Top Banner
July 1, 2016 Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary School 29 Hazel Wolf K-8 at Pinehurst 42 Meany Middle School 55 Olympic Hills Elementary School 63 Seattle New World School at TT Minor 74 New Thornton Creek Building 81
92

Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Apr 17, 2018

Download

Documents

lenhi
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

July 1, 2016

Building Excellence IV Capital Levy

Projects Under Construction

Project Slide Number

Arbor Heights Elementary School 2

Cascadia Elementary School & Robert Eagle Staff Middle School 14

Genesee Hill Elementary School 29

Hazel Wolf K-8 at Pinehurst 42

Meany Middle School 55

Olympic Hills Elementary School 63

Seattle New World School at TT Minor 74

New Thornton Creek Building 81

Page 2: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Building Excellence IV Capital Levy

Arbor Heights Elementary School

Site: Landscape irrigation and drainage installation ongoing, playground equipment installation in-progress, concrete sidewalks and stairs ongoing.

South Building: Exterior – Sun-shade installation and painting complete. South stair enclosure ongoing. Interior – Acoustical ceiling tile installation complete at third floor. Casework and finish carpentry ongoing. Rubber floor tile and base molding ongoing. Window shade installation ongoing. Mechanical, electrical and plumbing (MEP) fixture installation ongoing. HVAC, plumbing, and electrical installation ongoing at first and third floor mechanical rooms and first floor boiler room.

Arbor: Exterior – Sheet metal flashing and window installation in-progress.

North Building: Exterior – Painting ongoing, sun-shade installation in-progress. Interior – Hardwood floor finishing complete at gymnasium. Window installation complete. Painting ongoing at second and third floor. Casework installation ongoing. Ceramic tile and carpet installation ongoing. MEP fixture installation ongoing.

Page 3: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Arbor Heights Elementary School

Site Plan

July 1, 2015July 10, 2015

Page 4: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Arbor Heights Elementary School

Aerial View from the North

May 31, 2016

Page 5: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Arbor Heights Elementary School

North Building – Northeast Perspective

June 27, 2016

Page 6: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Arbor Heights Elementary School

South Building – Southeast Perspective

June 27, 2016

Page 7: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Arbor Heights Elementary School

Site – Northeast Perspective

June 27, 2016

Page 8: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Arbor Heights Elementary School

South Building – Mechanical Room

June 27, 2016

Page 9: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Arbor Heights Elementary School

South Building – Kindergarten Room

June 27, 2016

Page 10: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Arbor Heights Elementary School

South Building – Special Ed Room

June 27, 2016

Page 11: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Arbor Heights Elementary School

North Building – Library

June 27, 2016

Page 12: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Arbor Heights Elementary School

North Building – Commons

June 27, 2016

Page 13: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Arbor Heights Elementary School

North Building – Gymnasium

June 27, 2016

Page 14: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Building Excellence IV Capital LevyCascadia Elementary School and Robert Eagle Staff Middle School

Site: Maintaining temporary erosion sedimentation control (TESC)

measures.

ES: Exterior - Window installation and prep for cement fiber board

panels installation ongoing. Air barrier complete. Roofing ongoing with

mid-ply nearly complete and cap sheet moving from south to north.

Interior – Gypsum wallboard installation (GWB) ongoing.

MS: Exterior metal stud framing and sheathing ongoing. MEP rough-in

ongoing.

Page 15: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Site Plan

Page 16: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Zone Map

Middle School Elementary School

Page 17: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Aerial View from the South

June 2, 2016

Page 18: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Elementary School - Zone 1- Exterior Insulation/Prep for CFB Panels, Looking Northeast

June 21, 2016

Page 19: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Elementary School - Zone 1 - Window Installation, Looking Southeast

June 21, 2016

Page 20: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Elementary School - Zone 1- Gypsum Wallboard Installation, Classroom

June 21, 2016

Page 21: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Elementary School - Zone 2 – Gypsum Wallboard Installation, 1st Floor Admin

June 21, 2016

Page 22: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Elementary School - Zone 7 - Exterior of Child Care, Looking Southwest

June 21, 2016

Page 23: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Elementary School - Zone 7 - Roofing Installation, Looking West

