Top Banner
Bridge Standards Update John M. Holt, P.E. Texas of Transportation Department Transportation Short Course October 2011
43

Bridge Standards Update

Oct 15, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Bridge Standards Update

Bridge Standards Update

John M. Holt, P.E.

Texas

of TransportationDepartment

Transportation Short Course

October 2011

Page 2: Bridge Standards Update

Outline

• Precast Caps • Piles and Trestle Bents • Sidewalks/Medians on Bridge Decks • U-Beams • Parallel Wingwalls, PW • Crash Tests and Rails

Page 3: Bridge Standards Update

Precast Caps • Issued PBC-RC in April 2011

– Standard to be included with all standard bents with round columns

• Precasting caps is a Contractor option – Intended for “Standard Bents”, not necessarily

custom bents that look like standard bents – No minimum number of bents per bridge

specified—let the Contractor decide the most cost-effective option.

Page 4: Bridge Standards Update

Precast Caps Caney Creek Bridge SH 198, Henderson

County

Page 5: Bridge Standards Update

Precast Caps

Page 6: Bridge Standards Update

Precast Caps • PBC-P in final review (Standard with Piles)

– When made available, it is to be included with all standard trestle bents with either Concrete or Steel HP piles

• Allows precast caps as a Contractor option – No minimum number of bents per bridge

specified—let the Contractor decide the most cost-effective option

Page 7: Bridge Standards Update

Precast Caps

• PBC-P

Pockets in bottom of cap to receive concrete piles, then grouted

Steel H-piles are welded to embedded steel plates

Page 8: Bridge Standards Update

Precast Caps • Will there be a standard for abutments? Not

planning on developing one • The PBC standards can be modified to cover

precast abutment caps

Page 9: Bridge Standards Update

Piles and Trestle Bents • New HP Sections on Trestle Bent Standards

– HP18 x 135 is steel option to 20” Concrete Piles – HP16 x 101 is contractor option for HP14 x 117

– Only producer of these new HP sections is

Nucor-Yamato – Dimensions are in ASTM A6

Page 10: Bridge Standards Update

Piles and Trestle Bents • Revised Pile Embedment in Caps/Footings

– NEW: 18” Min Embed for 20” and 24” Concrete Piles

– 12” Min Embed for 18” and smaller piles

• All Trestle Bent standards refer the user to the FD standard for pile embedment (with exceptions)

• CP Standard is revised

Page 11: Bridge Standards Update

Piles and Trestle Bents • On all Trestle Bent Standards

– New restriction on unequal span lengths: • Shorter span must be at least 80 percent of the

longer span

• Piles are best suited for low-moment demand conditions and that means reasonably balanced span lengths

Page 12: Bridge Standards Update

Sidewalks/Medians on Bridge Decks

• Drawing is in final review stage • Option to have a drain thru the sidewalk,

using slip-resistant steel deck plate

Page 13: Bridge Standards Update

U-Beams • Revisions prompted by 2 research projects:

– Project 5834, Study of Elastomeric Bearings for Superelevated U-Beam Bridges, complete, Research Supervisor: Dr. Charles Newhouse, Texas Tech

– Project 5831, Bursting and Shear Behavior of

Prestressed Concrete Beams with End Blocks, on-going, Research Supervisor: Dr. Oguzhan Bayrak, UT-Austin

Page 14: Bridge Standards Update

U-Beams • Observations from Bearing Project:

– Superelevation should be considered in bearing design

• There is an eccentric reaction on bearing, producing a transverse moment

• Strain is strain—consider transverse strain together with longitudinal strain

– Significant slip can occur with 6 % and greater superelevations

Page 15: Bridge Standards Update

U-Beams • Draft UBEB Revisions:

– Beveled sole plates required when bearing pad taper report has taper over 5 percent OR when the span has a superelevation over 5 percent.

