, technical evidence 2.2 Need
(2)(b) options considered 3 Identify options
(2)(c) scope and grid outputs 2 Need verification and assessment level
(2)(d) technical and costing info & risks 4.3 Costs
(2)(e) costs by year and assumptions To be completed for final consultation
(2)(f) cost-benefit and sensitivity 4.5.4 Expected net electricity market benefit 4.5.5 Robustness of the results
(2)(g) consultation 6 Consultation to date A.3 September 2016 stakeholder consultation
(2)(h) Board and CEO sign-off To be completed for final consultation
(4)(a) consultation process as per base capex (publish / X-subs,etc) Appendix 3 (consultation responses)
(4)(b) evaluated as per base capex criteria, including Schedule A where relevant: - follow Transpower policies and planning standards for grid / base capex; - cost-effective; - reasonable assumptions (method); - risk-based good asset management, - grid output dependencies - deliverability; - reasonable asset replacement models (inputs & method); - reasonable demand forecasts (inputs & method); - scope for efficiency gains
2.2 Need 4.4 Economic assumptions
(5)(a) forecast CPI used for base capex in regulatory period; (b) forecast FX rates used for base capex for regulatory period; (c) percentage of foreign capex
A.2 Short-listed conductors In the below table we summarise the reconductoring options that were considered in order to derive our short-list.
Conductor Meets load growth scenarios
Future upgrade possible and reasonable
Property rights infringement and environmental impacts
Engineering issues Preferred conductor for JFD-WIL section
Zebra duplex ACSR/AC (@65°C)
Yes Yes, but at unnecessary expense if de-rated now
Will maintain the status quo Straight forward delivery.
Zebra duplex ACSR/AC (@75°C)
Yes Yes Will maintain the status quo Straight forward delivery.
Goat duplex ACSR/AC (@94°C)
Yes No, may anneal and mechanically damage the conductor
Will maintain the status quo Reasonably straight forward delivery. Dissimilar conductor requires more attention during construction.
Selenium duplex AAAC (@70°C)
Yes No, clearance rectifications would not be reasonable
Exceeds existing conductor envelope, risk many property infringements. Some clearance rectifications may require consents.
Some under-clearances may not have feasible mitigations. Reasonably straight forward wiring, dissimilar conductor requires more attention during construction.
Sulphur duplex AAAC (@57°C)
Yes No, clearance rectifications would not be reasonable
Exceeds existing conductor envelope, risk of many property infringements not covered in cost assessment, many assessments to be undertaken
Some under-clearances and structure overloads may not have feasible mitigations. Reasonably straight forward wiring, dissimilar conductor requires more attention during construction.
Yes Yes Will maintain the status quo. Consent and property rights required at JFD Tee site
Duplex --> Simplex requires more attention and management methods during construction. Substation works impose moderate programme dependencies and additional design work-streams (costs included).
A.3 September 2016 stakeholder consultation: summary
of submissions with Transpower responses
This section summarises submissions received on our long-list consultation paper
Bunnythorpe to Wilton line (Judgeford to Wilton section) reconductoring of September 2016
(long-list consultation)16. Below we have endeavoured to summarise submitter’s key points
briefly: please refer to their submissions for further detail.
Submissions were received from:
• Major Electricity Users Group (MEUG)
• Contact Energy Limited
We include the submitters’ comments against the 11 specific questions asked in the
consultation report, plus any general comments of relevance to specific questions. We also
provide our response to each issue raised.
Our questions, and additional questions from submitters, are listed under the relevant
subject heading from the long-list consultation report.
A.3.1 Need and project scope
Q1 Are there any other considerations relating to the need that we should incorporate into this project?
MEUG responded that Transpower should incorporate an assessment of the exacerbators
and beneficiaries of the preferred solution and the incremental cost they will pay versus the
benefit they will receive.
Transpower response:
We have not estimated the cost that proposed changes to the Transmission Pricing Methodology might impose on specific customers.
Contact Question
Is the higher North Island price (identified as a result of the HAY-BPE constraints) considered in the option analysis, i.e. the option that would have the least construction time and therefore lower exposure to the pricing risk?