June 21, 2016

Page 24: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Middle School - Zone 1 - Exterior Framing and Sheathing, Looking Northeast

June 21, 2016

Page 25: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Middle School - Zones 2 & 3 - Hollow Metal Door Frames, Looking East

June 21, 2016

Page 26: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Middle School - Zone 3 - Exterior Framing and Sheathing, Looking Northwest

June 21, 2016

Page 27: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Middle School - Zone 9 - Gym, Looking North

June 21, 2016

Page 28: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Cascadia Elementary School & Robert Eagle Staff Middle School

Middle School - Roof, Skylights and Mechanical Penthouses, Looking Northwest

Page 29: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Building Excellence IV Capital Levy

Genesee Hill Elementary School

Site: Landscaping is ongoing at the upper tier of site; continued installation of chain link

fencing at lower and upper tiers.

Area 1: Continued final cleaning; continued programming controls sequencing and

development of graphics.

Area 2: Continued final cleaning; continued programming controls sequencing and

development of graphics.

Area 3: Continued final cleaning; functional testing continued; contractor coordinating

Health Inspection for kitchen; continued programming controls sequencing and

development of graphics; coordinating meeting with SPS, DEL and eWorks to inspect

childcare rooms and coordinate licensing.

Area 4: Continued final cleaning; began functional testing; continued programming

controls sequencing and development of graphics.

Note: Owner mechanical training occurred and SPS furnished cleaning supplies in

preparation for occupancy. Furniture beginning to arrive.

Page 30: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Genesee Hill Elementary School

Site Plan

Page 31: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Genesee Hill Elementary School

Aerial View from the East

Page 32: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Genesee Hill Elementary School

Aerial View from the North

Page 33: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Genesee Hill Elementary School

Aerial View from the East Looking West

Page 34: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Genesee Hill Elementary School

Building's North Elevation - Visitor/Childcare Drop-off Parking Lot, Looking West

Page 35: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Genesee Hill Elementary School

Area 1 - Level 1 - Looking West at Main Corridor

Page 36: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Genesee Hill Elementary School

Area 1 - Level 1 - Typical Kindergarten Room

Page 37: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Genesee Hill Elementary School

Area 1 - Level 2 - Typical Common Teaching Space

Page 38: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Genesee Hill Elementary School

Area 2 - Level 2 - Library Space

Page 39: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Genesee Hill Elementary School

Area 2 - Level 1- Looking North at the Top of Stairs Toward Main Entrance

Page 40: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Genesee Hill Elementary School

Area 2 - Level 1- Looking South Towards Entrance to Area 3 Commons

Page 41: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Genesee Hill Elementary School

Area 3 – Looking From Stage, Through Commons to Area 4 Gymnasium

Page 42: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Building Excellence IV Capital Levy

Hazel Wolf K-8 at Pinehurst

Site: Grading of the courtyard, parking lots, and sidewalks. Final grading of

loading dock area continues. Installation of storm drain line tie-ins complete.

Building A: A1 Exterior - Top deck water proofing continues. Exterior stairs

complete. Interior - Cabinetry complete. Kitchen equipment install ongoing.

Ceiling grid/tile install ongoing. Painting ongoing. Area A2 Interior - Final coats

of paint ongoing at all floors. Grid ceiling complete, ceiling tiles nearly

complete. Commissioning of equipment ongoing. MEP fixtures being installed.

Concrete floors receiving final grinding. Elevator received initial inspections.

Area A3 Exterior - Water proof membrane installation ongoing. Concrete stairs

form work complete. Interior - GWB finishing complete. Painting ongoing.

Building B: Exterior - Roofing complete. Exterior sheeting and air barrier

complete. Interior - Band/choir room painting ongoing. Ceiling installation

ongoing.

Building C: Exterior - Metal siding complete. Interior - Elevator installation

complete. Painting ongoing. Gym wood floor work ongoing. Sound attenuation

and sports equipment installation complete.

