BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro • Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009 David Dobbs Publisher, Light Rail Now! Website
18

BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

Dec 24, 2015

Download

Documents

Randall Garrett
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

BRT as a Precursor of LRT?

Lyndon HenryData Analyst

Capital Metro • Austin, Texas

TRB/APTA Joint Light Rail Transit Conference

Los Angeles

20 April 2009

David DobbsPublisher, Light Rail Now! Website

Page 2: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

BRT as Precursor to Rail (Already)

• Guadalajara

• Dallas

Page 3: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

• Miami

• Seattle

• Los Angeles

Page 4: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

BRT vs. LRT – Comparative Issues

• BRT investment total cost typically lower (but total life-cycle costs may be higher)

• Signal protection system? Compatible?• BRT can use existing maintenance

facilities, but these may need expansion• Rail – longer life, higher salvage value• Rail – tends to attract more riders, longer

trips, lower unit O&M costs, more TOD

More…

Page 5: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

• BRT – major investment with 30-year life, possibly impediment to LRT

• Curbside alignments not optimal

• BRT typical cross-section: 20-54 ft• LRT typical cross-section: 30-35 ft• Different horizontal and vertical geometric

constraints and vehicle envelopes of BRT buses and LRT railcars

• If eventual conversion planned, LRT design requirements should rule

Page 6: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

BRT as Precursor to LRT – Advantages

• Build ridership in corridor, bolster case for LRT

• Some infrastructure elements could benefit LRT (e.g., signal prioritization, communications, PID system)

• Urban renovation elements (e.g., pedestrian amenities) could benefit LRT

• Stations, if movable/upgradable, could benefit LRT

Page 7: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

Case Examples

Page 8: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

Downtown Seattle Transit Tunnel

• 1.3 miles long, and has five stations• Intended for conversion to LRT, with tracks laid in

the busway pavement • Rails insufficiently insulated against stray current

leakage, insufficiently cushioned for noise control• Platforms too low to permit level boarding• $45 million overhaul necessary

Page 9: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

Seattle: I-90 Transit/HOV Project and East Link LRT

Page 10: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

Seattle: SR-99 RapidRide

• Pacific Highway South/International Boulevard (State Route 99)

• Intended to build transit ridership for eventual rail extensions

• Minimalist design, including mixed-traffic operation and lack of heavy infrastructure, may make conversion more feasible

Page 11: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

Ottawa: Transitway

• 16.0 miles dedicated “transitways" (busways), 26 stations + 1.2 route-miles CBD reserved lanes + 2.0 miles of mixed-traffic running + 6.6 miles of freeway shoulder lanes = 25.8 route-miles

• Severe CBD bus crowding

Page 12: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

Ottawa BRT-to-LRT Conversion Problems

• Service disruption during conversion• Value for money not sufficient to justify

conversion

Page 13: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

Austin: Capital MetroRapid

• Limited-stop service operating in mixed traffic

• 2 routes: N. Lamar/S. Congress and Burnet/S. Lamar.

• Lamar-Guadalupe-Congress route may build transit ridership for eventual LRT

• Minimalist design, low cost ($28 to$38 million) may make conversion to LRT more feasible

Page 14: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

Conclusions

Page 15: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

Conclusions

• Initial system design to facilitate conversion is critical

• BRT facilities should not represent an obstacle to the subsequent LRT

• BRT-specific infrastructure (including stations) should be designed to be very low in cost so sunk cost for BRT is not impediment to eventual conversion to LRT

More…

Page 16: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

• Conversion of “high-end” exclusive BRT facilities to LRT tend to involve some degree of transit service shutdown or disruption during conversion process

• In contrast, “lower-end” express-bus or limited-stop types of BRT service can probably continue parallel service on adjacent highway or arterial lanes during conversion period

More…

Page 17: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

• Alignments that have appropriated railway ROW for BRT make it virtually impossible to maintain a true parallel bus service – thus representing a serious obstacle facing conversion to LRT

• As planned BRT-to-LRT conversions become operational, updated assessments should be performed.

Page 18: BRT as a Precursor of LRT? Lyndon Henry Data Analyst Capital Metro Austin, Texas TRB/APTA Joint Light Rail Transit Conference Los Angeles 20 April 2009.

Lyndon Henry

Data Analyst

512.369-7756

[email protected]

512.441-3014

[email protected]