GREENVILLE TECHNICAL COLLEGEBUILDING 101 DEMOLITIONGREENVILLE, SOUTH CAROLINA
TMS# 0267000100305STATE PROJECT: H59-N079-MJ
PROJECT CONTACTS
OWNER: CIVIL ENGINEER & LANDSCAPE ARCHITECT: SURVEYOR:GREENVILLE TECHNICAL COLLEGE SEAMON WHITESIDE & ASSOCIATES, INC. FREELAND & ASSOCIATES, INC.506 S PLEASANTBURG DRIVE, 508 RHETT STREET, SUITE 101 323 WEST STONE AVE.GREENVILLE, SC 29607 GREENVILLE, SC 29601 GREENVILLE, SC 29609CONTACT: BILL TRIPP CONTACT: JOE BRYANT, P.E. PHONE: 864-271-4924PHONE: 864-250-8112 PHONE: 864-298-0534 EMAIL: [email protected]: [email protected]
MUNICIPALITY CONTACTS:POWER: ENCHROACHMENTLAND DISTURBANCE AND SANITARYDUKE ENERGY CITY OF GREENVILLESEWER:524 FAIRFOREST WAY CONSTRUCTION INSPECTION BUREAUCITY OF GREENVILLEGREENVILLE, SC 29607 206 S. MAIN STREET, 1ST FLOORENVIRONMENTAL ENGINEERING BUREAUPHONE: (800) 769-3766 GREENVILLE, SC 29602206 S. MAIN STREET, 8TH FLOOR
CONTACT: MR. JOHN BROGDONGREENVILLE, SC 29602PHONE: (864) 241-1224CONTACT: MR. DWAYNE COOPEREMAIL: [email protected]: (864) 467-4468
ARCHITECT: 407 WEST BROAD STREETSGA/NarmourWright Design GREENVILLE, SC 29602718 B SOUTH MAIN STREET PHONE: (864) 241-6100GREENVILLE, SC 29601 CONTACT: MR. MIKE SHARPLESS, PECONTACT: GABLE STUBBS EMAIL: [email protected]: 864-609-4199EMAIL: [email protected]
GENERAL NOTES
ALL RETAINING WALLS FOUR (4) FEET AND GREATER IN HEIGHT, WHEN MEASURED FROM THE BOTTOM OFTHE FOOTING TO THE TOP OF THE WALL AT ANY POINT, AND ALL RETAINING WALLS SUPPORTING ASURCHARGE OR IMPOUNDING CLASS I, II, OR IIIA LIQUIDS MUST BE ENGINEERED BY A REGISTERED SOUTHCAROLINA PROFESSIONAL ENGINEER AND SUBMITTED TO THE CITY OF GREENVILLE'S BUILDING CODESDEPARTMENT FOR REVIEW AND APPROVAL PRIOR TO INSTALLATION.
ANY REVIEW / ACCEPTANCE BY THE CITY OF GREENVILLE DOES NOT RELIEVE THE CONTRACTOR ORSUBCONTRACTORS FROM MEETING CODE / ORDINANCE REQUIREMENTS (SOUTH CAROLINA CODE OF LAWSSECTIONS 40-11-110 AND 40-59-90).
THE CONTRACTOR MUST NOTIFY THE CITY OF GREENVILLE'S CONSTRUCTION INSPECTION BUREAU (864)467-8890 A MINIMUM OF 72 HOURS PRIOR TO BEGINNING DEMOLITION AND CONSTRUCTION.
AN ENCROACHMENT PERMIT FROM THE SCDOT FOR STATE ROADS OR FROM THE CITY OF GREENVILLE FORCITY ROADS (CONTACT THE CONSTRUCTION INSPECTION BUREAU, (864) 467-8890) IS REQUIRED FOR ANYWORK PERFORMED WITHIN THE PUBLIC RIGHT-OF-WAY.
THE CONTRACTOR SHALL COORDINATE WITH THE ENGINEER OF RECORD FOR A DIGITAL STAKING PLAN TOESTABLISH COMPLETE HORIZONTAL AND VERTICAL CONTROL. THE CONTRACTOR IS RESPONSIBLE FORSURVEY STAKEOUT OF ALL IMPROVEMENTS. DISCREPANCIES BETWEEN THE PLANS, CONSTRUCTIONSTAKES, AND FIELD CONDITIONS SHALL BE REPORTED TO THE ENGINEER OF RECORD IMMEDIATELY FORRESOLUTION PRIOR TO INSTALLATION OF PROPOSED IMPROVEMENTS
PROJECT DESCRIPTION
THIS PROJECT CONSISTS OF THE DEMOLITION OF AN EXISTING BUILDING ANDSTABILIZATION OF THE SITE.
SITE LOCATION MAP
# SHEET REVISION HISTORY
C1.0
ALL ELEVATIONS ARE BASED ON THE TOPOGRAPHIC SURVEYCOMPLETED BY FREELAND & ASSOCIATES, INC. DATED FEBRUARY20, 2021.
SEDIMENT AND EROSION CONTROL PHASE 1 SEQUENCE OF CONSTRUCTION:
1. OBTAIN ALL NECESSARY PERMITS AND APPROVAL FROM THE CITY OF GREENVILLE AND SCDHEC. AFTER RECEIVING PLANAND PERMIT APPROVAL, SCHEDULE AN ONSITE PRE-CONSTRUCTION MEETING WITH THE ENGINEER, OWNER, CONTRACTOR,AND CITY OF GREENVILLE INSPECTOR BEFORE ANY MOBILIZATION OR WORK IS PERFORMED.
2. INSTALL SILT FENCE AND SEDIMENT TUBES AS SHOWN. DO NOT REMOVE VEGETATION OR TREES OUTSIDE OF THE LIMITSOF DISTURBANCE.
3. INSTALL PORTABLE SANITATION UNIT AND CONSTRUCTION DEBRIS ENCLOSURE. CONTRACTOR TO COORDINATE EXACTLOCATIONS AS SITE CONDITIONS ALLOW.
4. AFTER INSTALLATION OF PERIMETER BMPS, CONTRACTOR MAY BEGIN DEMOLITION ACTIVITIES PER THE DEMOLITION PLAN.CONTRACTOR TO REMOVE ALL DEMOLITION DEBRIS FROM THE SITE PER ALL LOCAL, STATE, AND FEDERAL REGULATIONS.
5. BEGIN PAVING OPERATIONS.6. INSTALL PERMANENT SEEDING AND LANDSCAPING ON THE SITE.7. CONTACT ENGINEER TO BEGIN CLOSE OUT PROCEDURES FOR THE PROJECT NO LATER THAN 30 DAYS BEFORE PROJECT
COMPLETION. SET UP INITIAL CLOSE OUT INSPECTION WITH THE ENGINEER AND CITY ENGINEER INSPECTOR.8. COMPLETE CORRECTION LIST FROM INITIAL CLOSE OUT INSPECTION. SCHEDULE FINAL CLOSE OUT INSPECTION WITH
ENGINEER AND CITY ENGINEER INSPECTOR.9. REMOVE (FLUSH) ALL SEDIMENT FROM STORM DRAIN PIPES AND STRUCTURES, AS NECESSARY.10. REMOVE ALL TEMPORARY EROSION AND SEDIMENT CONTROL DEVICES ONCE SITE IS COMPLETELY STABILIZED.11. PERFORM GENERAL CLEANUP OF THE SITE.12. SUBMIT NOTICE OF TERMINATION TO CITY OF GREENVILLE AND SCDHEC.