– Required bevel = the taper listed on the bearing taper report

– Smaller plan dimensions for U40 bearings – 8 x 0.25” layers, resulting in 2.75” overall bearing

height – Recommend not using U-beams for bridges with

superelevations above 6 %

Page 16: Bridge Standards Update

U-Beams • Observations from Shear & End Block

Project: – U-beam ends could benefit with more

reinforcement across the web - bottom flange interface

– Thicker webs and/or thicker end blocks would also be beneficial

Page 17: Bridge Standards Update

U-Beams • U-beam revisions:

– Additional reinforcement in end regions – End block length increased 12”

• Tested and they work

Page 18: Bridge Standards Update

U-Beams

CUT

End-region bottomflange-to-web interface

reinforcement, 𝜌𝑖𝑛𝑡 = 1%

A

B

Square end block length: 2'-6" to 3'-0"

Square end block length: 1'-6" to 2'-0"

R-bar

R-bar

L-bars

End-region bottomflange-to-web interface reinforcement, 𝜌𝑖𝑛𝑡 = 4%

End block vertical

reinforcement (V- and F-bars)

Page 19: Bridge Standards Update

Culvert Parallel Wingwalls • Change to top of wall geometry suggested to

us by Paris District to mitigate erosion at wing ends

1V:6H Slope at Wing Ends

Not used when railings are on top of wingwalls

Page 20: Bridge Standards Update

Crash Tests and Rails

Page 21: Bridge Standards Update

SSTR Retrofit to 6” Thick Pan Form Overhang, MASH TL-3, Pickup

Can a barrier rail be retrofit to the

longest and thinnest pan form overhang at slab edge?

Conventional wisdom said no

Page 22: Bridge Standards Update

SSTR Retrofit to 6” Thick Pan Form Overhang, MASH TL-3, Pickup

Two #8 dowels at

joints

Page 23: Bridge Standards Update
Page 24: Bridge Standards Update

Retrofit SSTR, MASH TL-3

Aftermath

Page 25: Bridge Standards Update

SSTR, MASH TL-4, Single Unit Truck

What is the Minimum Rail Height for the MASH Single Unit Truck?

MASH Single Unit Truck rolls over

32” tall barriers

Page 26: Bridge Standards Update
Page 27: Bridge Standards Update

SSTR, MASH TL-4,

Aftermath

Page 28: Bridge Standards Update

T223 with Shallow Anchorage Embedment, MASH TL-3, Pickup

Can we anchor a concrete rail only

within the 5” CIP slab on Box Beams and Slab Beams?

LRFD Spec requires 8.3” min for No. 5 Gr 60 bar, 90-deg hook,

uncoated

Page 29: Bridge Standards Update
Page 30: Bridge Standards Update
Page 31: Bridge Standards Update

31” Guardrail & Bridge Rails

• 31” guardrail implementation will trigger the retirement of our remaining 27” tall rails: T101, T101RC, T1-101R, and T6

• Unsuccessful crash test for a replacement to the T101 and T1-101R

• Currently working on curb mount retrofit, T131RC

• May need an exception for T101RC installations

Page 32: Bridge Standards Update

T131, MASH TL-3, Pickup

The T131 represents a “replacement” to the T101 and T1-

101R

Page 33: Bridge Standards Update
Page 34: Bridge Standards Update

T8, NCHRP 350 TL-3, Pickup

The T8 was an attempt to have a high speed version of T6

Page 35: Bridge Standards Update
Page 36: Bridge Standards Update

T101, MASH TL-3, Pickup

This is a 3rd high speed test with a rail having steel posts bolted

directly to the overhang

Page 37: Bridge Standards Update
Page 38: Bridge Standards Update
Page 39: Bridge Standards Update

Summary

Passing a high speed crash test with a rail having posts bolted directly to the deck is elusive

A low speed, all-steel rail, bolted directly to an overhang might be

possible

Page 40: Bridge Standards Update

No More T101 and T6? • Recommend using the T1W

– Very open for both view and hydraulics – Modular design—good for installation and

maintenance – Concrete curb:

• Great for strengthening the deck edge and limiting deck runoff

• Not so good for pushing snow off deck edge – Yes, it can be retrofitted to a bridge

Page 41: Bridge Standards Update

T1W Rail

Photos courtesy of Kerrville AO

Page 42: Bridge Standards Update

Bridge Railing Manual • A revised Bridge Railing Manual should be

available soon • Delays are from waiting on crash test

results, implementation of MASH, etc.

Page 43: Bridge Standards Update

• Email – [email protected]

• Or Call

– 512-416-2212

Questions?