Bringing It In House. Indian Trails Sports Complex expansion. Financial Factors Availability of Employees Equipment Needed Time in Schedule Expertise. Belle Terre Parkway median beautification. Gateway/Neighborhood Sign – Palm Coast Parkway East Construction cost $135,581 - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Bringing  It In House

Bringing It

In House

Page 2: Bringing  It In House
Page 3: Bringing  It In House
Page 4: Bringing  It In House

IndianTrails

SportsComple

xexpansi

on

Page 5: Bringing  It In House

• Financial Factors• Availability of

Employees• Equipment

Needed• Time in Schedule• Expertise

Page 6: Bringing  It In House

Belle Terre Parkway

median beautification

Page 7: Bringing  It In House
Page 8: Bringing  It In House
Page 9: Bringing  It In House

Gateway/Neighborhood Sign –

Palm Coast Parkway EastConstruction cost$135,581Consultant’s estimate for completion

by outside contractor$205,715

Cost savings to the public$70,134

Page 10: Bringing  It In House

• Cost Savings• Quicker• No Change

Orders• More Control• Greater Flexibility• Availability of

Crews During Emergencies

Page 11: Bringing  It In House

4 new fields at Indian Trails Sports Complex

Our cost: $342,361Outside cost: $440,000

Swale Rehabilitation & Maintenance

Our cost: $8/linear footOutside cost: $12/linear foot

Page 12: Bringing  It In House

Ditch Maintenance: 1,525,640’ in 2011-12 vs. 664,700’ in 2010-11

Page 13: Bringing  It In House

$2,270,000

Page 14: Bringing  It In House
Page 15: Bringing  It In House

Maintenance, Repair, RenovationSwale Rehabilitation/Maintenance Work

(including design) $1,054,000Ditch Maintenance$249,000Equipment Installation, Maintenance-Utility

Division $83,000Communication Equipment Maintenance

and Repair $14,000Smoke Testing$13,000Playground Renovations (Community Center,

Holland Park)$10,000Swimming Pool Maintenance$5,000Community Garden Reconstruction$4,000

Page 16: Bringing  It In House

New Construction/Design*Survey Services (*NOTE: the city has always

done some survey work in-house)$243,000Paths/Trails (construction) $113,000Section 31 Phase 1 Drainage Rehabilitation

(construction)$109,000Drainage Pipes (construction)$101,000Stormwater (design)$76,000Neighborhood/Gateway Signs – East Palm Coast

Parkway $70,000Minor Road Construction – ITSC Roadway

Extension $47,000Valley Gutters (design and construction)$41,000Median Beautification Program$13,000Old Kings Road Reuse Main installation –Town

Center to Hidden Lakes$11,000

Page 17: Bringing  It In House

Technical WorkStrategic Action Plan$10,000Environmental Plan Reviews$4,000

Other Citywide Traffic CountsLighting I-95 RampsOffice Renovations – City Marketplace

Phases 1 and 2

Page 18: Bringing  It In House

Bringing It In-House!

Watch for more in 2013

Questions?