Building Committee Presentation: JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT Hanson, MA | Whitman-Hanson Regional School District
39

Building Committee Presentation: JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Jan 10, 2016

Download

Documents

Halil

Building Committee Presentation: JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT Hanson, MA | Whitman-Hanson Regional School District. Module 3 Preferred Schematic Study and Report CONTENTS. EVALUATION OF EXISTING CONDITIONS FINAL EVALUATION OF ALTERNATIVES - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Building Committee Presentation: JULY 17, 2012PREFERRED SCHEMATIC STUDY AND REPORT Hanson, MA | Whitman-Hanson Regional School District

Page 2: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Module 3 Preferred Schematic Study and Report

CONTENTS

1. EVALUATION OF EXISTING CONDITIONS

2. FINAL EVALUATION OF ALTERNATIVES

3. SELECT PREFERRED OPTION

4. FINAL SUBMISSION REQUIREMENTS

5. NEXT STEPS MOVING FORWARD

Page 3: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Module 3 Preferred Schematic Study and Report

Evaluation of Existing Conditions

Updates to Original Existing Conditions Report

1. Wetlands

2. Historical

3. Geotechnical

Page 4: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Module 3 Preferred Schematic Study and Report

Evaluation of Existing Conditions

Updates to Original Existing Conditions Report

Page 5: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Module 3 Preferred Schematic Study and Report

Final Evaluation of Alternatives

1. Proposed Space Summaries• Options 4A & 4B: PK-2 New Construction Maquan School

• Options 5: PK-5 Addition/ Renovation to Indian Head School• Options 6A & 6B: PK-5 New Construction Combined Maquan & Indian Head

2. Conceptual Plans- All Options• Option 4A: Site Plan, Floor Plans, & Phasing Plans

• Option 4B: Site Plan, Floor Plans, & Phasing Plans• Option 5: Site Plan, Floor Plans, & Phasing Plans• Option 6A: Site Plan, Floor Plans, & Phasing Plans• Option 6B: Site Plan, Floor Plans, & Phasing Plans

3. Proposed Project Construction Schedule

4. Proposed Total Project Budget and Construction Cost Estimate

Page 6: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Module 3 Preferred Schematic Study and Report

1. Proposed Space Summaries

PK-2New ConstructionMaquan Only

PK-5 Addition/ Renovation to Indian Head

PK-5New ConstructionCombined Maquan & Indian Head

Existing New

Net Floor Area (NFA)

60,033 SF 17,258 SF 69,157 SF 89,558 SF

Gross Floor Area (GFA)

90,050 SF

36,996 SF 100,278 SF

129,859 SF137,274 SF

Page 7: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Maquan PK-2:Enrollment: 395

A new 2-story school building on the Maquan site for Pre-K to grade 2.

Demolition of existing Maquan School.Estimated Construction Costs:Total: $30,515,665

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Option 4A| PK-2, New 2-Story School on Maquan Site – Site Plan

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

New SepticField

Page 8: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 4A| PK-2, New 2-Story on Maquan Site – Building Plans

Maquan Elementary SchoolFeasibility Study

Hanson, MA

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

Page 9: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

New SepticField

Option 4A| PK-2, New 2-Story School on Maquan Site – Phasing Plan

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

1

NO WORK

PHASE 1: Septic – Early bid package. Temporary tie in of existing septic.

Page 10: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

New SepticField

Option 4A| PK-2, New 2-Story School on Maquan Site – Phasing Plan

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

1

2NO

WORK

PHASE 1: Septic – Early bid package. Temporary tie in of existing septic.

PHASE 2: Building & Site

Page 11: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

New SepticField

Option 4A| PK-2, New 2-Story School on Maquan Site – Phasing Plan

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

PHASE 1: Septic – Early bid package. Temporary tie in of existing septic.

1

PHASE 2: Building & Site

2PHASE 3: Demo & Site

3

NO WORK

Page 12: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 4B| PK-2, New 2-Story School on Maquan Site – Site Plan

Maquan PK-2:Enrollment: 395

A new 2-story school building on the Maquan site for Pre-K to grade 2.

Demolition of existing Maquan School

Estimated Construction Costs:Total: $31,201,959

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

New SepticField

Page 13: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 4B| PK-2, New 2-Story School on Maquan Site – Building Plans

Maquan Elementary SchoolFeasibility Study

Hanson, MA

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

Page 14: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 4B| PK-2, New 2-Story School on Maquan Site – Phasing Plan

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

New SepticField 1

NO WORK

PHASE 1: Septic – Early bid package.

Page 15: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 4B| PK-2, New 2-Story School on Maquan Site – Phasing Plan

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

New SepticField

2NO

WORK

PHASE 1: Septic – Early bid package.