Transpower response:
The duration of construction has not been considered in our options assessment. However, we do not consider it material to our option assessment for this project. The preferred option requires less tower and foundation strengthening than the other reconductoring options considered. Also, after the Judgeford tee is commissioned at the beginning of the second year of work, generation constraints during most construction will be similar to the existing system with all circuits in service as the BPE-WIL circuit will be disconnected at the tee point (JFD). Therefore, outages on the JFD-WIL section will have little impact on HAY-
16 The consultation paper, the non-confidential submissions and this document are available at
BPE capacity. There will be some outages equivalent to taking HAY-LTN out of service in the present system to commission the double tee and complete the associated protection work.
Contact Question
If a decision to shut or reduce demand at Tiwai is made then would this project be expedited so that it occurs prior to this demand reduction occurring to minimise the pricing risk due to higher DC north flow?
Transpower response:
We intend to proceed with delivery as soon as we obtain regulatory approval, therefore there is not an opportunity to expedite commissioning of the project.
A.3.2 Long-list of options
Q2 Is our long-list of options reasonable? Should any other options be added to the list?
No responses received.
A.3.3 Non-transmission solution information
Q3 Do you have any suggestions or proposals for non-transmission solutions to meet the need? If so, please provide the information requested (in section 5.4) so that we can apply a high-level assessment against our short-listing criteria?
Contact has responded with a battery storage non-transmission solution to address the
reduction in security during construction. Further details of this solution can be found in
Contact’s submission on the project website16.
Contact Question
It is mentioned that a Non-Transmission Solution (NTS) is likely to be required during the construction phase to mitigate the risk of reduced security. What is the timeframe of this construction phase and scale of NTS required?
Transpower response:
There will be little or no reduction in security, so non-transmission solutions will not be required. We identified that there may be a role for non-transmission solutions to mitigate any potential reduction in security to Wellington during construction. However, we have now confirmed that the value of any such mitigation would be very low to zero.
A.3.4 Short-listing criteria
Q4 Do you agree with our criteria for short-listing? If not, which criteria should we modify, include or remove, and why?
Q5 Are our demand forecast assumptions appropriate for this investigation? If not, please outline any significant (>5 MW) increases or decreases in load you expect to occur in the Wellington region.
MEUG is unsure whether the use of a one-size fits all P90 forecast is appropriate. They
suggest a lower percentile forecast in the near term where there are maintenance or other
options available allowing deferral of high cost decisions.
Transpower response:
This option assessment is based on expected (P50) forecasts and a range of market development scenarios. Transpower uses our prudent (P90) forecast to identify future needs that are driven by load growth to ensure that the needs are identified early. All economic assessments are undertaken using the expected forecast.
A.3.6 Market development scenarios
Q6 Are these market development scenarios appropriate for this investigation? If not, we welcome specific information regarding changes.
No responses received.
A.3.7 Analysis period
Q7 Do you consider the proposed calculation period of 40 years appropriate for the Bunnythorpe to Wilton A (Judgeford to Wilton Section) Line Reconductoring investigation?
MEUG responded “yes”, and also suggested to test a scenario with a 20-year horizon as
defined in the Capex IM.
A.3.8 Value of expected unserved energy
Q8 Do you consider this VoLL ($25,300/MWh) appropriate for valuing unserved energy?
MEUG responded that Transpower should consider the more recent analysis by the
Electricity Authority (Investigation into the Value to Lost Load in New Zealand – Report on
methodology and key findings, 23rd July 2013).
Transpower response:
We note the caveats included in the EA’s report regarding the applicably of the published VoLL figures to the general population. As such, we consider the report a valuable start to a comprehensive VoLL review, but insufficient justification to change the VoLL figures at this time. We have undertaken sensitivity analysis to ensure our results are not sensitive to this figure.
Q9 Do you consider this VoLL appropriate for valuing lost load for your business? If, not, what alternative VoLL would you recommend and what evidence are you able to provide to support your recommendation?
MEUG responded that Transpower should consider the more recent analysis by the
Electricity Authority (Investigation into the Value to Lost Load in New Zealand – Report on
methodology and key findings, 23rd July 2013).
Transpower response:
See our comments above.
A.3.9 Discount rate
Q10 Do you consider a discount rate of 7% appropriate for this investigation?
MEUG pointed to the Capex IM review in 2017 which might specify the discount rate to be
applied.
Transpower
response:
Transpower will adopt the discount rate as suggested by the Capex IM.
A.3.10 Expected Net Electricity Market Benefit
Q11 Are there other market costs or benefits which should be reflected in the analysis?