Page 43: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Hazel Wolf K-8 at Pinehurst

Site Plan

Page 44: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Hazel Wolf K-8 at Pinehurst

Aerial View from the East

June 16, 2016

Page 45: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Hazel Wolf K-8 at Pinehurst

Areas A1 and C – Exterior Metal Siding Finish

June 23, 2016

Page 46: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Hazel Wolf K-8 at Pinehurst

Area B – Outside Play Area, looking North East

June 23, 2016

Page 47: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Hazel Wolf K-8 at Pinehurst

Site – Loading Dock Final Grades, looking East

June 23, 2016

Page 48: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Hazel Wolf K-8 at Pinehurst

Courtyard – Forming Concrete Walkway, looking Southwest

June 23, 2016

Page 49: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Hazel Wolf K-8 at Pinehurst

Area A1 – Kitchen Finishes

June 23, 2016

Page 50: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Hazel Wolf K-8 at Pinehurst

Area A1 – Library Finishes

June 23, 2016

Page 51: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Hazel Wolf K-8 at Pinehurst

Area A1 – Hydronic Loop Pump Room

June 23, 2016

Page 52: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Hazel Wolf K-8 at Pinehurst

Area A2 – Corridor, Polished Concrete Floor

June 23, 2016

Page 53: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Hazel Wolf K-8 at Pinehurst

Areas B and C – Commons Finishes

June 23, 2016

Page 54: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Hazel Wolf K-8 at Pinehurst

Area C – Gym Floor

June 23, 2016

Page 55: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Building Excellence IV Capital Levy

Meany Middle School

Site: Partial site mobilization.

1954 Classroom Wing: Interior – Window concrete infill is progressing in

Sector 4 and 5. This activity will continue until the end of the month. Wall

framing and installation of shear walls is progressing in Sector 4 and parts

of Sector 5. Plumbing rough-in has started in restrooms. Band and Choir

room concrete cuts complete for receipt of new windows. Insulation at Band

and Choir will complete this week. MEP rough-in progressing and will

continue in sector 4 and 5 for another week. Trenching for MEP rough-in to

continue into next week.

Remainder of building: No work occurring until after Seattle World School

leaves site. Contractor has full access to site not later than July 12, 2016

Page 56: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Meany Middle School

1964 Aerial Photo

July 1, 2015July 10, 2015

1954 Classroom Wing

Page 57: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Meany Middle School

Trenching for Mechanical/Electrical/Plumbing Rough-in

June 24, 2016

Page 58: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Meany Middle School

Trenching and Framing in Science Classrooms

June 24, 2016

Page 59: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Meany Middle School

Mechanical/Plumbing Rough–In at Restrooms

June 24, 2016

Page 60: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Meany Middle School

Shear Wall Framing Progressing in Sector 4

June 24, 2016

Page 61: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Meany Middle School

Typical Partial Demolition at Window Sills

June 24, 2016

Page 62: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Meany Middle School

Mechanical Piping Routing Conflict W/ Existing Conditions

June 24, 2016

Page 63: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Building Excellence IV Capital Levy

Olympic Hills Elementary School

Site: Continued potholing and demo for street improvements.

Monitoring TESC measures ongoing.

Zone A: Framing complete. Brick installation ongoing. MEP rough-in

ongoing.

Zone B: Framing wood walls, 2nd floor. Pouring slab-on-wood-deck.

Zone C: Framing wood walls.

Zone D: Started wood framing.

Page 64: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Olympic Hills Elementary School

Site Plan

Page 65: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Olympic Hills Elementary School

Zone Map

Page 66: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Olympic Hills Elementary School

Aerial View from the West

June 1, 2016

Page 67: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Olympic Hills Elementary School

Zone A - Overhead HVAC Ductwork, 1st Floor Classroom

June 22, 2016

Page 68: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Olympic Hills Elementary School

Zone A - In-Wall MEP Rough-In, 1st Floor Classroom

June 22, 2016

Page 69: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Olympic Hills Elementary School

Zone A - Interior Framing, 2nd Floor

June 22, 2016

Page 70: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Olympic Hills Elementary School

Zone B - Concrete Slab-On-Wood-Deck, 2nd Floor Hallway

June 22, 2016

Page 71: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Olympic Hills Elementary School

Zone B - Framing and Standing Walls, 2nd Floor, Looking South East

June 22, 2016

Page 72: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Olympic Hills Elementary School

