Bridge Standards Update John M. Holt, P.E. Texas of Transportation Department Transportation Short Course October 2011
Bridge Standards Update
John M. Holt, P.E.
Texas
of TransportationDepartment
Transportation Short Course
October 2011
Outline
• Precast Caps • Piles and Trestle Bents • Sidewalks/Medians on Bridge Decks • U-Beams • Parallel Wingwalls, PW • Crash Tests and Rails
Precast Caps • Issued PBC-RC in April 2011
– Standard to be included with all standard bents with round columns
• Precasting caps is a Contractor option – Intended for “Standard Bents”, not necessarily
custom bents that look like standard bents – No minimum number of bents per bridge
specified—let the Contractor decide the most cost-effective option.
Precast Caps Caney Creek Bridge SH 198, Henderson
County
Precast Caps
Precast Caps • PBC-P in final review (Standard with Piles)
– When made available, it is to be included with all standard trestle bents with either Concrete or Steel HP piles
• Allows precast caps as a Contractor option – No minimum number of bents per bridge
specified—let the Contractor decide the most cost-effective option
Precast Caps
• PBC-P
Pockets in bottom of cap to receive concrete piles, then grouted
Steel H-piles are welded to embedded steel plates
Precast Caps • Will there be a standard for abutments? Not
planning on developing one • The PBC standards can be modified to cover
precast abutment caps
Piles and Trestle Bents • New HP Sections on Trestle Bent Standards
– HP18 x 135 is steel option to 20” Concrete Piles – HP16 x 101 is contractor option for HP14 x 117
– Only producer of these new HP sections is
Nucor-Yamato – Dimensions are in ASTM A6
Piles and Trestle Bents • Revised Pile Embedment in Caps/Footings
– NEW: 18” Min Embed for 20” and 24” Concrete Piles
– 12” Min Embed for 18” and smaller piles
• All Trestle Bent standards refer the user to the FD standard for pile embedment (with exceptions)
• CP Standard is revised
Piles and Trestle Bents • On all Trestle Bent Standards
– New restriction on unequal span lengths: • Shorter span must be at least 80 percent of the
longer span
• Piles are best suited for low-moment demand conditions and that means reasonably balanced span lengths
Sidewalks/Medians on Bridge Decks
• Drawing is in final review stage • Option to have a drain thru the sidewalk,
using slip-resistant steel deck plate
U-Beams • Revisions prompted by 2 research projects:
– Project 5834, Study of Elastomeric Bearings for Superelevated U-Beam Bridges, complete, Research Supervisor: Dr. Charles Newhouse, Texas Tech
– Project 5831, Bursting and Shear Behavior of
Prestressed Concrete Beams with End Blocks, on-going, Research Supervisor: Dr. Oguzhan Bayrak, UT-Austin
U-Beams • Observations from Bearing Project:
– Superelevation should be considered in bearing design
• There is an eccentric reaction on bearing, producing a transverse moment
• Strain is strain—consider transverse strain together with longitudinal strain
– Significant slip can occur with 6 % and greater superelevations
U-Beams • Draft UBEB Revisions:
– Beveled sole plates required when bearing pad taper report has taper over 5 percent OR when the span has a superelevation over 5 percent.
– Required bevel = the taper listed on the bearing taper report
– Smaller plan dimensions for U40 bearings – 8 x 0.25” layers, resulting in 2.75” overall bearing
height – Recommend not using U-beams for bridges with
superelevations above 6 %
U-Beams • Observations from Shear & End Block
Project: – U-beam ends could benefit with more
reinforcement across the web - bottom flange interface
– Thicker webs and/or thicker end blocks would also be beneficial
U-Beams • U-beam revisions:
– Additional reinforcement in end regions – End block length increased 12”
• Tested and they work
U-Beams
CUT
End-region bottomflange-to-web interface
reinforcement, 𝜌𝑖𝑛𝑡 = 1%
A
B
Square end block length: 2'-6" to 3'-0"
Square end block length: 1'-6" to 2'-0"
R-bar
R-bar
L-bars
End-region bottomflange-to-web interface reinforcement, 𝜌𝑖𝑛𝑡 = 4%
End block vertical
reinforcement (V- and F-bars)
Culvert Parallel Wingwalls • Change to top of wall geometry suggested to
us by Paris District to mitigate erosion at wing ends
1V:6H Slope at Wing Ends
Not used when railings are on top of wingwalls
Crash Tests and Rails
SSTR Retrofit to 6” Thick Pan Form Overhang, MASH TL-3, Pickup
Can a barrier rail be retrofit to the
longest and thinnest pan form overhang at slab edge?
Conventional wisdom said no
SSTR Retrofit to 6” Thick Pan Form Overhang, MASH TL-3, Pickup
Two #8 dowels at
joints
Retrofit SSTR, MASH TL-3
Aftermath
SSTR, MASH TL-4, Single Unit Truck
What is the Minimum Rail Height for the MASH Single Unit Truck?
MASH Single Unit Truck rolls over
32” tall barriers
SSTR, MASH TL-4,
Aftermath
T223 with Shallow Anchorage Embedment, MASH TL-3, Pickup
Can we anchor a concrete rail only
within the 5” CIP slab on Box Beams and Slab Beams?
LRFD Spec requires 8.3” min for No. 5 Gr 60 bar, 90-deg hook,
uncoated
31” Guardrail & Bridge Rails
• 31” guardrail implementation will trigger the retirement of our remaining 27” tall rails: T101, T101RC, T1-101R, and T6
• Unsuccessful crash test for a replacement to the T101 and T1-101R
• Currently working on curb mount retrofit, T131RC
• May need an exception for T101RC installations
T131, MASH TL-3, Pickup
The T131 represents a “replacement” to the T101 and T1-
101R
T8, NCHRP 350 TL-3, Pickup
The T8 was an attempt to have a high speed version of T6
T101, MASH TL-3, Pickup
This is a 3rd high speed test with a rail having steel posts bolted
directly to the overhang
Summary
Passing a high speed crash test with a rail having posts bolted directly to the deck is elusive
A low speed, all-steel rail, bolted directly to an overhang might be
possible
No More T101 and T6? • Recommend using the T1W
– Very open for both view and hydraulics – Modular design—good for installation and
maintenance – Concrete curb:
• Great for strengthening the deck edge and limiting deck runoff
• Not so good for pushing snow off deck edge – Yes, it can be retrofitted to a bridge
T1W Rail
Photos courtesy of Kerrville AO
Bridge Railing Manual • A revised Bridge Railing Manual should be
available soon • Delays are from waiting on crash test
results, implementation of MASH, etc.