PHASE 2: Building & Site

1

Page 16: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 4B| PK-2, New 2-Story School on Maquan Site – Phasing Plan

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

PHASE 1: Septic – Early bid package.

PHASE 2: Building & Site

2PHASE 3: Demo & Site

3

NO WORK

New SepticField 1

Page 17: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 5| PK-5, Renovation and Addition to Indian Head with Partial Demolition – Site Plan

Combined PK-5:Enrollment: 800

Demolition of the Indian Headone story wing.

New 2-story additions.

Targeted renovation of the existing 2-story 1951 wing.

Demolition or re-purposing of Maquan School

Estimated Construction Costs:Total: $43, 841, 800

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

New SepticField

Page 18: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 5| PK-5, Renovation and Addition to Indian Head with Partial Demolition – Building Plans

Maquan Elementary SchoolFeasibility Study

Hanson, MA

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

Page 19: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 5| PK-5, Renovation and Addition to Indian Head with Partial Demolition – Phasing Plan

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

1

PHASE 1: Addition; Serves as a 2 story swing space for Phase 2

New SepticField

Page 20: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 5| PK-5, Renovation and Addition to Indian Head with Partial Demolition – Phasing Plan

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

1

2

PHASE 1: Addition; Serves as a 2 story swing space for Phase 2

PHASE 2: Demo & Addition

New SepticField

Page 21: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 5| PK-5, Renovation and Addition to Indian Head with Partial Demolition – Phasing Plan

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

1

2

3A3B

PHASE 1: Addition; Serves as a 2 story swing space for Phase 2

PHASE 2: Demo & Addition

PHASE 3A & 3B: Summer RenovationsNew

SepticField

Page 22: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 5| PK-5, Renovation and Addition to Indian Head with Partial Demolition – Phasing Plan

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

PHASE 1: Addition; Serves as a 2 story swing space for Phase 2

1

PHASE 2: Demo & Addition

2 PHASE 3A & 3B: Summer Renovations

3A3B

PHASE 4: Demo & Site

4

New SepticField

Page 23: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 6A| New 2-Story School on Indian Head Site – Site Plan

Combined PK-5:Enrollment: 800

A new 2-story building for Pre-K to grade 5 on the Indian Head site.

Demolition or re-purposing of Maquan and Indian Head Schools

Estimated Construction Costs:Total: $42,594,292

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

New Septic Field

Page 24: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 6A| New 2-Story School on Indian Head Site – Building Plans

Maquan Elementary SchoolFeasibility Study

Hanson, MA

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

Page 25: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 6A| New 2-Story School on Indian Head Site – Phasing Plan

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

1

PHASE 1: Building , Septic, & Site

New SepticField

Page 26: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 6A| New 2-Story School on Indian Head Site – Phasing Plan

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

PHASE 1: Building , Septic, & Site

1

PHASE 2: Demo & Site

2

New SepticField

Page 27: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 6B| New 2-Story School on Maquan Site- Site Plan

Combined PK-5:Enrollment: 800

A new 2-story building for Pre-K to grade 5 on the Maquan site.

Demolition of Maquan School and demolition of re-purposing of Indian Head School

Estimated Construction Costs:Total: $43,017,532

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

New SepticField

Page 28: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 6B| New 2-Story School on Maquan Site – Building Plans

Maquan Elementary SchoolFeasibility Study

Hanson, MA

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

Page 29: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 6B| New 2-Story School on Maquan Site- Phasing Plan

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

1

PHASE 1: Septic – Early bid package. Temporary tie in of existing.

New SepticField

Page 30: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 6B| New 2-Story School on Maquan Site- Phasing Plan

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

2

PHASE 1: Septic – Early bid package. Temporary tie in of existing.

PHASE 2: Building & Site

1New SepticField

Page 31: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option 6B| New 2-Story School on Maquan Site- Phasing Plan

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Module 3 Preferred Schematic Study and Report Conceptual Plans- All Options

PHASE 1: Septic – Early bid package. Temporary tie in of existing.

PHASE 2: Building & Site

2PHASE 3: Demo & Site

3 1New SepticField

Page 32: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Option 4A & 4B| PK-2, New 2-Story School on Maquan Site

Module 3 Preferred Schematic Study and Report Project Construction Schedule

PHASE 2 – 18 MONTHS

Mar

ch 1

4, 2

014

Early

bid p

acka

ge

4 MONTHS

8 WEEKS

June

20, 2

014

Constr

uctio

n sta

rts

Jan

4, 2

015

NEW SEPTICSYSTEM

13 WEEKS

April 2

5, 2

014

Bidding

star

ts

BUILD NEW BUILDING + SITEWORK

DEMO OLD BLDG + SITEWORK

Dec. 2

1, 2

014

Mov

e int

o ne

w bldg

.