Zone C - Framing, Looking Southwest

June 22, 2016

Page 73: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Olympic Hills Elementary School

Zone D - Steel Columns Partially Erected, Looking South

June 22, 2016

Page 74: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Building Excellence IV Capital Levy

Seattle World School at T.T. Minor

Area A – Administration Office, Student Services, Health Clinic and Library: GWB finishing nearing completion. Overhead MEP rough-in work complete. Ceiling grid installation ongoing. Light fixture installation ongoing. Low voltage data installation ongoing. Casework installation ongoing. Finish painting ongoing. ADA stage ramp in progress.

Area B – Multipurpose, Kitchen, Boiler Room: GWB finishing nearing completion. Overhead MEP rough-in work complete. Ceiling grid installation ongoing. Light fixture installation ongoing. Low voltage data installation ongoing. Casework installation ongoing. Finish painting ongoing.

Area C – Classrooms: Painting on going. Air Handling Units being set in place. Ceiling grid installation ongoing, Data cable installation ongoing. Cabinet and casework installation ongoing. Finish floor material installation ongoing.

Site: Work on 18th Street complete.

Page 75: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Seattle World School at T.T. Minor

Site Plan

Area C

Area B

Area A

Area C

Area B

Area A

Page 76: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Seattle World School at T.T. Minor

Site – Seattle City Light Hooking Up Permanent Power

June 28, 2016

Page 77: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Seattle World School at T.T. Minor

Area A – Floor Sealer and Flooring Preparation

June 28, 2016

Page 78: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Seattle World School at T.T. Minor

Area B – Exterior Painting

June 28, 2016

Page 79: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Seattle World School at T.T. Minor

Area C – Window Installation On-Going

June 28, 2016

Page 80: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Seattle World School at T.T. Minor

Site – ADA Ramp Concrete Walls

June 28, 2016

Page 81: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

Building Excellence IV Capital Levy

New Thornton Creek Building Site: Finishing subgrade for playfield. Chain link fencing around athletic field

on-going. Poured concrete entry and exit drives for west parking lot. Began landscaping in interior courtyard.

Off-site Improvements: Ongoing pouring of concrete sidewalks, curbs and ADA ramps along NE 80th St. Poured porous pavement on NE 80th St and 40th Ave. NE.

Building A: Roofing over Gym and Childcare on-going. Hardie panel installation on-going. Preparing and painting GWB in Commons, Gym and Childcare. Preparing floor for resilient flooring installation. Placed kitchen tile flooring. Delivered kitchen equipment. Ongoing placement of ductwork and louvers.

Building B: Hardie panel installation on-going. Completed painting on first and second floors classrooms. Completed installation of roller shades and wall panels. Began tackable wall surface installation. HVAC rough-in at mechanical penthouse on-going.

Building C: Ceramic tile installation in bathrooms on-going. Installing casework in classrooms. Completed installation of roller shades and wall panels. Began tackable wall surface installation. Trim of electrical devices on-going.

Page 82: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

New Thornton Creek Building

Key Plan

Building C

Building B

Building A

D

Page 83: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

New Thornton Creek Building

Aerial View from the West

June 15, 2016

Page 84: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

New Thornton Creek Building

Site – Pavement around Dugout at Athletic Field

Page 85: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

New Thornton Creek Building

Site – Landscaping in K-1 Courtyard

Page 86: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

New Thornton Creek Building

Building A – Loading Dock

Page 87: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

New Thornton Creek Building

Building A – Painting Ceilings and Walls in Gym

Page 88: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

New Thornton Creek Building

Building A – Painting in Childcare

Page 89: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

New Thornton Creek Building

Building A – Kitchen Equipment

Page 90: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

New Thornton Creek Building

Building A – Geothermal Piping in Main Mechanical Room

Page 91: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

New Thornton Creek Building

Building B – Tackable Surface over Lockers

Page 92: Building Excellence IV Capital Levy Projects Under ... · Building Excellence IV Capital Levy Projects Under Construction Project Slide Number ... electrical and plumbing (MEP) ...

New Thornton Creek Building

Building B – Whiteboard Installation at Classrooms