May

3, 2

016

Constr

uctio

n co

mple

te

PHASE 1 PHASE 2 PHASE 3

Page 33: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Option 5| PK-5, Renovation and Addition to Indian Head with Partial Demolition

Module 3 Preferred Schematic Study and Report Project Construction Schedule

PHASE 2 – 18 MONTHS

9 WEEKS

8 WEEKS

April 2

0, 2

015

Mov

e int

o so

uth

addit

ion

Augus

t 24,

201

5

BUILD NEW ADDITION (SOUTH)

10 MONTHS

April 2

5, 2

014

Bidding

star

ts

DEMO 1960’S WING + BUILD SEPTIC SYSTEM + NEW

ADDITION (NORTH)

DEMO MAQUAN

Nov. 21

, 201

6

Mov

e int

o no

rth

addit

ion

Ma

rch

20

, 2

01

7C

on

stru

ctio

n c

om

ple

te

PHASE 1 PHASE 2 PHASE 4

4 MONTHS

June

20, 2

014

Constr

uctio

n sta

rts

RENO EXIST. INDIAN HEAD

PHASE 3A

9 WEEKS

June

22,

201

5

Augus

t 24,

201

6

RENO EXIST. INDIAN HEAD

PHASE 3B

June

22,

201

6

Page 34: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Option 6A| New 2-Story School on Indian Head Site

Module 3 Preferred Schematic Study and Report Project Construction Schedule

PHASE 2 – 6 MONTHS

8 WEEKS

April 2

0, 2

016

Mov

e int

o ne

w buil

ding

NEW SEPTIC SYSTEM + BUILD NEW BUILDING

PHASE 1 - 22 MONTHS

April 2

5, 2

014

Bidding

star

ts

Nov. 21

, 201

6

Constr

uctio

n

com

plete

PHASE 1 PHASE 2

June

20, 2

014

Constr

uctio

n sta

rts

DEMO OLD BLDGS. + SITEWORK

Page 35: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Maquan Elementary SchoolFeasibility Study

Hanson, MA Whitman-Hanson Regional School District

Option 6B| New 2-Story School on Maquan Site

Module 3 Preferred Schematic Study and Report Project Construction Schedule

PHASE 2 – 22 MONTHS

Mar

ch 1

4, 2

014

Early

bid p

acka

ge

6 MONTHS

8 WEEKS

June

20, 2

014

Constr

uctio

n sta

rts

NEW SEPTICSYSTEM

13 WEEKS

April 2

5, 2

014

Bidding

star

ts

DEMO OLD BLDGS. + SITEWORK

April 2

0, 2

016

Mov

e int

o ne

w bldg

.

Nov. 21

, 201

6

Constr

uctio

n co

mple

te

PHASE 1 PHASE 2 PHASE 3

BUILD NEW BUILDING + SITEWORK

Page 36: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Option Construction CostProject Cost

6A New School at Indian Head $42,594,292 $53,242,865or Maquan, PK-5

4A New school at Maquan $30,515,665$38,144,581PK-2

5 Add. Reno. Indian Head $43,841,800$54,802,250(partial demo) PK-5

Module 3 Preferred Schematic Study and Report Proposed Total Project Budget and Construction Cost Estimate

4B New school at Maquan $31,201,959$39,002,449PK-2

6B New School at Indian Head $43,071,532 $53,771,915or Maquan, PK-5

Recommended Option

Page 37: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Module 3 Preferred Schematic Study and Program

Final Submission Requirements

1. Overview

2. Educational Program

3. Space Summary

4. Building Plans

5. LEED/CHPS Scorecard

6. Site Plans

7. Budget

8. Updated Project Schedule

Page 38: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Module 3 Preferred Schematic Study and Report

Next Steps Moving Forward

Target Dates

1. Vote Approval of Submission July 24, 2012

2. Feasibility Submission to MSBA August 6, 2012

3. Board Meeting & Proceed to Schematic Design October 3, 2012

4. Schematic Design Submission to MSBA December 13, 2012

5. Project Scope & Budget Meeting December 28, 2012

6. Hanson Town Meeting May 8, 2013

7. Ballot Vote May 18, 2013

8. Bidding Starts April 25, 2014

9. Construction Complete May 3, 2016 – March 20, 2017

Page 39: Building Committee Presentation:        JULY 17, 2012 PREFERRED SCHEMATIC STUDY AND REPORT

Thank You